Professional Documents
Culture Documents
BS 8102 2022 Protection of Below Ground Structures Against Water
BS 8102 2022 Protection of Below Ground Structures Against Water
@seismicisolation
@seismicisolation
BS 8102:2022 BRITISH STANDARD
The BSI copyright notice displayed in this document indicates when the document was last issued.
ICS 91.120.30
@seismicisolation
@seismicisolation
© THE BRITISH STANDARDS INSTITUTION 2022 – ALL RIGHTS RESERVED
BRITISH STANDARD BS 8102:2022
Contents Page
Foreword iii
1 Scope 1
2 Normative references 1
3 Terms and definitions 2
4 Design philosophy 4
4.1 General 4
4.2 Design team 5
4.3 Principal considerations 5
Figure 1 — Design flowchart 8
5 Site evaluation 9
5.1 General 9
5.2 Inspection and survey for existing structures 10
6 Water resisting design 12
6.1 Groundwater 12
6.2 Waterproofing protection 13
Figure 2 — Schematic illustrations of Type A, Type B and Type C waterproofing protection – Type
A (barrier) protection 15
Figure 3 — Schematic illustrations of Type A, Type B and Type C waterproofing protection – Type
B (structurally integral) protection 15
Figure 4 — Schematic illustrations of Type A, Type B and Type C waterproofing protection – Type
C (drained) protection 16
Table 1 — Use of different protection types based on water table classification 17
Table 2 — Waterproofing protection – Grades of performance for below ground spaces 19
6.3 Exclusion of surface water 20
6.4 External sub‑surface drainage 20
Figure 5 — Sub‑surface drainage positioning 21
6.5 Buried decks below ground level 22
Figure 6 — Typical details of a buried deck with drainage 23
6.6 Ground gases 24
7 General construction issues 24
7.1 Site dewatering 24
7.2 Unexpected hazards 25
7.3 Structural elements 26
7.4 Continuity in construction 26
7.5 Protecting waterproofing 26
8 Type A (barrier) protection 27
8.1 Structural aspects 27
Figure 7 — Effect of structure on applied waterproofing barrier 28
Figure 8 — Examples of pile to floor slab junction 29
8.2 Waterproofing barrier materials 30
Table 3 — Waterproofing barriers 31
Figure 9 — Effect of bonded or partially bonded barriers 33
9 Type B (structurally integral) protection 36
9.1 General 36
9.2 Materials for structurally integral protection 36
9.3 Embedded retaining walls 39
10 Type C (drained) protection 41
10.1 Structural aspects 41
@seismicisolation
@seismicisolation
© THE BRITISH STANDARDS INSTITUTION 2022 – ALL RIGHTS RESERVED i
BS 8102:2022 BRITISH STANDARD
Summary of pages
This document comprises a front cover, an inside front cover, pages I to IV, pages 1 to 53, an inside back cover and a
back cover.
@seismicisolation
@seismicisolation
ii © THE BRITISH STANDARDS INSTITUTION 2022 – ALL RIGHTS RESERVED
BRITISH STANDARD BS 8102:2022
Foreword
Publishing information
This British Standard is published by BSI Standards Limited, under licence from The British
Standards Institution, and came into effect on 31 March 2022. It was prepared by Technical
Committee B/526, Geotechnics. A list of organizations represented on this committee can be obtained
on request to its committee manager.
Supersession
This British Standard supersedes BS 8102:2009, which is withdrawn.
@seismicisolation
@seismicisolation
© THE BRITISH STANDARDS INSTITUTION 2022 – ALL RIGHTS RESERVED iii
BS 8102:2022 BRITISH STANDARD
Presentational conventions
The provisions of this standard are presented in roman (i.e. upright) type. Its requirements are
expressed in sentences in which the principal auxiliary verb is “should”.
Commentary, explanation and general informative material is presented in smaller italic type, and does
not constitute a normative element.
Where words have alternative spellings, the preferred spelling of the Shorter Oxford English
Dictionary is used (e.g. “organization” rather than “organisation”).
@seismicisolation
@seismicisolation
iv © THE BRITISH STANDARDS INSTITUTION 2022 – ALL RIGHTS RESERVED
BRITISH STANDARD BS 8102:2022
1 Scope
This British Standard gives recommendations and provides guidance on methods of dealing with
and preventing the entry of water from external sources into structures that are partly or wholly
below ground.
It covers the use of:
a) waterproofing barrier materials applied to the structure;
b) structurally integral watertight construction; and
c) drained cavity construction.
It refers to the evaluation of groundwater conditions and consideration of harmful ground gases, risk
assessment and how to manage these risks in below ground structures.
This British Standard includes guidance on the drainage outside the structure and recognizes the risk
of water entering a structure through openings.
NOTE 1 Structures that are partly or wholly below ground can include occupied rooms, tunnels, plantrooms, car
parks, residential or commercial spaces, and service ducts. These structures can consist of any combination of
solid masonry, concrete and steel as the primary ground retaining structures. This British Standard is relevant to
structures below buildings or that are fully underground and covered by buried roofs, podium decks, or tunnel roofs.
Structures are generally characterized as “deep” if they have more than one storey below ground
level, or “shallow” if they have only a single storey below ground. This British Standard is
applicable to both.
NOTE 2 The principles for achieving waterproof underground spaces in this standard are relevant to most forms
of underground space. However, it is recognized that deep tunnels, rock caverns, mines, pipelines and some water
containment structures might follow design principles that are different to the approach set out in this British
Standard. In these types of structures, the acceptable levels of water ingress can be very different to those defined in
this standard.
NOTE 3 Standards and guidance for the protection of buildings against flooding by means of property level flood
resistance and resilience measures are given in BS 85500.
2 Normative references
The following documents are referred to in the text in such a way that some or all of their
content constitutes provisions of this document1). For dated references, only the edition cited
applies. For undated references, the latest edition of the referenced document (including any
amendments) applies.
BS 5930, Code of practice for ground investigations
BS 6100‑3, Building and civil engineering — Vocabulary — Part 3: Civil engineering — General
BS 8000‑2 (all sections), Workmanship on building sites — Part 2: Code of practice for concrete work
BS 8204‑1, Screeds, bases and in situ floorings — Part 1: Concrete bases and cement sand levelling
screeds to receive floorings — Code of practice
BS EN 1504 (all parts), Products and systems for the protection and repair of concrete structures —
Definitions, requirements, quality control and evaluation of conformity
BS EN 1542, Products and systems for the protection and repair of concrete structures — Test
methods — Measurement of bond strength by pull-off
1)
Documents that are referred to solely in an informative manner are listed in the Bibliography.
@seismicisolation
@seismicisolation
© THE BRITISH STANDARDS INSTITUTION 2022 – ALL RIGHTS RESERVED 1
BS 8102:2022 BRITISH STANDARD
@seismicisolation
@seismicisolation
2 © THE BRITISH STANDARDS INSTITUTION 2022 – ALL RIGHTS RESERVED
BRITISH STANDARD BS 8102:2022
NOTE On contact with the atmosphere, calcium hydroxide reacts with carbon dioxide to form calcium carbonate,
which is precipitated as a solid deposit when the water evaporates.
3.9 groundwater
water in the ground outside the structure from any source
3.15 seepage
slow transmission of water through discrete pathways of a structure
NOTE This can also be known as weeping, as defined in ICE publication, Specification for piling and embedded
retaining walls [1].
3.16 tanking
application of an appropriate waterproofing barrier to the walls, the base slab and, where relevant,
the buried deck of a below ground structure, such that the entire envelope of the structure below
ground is protected against water ingress
NOTE A cavity drain membrane is not considered to constitute tanking.
@seismicisolation
@seismicisolation
© THE BRITISH STANDARDS INSTITUTION 2022 – ALL RIGHTS RESERVED 3
BS 8102:2022 BRITISH STANDARD
3.20 waterproof
impervious to free water
NOTE This can also be known as “watertight”.
3.21 waterproofing
application of waterproof/water resisting materials
3.26 waterstop
material designed to inhibit the transmission of water through joints in the structure
4 Design philosophy
4.1 General
Strategies for dealing with all external sources of groundwater, surface/flood water, soil gases
and contaminants should be determined from the very earliest stages of the planning and design
processes for any project involving below ground structures.
For new structures, the structural design, overall weatherproofing design, waterproofing design and
construction processes sequencing, and buildability of the structure should be reviewed together, as
they generally interact.
@seismicisolation
@seismicisolation
4 © THE BRITISH STANDARDS INSTITUTION 2022 – ALL RIGHTS RESERVED
BRITISH STANDARD BS 8102:2022
In addition, during the design process and at all stages of the construction process, the designers,
specialists, manufacturers and installing contractors should establish and maintain effective channels
of communication.
NOTE Regular and clear communication coupled with good site supervision allows variations and amendments
to the design to be planned and executed without compromising the performance of the waterproofed structure
(see also 4.2 and Clause 7).
