Project: OSBL Buildings & Roads Project KE-18129

Location: Jubail Industrial City, Kingdom of Saudi Arabia 18 OCT 2023

Page 1 of 1

ELECTRICAL TRENCH INSPECTION CHECKLIST KE-18129


Tag Description: Tag No.:
P. O. No.: Inspection Classification Area/Unit:
Contractor: Contractor Client Turnover System:
Work Package: Vendor Other Sub System:

ACCEPTABLE
Sl.No Items to be Inspected
YES NO N/A

1 Correct location as per drawings / specifications

2 Width and depth of excavation conforms to drawing / specifications

Ensure that the trench is clean and free from any foreign materials.
3 Prior to sand Bedding

Underground installation within the trench is properly protected. (if


4 any)

Ensure post lay sand bedding is correctly applied and free from
5 stones and Debris

6 Post lay dry sand cushion installed free from stones and debris

Correct debris free backfill completed, correct tiles laid, and markers
7 installed

8 Correct segregation

Remarks:

Contractor Client Others

Name: Name: Name:

Signature: Signature: Signature:

Date: Date: Date: