Professional Documents
Culture Documents
HS - Progress Slide - 25 Sept
HS - Progress Slide - 25 Sept
1. PROJECT PARTICULAR
2. PROJECT ORGANIZATION CHART
3. SITE LOCATION
4. PROJECT STATUS
WORK PROGRESS
PHYSICAL S-CURVE
FINANCIAL S-CURVE
5. MASTER WORK PROGRAMME
6. MANPOWER & MACHINERIES UTILIZATION
7. PROGRESS PHOTOGRAPH
PROJECT PARTICULAR
CONTRACT PARTICULARS
PROJECT DIRECTOR
01112699899
BRYAN BRANDON
PROJECT MANAGER
0109722288
PROJECT MANAGER
0128205558
NEYROL JIMMY
0135730753 0198558831
SITE LOCATION
The Site
PROJECT STATUS
PHYSICAL REPORTING:
Schedule Progress -
Actual -
Status -
PHYSICAL S-CURVE
FINANCIAL REPORTING:
Schedule Progress -
Actual -
Status -
FINANCIAL S-CURVE
REVISED WORK PROGRAMME
ATTACHMENT
MANPOWER & MACHINERIES
UTILIZATION
MANPOWER RESOURCE UTILIZATION PROGRAMMES
(RUP)
26-Aug 27-Aug 28-Aug 29-Aug 30-Aug 31-Aug 1-Sep 2-Sep 3-Sep 4-Sep 5-Sep 6-Sep 7-Sep 8-Sep 9-Sep 10-Sep 11-Sep 12-Sep 13-Sep 14-Sep 15-Sep 16-Sep 17-Sep 18-Sep 19-Sep 20-Sep 21-Sep 22-Sep 23-Sep 24-Sep 25-Sep
Manpower
Wed Thu Fri Sat Sun Mon Tue Wed Thu Fri Sat Sun Mon Tue Wed Thu Fri Sat Sun Mon Tue Wed Thu Fri Sat Sun Mon Tue Wed Thu Fri
Project Manager
Ast. Project Manager
Project Coordinator
Supervisor 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 1 1 1 1 1 1 1 1
SSS
Quantity Surveyor
Project Clerk
Plant Operator
Lorry/Trailer Driver
Piling Worker
General Worker 2 3 5
Roofer
M&E
Surveyor
TOTAL = 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 3 1 1 4 6 1 1 1
MACHINERIES RESOURCE UTILIZATION PROGRAMME (RUP)
Plant & 26-Aug 27-Aug 28-Aug 29-Aug 30-Aug 31-Aug 1-Sep 2-Sep 3-Sep 4-Sep 5-Sep 6-Sep 7-Sep 8-Sep 9-Sep 10-Sep 11-Sep 12-Sep 13-Sep 14-Sep 15-Sep 16-Sep 17-Sep 18-Sep 19-Sep 20-Sep 21-Sep 22-Sep 23-Sep 24-Sep 25-Sep
Machineries Wed Thu Fri Sat Sun Mon Tue Wed Thu Fri Sat Sun Mon Tue Wed Thu Fri Sat Sun Mon Tue Wed Thu Fri Sat Sun Mon Tue Wed Thu Fri
Excavator
Piling Rig
Mixer Truck
Dump Truck
Compacter
Dozer
Lorry/Trailer
Crane
TOTAL = 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
PAYMENT STATUS
CONTRACTOR JKR SARAWAK PAYMENT STATUS
5
PROGRESS PHOTOGRAPH
Excavation of trench
Excavation of trench
Underground cable trace by SESCO
THANK YOU ;)