@seismicisolation
@seismicisolation
© THE BRITISH STANDARDS INSTITUTION 2022 – ALL RIGHTS RESERVED 5
BS 8102:2022 BRITISH STANDARD
NOTE 2 Mechanical heating and ventilation often play an important role in creating the internal environment and
controlling condensation, particularly where higher grades are required. The design of such systems is a specialist
activity, outside the scope of this British Standard.
c) inappropriate use of the materials being used and defects owing to the specific properties of the materials
being used; and
NOTE 2 Reference to "defects" does not apply to normal designed flexural cracks or surface crazing in concrete
elements but only to cracking, which might need to be locally sealed.
The construction methods, installation personnel, materials and protection thereof, used to realize
the design, should be such that the defects in all of the above are avoided.
Materials should be used in accordance with the conditions and requirements set out in the relevant
technical product information and in accordance with the manufacturer’s recommendations by
personnel trained in their use and application (see also Clause 11).
The potential for defects should be recognized and catered for in the design. Contingency planning for
dealing with any localized defects or system failure that arise should be included as part of the overall
waterproofing design for the structure (see also Clause 11).
@seismicisolation
@seismicisolation
6 © THE BRITISH STANDARDS INSTITUTION 2022 – ALL RIGHTS RESERVED
BRITISH STANDARD BS 8102:2022
In either case, the issue of repairability should be taken into account and the form and feasibility of
remedial measures after completion of the project with finishes in place assessed.
Figure 1 outlines the principal factors and stages that should be addressed in order to produce a
robust waterproofing solution for a below ground structure. The principal issues (shown in boxes) do
not necessarily need to be addressed in the order shown but all should be understood and evaluated.
NOTE 3 Figure 1 demonstrates that some matters are interrelated and that a degree of iteration might result from
a need to address buildability and repairability.
@seismicisolation
@seismicisolation
© THE BRITISH STANDARDS INSTITUTION 2022 – ALL RIGHTS RESERVED 7
BS 8102:2022 BRITISH STANDARD
NOTE Figure 1 outlines the principal factors and stages that need to be addressed in order to produce a
robust waterproofing solution for a below ground structure. The principal issues (boxes) do not necessarily
need to be addressed in the order shown but all need to be understood and evaluated.
@seismicisolation
@seismicisolation
8 © THE BRITISH STANDARDS INSTITUTION 2022 – ALL RIGHTS RESERVED
BRITISH STANDARD BS 8102:2022
5 Site evaluation
COMMENTARY ON CLAUSE 5
Attention is drawn to the fact that many of the issues addressed in this Clause are also relevant to the
design of the structure itself. For further guidance, see the relevant Eurocodes, e.g. BS EN 1992 (all parts)
or BS EN 1997 (all parts).
5.1 General
5.1.1 Desk study
The design team should carry out a desk study in accordance with BS 5930 and BS EN 1997‑2 to:
a) assess the geology and hydrogeology, including soil permeabilities, flood risk, radon, methane
and other ground gases and contaminants (e.g. hydrocarbons, chlorides and acids);
b) assess the topography of the surrounding ground in relation to the below ground structure;
c) establish the likely highest level of the water table and the potential for the occurrence of a
perched water table;
d) establish the impact of flooding; and
e) identify any missing ground and groundwater information, which should then be obtained by
undertaking a site investigation in accordance with BS 5930 and BS EN 1997 (all parts).
NOTE 1 Guidance on best practice in ground investigation, laboratory and field‑testing for embedded retaining
walls is given in CIRIA publication C760 [2].
NOTE 2 For guidance on good practice for assessment on impact of flooding, see BS 8533.
The drainage characteristics from analysis of the soil should be determined in accordance
with BS 5930.
A risk assessment should be carried out which determines the long‑term water pressures, the effects
of surface water infiltration and the use of external drainage and cut‑off walls.
The risk assessment should also take into account:
a) the potential effects of climate change, burst water mains, flooding, defects in underground
sustainable urban drainage (SUD) systems and defective soakaways and sewers, adjacent trees,
sulfates, radon, methane and other ground gases and contaminants; and
b) where external drainage is proposed, the effects of drawdown on adjacent structures, the
potential silting of drainage and biofouling issues.
Even when the site investigation indicates dry conditions, the risk of some waterlogging (see Note 2)
in the future should be assumed.
NOTE 2 Even in a permeable subsoil, groundwater requires time to drain away and this can result in limited
pressure periodically coming to bear against the structure.
@seismicisolation
@seismicisolation
© THE BRITISH STANDARDS INSTITUTION 2022 – ALL RIGHTS RESERVED 9
BS 8102:2022 BRITISH STANDARD
NOTE 2 The type of structure can inherently raise the risk, e.g. block work construction below ground level, due to
number of joints within these forms of construction.
Modular systems, such as twin wall and insulated concrete formwork (ICF) construction should be
deemed inherently high risk. See 4.3.2 on defects and remedial viability.
@seismicisolation
@seismicisolation
10 © THE BRITISH STANDARDS INSTITUTION 2022 – ALL RIGHTS RESERVED
BRITISH STANDARD BS 8102:2022
NOTE 2 Less movement would be expected in cases where the floor is set into the wall, although horizontal
movement can occur unless the floor is reinforced, such as to achieve the necessary fixity.
NOTE 3 Existing waterproofing might have to be removed completely and replaced with an entirely new system,
although in some instances it might be possible to apply a Type A barrier or a Type C drained cavity system directly.
These systems can be considered where there is no existing waterproofing, but the suitability of barrier materials
depends on the characteristics of the surface of the wall or floor, and any preparatory works that might be required.
@seismicisolation
@seismicisolation
© THE BRITISH STANDARDS INSTITUTION 2022 – ALL RIGHTS RESERVED 11
BS 8102:2022 BRITISH STANDARD
4) the presence, strength and efficacy of concealed drainage, such as drainage tiles, no fines
concrete and historic floor channels.
The survey should include any constructions which abut the main structure, such as garden walls and
arches under steps, as these are a potential source of moisture transfer.
An assessment of the building’s drainage should always form part of any evaluation of the building
before the final design and waterproofing measures are finalized.
All reasonable steps should be taken to ensure that drainage is optimized and that any existing
drainage systems are functioning correctly. Drainage surveys and careful considerations of other
factors, such as rainwater goods, gullies, ditches, culverts and watercourses, should form part of the
site evaluation process.
NOTE 2 Addressing any drainage defects could reduce the rate of water into the ground and in doing so could assist
with conservation of the existing structures above and below ground.
Extreme caution should be taken if dewatering is to be considered within or adjacent to any old
building (see Clause 7). In addition, the use of waterproofing systems that could significantly increase
the hydrostatic load on existing structures should be undertaken only after it is proved that this will
not compromise the integrity of the building.
Where Type C waterproofing systems are considered, the location and impact of any water discharge
points should be carefully assessed and mitigated.
@seismicisolation
@seismicisolation
12 © THE BRITISH STANDARDS INSTITUTION 2022 – ALL RIGHTS RESERVED
BRITISH STANDARD BS 8102:2022
Protection against water ingress from the following three sources should also be taken into account:
1) the inflow of surface water, including percolation of rain, inundation of water during storm
events and from burst water mains (see 6.3);
2) the water pressures acting on the external structure; and
3) flooding from surface pluvial, fluvial, groundwater, or coastal or drainage/other sources.
The risk of flooding from surcharge of sewers should be taken into account (see BS EN 752).
The waterproofing specialist, together with the design team, should agree a head of water which the
system is designed to accommodate. This head of pressure should be informed by the risk assessment
covered in Clause 5.
One or both of the following methods may be used in conjunction with the waterproofing protection
(see 6.2) to reduce water penetration, depending on the conditions of the site and the required
internal environment:
i) exclusion of surface water (see 6.3); and
ii) sub‑surface drainage (see 6.4).
@seismicisolation
@seismicisolation
© THE BRITISH STANDARDS INSTITUTION 2022 – ALL RIGHTS RESERVED 13
BS 8102:2022 BRITISH STANDARD
There are a range of waterproofing systems that can be incorporated in each type of waterproofing
protection and these should be assessed in accordance with Clause 8, Clause 9 and Clause 10, as
appropriate. Relevant manufacturers’ product information should be checked to confirm that the
system selected is suitable for the structure to which it is to be applied.
The manufacturer’s recommendations for installation, including provision of protection, should
always be followed.
Similarly, recommendations for fixings and penetrations where proprietary products are used should
be followed.
NOTE 2 See 6.6 for recommendations on ground gases.
The types of waterproofing systems given in 6.2.1 should be used, subject to their suitability for
application and their ability to be repaired (see Figures 2, 3, 4).
Where Type A protection is used, it should be an internal waterproofing barrier on a structure of
suitable strength and stiffness, built of concrete or masonry (subject to the condition of the surface)
see (Figure 2).
The full design team should take into account the following:
a) the impact on floatation forces; and
b) the impact on the existing structure on elements such as embedded timbers.
NOTE 2 Other interested parties, such as local conservation officers, might need to be consulted in regard to the
waterproofing design adopted.
