JKL DESIGN GROUP CO.

Room 202 Acre Building, 137 Malakas st., Brgy Central, Diliman, Quezon City
(02) 83550293 | jkldesigngroupco@gmail.com

DAILY PROGRESS REPORT

PROJECT NAME: WEEK NO. DAY NO. WEATHER.: DATE:


PROPOSED 3-STOREY RESIDENCE 5 24 SUNNY NOV 20, 2023
PROJECT LOCATION:
B1 LOT 15 PHASE 8, AYALA GREENFIELD ESTATES, CALAMBA, LAGUNA
OWNER:
MR. JOSE ANGEL L. TALAMPAS

I. MANPOWER:
1. FOREMAN – 1
2. LABORS- 4

II. ACTIVITIES ON SITE:


1. HAULING OUT EXCESS SOIL
2. LAYOUT AND STAKING FOR COLUMN FOOTINGS

III. SITE MAPPINGS:

LEGEND
ESTABLISHED GRADE

IV. TOOLS AND EQUIPMENTS:


1. BACKHOE- 1

V. MATERIAL DELIVERY:
1. 10MM DIA REBAR

VI. REPRESENTATIVE ON SITE:

VII. REMARKS:
GENERAL OVERVIEW OF TARGET WORKS LAST WEEK BY THE CONTRACTOR:
1. To start the excavation of column footings
2. To start the fabrication of rebar

ASSESSMENTS:
1. Already established the grade of the site
2. Started the staking and layouting of column grids

KINDLY SEE THE ATTACHED PICTURES:

PREPARED BY: CHECKED BY:

AR. JOSUA S. MARIN AR. SHEREE ANN CRUZ- ACUTINA


Project Architect, JKL Design Group Co. Principal Architect, JKL Design Group Co.

ENGR. FRANCIS LAGAMAYO


Site Engineer, JKL Design Group Co.

CONFORME:

ENGR. JOSE ANGEL L. TALAMPAS


Project Owner
JKL DESIGN GROUP CO.
Room 202 Acre Building, 137 Malakas st., Brgy Central, Diliman, Quezon City
(02) 83550293 | jkldesigngroupco@gmail.com

DAILY PROGRESS REPORT

PROJECT NAME: WEEK NO. DAY NO. WEATHER.: DATE:


PROPOSED 3-STOREY RESIDENCE 5 25 SUNNY NOV 21, 2023
PROJECT LOCATION:
B1 LOT 15 PHASE 8, AYALA GREENFIELD ESTATES, CALAMBA, LAGUNA
OWNER:
MR. JOSE ANGEL L. TALAMPAS

I. MANPOWER:
1. FOREMAN – 1
2. LABORS- 5

II. ACTIVITIES ON SITE:


1. LAYOUT AND STAKING FOR COLUMN FOOTINGS
2. FABRICATION OF REBARS

III. SITE MAPPINGS:

LEGEND
ESTABLISHED GRADE

IV. TOOLS AND EQUIPMENTS:


1. BACKHOE- 1
2. BAR CUTTER - 1

2. MATERIAL DELIVERY:
1. 10MM DIA REBAR

V. REPRESENTATIVE ON SITE:
1. ENGR. BRYAN MENDOZA

VI. REMARKS:
GENERAL OVERVIEW OF TARGET WORKS LAST WEEK BY THE CONTRACTOR:
1. To start the excavation of column footings
2. To start the fabrication of rebar

ASSESSMENTS:
1. Started the fabrication of rebars
2. Started the staking and layouting of column grids

KINDLY SEE THE ATTACHED PICTURES:

PREPARED BY: CHECKED BY:

AR. JOSUA S. MARIN AR. SHEREE ANN CRUZ- ACUTINA


Project Architect, JKL Design Group Co. Principal Architect, JKL Design Group Co.

ENGR. FRANCIS LAGAMAYO


Site Engineer, JKL Design Group Co.

CONFORME:

ENGR. JOSE ANGEL L. TALAMPAS


Project Owner
JKL DESIGN GROUP CO.
Room 202 Acre Building, 137 Malakas st., Brgy Central, Diliman, Quezon City
(02) 83550293 | jkldesigngroupco@gmail.com

DAILY PROGRESS REPORT

PROJECT NAME: WEEK NO. DAY NO. WEATHER.: DATE:


PROPOSED 3-STOREY RESIDENCE 5 26 CLOUDY NOV 22, 2023
PROJECT LOCATION:
B1 LOT 15 PHASE 8, AYALA GREENFIELD ESTATES, CALAMBA, LAGUNA
OWNER:
MR. JOSE ANGEL L. TALAMPAS

I. MANPOWER:
1. FOREMAN – 1
2. LABORS- 6

II. ACTIVITIES ON SITE:


3. LAYOUT AND STAKING FOR COLUMN FOOTINGS
4. FABRICATION OF REBARS

III. SITE MAPPINGS:

LEGEND
ESTABLISHED GRADE

IV. TOOLS AND EQUIPMENTS:


1. BACKHOE- 1
2. BAR CUTTER - 1

V. MATERIAL DELIVERY:
1. H-FRAMES
2. SHORING JACKS
3. GI PIPES

VI. REPRESENTATIVE ON SITE:

VII. REMARKS:
GENERAL OVERVIEW OF TARGET WORKS LAST WEEK BY THE CONTRACTOR:
1. To start the excavation of column footings
2. To start the fabrication of rebar

ASSESSMENTS:
1. Checked the layout

KINDLY SEE THE ATTACHED PICTURES:

PREPARED BY: CHECKED BY:

AR. JOSUA S. MARIN AR. SHEREE ANN CRUZ- ACUTINA


Project Architect, JKL Design Group Co. Principal Architect, JKL Design Group Co.

