JTB UNITIZATION GAS PROJECT DES

PRECOMM HOT WORK PERMIT REGISTER NUMBER

Review Jumlah
No. Tanggal Berlaku Nomor Permit Deskripsi Pekerjaan Area Area Spesifik Supervisor SRBA Nomor SIKA Umum Masa Berlaku SIKA UMUM Overtime Status
HSE RJJ POB
Column1 Column2 Column3 Column4 Column5
Column6Column7
Column8 Column9 Column10 Column11 Column12 Column13 Column14 Column15 7 Column17 Column18
6105 18 December 2021 JTB/PCSU/HW KOPRES-SS 12 21 6105 Prepare tali Air Utility GTG 420 Supriyono Bagus 3 871D/PRECOMM/SIKA/2021/KOPRES-SS 15 Desember 2021 - 21 Desember 2021 On Going
6106 18 December 2021 JTB/PCSU/HW KOPRES-SS 12 21 6106 Install Tray, Pulling Kabel, Terminasi Kabel HVAC SS-3 SS-3 Rooftop Murji Bagus 7 643K/PRECOMM/SIKA/2021/KOPRES-SS 16 Desember - 22 Desember 2021 On Going
6107 18 December 2021 JTB/PCSU/HW RJJ-ELECT 12 21 6107 Loop Sequence Tet MCC-LCS-IRP + ECMS SS3 SS3 Electrical Room Made Dimas Abia 5 947D/COMM/SIKA/2021/RJJ 11 Desember 2021 - 17 Desember 2021 On Going
6108 18 December 2021 JTB/PCSU/HW RJJ-ELECT 12 21 6108 Energized Control Power Suply VSD 323 SS3 Electrical Room Made Dimas Abia 5 1051B/COMM/SIKA/2021/RJJ 15 Desember 2021 - 21 Desember 2021 On Going
6109 18 December 2021 JTB/PCSU/HW RJJ-ELECT 12 21 6109 ECMS Commisioning (Include SAT & Function Test) And Load Sheding SS1 & SS4 Electrical Room Made Dimas Abia 10 1102A/COMM/SIKA/2021/RJJ 16 Desember 2021 - 21 Desember 2021 On Going
6110 18 December 2021 JTB/PCSU/HW RJJ-ELECT 12 21 6110 ECMS Commisioning (Include Performance Test & Function Test) And Load Sheding SS2 Electrical Room Alif Abia 10 1100A/COMM/SIKA/2021/RJJ 16 Desember 2021 - 21 Desember 2021 On Going
6111 18 December 2021 JTB/PCSU/HW RJJ-ELECT 12 21 6111 ECMS Commisioning (Include Performance Test & Function Test) and Load Sheding SS3 Electrical Room Denik Abia 10 1011A/COMM/SIKA/2021/RJJ 16 Desember 2021 - 21 Desember 2021 On Going
6112 18 December 2021 JTB/PCSU/HW RJJ-ELECT 12 21 6112 Energized dan SAT ECMS&OWS area Centrall Wellpad Centrall Wellpad Electrical Room Deni K Abia 5 New New On Going
6113 18 December 2021 JTB/PCSU/HW RJJ-ELECT 12 21 6113 Energized dan SAT ECMS&OWS area East Wellpad East Wellpad Electrical Room Deni K Abia 5 New New On Going
6114 18 December 2021 JTB/PCSU/HW RJJ-TF 12 21 6114 Cutting, Grinding, Fit up Welding Proses-1 260 Kadiran Abia 8 On Going
6115 18 December 2021 JTB/PCSU/HW RJJ-TF 12 21 6115 Cutting, Grinding, Fit up Welding Proses-1 222 Rochman Abia 4 On Going
6116 18 December 2021 JTB/PCSU/HW RJJ-TF 12 21 6116 Cutting, Grinding, Fit up Welding Proses-1 241 CSL-1008 Joko Abia 5 On Going
6117 18 December 2021 JTB/PCSU/HW RJJ-TF 12 21 6117 Cutting, Grinding, Fit up Welding Proses-1 241 Joko Abia 5 On Going
6118 18 December 2021 JTB/PCSU/HW RJJ-TF 12 21 6118 Cutting, Grinding, Fit up Welding Proses-1 241 CSL-1012 Joko Abia 5 On Going
6119 18 December 2021 JTB/PCSU/HW CYTR 12 21 6119 Welding Support Proses-2 322 Budi S Bagus 15 921E/PRECOMM/SIKA/2021/CTYR 13 Desember - 19 Desember 2021 On Going
6120 18 December 2021 JTB/PCSU/HW SWG-HVAC 12 21 6120 Pengecekan outdoor dan indoor, Cleaning AHU,Commissioning dan balancing IF All Area Building IF Darminto Imam M 8 604N/PRECOMM/SIKA/2021/SWG-ME 15 Desember 2021 - 21 Desember 2021 On Going
