Professional Documents
Culture Documents
SATIP-W-011-01 Rev 8
SATIP-W-011-01 Rev 8
SATIP-W-011-01 Rev 8
SAUDI ARAMCO TYPICAL INSPECTION PLAN SATIP No. APPROVED DATE DISCIPLINE:
INSPECTION RESPONSIBILITY
ITEM QUALITY QUALITY ASSIGNMENTS
PROJECT PHASE TASK / ACTIVITY REMARKS
NO. PROCEDURE RECORD SAUDI
CNTRCTR
ARAMCO
SAIC-W-2035 SAIC-W-2035
Welder/Welding Operator Certs Review Use SATR-W-2003
1.2 RH R
and Issuance of JCC
SAUDI ARAMCO TYPICAL INSPECTION PLAN SATIP No. APPROVED DATE DISCIPLINE:
INSPECTION RESPONSIBILITY
ITEM QUALITY QUALITY ASSIGNMENTS
PROJECT PHASE TASK / ACTIVITY REMARKS
NO. PROCEDURE RECORD SAUDI
CNTRCTR
ARAMCO
1.12 Welding Strip Linings* (As Required) See Remarks See Remarks Refer to SATIP-W-015-01 (*Rare application)
3.0 INSTALLATION
3.1 Welding Overlays & Clad Materials See Remarks See Remarks See SATIP-W-014-01 (As Required)
3.2 Welding Strip Linings See Remarks See Remarks See SATIP-W-015-01, etc. (As required)
3.3 Welding Special* Corr-Resistant Mat'ls See Remarks See Remarks See SATIP-W-016-01 (As Required)
SAUDI ARAMCO TYPICAL INSPECTION PLAN SATIP No. APPROVED DATE DISCIPLINE:
INSPECTION RESPONSIBILITY
ITEM QUALITY QUALITY ASSIGNMENTS
PROJECT PHASE TASK / ACTIVITY REMARKS
NO. PROCEDURE RECORD SAUDI
CNTRCTR
ARAMCO
SAIC-W-2007
3.9 Post-Welding Visual Inspection SAIC-W-2007 H W
SATR-W-2007
SAUDI ARAMCO TYPICAL INSPECTION PLAN SATIP No. APPROVED DATE DISCIPLINE:
INSPECTION RESPONSIBILITY
ITEM QUALITY QUALITY ASSIGNMENTS
PROJECT PHASE TASK / ACTIVITY REMARKS
NO. PROCEDURE RECORD SAUDI
CNTRCTR
ARAMCO
Verify NDE Method Application and *Refer to the respective NDE SATIP
3.12 Evaluation, Documentation & Reporting of See Remarks See Remarks W / RH* W / R* (SATIP-NDE-UT-01, LPT-01, MPT-01, RT-01,
Results* etc.):
SAIC-W-2004
3.14 Post Weld Heat Treatment Inspection SAIC-W-2004 H W&R Refer to Note 1 of the General Notes
SATR-W-2005
4.0 PRE-COMMISSIONING
Final Welding Insp & Documentation a) Refer to SATIP for Pressure Testing.
4.1 (Database Report, Welding Summary/ SATR-W-2008 H R b) Verify SAEP-1160 Database Requirements are
Record & Weld Map) per SAEP-1160 complied.
SAUDI ARAMCO TYPICAL INSPECTION PLAN SATIP No. APPROVED DATE DISCIPLINE:
INSPECTION RESPONSIBILITY
ITEM QUALITY QUALITY ASSIGNMENTS
PROJECT PHASE TASK / ACTIVITY REMARKS
NO. PROCEDURE RECORD SAUDI
CNTRCTR
ARAMCO
GENERAL NOTES
The first three incidents of each Inspection or testing activity listed as "W' require 100 % participation by Saudi Aramco Site Inspection Personnel. After this period, Saudi Aramco Inspection may adjust the
1
levels of Saudi Aramco participation based upon the Contractor’s performance.
2 Surveillance: QA/QC organization to monitor work in progress without notice from Construction Organization
Witness: QA/QC organization shall be notified of the timing of Inspection or test in advance. However, the inspection or test shall be performed as scheduled if the QA/QC
3
organization representative is not present.
Hold: QA/QC organization shall be notified of the timing of inspection or test in advance. Inspection or test shall not be carried out without the QA/QC organization
4
representative in attendance.
5 If the Main Contractor delegates the assigned responsibility to the Subcontractor, then the Main Contractor will have the same degree of responsibility as assigned to Saudi Aramco.
LEGEND
H Hold Point for QC Inspection/ Test R Review of Documents
W Witness Inspection/Test RH Review and Approval of Documents
S Surveillance I 100% Contractor Inspection
MECHANICAL
CONTRACTOR/SUBCONTRACTOR
REMARKS
Use SATR-W-2003
MECHANICAL
CONTRACTOR/SUBCONTRACTOR
REMARKS
MECHANICAL
CONTRACTOR/SUBCONTRACTOR
REMARKS
MECHANICAL
CONTRACTOR/SUBCONTRACTOR
REMARKS
MECHANICAL
CONTRACTOR/SUBCONTRACTOR
REMARKS
GENERAL NOTES
participation by Saudi Aramco Site Inspection Personnel. After this period, Saudi Aramco Inspection may adjust the
truction Organization
dvance. However, the inspection or test shall be performed as scheduled if the QA/QC
dvance. Inspection or test shall not be carried out without the QA/QC organization
e Main Contractor will have the same degree of responsibility as assigned to Saudi Aramco.
LEGEND
Review of Documents
Review and Approval of Documents
100% Contractor Inspection