When combining types of protection, the compatibility of the different protection types should be
assessed in order to minimize the risks and negate the need for remedial measures. When combining
Type A and Type B, these systems should be bonded (see 8.2.2 and Figure 7).
@seismicisolation
@seismicisolation
14 © THE BRITISH STANDARDS INSTITUTION 2022 – ALL RIGHTS RESERVED
BRITISH STANDARD BS 8102:2022
Figure 2 — Schematic illustrations of Type A, Type B and Type C waterproofing protection – Type A (barrier)
protection
Key
1 External waterproofing
2 Masonry or concrete wall, as appropriate (see Table 1)
3 Concrete floor slab
4 Internal waterproofing
Figure 3 — Schematic illustrations of Type A, Type B and Type C waterproofing protection – Type B (structurally
integral) protection
NOTE Seek the manufacturer’s advice with respect to waterstops to suit the specific construction.
Key
1 Watertight reinforced concrete wall and slab
2 Appropriate joint protection to be employed (see 9.2.1.4 for waterstops)
3 Concrete/steel piled wall
4 Watertight reinforced concrete floor slab or slab with added barrier
5 Possible liner wall to achieve desired water resistance (see Table 1)
@seismicisolation
@seismicisolation
© THE BRITISH STANDARDS INSTITUTION 2022 – ALL RIGHTS RESERVED 15
BS 8102:2022 BRITISH STANDARD
Figure 4 — Schematic illustrations of Type A, Type B and Type C waterproofing protection – Type C (drained)
protection
@seismicisolation
@seismicisolation
16 © THE BRITISH STANDARDS INSTITUTION 2022 – ALL RIGHTS RESERVED
BRITISH STANDARD BS 8102:2022
2) initial capital costs compared with costs for future maintenance and any necessary upgrades;
3) the scope for testing and/or quality assurance during installation;
4) the risks associated with aggressive groundwater and other ground contaminants, which might
require the use of a specific protection barrier; and
5) the need or ability to provide heating and/or ventilation conditional of use and the consequences
arising in terms of water vapour.
NOTE 1 This might call for the adoption of an improved grade of waterproofing protection (see Table 1
and 6.2.2) or active environmental control in order to manage water vapour (see Table 2).
Variable Acceptable
if the “variable”
classification is due
to surface water.
The manufacturer’s
advice should be
sought.
@seismicisolation
@seismicisolation
© THE BRITISH STANDARDS INSTITUTION 2022 – ALL RIGHTS RESERVED 17
BS 8102:2022 BRITISH STANDARD
Table 1 — Use of different protection types based on water table classification (continued)
a) an appropriate
cementitious
multi‑coat render
or cementitious
coatings are used;
b) the wall is of
concrete to 9.2.1;
or
c) a fully bonded
Type A system is
used (see Figure 9)
Measures to reduce risk • Use combined protection (see 6.2.2).
• Ensure that drainage and discharge systems, e.g. pumps, are maintained so that the
system remains effective (see 10.3.1).
NOTE The water table classifications are defined as follows (see also 5.1.3).
• High – where the water table or perched water table is assessed to be permanently above the underside of the base slab. Ground
permeability might affect risk under a low or variable water table (see 5.1).
• Low – where the water table or perched water table is assessed to be permanently below the underside of the base slab. This only
applies to free‑draining strata.
@seismicisolation
@seismicisolation
18 © THE BRITISH STANDARDS INSTITUTION 2022 – ALL RIGHTS RESERVED
BRITISH STANDARD BS 8102:2022
Ventilation, dehumidification or air conditioning necessary; appropriate to the intended useD), E).
A)
The agreed grade should meet with the client’s expectations for the intended use of the below ground
space. Reducing the grade could increase the risk of not meeting the expectations of the client for the
intended use of the below ground space.
B)
Seepage (sometimes referred to as weeping) is defined in 3.15. If there is seepage, there is a possibility
of mineral deposits forming.
C)
Damp area is defined in 3.4.
D)
The scope of this document is limited to detailing the process and best practices that can be followed
when creating a waterproof or water‑resistant structure below ground. The additional considerations
that are required to achieve the required environment are beyond the scope of this document.
E)
See BS 5454 for recommendations for the storage and exhibition of archival documents.
The performance grades should be agreed at the earliest stage in the process; see Figure 1.
Different areas or aspects of the below ground structure might have different performance grade
requirements; these should be clearly identified within the waterproofing design.
NOTE 2 Changes to performance grades during construction may, subject to the waterproofing specialist’s
agreement, be addressed with either remedial measures ( Clause 11) or introducing a secondary waterproofing
system (6.2.2), combined systems (6.2.3) or introduction of ventilation, dehumidification or air conditioning.
@seismicisolation
@seismicisolation
© THE BRITISH STANDARDS INSTITUTION 2022 – ALL RIGHTS RESERVED 19
BS 8102:2022 BRITISH STANDARD
NOTE 4 Once above ground level, attention is drawn to national regulations related to fire protection.
NOTE 2 Burst water mains and surcharged sewers can provide additional sources of surface water. These can affect
perched water tables. The drainage behind the wall needs to be able to cope with the highest inflow rates, e.g. the
burst water main, which might not be practicable in coarse‑grained soils.
Where feasible, external sub‑surface drainage can be used to lower the potential for hydrostatic
pressure on the waterproofing system and reduce the risk of water ingress through defects. It should
be provided by one of the following methods:
a) perimeter drainage;
b) permeable granular fill;
c) geosynthetic drainage composite;
d) underslab drainage;
e) vertical drainage conduits; or
f) a combination of the above.
NOTE 2 Vertical drainage conduits are high‑density polymer extrusions inserted vertically into the ground to
improve infiltration and percolation of surface water into unsaturated sub soil strata around and below a structure.
NOTE 3 Figure 5 gives examples of the positioning of land drains, drainage channels and sub‑surface drainage.
NOTE 4 The inclusion of external sumps and pumps to facilitate the management of external groundwater can be
considered where required and achievable.
Such provisions should be made maintainable with reference to a suitably qualified drainage
engineer and any relevant standards.
Where practicable, water should be kept from prolonged contact with perimeter structure walls or
base slabs by porous or open‑jointed land drains, combined with a geosynthetic drainage composite
installed to the full height of the earth‑retaining wall and laid to proper falls around the perimeter of
the structure, adjacent to the wall footing and, where appropriate, beneath the slab itself.
The sub‑surface system should be graded to an open outlet below the level of the lowest slab, such as
to a stormwater drain protected by a pumped surcharge device or to a pumped sump. The need for
the use of non‑return valves to protect against surcharge should be determined.
Perimeter drainage at floor level is likely to lower the groundwater table to a degree that varies with
the permeability of the subsoil, and the possible consequences of this (such as permanent lowering of
the water table in the surrounding area) should be taken into account.
Any existing system of land drains should be tested, checked and only retained if both appropriate
and maintainable. Any local diversions necessary should retain the existing geometry so far as
practicable with new and easily maintainable pipework.
Care should be taken so that no damage is caused in nearby structures.
@seismicisolation
@seismicisolation
20 © THE BRITISH STANDARDS INSTITUTION 2022 – ALL RIGHTS RESERVED
BRITISH STANDARD BS 8102:2022
NOTE 5 Where sub‑surface drainage is considered/proposed at least within 3 m (and sometimes within 6 m)
of a nearby structure, attention is drawn to the Party Wall etc. Act 1996 [3]. Often this can be established at the
conceptual design stage of such a project by a suitably qualified building professional.
Where structures are contemplated in built‑up areas, groundwater lowering should not be
undertaken without careful investigation in conjunction with a groundwater specialist (see 4.2).
Perimeter walls providing a cut‑off into an impervious layer or stabilization of granular subsoils by
grout injection or similar alternative treatments may be used instead.
NOTE 6 For structures in coarse‑grained soil, with variable and high water tables (see 5.1.3), the flow rates are
likely to make it impracticable to pump for the design life of the structure. In these cases, a hydraulic cut‑off wall
into fine‑grained soils is required to isolate the ground below the base slab. This enables an underslab drainage
system to relieve the water pressure below the base slab.
NOTE 7 For structures in fine‑grained soil, with variable and high water tables (see 5.1.3), the flow rates are more
likely to make it practical to pump for the design life of the structure. A drainage system may be provided outside
the retaining wall to control the water pressures. An underslab drainage system may also be provided below the
base slab to control the water pressures.
Specified tolerances should be such that there is adequate intersection between piles or provision
of continuous water bars at diaphragm wall panel joints, and particular attention should be given
to workmanship. Drainage below basement slabs within a zone protected by cut‑off walls should be
designed by a suitably qualified and experienced professional.
NOTE 8 Cut‑off walls are formed from diaphragm walls, secant piles or steel piles. Over the excavated wall depth,
remedial works can be carried out on leaky walls. This is not feasible for the length of wall below formation.
In interbedded soils, relief wells may be used below formation level. The cut‑off wall may also be used
to reduce the flow rate and control the drawdown outside the site.