ENGR. FRANCIS LAGAMAYO


Site Engineer, JKL Design Group Co.

CONFORME:

ENGR. JOSE ANGEL L. TALAMPAS


Project Owner
JKL DESIGN GROUP CO.
Room 202 Acre Building, 137 Malakas st., Brgy Central, Diliman, Quezon City
(02) 83550293 | jkldesigngroupco@gmail.com

DAILY PROGRESS REPORT

PROJECT NAME: WEEK NO. DAY NO. WEATHER.: DATE:


PROPOSED 3-STOREY RESIDENCE 5 27 SUNNY NOV 23, 2023
PROJECT LOCATION:
B1 LOT 15 PHASE 8, AYALA GREENFIELD ESTATES, CALAMBA, LAGUNA
OWNER:
MR. JOSE ANGEL L. TALAMPAS

I. MANPOWER:
1. FOREMAN – 1
2. LABORS- 5

II. ACTIVITIES ON SITE:


1. LAYOUT AND STAKING FOR COLUMN FOOTINGS
2. FABRICATION OF REBARS
3. SITE INSPECTION OF JKL TEAM AND OWNER REPRESENTATIVE

III. SITE MAPPINGS:

LEGEND
ESTABLISHED GRADE

IV. TOOLS AND EQUIPMENTS:


1. BACKHOE- 1
2. BAR CUTTER - 1

V. MATERIAL DELIVERY:
1. H-FRAMES
2. SHORING JACKS
3. GI PIPES
VI. REPRESENTATIVE ON SITE:
1. ENGR. RAJ DEEP SINGH
2. ENGR. BERNIE

VII. REMARKS:
1. SCHEDULED THE MATERIAL TEST FOR REBARS
GENERAL OVERVIEW OF TARGET WORKS LAST WEEK BY THE CONTRACTOR:
1. To start the excavation of column footings
2. To start the fabrication of rebar

ASSESSMENTS:
1. Started the fabrication of rebars
2. Continued the staking and layouting of column grids

KINDLY SEE THE ATTACHED PICTURES:

PREPARED BY: CHECKED BY:

AR. JOSUA S. MARIN AR. SHEREE ANN CRUZ- ACUTINA


Project Architect, JKL Design Group Co. Principal Architect, JKL Design Group Co.

ENGR. FRANCIS LAGAMAYO


Site Engineer, JKL Design Group Co.

CONFORME:

ENGR. JOSE ANGEL L. TALAMPAS


Project Owner
JKL DESIGN GROUP CO.
Room 202 Acre Building, 137 Malakas st., Brgy Central, Diliman, Quezon City
(02) 83550293 | jkldesigngroupco@gmail.com

DAILY PROGRESS REPORT

PROJECT NAME: WEEK NO. DAY NO. WEATHER.: DATE:


PROPOSED 3-STOREY RESIDENCE 5 28 SUNNY NOV 24, 2023
PROJECT LOCATION:
B1 LOT 15 PHASE 8, AYALA GREENFIELD ESTATES, CALAMBA, LAGUNA
OWNER:
MR. JOSE ANGEL L. TALAMPAS

I. MANPOWER:
1. FOREMAN – 1
2. LABORS- 6

II. ACTIVITIES ON SITE:


1. FABRICATION OF REBARS
2. EXCAVATION OF COLUMN FOOTING

III. SITE MAPPINGS:

LEGEND
ESTABLISHED GRADE
EXCAVATED COLUMN FOOTING

IV. TOOLS AND EQUIPMENTS:


1. BACKHOE- 1
2. BAR CUTTER - 1

V. MATERIAL DELIVERY:

VI. REPRESENTATIVE ON SITE:

VII. REMARKS:
GENERAL OVERVIEW OF TARGET WORKS LAST WEEK BY THE CONTRACTOR:
1. To start the excavation of column footings
2. To start the fabrication of rebar

ASSESSMENTS:
1. Started the excavation for column footing

KINDLY SEE THE ATTACHED PICTURES:

PREPARED BY: CHECKED BY:

AR. JOSUA S. MARIN AR. SHEREE ANN CRUZ- ACUTINA


Project Architect, JKL Design Group Co. Principal Architect, JKL Design Group Co.

ENGR. FRANCIS LAGAMAYO


Site Engineer, JKL Design Group Co.

CONFORME:

ENGR. JOSE ANGEL L. TALAMPAS


Project Owner