6121 18 December 2021 JTB/PCSU/HW SWG-ME 12 21 6121 Preservasi Electrical System IF All Building IF M. Thohar Imam M 4 860A/PRECOMM/SIKA/2021/SWG-ME 3 Desember 2021 - 6 Januari 2022 On Going
6122 18 December 2021 JTB/PCSU/HW SWG-ME 12 21 6122 Preservasi Electrical System (NS) IF All Building IF M. Thohar Imam M 4 860A/PRECOMM/SIKA/2021/SWG-ME 3 Desember 2021 - 6 Januari 2022 On Going
6123 18 December 2021 JTB/PCSU/HW SWG-ME 12 21 6123 Preservasi Electrical System IF All Building IF M. Thohar Imam M 4 860A/PRECOMM/SIKA/2021/SWG-ME 8 Desember - 14 Desember 2021 On Going
6124 18 December 2021 JTB/PCSU/HW SWG-ME 12 21 6124 Closing Punchlist Telekomunikasi System IF All Building IF M. Thohar Imam M 4 861A/PRECOMM/SIKA/2021/SWG-ME 3 Desember 2021 - 6 Januari 2022 On Going
6125 18 December 2021 JTB/PCSU/HW TELCON 12 21 6125 Install / Modifikasi support trau Proses-1 241 Selexol Mahrus 1118A/PRECOMM/SIKA/2021/TELCON 17 Desember - 23 Desember 2021 On Going
6126 18 December 2021 JTB/PCSU/HW WEN 12 21 6126 Install support,tray,tubbing,pulling cable dan terminasi. Proses-2 322 Kuswanto Bagus 10 On Going
6127 18 December 2021 JTB/PCSU/HW TELCON 12 21 6127 Energize,Re-energize Telecom, Function test LNC kabinet SGM Instrument Room Yuda Ardian Anggiat 5 582A/PRECOMM/SIKA/2021/TELCON 16 Desember - 22 Desember 2021 On Going
6128 18 December 2021 JTB/PCSU/HW RJJ-COMM 12 21 6128 Precommisioning 440 (IA Compressor, N2 Compressor, IA Dryer, N2 Generator) Utility 440 Albert Andi Hakim 10 1057A/PRECOMM/SIKA/2021/RJJ 16 Desember - 22 Desember 2021 On Going
6129 18 December 2021 JTB/PCSU/HW RJJ-COMM 12 21 6129 Start Up gas Buyback Phase 2 and Flarring GPF 221.410.420.430.470 Deden Noor Andi Hakim 10 new On Going
6130 18 December 2021 JTB/PCSU/HW RJJ-COMM 12 21 6130 Buyback Gas In SGM Offsite Deden Noor Andi Hakim 10 new On Going
6131 18 December 2021 JTB/PCSU/HW 12 21 6131 Submit
6132 18 December 2021 JTB/PCSU/HW RJJ-TF 12 21 6132 Cutting, Grinding, Fit up Welding Proses-1 241 CSR Rachman Abia 4 On Going
6133 18 December 2021 JTB/PCSU/HW RJJ-TF 12 21 6133 Cutting, Grinding, Fit up Welding Proses-1 241 Rachman Abia 5 On Going
6134 18 December 2021 JTB/PCSU/HW RJJ-TF 12 21 6134 Cutting, Grinding, Fit up Welding Proses-1 223 Rachman Abia 5 On Going
6135 18 December 2021 JTB/PCSU/HW SK 12 21 6135 Alignment Flange to Pump dan Cutting, Grinding Proses-2 322T Eko Andi Hakim 8 872G/PRECOMM/SIKA/2021/SK 17 Desember - 23 Desember 2021 On Going
6136 18 December 2021 JTB/PCSU/HW SK 12 21 6136 Alignment Flange to Pump dan Cutting, Grinding Proses-2 322B Eko Andi Hakim 8 873E/PRECOMM/SIKA/2021/SK 14 Desember - 20 Desember 2021 On Going
6137 18 December 2021 JTB/PCSU/HW SWC 12 21 6137 Finishing Chemical Coating Proses-2 322 Nasrullah Andi Hakim 8 1016C 15 Desember 2021 - 21 Desember 2021 On Going
6138 18 December 2021 JTB/PCSU/HW SWC 12 21 6138 Install Rebar Formwork & Pouring Concrete Proses-1 221 Bagus Andi Hakim 6 973C 15 Desember 2021 - 21 Desember 2021 On Going
6139 18 December 2021 JTB/PCSU/HW RJJ-INSTR 12 21 6139 ENERGIZE & SAT ICSS JE SS-212 MAKMUR ANDI HAKIM 10 997C/PRECOMM/SIKA/2021/RJJ 11 Desember 2021 - 17 Desember 2021 On Going