Figure 5 — Sub‑surface drainage positioning
@seismicisolation
@seismicisolation
© THE BRITISH STANDARDS INSTITUTION 2022 – ALL RIGHTS RESERVED 21
BS 8102:2022 BRITISH STANDARD
c) Construction without a toe and vertical drainage d) Construction with a toe and vertical drainage
Key
1&2 Maintainable land drain (see 6.4) not to be positioned closer than a line of 45° from the underside of
the slab/blinding or with an invert above the upper surface of the floor slab
3 Incorrect position of land drain, which can cause hydrostatic pressure on structure leading to water
ingress if defects are present
4 Sub‑surface drainage layer, where appropriate (see 6.4)
5 Structural wall and foundation slab
6 Continue to minimum 1.5 m below the base of the slab
7 Vertical Drainage system
In cases where the below ground structure is fully buried or the substructure extends beyond the
superstructure, protection should be provided against water ingress through the roof slab.
Such decks should ideally be formed of in‑situ reinforced concrete, cast to achieve a fall of 1:80 such
that no additional screed is required to achieve falls. When using alternative methods of construction,
an unbonded screed should be provided to achieve a fall of 1:80.
The substrate movement and cracking and possible implications of damage to the waterproofing
layer should be taken into account.
Where waterproofing is applied directly to the structural deck, this waterproofing should be
fully bonded.
NOTE 2 Warm roof build‑ups and loose laid waterproofing systems are acceptable where permanent leak detection
systems are employed such that leak locations can be identified and repairability is achieved (see 4.3.2).
NOTE 3 Service entries are particularly vulnerable to water penetration. Where they cannot be avoided or are
introduced post‑construction or waterproofing, they should be carefully detailed, incorporating sealing of the
adopted form(s) of waterproofing to minimize the risk of water ingress (see also 8.1.3).
Waterproofing should be applied onto a surface with a gradient to falls leading to suitable
maintainable outlets. There should be no ponding or “backfalls”.
A drainage path should be provided directly above the waterproofing layer in order to promote
the drainage of water away from the waterproofing layer. Any drainage collectors/outlets that
are included should be designed to be maintainable and should be maintained at an appropriate
@seismicisolation
@seismicisolation
22 © THE BRITISH STANDARDS INSTITUTION 2022 – ALL RIGHTS RESERVED
BRITISH STANDARD BS 8102:2022
frequency. Details should be provided within a maintenance schedule included in the building’s
operation manual.
NOTE 4 Alternative design approaches might be required when buried decks are below the water table.
Movement joints in buried decks should not be used unless unavoidable; where unavoidable, these
should be located in raised upstands.
NOTE 5 Figure 6 shows some typical details of a buried deck.
@seismicisolation
@seismicisolation
© THE BRITISH STANDARDS INSTITUTION 2022 – ALL RIGHTS RESERVED 23
BS 8102:2022 BRITISH STANDARD
Key
1 Deck to falls 4 Maintainable drainage for buried roof/deck
2 Waterproofing barrier 5 Continuous cavity tray
3 Drainage layer 6 Flashing
The inclusion of a ground gas barrier (see 3.8) for the prevention of migration of radon, methane and
other ground gases and contaminants from entering a structure should be taken into account in the
risk assessment, design, choice of the materials and installation of any waterproofing system.
NOTE 2 Further guidance on the characterization and remediation of ground gases is given in BS 8485 and TBIC
document, Basements: Ground gases and structural waterproofing [4].
NOTE 3 The BRE report BR211 [5] refers to basements in paragraph 6.12.
7.1.2 Where adjacent structures and utility assets could be affected, measures should be adopted to ensure
that any dewatering cannot cause harm during construction and in the future.
7.1.3 During construction, below ground structures are at risk of water entry until the project is watertight
and all aspects of the waterproofing are complete; account should be taken of all likely sources and
entry points for water ingress affecting the works prior to completion.
7.1.4 The installation of plant, equipment, fixtures and fittings before the basement is fully waterproof
should be avoided whenever possible. If the delivery or installation of plant or equipment into the
basement is planned before the waterproofing is complete, then measures should be taken to ensure
the continuity of the waterproofing is not compromised and the equipment is protected from the risk
of uncontrolled water ingress.
7.1.5 A “Water Management Plan” should be produced by the main contractor recommending the
following, as a minimum:
a) the appointment of a responsible person to manage the risk of water damage during
construction;
b) a risk assessment process for mitigating exposures to water ingress during the works at
design stage;
@seismicisolation
@seismicisolation
24 © THE BRITISH STANDARDS INSTITUTION 2022 – ALL RIGHTS RESERVED
BRITISH STANDARD BS 8102:2022
c) the selection of competent waterproofing contractors with appropriate insurance cover during
installation;
d) mitigation measures and emergency response plans;
e) comprehensive details of dewatering; and
f) a programme identifying when the structure below ground will be weathertight.
7.1.6 Water ingress during construction should be taken into account in the design.
NOTE Some examples include, but are not limited to:
a) water ingress through the structure prior to the installation and commissioning of pumps and water
management systems;
b) water ingress overtopping basement waterproofing systems in advance of building closure, waterproofing of
podium slabs or installation of ground level terminations;
c) water ingress through ducts and service entries prior to final sealing of entry points; and
d) water ingress from surface water flooding, rainstorms, burst or leaking water mains, incomplete drainage and
escape of water from services.
7.1.7 The construction work should be phased so as to mitigate the extent of damage if an escape of water
or flooding occurs. Examples of good practice are as follows:
a) All areas below ground should be made weathertight prior to the installation of elements
susceptible to moisture;
b) Permanent drainage should be installed early with full functionality or, alternatively, specific
measures put in place to temporarily manage the discharge of water from the building;
c) Sump pump alarms, flow detection, water management devices and monitoring systems
including the Building Management System should be commissioned early. Any alert system
should be routinely checked or remotely monitored; and
d) Rainwater goods should be temporarily routed until final connection to permanent
underground drainage.
Mitigation of water damage requires rapid detection and quick isolation measures. Emergency
response procedures should be detailed and include equipment, such as spill kits, wet vacs, sump
pumps, squeegees, etc; these should be provided and stored on site.
7.1.8 Any incidents of water ingress should be fully investigated and documented, and measures should be
put in place to prevent any recurrence.
NOTE In many situations where water has been discovered in a basement that is still under construction, it might
not be possible to properly assess the performance of a basement waterproofing system until the building is closed.
In the event that unexpected conditions are discovered that were not apparent during
the site assessment and planning stage, these should be reported to the design team and
waterproofing specialist.
NOTE 2 Features such as made ground, archaeological or geological anomalies, undetected water course or
perched water tables might need to be given special consideration as they could affect the waterproofing design and
work schedules.
@seismicisolation
@seismicisolation
© THE BRITISH STANDARDS INSTITUTION 2022 – ALL RIGHTS RESERVED 25
BS 8102:2022 BRITISH STANDARD
2) precast concrete;
3) in‑situ concrete, either cast in form (plain, reinforced or prestressed) or embedded walls; or
b) base slab – constructed from concrete cast in situ, plain or reinforced, raft or other form; and
c) buried deck, where applicable – constructed from reinforced in‑situ concrete, precast concrete with an in‑situ
topping, or a steel composite slab, as appropriate.
For structures cast entirely below ground, or where the substructure extends beyond the
superstructure, the roof slab should have protection against water ingress (see 6.5). In addition,
there should be continuity linking the waterproofing to the horizontal damp proof course above
ground (see 6.2.1). In most situations, below ground waterproofing should continue to a minimum of
150 mm above finished external ground.
NOTE 2 Further guidance on construction methods for each type of waterproofing protection is given in Clause 8,
Clause 9 and Clause 10.
To avoid delays, additional costs and defects in the waterproofing systems, every effort should be
made at the planning and sequencing phase of the project to ensure that waterproofing works can be
carried out without obstruction or interruption.
Every effort should be made to prevent damage and maintain the integrity of structural underground
waterproofing during and after the construction phase.
Damage can occur accidentally or as a result of poor sequencing or inadequate planning; every effort
should be made to avoid damaging waterproofing elements.
If damage does occur to any waterproofing component or waterproofed structure, this should be
brought to the attention of the installing contractor and the waterproofing specialist immediately.
Any damage should then be assessed and properly documented. When necessary, rectification and
repair work should be designed, sequenced and undertaken to re‑establish the integrity of the
waterproofing system.
@seismicisolation
@seismicisolation
26 © THE BRITISH STANDARDS INSTITUTION 2022 – ALL RIGHTS RESERVED
BRITISH STANDARD BS 8102:2022
8.1.1 General
Barrier protection design should be based on an evaluation of:
a) the nature of the substrate(s);
b) the likely overall and local movements that might cause distress in the waterproofing barrier;
c) the ability of the barrier system to accommodate these movements;
d) the essential characteristics of the waterproofing system, e.g. bonded/unbonded, pre‑applied/
post‑applied, liquid‑applied or pre‑formed;
e) the need for external or internal application;
f) the effects of environmental contaminants; and
g) achievable continuity of waterproofing system.
