Professional Documents
Culture Documents
Pull Cord Switch-BX - Phisher
Pull Cord Switch-BX - Phisher
3
STOP
1 Safety Instruction
1.1 Intended Application Only qualified personnel that are familiar
BX Pull Cord Switch is used for emergency with the safety regulations and standards,
stop conveying equipment. It comply are allowed to work on the device.
with industrial safety regulations, which It will ensure to protect person and avoid
requires safety device can instantly stop damage to the device。
conveyor in order to secure personal 1.2 Symbols
safety. Please pay particular attention to the text
Applications other than specified and passages that are marked with the following
unauthorized modifications to the device symbols:
or its components may lead to injury to Danger!
STOP
persons and damage to the device for Information for person safety
which the manufacturer is not liable.
Any work performed with the device or ! Attention!
on the device must be carried out in Information for avoiding device
accordance with User Manual. damage
5
Pull Cord Switch User Manual
3 Designs and Function
BX Pull cord switches are use on conveyor systems as emergency power off switches
for continuous conveyors.
The devices are designed for long term service in extreme environmental conditions.
STOP Danger: After activating and before resetting the pull cord switch the system
must be checked along the total length of the release wire, in order to
determine the reason for activating of the pull rope switch.
Contact Quantity 2
Tension of Cord 49±10N (5±1kgf)
Cable Size 6~12mm
Ambient Temperature -20°C ~ +60°C
Humility ≤ 80%
Housing Protection IP67
11
4.1 Accessories
PVC coated steel wire Φ3 ,Φ4 red 100M for each device
Tension spring 140mm*20mm*3mm 2 pcs for each device
: Power to the conveyor belt 5. Loosen the two screws, and remove
! system must be disconnected
before dismounting. Ensure that the device
power cannot be switched on
! again.
: Open the cover only under the
condition of device complete
power off.
1. Disconnect the conveyor system from
the power supply, and prevent it being
switched on again.
2. Open the cover by loosening the
screws.
3. Loose the cable gland.
4. Separate the electrical connections
Repairing
Defect pull cord switch or component can
be sent to manufacture for replacement.
23