RISK CONTROL
HAZARD IDENTIFICATION RISK ASSESSMENT
Recommendation
No. Sub-Activity Type Hazard Effect Existing Risk Control L S RPN = L x S RC Recommended Risk Control Person in Charge/Due date/ Status
Type of Activity
R = Routine Rating Likelihood (L) Description
Risk Priority Number ( RPN ) Risk Category Risk Level Action and Time Scale
NR = Non Routine 1 Inconceivable Is practically impossible and has never occurred
( RC )
2 Remote/unlikely Has not been known to occur after many years A risk identified as LOW may be considered as
Conceivable acceptable
3 Might be occur at sometimes in future
1-4 I Tolerable and further reduction may not be necessary.
4 Possible Has a good chance of occurring and is not unusual However, if the
Most likely risk can be resolved quickly and efficiently, control
5 The most likely result of the hazard/ event being relized
measures
A MEDIUM risk requires a planned approach to controlling
the hazard and applies temporary measure if required.
Severity ( S )
5 - 12 II Significant Actions taken must be documented on the risk assessment
Form including date for completion.
Rating Nature of Injury / ill health Estimate loss (RM) UiTM Reputation
1 First Aid only < 10 Slightly effected
2 Minor injury (1 day MC) < 100 Discussion at the management level A HIGH risk requires immediate action to control the hazard
3 Major injury (> 4 days MC) < 1000 Becomes an issue to the clients as detailed in the hierarchy of control. Actions taken must
15 - 25 III Intolerable be Documented on the risk assessment form Including date
4 Permanent disability < 10,000 Becomes an issue among the public Universities for completion.
5 Fatal > 10,000 Page
Becomes an issue at the level of the Ministry 1 of Education
of Higher 2
HAZARD IDENTIFICATION, RISK ASSESSMENT & RISK CONTROL ( HIRARC ) REGISTER
Function / Department : MAKMAL GEOTEKNIK 2
Title of Activity : CONE PENETRATION
RISK CONTROL
HAZARD IDENTIFICATION RISK ASSESSMENT
Recommendation
No. Sub-Activity Type Hazard Effect Existing Risk Control L S RPN = L x S RC Recommended Risk Control Person in Charge/Due date/ Status
Page 2 of 2