A load‑bearing substrate should be capable of supporting the barrier material, even under sustained
water pressure, particularly around openings or service penetrations. A levelling or smoothing layer
should be applied to masonry structures, as required.
NOTE 2 There are two issues in regard to the possible influence of cracks on barrier performance. One relates to
cracks pre‑existing at the time of application and the ability of the selected system to initially bridge the crack.
Decisions based on the specific properties of the barrier material would be needed before deciding whether any
such cracks require pre‑treatment. The second issue is the ability of the selected system to accommodate cracks that
might form after application.
Remedial measures to fill significant voids or openings should be undertaken as the effect of
sustained water pressure forcing the barrier material into them might create a risk of failure.
@seismicisolation
@seismicisolation
© THE BRITISH STANDARDS INSTITUTION 2022 – ALL RIGHTS RESERVED 27
BS 8102:2022 BRITISH STANDARD
@seismicisolation
@seismicisolation
28 © THE BRITISH STANDARDS INSTITUTION 2022 – ALL RIGHTS RESERVED
BRITISH STANDARD BS 8102:2022
a) Example 1
b) Example 2
@seismicisolation
@seismicisolation
© THE BRITISH STANDARDS INSTITUTION 2022 – ALL RIGHTS RESERVED 29
BS 8102:2022 BRITISH STANDARD
c) Example 3
Key
1 Floor slab
2 Pile cap, as appropriate
3 Pile
4 Continuity of appropriate Type A systems through the structural elements
5 Type A
@seismicisolation
@seismicisolation
30 © THE BRITISH STANDARDS INSTITUTION 2022 – ALL RIGHTS RESERVED
BRITISH STANDARD BS 8102:2022
All Type A waterproofing barriers should be installed in accordance with the manufacturer’s
instructions, including any recommendations regarding:
a) protection from damage, following application and curing;
b) penetrations through the barrier, e.g. temporary works, drainage and service penetrations;
c) fixings, where these are necessary, e.g. machinery, first or second fix fit outs, electrical or pipe
work, cable, sprinkler or ventilation ducts;
d) application over joints in the substrate, e.g. expansion or movement joints, junctions between
different building elements or the intersections of buildings of different ages;
e) compatibility, durability and buildability, e.g. whether bonded materials are compatible with the
substrates, whether the complexity of a design precludes the use of materials that are difficult
to joint or shape, or if materials are susceptible to frost, moisture, heat or exposure to sunlight
where these are likely to affect the build; and
f) membranes should be fully bonded to:
1) prevent lateral migration of water from a defect as per Figure 9. This can be tested by
manufacturer to BS EN 1928 method A; and
2) provide resistance negative hydrostatic head (see DIN 1048/BS EN 1542).
In each case, the level of full bond is relevant to depth of use or water pressure.
Table 3 — Waterproofing barriers
b) hot‑applied (“torch‑on”
or bonded using a hot melt
bitumen adhesive); or
c) adhesively bonded
Liquid applied There are many types of liquid Full bond Can be post‑applied BS EN 15814
membranes applied membranes, which internally or
include one- or two‑part externally.
(see 8.2.3)
systems
Internal use has to
resist counter thrust
pressure
@seismicisolation
@seismicisolation
© THE BRITISH STANDARDS INSTITUTION 2022 – ALL RIGHTS RESERVED 31
BS 8102:2022 BRITISH STANDARD
• dry bentonite;
• polymer‑core products
Mastic asphalt These are applied in multiple Full or partial External BS EN 12970
membranes coats as a hot liquid bond
(see 8.2.5)
Cementitious These form an active coating Full bond External or BS EN 1504‑3
crystallization that penetrates and seals the internal pre- or
coatings capillaries and fine cracks post‑application
in concrete. They may be
(see 8.2.6)
applied as slurries, solutions
or powder coatings to concrete
surfaces
Cementitious These are generally applied in Full bond External or internal BS EN 1504‑2
multi‑coat renders, multiple coats as slurries to post‑application
toppings and concrete surfaces
coatings
(see 8.2.7)
NOTE Membranes should be fully bonded in order to:
a) prevent lateral migration of water from a defect as per Figure 9 (see also 8.2.2); and
In each case the level of full bond is relevant to depth of use or water pressure.
@seismicisolation
@seismicisolation
32 © THE BRITISH STANDARDS INSTITUTION 2022 – ALL RIGHTS RESERVED
BRITISH STANDARD BS 8102:2022
in‑situ concrete with secondary layers to resist water movement, or compartmentalization using
waterstops and/or resin injections.
A pre- or post‑applied membrane can be considered fully bonded if it prevents lateral migration of water
from a defect as per Figure 9 and is deemed fully bonded up to the depth of pressure outlined within the
test report.
Characteristics of sheet membranes for water tightness and lateral water migration can be assessed by
their performance to BS EN 1928 (Method B).
Figure 9 — Effect of bonded or partially bonded barriers
Key
1 Fully bonded barrier preventing water from tracking from a defect in the membrane to a crack/joint in
the supporting concrete wall
NOTE If the defect is coincident with a crack, the crack can be repaired with crack injection.
2 Partially bonded barrier allowing water to track from a defect
3 Defect in barrier
Substrates should provide full and stable support to the membrane during pouring of concrete.
The surface may be damp, but the membrane should not be laid into standing water.
Pre‑applied membranes remain exposed during the fixing of reinforcement and concrete placement;
damage resistance, UV exposure and contamination from dirt that could interfere with bonding to
concrete should be taken into account.
To ensure continuity of waterproofing, designers should verify full compatibility between pre- and
post‑applied membranes. The performance of all sheet membranes relies on effective lap sealing. Lap
sealing procedures under all site conditions should follow the manufacturer’s instructions.
@seismicisolation
@seismicisolation
© THE BRITISH STANDARDS INSTITUTION 2022 – ALL RIGHTS RESERVED 33
BS 8102:2022 BRITISH STANDARD
To ensure continuity of waterproofing, designers should verify full compatibility between pre- and
post‑applied membranes. The performance of all sheet membranes relies on effective lap sealing. Lap
sealing procedures under all site conditions should follow the manufacturer’s instructions.
Where continuity is required with other forms of Type A, Type B and Type C waterproofing, designers
should verify full compatibility of the systems.
NOTE 2 An additional protection layer is generally required to protect the liquid system from being damaged by
backfill activities and general site activities. This could be a plastic or bitumen type board, a composite drainage
sheet or extruded insulation.
Details on the preparation of the substrate, application rate, method and curing requirements should
be in accordance with the manufacturer’s recommendations.
8.2.4.1 General
Active core waterproofing should only be used where the liner remains confined between two
surfaces and cannot be left exposed. Active core liners should be firmly supported by a load‑bearing
structure so that external ground and water pressures are adequately resisted.
@seismicisolation
@seismicisolation
34 © THE BRITISH STANDARDS INSTITUTION 2022 – ALL RIGHTS RESERVED
BRITISH STANDARD BS 8102:2022
Active core liners should be laid onto a stable substrate, such as well compacted sub‑base, blinding
concrete, temporary or permanent formwork or directly to property line construction. Substrates
should provide full and stable support to the membrane during pouring of concrete. The site
conditions should be taken into account; the membrane should not be laid into standing water.
The manufacturer’s instructions should be followed.
@seismicisolation
@seismicisolation
© THE BRITISH STANDARDS INSTITUTION 2022 – ALL RIGHTS RESERVED 35
BS 8102:2022 BRITISH STANDARD
9.2.1.1 General
Concretes, with or without water resisting admixtures, should be designed to meet minimum design
requirements for structural use and durability in the ground, and be properly placed and compacted.
Reinforced concrete structures should be designed and detailed specifically to minimize
water ingress.
Where some seepage is tolerable (as Grade 1a), the provisions in tightness class 0 of
BS EN 1992‑1‑1 may be adopted.
Where Grade 1b is required, the maximum permissible through crack width of the concrete should
conform to BS EN 1992‑3:2006, tightness class 1.
Where higher waterproofing performance grades are required, additional measures (such as a
combined protection, water resisting admixture, pre- or post‑tensioning) should be used.
@seismicisolation
@seismicisolation
36 © THE BRITISH STANDARDS INSTITUTION 2022 – ALL RIGHTS RESERVED
BRITISH STANDARD BS 8102:2022
NOTE 1 A degree of resistance to water vapour transmission can be achieved dependent on section thickness and
tightness class.
NOTE 2 Seepage encountered might be associated with poor joints, poor workability and compaction, cracks due to
incorrect curing, restraint and shrinkage, or other discontinuities, such as service penetrations.
NOTE 3 Guidance on the design and detailing of water retaining concrete can be found in BS EN 1992‑3 and the
Concrete Centre publication “Concrete Basements” [6].
Autogenous crack healing can be expected to occur if the hydraulic gradient is less than five and the
crack width is less than 0.2 mm; for higher hydraulic gradients, crack widths should be reduced in
accordance with BS EN 1992‑3.
