Praktikum Aplikom MK_Khoirul Soleh_053120017

ID Task Name Act. Start Act. Finish % Comp. Phys. % Act. Dur. Rem. Dur. Act. Cost Act. Work
Comp.
1 PEKERJAAN RUMAH JAGA Mon 27/11/23 NA 61% 0% 41,36 days 25,91 days Rp 397.192.720 6.736,8 hours
2 PEKERJAAN PERSIAPAN Mon 27/11/23 NA 99% 0% 1 day 0 days Rp 6.016.620 32 hours
3 Pas. Papan nama kegiatan Mon 27/11/23 NA 99% 0% 1 day 0 days Rp 2.516.620 32 hours
4 PEKERJAAN PASANGAN, PLESTERAN Thu DAN
07/12/23
ACIAN LT II NA 99% 0% 33 days 0 days Rp 130.548.890 2.280 hours
5 Pas. Bata 1pc : 5psr Thu 07/12/23 NA 99% 0% 8 days 0 days Rp 81.762.390 576 hours
6 Plesteran dinding 1pc : 5psr Tue 19/12/23 Wed 27/12/23 100% 0% 9 days 0 days Rp 26.510.500 936 hours
7 Acian dinding Mon 01/01/24 Mon 08/01/24 100% 0% 8 days 0 days Rp 22.276.000 768 hours
8 PEKERJAAN BETON LANTAI II Tue 28/11/23 NA 68% 0% 27,2 days 12,8 days Rp 47.459.500 675,2 hours
9 Pek. Beton kolom 20/25 Fe 180Tue 28/11/23 NA 70% 0% 2,8 days 1,2 days Rp 21.213.500 291,2 hours
10 Pek. Beton ring 20x25 Fe 215 Mon 01/01/24 NA 67% 0% 4 days 2 days Rp 26.246.000 384 hours
11 PEKERJAAN KAP / ATAP Tue 09/01/24 NA 46% 0% 8,71 days 10,04 days Rp 81.757.940 1.082,8 hours
12 Pek. Kuda-kuda kruing Tue 09/01/24 NA 44% 0% 1,5 days 1,91 days Rp 29.121.500 300 hours
13 Pek. Usuk kruing baru Fri 12/01/24 NA 34% 0% 1,8 days 3,51 days Rp 5.504.100 115,2 hours
14 Pek. Reng kamper Wed 17/01/24 NA 75% 0% 1,5 days 0,5 days Rp 8.836.500 96 hours
15 Pas. Atap genteng press lokal Fri 19/01/24 NA 80% 0% 2,4 days 0,6 days Rp 24.009.840 211,2 hours
16 Pas. Genteng bubungan Thu 18/01/24 NA 30% 0% 0,9 days 2,1 days Rp 2.682.300 72 hours
17 Pas. Listplank kamper Mon 22/01/24 NA 20% 0% 0,4 days 1,6 days Rp 3.122.400 54,4 hours
18 Pas. Ikut celedu paras ukir Wed 24/01/24 NA 50% 0% 1,5 days 1,5 days Rp 5.049.000 144 hours
19 Pas. Murdha paras ukir Fri 19/01/24 NA 43% 0% 1,2 days 1,6 days Rp 1.929.300 48 hours
20 Pas. Bentala paras ukir Thu 25/01/24 NA 63% 0% 0,75 days 0,45 days Rp 1.503.000 42 hours
21 PEKERJAAN PLAFOND DAN LANTAI Tue 09/01/24 NA 38% 0% 9,1 days 15,17 days Rp 34.265.700 662,4 hours
22 Pas. Penutup plafond kalsiboardTue
rangka
09/01/24
metal furing lt II NA 40% 0% 3,6 days 5,4 days Rp 23.123.400 432 hours
23 Pas. Lis plafond gypsum Mon 22/01/24 NA 33% 0% 1,8 days 3,6 days Rp 11.142.300 230,4 hours
