Dear Sir,
Thankyou very much for your E-mail request dated 23-12-2023 regarding the above subject. Please
find below our best prices.
A). SOIL
01 Washed Sieve Analysis with 75 micron sieve (#200) ASTM D-422 70/Test
02 Proctor Test (Moisture density relationship of cohesive soil) ASTM D-1557 130/Test
ASTM D-4253 &
03 Maximum & Minimum Index Density 110/Test
4254
04 Atterberg limits test ASTM D-4318 60/Test
(B) CONCRETE
(C) ASPHALT
ASTM D-
1 Asphalt extraction & gradation 150/Test
2172/D-5444
2 Max. Theoretical specific gravity ASTM D-2041 140/Test
3 Loss of stability (Set of 3) ASTM D-6927 150/Test
(D) AGGREGATE
(E) WATER
(F) STEEL
Tensile, yield & elongation test on reinforcing steel ASTM A-370 250/Test/
1
Ranging from 10mm – 16mm diameter bar size Sample
Bend test of reinforcing steel ranging from 6mm-16mm ASTM A-370 160/Test/
2
Ranging from 10mm – 16mm diameter bar size Sample
Tensile, yield & elongation test on reinforcing steel ASTM A-370 350/Test/
3
Ranging from 20mm – 32mm diameter bar size Sample
Bend Test of reinforcing steel ranging from 20mm-32mm ASTM A-370 200/Test/
4
diameter bar size Sample
(Note :- Client has to provide 2 Nos. steel bars 72 cm length of each size)
PAYMENT CONDITION: Full payment has to be settled at the time of releasing the report
We hope our quotation will meet your approval. In case of approval please send P.O. with your official notice to
proceed.
RABAH YEHYA
General Manager
1. Mobilization: Client to issue an official Purchase Order upon approval of the quotation.
2. Payment: Full payment has to be settled at the time of releasing the reports. For the Credit facilities, if payment is
not done on time as mutually agreed, GCSMT will have right to stop submitting reports until payment issue
resolved.
3. Value Added Tax (VAT): An amount equivalent to the mandatory percentage of the total invoice value
representing VAT will be applied
4. Validity : Validity of our cost proposal is 90 days from date of this Proposal.
5. Exclusion: The quoted rates for field tests are applicable only within our office normal working hours (7:00 AM
to 12:00 NN and 1:00 PM to 5:00 PM during weekdays & 7:00-12:00 NN during Thursday). In case fieldwork is
required outside regular working hours, additional SR 20 per hour will be charged.
6. Site Access: client is completely responsible in facilitating the application and eventual issuance of the necessary
access permits/IDs’ for GCSMT personnel, equipment and vehicle to enable our field crew gain an access to the
project location at no absolute cost to GCSMT.
7. Advance Notice: Client should give an advance notice, at least 24 hours, for site testing and/or sampling for an
on-call basis option.
8. Toxic & Hazardous Materials: It will be client’s obligation to voluntarily present GCSMT with sufficient
information readily available in his possession or knowledge on matters pertaining to the potential presence of
toxic or hazardous materials at the project site being investigated.
9. Warranty: GCSMT hereby extend its warranty that our services will be conducted in a manner consistent with
the level of case and skill ordinarily exercised by member of the profession currently practicing under similar
conditions. No other implied warranty is included or intended in our proposal.
10. Liability: For any unforeseen damage/s occurred on the account of human error, unintentional omission and other
professional negligence, we herein signify that our liability to compensate this unforeseen damage/s will be
limited to a sum not exceeding our fees charged form this particular undertaking.
11. Records: All pertinent records relating to testing services performed herein under shall be retained for a period of
not more than five (5) consecutive years after completion of work. Client shall have an access to the records, at all
reasonable times, during the mentioned period.
12. Reporting: Test reports shall be submitted within 1 week after completion of the test, as per the relevant test
standard and as per agreed payment condition.
13. Proper Storage and Disposal of Samples: Samples submitted to our laboratory for necessary testing services
will be discarded immediately after 30 days from the submission of our written report. Upon an official request,
we will be delivering the samples in accordance with the client’s instruction with corresponding charges or store
the sample/s longer than the specified period for an agreed fee.
14. Scaffoldings & Power supply: Necessary scaffolding and Power Supply of 110/220 volts will be provided by
client (in case necessary).
15. Propriety Information: “Propriety Information” Client request for Quotation in form of hard copy, digital, oral,
electronic to be treated as restricted and confidential in nature. Gulf Consult will not be disclosed to any Third
Party without Client consent.
16. Decision Rule: a). Decision Rule shall be implemented to determine the conformity of test result.
b). Decision rule shall take measurement uncertainty into account.
c). Decision rule shall be agreed with the customer before starting the test.
d). Decision rule shall be implemented when required.
e). Decision Rule Adopted: when the Test Result + the value of expanded uncertainty is
within the limits of the test, then the result is considered Pass. IF Test Result + the value of
expanded uncertainty is fully or partially outside the test limits, then the result is considered
Fail.