The following factors are of particular importance in achieving a water‑resistant concrete structure
and should be taken into account:
a) the design of the structure (general and detailed), and the specification of materials;
b) the quality of workmanship in preparing substrates and placing concrete;
c) pour sizes and aspect ratios;
d) curing;
e) the use of integral kickers cast monolithically with the slab; separate kickers present a high risk
of water penetration and should be avoided;
f) site logistics;
g) the condition of the formation, i.e. the formation should be clean with no running or
standing water;
h) material storage;
i) the close-fitting of formwork, the fixing of reinforcement(s) and the preparation of joints; and
j) implementation of an on‑site quality assurance programme.
Crack widths in concrete should be controlled by using the appropriate design of reinforcement,
concrete mix specification, construction joint detailing, pour layouts and aspect ratios (and shapes of
pours), pour sequences, construction supervision and curing (especially in relation to temperature).
The effects of shrinkage cracking due to early‑age thermal effects, drying and restraint locations
should be taken into account.
NOTE 4 For guidance on limiting crack widths, see BS EN 1992‑1‑1, BS EN 1992‑3 and CIRIA publication C766 [7].
Workmanship of placing and curing concrete, and the preparation of joints should comply with
BS EN 13670 and BS 8000‑2.
When selecting applied internal finishes, the residual moisture in the concrete should be taken into
account and sequencing should allow time for sufficient drying. Where appropriate, advice should be
sought from the manufacturer of the internal finishes. Moisture content and relative humidity should
also be assessed in accordance with BS 8204‑1.
@seismicisolation
@seismicisolation
© THE BRITISH STANDARDS INSTITUTION 2022 – ALL RIGHTS RESERVED 37
BS 8102:2022 BRITISH STANDARD
by each product to achieve these aims are quite diverse, it is not possible in this British Standard to give
specific guidance on their use.
See Table 9 of BS EN 934‑2:2009+A1:2012 for guidance on requirements for water resisting admixtures.
Manufacturers should be consulted as to the performance of a specific water resisting admixture
in reducing the risk of water penetration through a crack, possibly under considerable
hydrostatic pressure.
NOTE Areas at high risk of water ingress, such as penetrations and joints, would typically be addressed by design
(e.g. waterstops; see 9.2.1.4).
Where the waterproofing admixture has been assessed and certified by a UKAS‑accredited body or
a European Technical Approval body, certification information should be referred to for guidance on
use and the extent or limitation of technical benefit.
Other waterproofing components, e.g. waterstops and sealants, should be compatible with each other
and the waterproofing admixtures.
9.2.1.4 Waterstops
COMMENTARY ON 9.2.1.4
The principal types of waterstops can be classified as the following.
a) Passive sections:
1) polymeric profiles cast into the concrete on both sides of the joint, either at the concrete
surface or mid‑depth of the concrete section, to form a physical obstruction to water
transmission; and
2) steel water bar strips placed mid‑depth of the concrete section to form a physical obstruction
to water transmission.
b) Active or hydrophilic strips or crystallization slurries:
1) pre-formed profiles; or
2) sealant composition applied to the concrete joint at depth in the section.
NOTE The materials swell or give rise to crystal growth on contact with water providing an enhanced
obstruction. They can be used as a sole material or in a composite product with passive waterstop sections.
c) Permeable hose or other sections that are fixed to the construction joint surface before casting the
second pour, to facilitate the injection of a specialist sealing resin into the joint, when required.
Waterstops should be used to prevent water ingress at joints in the concrete structure, e.g. at
construction or day‑work joints, services or other penetrations (see Figures 2, 3, 4). The positioning
of the waterstop(s) (external and/or internal) should be appropriate for the method of construction
and the level of risk. Particular attention should be given to the use of waterstops at movement joints
(see 8.1.5).
Waterstops should be tested for the application, service conditions and groundwater
chemistry proposed.
Robust methods of fixing waterstops should be used to keep the components in place during
concreting operations. Correct orientation should be provided to facilitate adequate compaction
of the concrete around any internal components and to avoid creating paths for subsequent
water ingress. Where active or hydrophilic waterstops are used, care should be taken to prevent
premature swelling.
The full waterstop network should be designed such that a continuous system is created or is
appropriately terminated at ground level.
@seismicisolation
@seismicisolation
38 © THE BRITISH STANDARDS INSTITUTION 2022 – ALL RIGHTS RESERVED
BRITISH STANDARD BS 8102:2022
NOTE Special attention is required where active and passive waterstops are to be linked and act as a
continuous network.
9.2.2 Steel
Steel piles in either sheet or tubular form, or combined walls made up of high modulus elements
(tubes or HZ sections) with sheet pile infills may be used as the permanent structural wall in cases
where the pile clutch interlock system between individual sections can be adequately sealed from
blinding level to the full height, and sealed on both sides within any capping beam.
Steel structures should be designed and constructed in accordance with BS EN 1993‑5.
Sections should be formed of structural steel of a weldable grade conforming to the following
standards, as relevant:
a) BS EN 10248 (all parts) for hot rolled steel sheet piles;
b) BS EN 10249 for cold formed steel sheet piles;
c) BS EN 10210 (all parts) for hot finished hollow sections; or
d) BS EN 10219 (all parts) for cold finished hollow sections.
NOTE BS EN 10248 also covers special interlock sections, which are produced to allow hollow sections to be
connected together or to intermediate sheet piles.
For all embedded retaining walls, whether concrete or steel, the joint between the base slab and
the wall should be precisely detailed to achieve structural continuity consistent with the design.
This junction should be viewed as a three‑dimensional arrangement (see also 4.3.1), such that all
potential water paths can be identified and detailed.
The joint should be carefully detailed and waterstops should be attached to, and follow, the profile of
the wall in accordance with the manufacturer’s instructions.
NOTE 2 Grouting tubes may also be installed within a clean flush joint so that remedial grouting can be
undertaken, if necessary. Attempts to install grout tubes that maintain intimate contact with convoluted joints
might be unsuccessful; in this situation, a hydrophilic strip bonded to the joint with adhesive might be more suitable
(see also Clause 11).
@seismicisolation
@seismicisolation
© THE BRITISH STANDARDS INSTITUTION 2022 – ALL RIGHTS RESERVED 39
BS 8102:2022 BRITISH STANDARD
NOTE 1 The water penetration through well‑formed walls using these techniques is normally limited to, and
controlled by, the vertical joints rather than the flow through the concrete elements and there is thus little benefit
in designing concrete piled and diaphragm walls in accordance with the higher tightness classes specified in
BS EN 1992‑3.
Where secant pile retaining walls are used, specialist advice should be obtained as to the appropriate
system and construction method for the project.
NOTE 2 The joints between diaphragm wall panels can be enhanced by the incorporation of water bars, where the
performance requirements justify it. Such water bars can be effective at restricting water ingress via transverse
flow through the wall section but further attention might be necessary to deal with water flowing up the wall joints
inboard of the water bar location.
For integral protection, sheet pile interlocks should be welded or sealed with a suitable material in
accordance with BS EN 12063. Sealing welds along the interlock should be capable of accommodating
any movement that might take place. The welding process should be selected to suit the environment
to which the welds are exposed and the site conditions in which welding occurs.
NOTE 2 Steel sheet pile interlocks can be seal‑welded after installation to provide watertight structural walls.
The connection to the base slab should cater for any uplift forces in addition to providing a robust
barrier to water ingress. Horizontal sealants should be provided at the junction between the base slab
and the perimeter wall using suitable active or passive methods.
Where possible, sheet piles should be shop‑welded and subsequently driven in sets of two or three,
thus reducing the extent of site welding required. If welding is undertaken on site, only the exposed
length of the sheet piles should be treated. Appropriate working conditions should be provided and
the piles should be driven within acceptable deviations to form the joint.
NOTE 3 Failure to prepare the surfaces appropriately increases the risk of porosity in the welds, with reduction in
the degree of water resistance over time.
NOTE 4 Guidance on welding is given in BS EN 1011 (all parts) and BS EN ISO 15614‑1. Further guidance is also
given in the ICE’s Specification for piling and embedded retaining walls [1] and BS EN 1993‑5.
@seismicisolation
@seismicisolation
40 © THE BRITISH STANDARDS INSTITUTION 2022 – ALL RIGHTS RESERVED
BRITISH STANDARD BS 8102:2022
NOTE 2 For existing structures, see 5.2 and refer to a structural engineer.
Cavity drain membranes should be used in accordance with the manufacturer’s instructions.
In particular, the stud height or profile of the membrane should be selected in conjunction with the
manufacturer’s data and after considering the external hydrostatic pressure, the porosity of the
structure and the predicted rates of water ingress though the structure’s external fabric.
Before a cavity drain membrane is laid or fitted on walls and floors constructed of new concrete, the
concrete surface should be treated to reduce the risk of leaching of free lime or mineral salts so as to
avoid the obstruction of the drainage system.
@seismicisolation
@seismicisolation
© THE BRITISH STANDARDS INSTITUTION 2022 – ALL RIGHTS RESERVED 41
BS 8102:2022 BRITISH STANDARD
Drainage channels should ideally be installed at the wall floor junction around the perimeter of the
treated area.