24 PEKERJAAN KUSEN, PINTU, JENDELA Tue DAN
19/12/23
VENTILASI LT II NA 55% 0% 5,93 days 4,94 days Rp 57.555.200 1.121,2 hours
25 Pek. Kusen kamper Tue 19/12/23 NA 48% 0% 0,65 days 0,7 days Rp 8.323.900 114,4 hours
26 Pas. Pintu panil kamper Wed 20/12/23 NA 44% 0% 0,7 days 0,9 days Rp 1.362.550 50,4 hours
27 Pas. Daun jendela kamper Wed 20/12/23 NA 68% 0% 2,25 days 1,05 days Rp 13.369.875 270 hours
28 Pas. Papan ram Tue 19/12/23 NA 55% 0% 6 days 4,87 days Rp 31.635.600 624 hours
29 Pas. Kaca 5 m untuk daun jendelaFri 22/12/23 NA 43% 0% 1,2 days 1,6 days Rp 1.532.400 38,4 hours
30 Pas. Kaca mati 5 mm bening Tue 26/12/23 NA 60% 0% 0,75 days 0,5 days Rp 1.330.875 24 hours

Page 1
Praktikum Aplikom MK_Khoirul Soleh_053120017
ID Task Name Act. Start Act. Finish % Comp. Phys. % Act. Dur. Rem. Dur. Act. Cost Act. Work
Comp.
31 PEKERJAAN PENGGANTUNG DANThu PENGUNCI
21/12/23 NA 85% 0% 7,19 days 1,31 days Rp 7.865.750 208 hours
32 Pas. Kunci pintu 2 slaag Thu 21/12/23 NA 33% 0% 0,5 days 1 day Rp 580.250 16 hours
33 Pas. Engsel pintu Thu 21/12/23 Thu 21/12/23 100% 0% 1 day 0 days Rp 1.155.500 32 hours
34 Pas. Engsel jendela Tue 26/12/23 Tue 26/12/23 100% 0% 1 day 0 days Rp 1.613.500 40 hours
35 Pas. Grendel jendela Wed 27/12/23 Wed 27/12/23 100% 0% 1 day 0 days Rp 1.469.500 40 hours
36 Pas. Kait angin jendela Wed 27/12/23 Wed 27/12/23 100% 0% 1 day 0 days Rp 1.996.500 48 hours
37 Pas. Espagnolet pintu double Thu 21/12/23 Thu 21/12/23 100% 0% 1 day 0 days Rp 1.050.500 32 hours
38 PEKERJAAN FINISHING DAN STYLEFri BALI22/12/23 NA 40% 0% 14,95 days 22,25 days Rp 31.531.120 667,2 hours
39 Cat dinding dengan vinilex Fri 12/01/24 NA 16% 0% 0,2 days 1,09 days Rp 1.525.400 36,8 hours
40 Cat plafond dan lis dengan vinilex
Thu 25/01/24 NA 18% 0% 0,3 days 1,4 days Rp 1.799.400 43,2 hours
41 Cat kusen, daun pintu dan daunTuejendela
26/12/23
dengan emco
Thu 28/12/23 100% 0% 3 days 0 days Rp 12.196.500 192 hours
42 Cat listplank dengan emco Wed 24/01/24 Thu 25/01/24 100% 0% 1 day 0 days Rp 2.052.500 40 hours
43 Pas. Style Bali pintu Fri 22/12/23 NA 20% 0% 0,2 days 0,8 days Rp 674.700 9,6 hours
44 Pas. Bata paras + bata gosok Mon 01/01/24 NA 25% 0% 2,4 days 7,28 days Rp 13.282.620 345,6 hours
45 PEKERJAAN LAIN-LAIN Mon 25/12/23 NA 99% 0% 1 day 0 days Rp 192.000 8 hours
46 Pembersihan akhitr Mon 25/12/23 NA 99% 0% 1 day 0 days Rp 192.000 8 hours