6140 18 December 2021 JTB/PCSU/HW RJJ-INSTR 12 21 6140 ENERGIZE & SAT PANEL 490 LCP P-9008 JOCKEY PUMP UTILITY 490 MAKMUR BAGUS P.A 10 1078A/PRECOMM/SIKA/2021/RJJ 11 Desember 2021 - 17 Desember 2021 On Going
6141 18 December 2021 JTB/PCSU/HW RJJ-INSTR 12 21 6141 ENERGIZE & SAT PANEL 234 UCP-9100 & UCP-9200 SS-2 ELECT.ROOM MAKMUR ABIA 10 On Going
6142 18 December 2021 JTB/PCSU/HW RJJ-PRECOMM 12 21 6142 Lube Oil Flushing ( Day shift) Proses-1 242 Kukuh Andi Hakim 5 new On Going
6143 18 December 2021 JTB/PCSU/HW RJJ-PRECOMM 12 21 6143 Lube Oil Flushing ( Day shift) Proses-1 242 Kukuh Andi Hakim 5 new On Going
6144 18 December 2021 JTB/PCSU/HW RJJ-PRECOMM 12 21 6144 Lube Oil Flushing ( Day shift) Proses-1 241 Kukuh Andi Hakim 5 new On Going
6145 18 December 2021 JTB/PCSU/HW RJJ-PRECOMM 12 21 6145 Lube Oil Flushing ( Day shift) Proses-1 241 Kukuh Andi Hakim 5 new On Going
6146 18 December 2021 JTB/PCSU/HW CMG 12 21 6146 Touch Up Painting Proses-1 221 Ruminto Andi Hakim 4 1065A 9 - 15 dec 21 On Going
6147 18 December 2021 JTB/PCSU/HW CMG 12 21 6147 Touch Up Painting Proses-1 470 Ruminto Andi Hakim 4 844D 11 - 17 dec 21 On Going
6148 18 December 2021 JTB/PCSU/HW CMG 12 21 6148 Touch Up Painting Proses-1 475 Ruminto Andi Hakim 4 845E 11 - 17 dec 21 On Going
6149 18 December 2021 JTB/PCSU/HW CMG 12 21 6149 Touch Up Painting Utility 480 Ruminto Andi Hakim 4 1074B/PRECOMM/SIKA/2021/CMG 18 Desember - 24 Desember 2021 On Going
6150 18 December 2021 JTB/PCSU/HW CMG 12 21 6150 Grouting Support Pipe Utility 450 M. Sudib Andi Hakim 11 887F/PRECOMM/SIKA/2021/CMG 15 Desember 2021 - 21 Desember 2021 On Going
6151 18 December 2021 JTB/PCSU/HW CMG 12 21 6151 Grouting Support Pipe Utility 410 M. Sudib Andi Hakim 2 970D/PRECOMM/SIKA/2021/CMG 15 Desember 2021 - 21 Desember 2021 On Going
6152 18 December 2021 JTB/PCSU/HW CMG 12 21 6152 Grouting Support Pipe Proses-2 322 M. Sudib Andi Hakim 11 1089A/PRECOMM/SIKA/2021/CMG 13 Desember - 19 Desember 2021 On Going
6153 18 December 2021 JTB/PCSU/HW KEJORA 12 21 6153 Civil Work Finishing Manpower Supply Proses-1 241 Manan ABIA 6 986D 17 Desember - 23 Desember 2021 On Going
6154 18 December 2021 JTB/PCSU/HW KEJORA 12 21 6154 Civil Work Finishing Manpower Supply Proses-1 470 Mujiono Abia 5 On Going
6155 18 December 2021 JTB/PCSU/HW RJJ-PRECOMM 12 21 6155 MRT 490 Utility Berri D P Andi Hakim 4 1121A/PRECOMM/SIKA/2021/RJJ 17 Desember - 23 Desember 2021 On Going
6156 18 December 2021 JTB/PCSU/HW RJJ-PRECOMM 12 21 6156 Solo Run Test 323 Proses 2 Berri D P Andi Hakim 4 1061/PRECOMM/SIKA/2021/RJJ 17 Desember - 23 Desember 2021 On Going
6157 18 December 2021 JTB/PCSU/HW CMT 12 21 6157 Prepare maintenance dan troubleshooting HVAC IF SS-5 Bayu L Andi Hakim 10 On Going
6158 18 December 2021 JTB/PCSU/HW CMT 12 21 6158 Commisioning HVAC System UTILITY CB Bayu L Andi Hakim 10 On Going
6159 18 December 2021 JTB/PCSU/HW CMT 12 21 6159 Commisioning HVAC System UTILITY SS-1 Bayu L Andi Hakim 10 On Going
6160 18 December 2021 JTB/PCSU/HW CMT 12 21 6160 Commisioning HVAC System UTILITY SS-4 Bayu L Andi Hakim 10 On Going
6161 18 December 2021 JTB/PCSU/HW TELCON 12 21 6161 Energize Telecom equipment precomm & commissioning IF Telecom Building Ricky Imam M 4 1091A/PRECOMM/SIKA/2021/TELCON 14 Desember - 20 Desember 2021 On Going