Where channels cannot be installed local to the wall floor junction, where they are stepped in or away
from any other anticipated location of ingress, the depth and associated drainage capacity of the
intermediate drainage cavity should be maximized accordingly. Additionally, the requirement for and
feasibility of maintenance of the intermediate drainage space should be assessed.
Cross‑floor span channels should be included within larger footprints to reduce the distance over
which water drains to reach the discharge point(s).
Principally, membranes should be installed above the drainage channels; how this is achieved can
differ with the use of rebated chases or spacer materials to lift floor membranes above channel level.
NOTE 2 Either is an acceptable method with due consideration of the structure and an assessment of the probable
point of any ingress, with the ideal being that channels are positioned at anticipated points of ingress, such as wall
floor junctions and joints.
@seismicisolation
@seismicisolation
42 © THE BRITISH STANDARDS INSTITUTION 2022 – ALL RIGHTS RESERVED
BRITISH STANDARD BS 8102:2022
Sections of the membrane(s) fitted to the walls should be joined and sealed in accordance with the
manufacturer’s recommendations.
NOTE 2 The cavity drain membrane may be covered with a variety of wall finishes dependent on the design
requirements of the structure.
The drainage channel should be sealed using conventional Type A and B methods to isolate water
within from the slab, and where practical, such as in new construction, details should also isolate
slabs from the adjacent retaining walls.
The waterproofing specialist should take into account a number of factors when formulating a design.
a) Larger diameter (40 mm) continuity flow pipes are preferable, being less prone to clogging.
These should ideally be cast into the intermediate slab.
NOTE Where necessary, fire stopping is required to comply with relevant national Building
Regulations [8], [9], [10].
b) A drip detail should be included beneath to discourage water tracking laterally along the
underside of the slab. Omission of drip details places greater reliance on and requirement for
seal details between the head of the cavity membrane and the underside of the slab.
c) Distance between and maintenance of continuity flow pipes:
1) a series of pipes at reduced intervals assists in distributing water behind the membrane
beneath as opposed to encouraging localized concentrations;
2) it is unlikely that means of access for maintenance can be provided to each and every
continuity flow pipe, where these are formed at reduced intervals;
3) designers should decide on the requisite number of maintenance points, such that
the system can continue to function effectively if the pipes other than those which are
maintainable, reduce in efficacy;
4) increasing distance between continuity flow pipes is acceptable where the drainage detail
above the slab is suitably robust and duly considered by the waterproofing specialist; and
5) in existing structures, it is not viable to isolate suspended slabs from the retaining walls
which they bear into and where applicable, clients should be advised of the risk to formation
of a totally dry environment.
d) Bunds should ideally be formed in monolithically cast concrete.
NOTE Figure 10 gives an example of a multi‑level system.
@seismicisolation
@seismicisolation
© THE BRITISH STANDARDS INSTITUTION 2022 – ALL RIGHTS RESERVED 43
BS 8102:2022 BRITISH STANDARD
Key
1 Type A barrier protection 5 8 mm Cavity membrane
2 Concrete upstand 6 Over seal tape
3 Discharge pipe 7 DPC
4 Perimeter channel 8 Inspection/access port
@seismicisolation
@seismicisolation
44 © THE BRITISH STANDARDS INSTITUTION 2022 – ALL RIGHTS RESERVED
BRITISH STANDARD BS 8102:2022
NOTE 2 Open free drain cavities might require an additional vapour barrier.
Where ground gas/contaminants are present and Type C waterproofing protection (i.e. drained
cavities) are being considered, specialist advice should be sought during the design phase.
The presence of or proposals for services (pipes, cables) within the area of installation should be
identified, as these could complicate or prevent formation of an effective system. Penetrations
through inverted membranes should be avoided.
Where membrane is applied to vaults and barrel arched ceilings, support may be provided by
proprietary plug fixings and manufacturer advice should be sought on the correct fixing detail for this
application.
NOTE 2 In the case of vaulted ceilings, it can be more practical to effectively treat larger areas.
Defects within inverted systems are more prone to causing issues, and inspection/testing should be
undertaken to avoid this.
NOTE 3 The inherent depressurization of water associated with cavity drainage can mitigate defects (holes) within
vertically installed cavity membranes; however, where inverted, water ingress always runs over the membrane.
Inverted applications are generally deemed to be higher risk and, therefore, specialist designers and
installers should be included from the outset.
@seismicisolation
@seismicisolation
© THE BRITISH STANDARDS INSTITUTION 2022 – ALL RIGHTS RESERVED 45
BS 8102:2022 BRITISH STANDARD
NOTE The flood loop enables the pump system from the drained cavity to remain operational during flooding
periods and the discharge of the system is not reliant on valves which could leak and not prevent odours.
Key
1 Pump system 5 Pump discharge pipe
2 Basement 6 Flood loop
3 Combined sewer 7 Internal drainage to pump
4 Surface water manhole 8 Ground level
10.2.7 Pumps
For discharge via mechanical pumping, the number/type of pumps and sump capacity of the system
should be designed taking into account the usable void space of the cavity drain system, anticipated
rate of water ingress, distance/length of any discharge pipework and potential running cycles
of the pumps.
Battery back‑up pump systems should be included to protect in the event of power failure; such
systems could include high level alarms to forewarn in the event of a problem, which could alert via
local audible alarm or, where required, remote telemetric relays.
NOTE 1 Basement waterproofing pump systems are typically provided as a packaged unit comprising a
purpose‑designed pre‑formed sump liner or chamber with an integrated access cover unit, which houses, as a
minimum, dual (duty and standby) automatic float switch operated pumps. The pumps activate and discharge
water when it reaches a set height within the sump liner in accordance with the design requirements.
Pumps should always be located at the lowest point(s) within a structure, or externally in a sealed
sump where the invert level of the drainage into the sump is lower than the drainage channel
@seismicisolation
@seismicisolation
46 © THE BRITISH STANDARDS INSTITUTION 2022 – ALL RIGHTS RESERVED
BRITISH STANDARD BS 8102:2022
internally allowing collection of penetrating water by gravity, and then pumping this to a suitable
external discharge point which should be identified and approved.
Each pump should be individually fused and provided with a dedicated discharge pipe of a suitable
pressure rating.
Water should be discharged appropriately, ideally into a suitable drainage or attenuation system,
which can accommodate designed quantities of water and is not susceptible to flood, freezing or
surcharge back into the building.
Pump discharge directly into a combined sewer should not occur without appropriate consents, and
suitable non‑return valves. Consideration should be given to potential smells and vermin ingress.
Where contaminated water is anticipated, the appropriate discharge consents should be sought.
Requirements for servicing and maintenance should be incorporated in both the design and upon
completion and should be included in the Operation & Maintenance Manual (O&M).
The first inspection should be on completion of installation of the Type C system at handover and
commissioning.
The second inspection should be within the first three months after installation or as soon after
completion of building works that could affect the drainage installation, whichever is the sooner.
Service visits should be carried out no less frequently than annually.
In some circumstances it might be necessary to amend the frequency and scope of the service visits
considering findings from the first or second inspection; any changes to the schedule of planned
maintenance should be agreed with the client so that the service schedule is amended accordingly.
In circumstances where pumps are running for long periods of time, or where the system is subject
to silting or the deposition of free lime, the first inspection should be sooner, and more frequent
servicing might be necessary for a period of time thereafter.
Where pump activity has noticeably increased after installation, there should be further investigation
to identify the source of additional ingress.
@seismicisolation
@seismicisolation
© THE BRITISH STANDARDS INSTITUTION 2022 – ALL RIGHTS RESERVED 47
BS 8102:2022 BRITISH STANDARD
11 Remedial measures
11.1 General
NOTE 1 There are many causes of seepage in new and existing structures, principally poor design and/
or specification, defective materials, defective workmanship, deterioration of the structure, a change in the
external environment (e.g. rising groundwater or locally leaking sewers or water mains), or construction not
being completed.
The likelihood of seepage during the temporary conditions as a result of movement due to loading
and/or settlement of the structure during construction should be determined and taken into account.
NOTE 2 Adjacent construction works can also affect the pattern of groundwater flow and surface water run‑off.
A number of these factors can also combine to cause problems.
Many of these issues can be pre‑empted and should be addressed at the design stage with form and
feasibility of repair in mind (see Clause 4).
Before any remedial action is taken, the source of any water should be identified to
determine the cause.
NOTE 3 The correct diagnosis of the source is of vital importance, to establish whether faults exist within the
system as a whole, whether faults are localized, or whether water is bypassing an incomplete system.
@seismicisolation
@seismicisolation
48 © THE BRITISH STANDARDS INSTITUTION 2022 – ALL RIGHTS RESERVED
BRITISH STANDARD BS 8102:2022
3) composite and modular structures, such as precast and twin wall, and certainly masonry,
beam and block and ICF, have increased risk of failure and are potentially difficult to repair
so remediation can be extensive and costly; and
4) repairs to concrete should be carried out in accordance with the relevant part(s) of
BS EN 1504. All repair methods and materials should be approved by a structural engineer.
Strategies for repair should be taken into account at the design stage (see Clause 4).
The points above should be assessed irrespective of whether planned remedial treatment has been
included as a contingency measure.
Localized drainage should be taken into account in association with this work.
NOTE 4 Defects in internal type A systems are generally located at the position where dampness or seepage has
occurred and can be repaired or locally replaced.
Where access is not feasible, grouting should be done in accordance with 11.2 and 11.4.
The following should be taken into account before deciding on the method of repair:
a) the nature and size of the defect;
b) the likelihood of ongoing structural movement;
c) rate and pressure of water ingress;
d) the type of construction;
e) the moisture content of the substrate;
f) the temperature of the structure; and
g) the location and type of local structures/utilities.
NOTE 2 Options for repair can be one of or a combination of the following given in 11.2.2 and 11.2.3.
As grout or resin selection and application are specialized techniques, advice should be sought from
manufacturers and appropriately trained applicators prior to use.
Care should be taken when injecting areas to avoid damage or blocking to any services/utilities or
injecting at pressure that can damage the structure (see Clause 5).
b) bentonite;
d) expansive polyurethane.
@seismicisolation
@seismicisolation
© THE BRITISH STANDARDS INSTITUTION 2022 – ALL RIGHTS RESERVED 49
BS 8102:2022 BRITISH STANDARD
Holes should be drilled into the walls, floor or soffit of the structure inclined to intersect seepage
paths and the pressure or vacuum grout should be driven into the crack, joint or void to seal the leak.
NOTE 2 There are several materials suitable for use including:
a) polyurethane resin;
b) acrylic resin;
c) epoxy resin;
e) cementitious grouts.
Written records should be maintained of what materials have been used for the inclusion in operation
and maintenance manuals.
NOTE 3 Porous areas of concrete can sometimes be injected successfully, but severe honeycombing might require
the defect to be cut out and replaced.
NOTE 4 Often more than one phase of grouting or injection is needed as the seepage might have moved to defects
elsewhere in the structure or higher up in the walls.
Concrete should be prepared and grouts or mortars should be trowel, brush, spray or roller applied
in accordance with the manufacturer’s recommendations. As grout selection and application are
specialized techniques, advice should be sought from manufacturers and experienced applicators
prior to use.
NOTE 2 Suitable materials include:
a) cementitious systems;
NOTE 2 Surface preparation and the compatibility of the physical and chemical properties of the repair material
are important. Many types of repair materials are available, including:
@seismicisolation
@seismicisolation
50 © THE BRITISH STANDARDS INSTITUTION 2022 – ALL RIGHTS RESERVED
BRITISH STANDARD BS 8102:2022
The properties of the repair material should be selected to match the substrate as closely as possible,
particularly the shrinkage and thermal behaviour. Specialist advice should be obtained to select the
most suitable concrete repair system and to specify the required performance of the material to suit
the size, depth, and location of the area to be repaired.
Where proprietary mortars or concretes are used, they should be applied in accordance with the
manufacturer’s instructions, and any repair should be undertaken by experienced contractors.
11.5.2 Investigation/Diagnosis
The type and form of construction of the structure and the presence of voids and pathways for water
movement within the structural elements should be taken into account.
A detailed external survey should always be carried out (see 5.2).
@seismicisolation
@seismicisolation
© THE BRITISH STANDARDS INSTITUTION 2022 – ALL RIGHTS RESERVED 51
BS 8102:2022 BRITISH STANDARD
Bibliography
Standards publications
For dated references, only the edition cited applies. For undated references, the latest edition of the
referenced document (including any amendments) applies.
BS 5454, Recommendations for the storage and exhibition of archival documents
BS 6229, Flat roofs with continuously supported flexible waterproof coverings — Code of practice
BS 8485, Code of practice for the design of protective measures for methane and carbon dioxide ground
gases for new buildings
BS 8533, Assessing and managing flood risk in development — Code of practice
BS 85500, Flood resistant and resilient construction — Guide to improving the flood performance
of buildings
BS EN 934‑2:2009+A1:2012, Admixtures for concrete, mortar and grout –Concrete admixtures —
Definitions, requirements, conformity, marking and labelling
BS EN 752, Drain and sewer systems outside buildings — Sewer system management
BS EN 1011 (all parts), Welding — Recommendations for welding of metallic materials
BS EN 1504‑2, Products and systems for the protection and repair of concrete structures — Definitions,
requirements, quality control and evaluation of conformity – Part 2: Surface protection systems
for concrete
BS EN 1504‑3, Products and systems for the protection and repair of concrete structures —
Definitions, requirements, quality control and evaluation of conformity — Part 3: Structural and
non‑structural repair
BS EN 1928, Flexible sheets for waterproofing — Bitumen, plastic and rubber sheets for roof
waterproofing — Determination of watertightness
BS EN 12970, Mastic asphalt for waterproofing — Definitions, requirements and test methods
BS EN 13491, Geosynthetic barriers — Characteristics required for use in the construction of tunnels
and associated underground structures
BS EN 13967, Flexible sheets for waterproofing — Plastic and rubber damp proof sheets including
plastic and rubber basement tanking sheet — Definitions and characteristics
BS EN 13969, Flexible sheets for waterproofing — Bitumen damp proof sheets including bitumen
basement tanking sheets — Definitions and characteristics
BS EN 15814, Polymer modified bituminous thick coatings for waterproofing — Definitions and
requirements
BS EN ISO 15614‑1, Specification and qualification of welding procedures for metallic materials —
Welding procedure test – Part 1: Arc and gas welding of steels and arc welding of nickel and nickel alloys
Other publications
[1] INSTITUTE OF CIVIL ENGINEERS. Specification for piling and embedded retaining walls. Second
edition. London: Thomas Telford Publishing, 2017.
[2] CONSTRUCTION INDUSTRY RESEARCH AND INFORMATION ASSOCIATION. Guidance on
embedded retaining wall design. C760. London: CIRIA, 2017.
[3] GREAT BRITAIN. The Party Wall etc. Act 1996. London: The Stationery Office.
@seismicisolation
@seismicisolation
52 © THE BRITISH STANDARDS INSTITUTION 2022 – ALL RIGHTS RESERVED
BRITISH STANDARD BS 8102:2022
[4] THE BASEMENT INFORMATION CENTRE. Basements: Ground gases and structural
waterproofing. BSIC, 2021.
[5] BUILDING RESEARCH ESTABLISHMENT. Radon: Guidance on protective measures for new
buildings. BR211. Watford: BRE Press, 2015.
[6] THE CONCRETE CENTRE. Concrete basements. The Concrete Centre, 2012.
[7] BAMFORTH, P.B. Early‑age thermal crack control in concrete. C766. London: CIRIA, 2018.
[8] GREAT BRITAIN. Building Regulations 2000 and subsequent amendments. London: The
Stationery Office.
[9] GREAT BRITAIN. Building (Scotland) Regulations 2004, as amended. Edinburgh: The
Stationery Office.
[10] GREAT BRITAIN. Building Regulations (Northern Ireland) 2000, as amended. London: The
Stationery Office.
[11] WILSON, S., SOPP, G., MALLETT, H., and CARD, G. Retrofitting hazardous ground gas protection
measures in existing or refurbished buildings. C795. London: CIRIA, 2020.
Further reading
ASTM D5385/D5385M, Standard Test Method for Hydrostatic Pressure Resistance of
Waterproofing Membranes
BS EN 12390‑8, Testing hardened concrete — Depth of penetration of water under pressure
BS EN 1991, Eurocode 1: Actions on structures
BS EN 1996, Eurocode 6: Design of masonry structures
BS EN 13252, Geotextiles and geotextile‑related products — Characteristics required for use in
drainage systems
BS EN 13508 (all parts), Investigation and assessment of drain and sewer systems outside buildings
BUILDING RESEARCH ESTABLISHMENT. Radon — Guidance on protective measures for new dwellings
in Scotland. BR376. Watford: BRE Press, 1999.
BUILDING RESEARCH ESTABLISHMENT. Radon — Guidance on protective measures for new dwellings
in Northern Ireland. BR413. Watford: BRE Press, 2001.
GABA, A.R., SIMPSON, B., POWRIE, R. AND BEADMAN, D.R. Embedded retaining walls — Guidance for
economic design. C580. London: CIRIA, 2003.
GREEN, B.M.R., MILES, J.C.H. AND REES, D.M. Radon in Dwellings in Scotland: 2008 Review and Atlas.
HPA-RPD‑051. Didcot: Health Protection Agency, 2009.2)
2)
Available from www.hpa.org.uk.
@seismicisolation
@seismicisolation
© THE BRITISH STANDARDS INSTITUTION 2022 – ALL RIGHTS RESERVED 53
NO COPYING WITHOUT BSI PERMISSION EXCEPT AS PERMITTED BY COPYRIGHT LAW
• A single paper copy may be printed for personal or internal company use only.
Knowledge Centre
Standards purchased in hard copy format: Tel: +44 20 8996 7004
• A British Standard purchased in hard copy format is for personal or internal Email: knowledgecentre@bsigroup.com
company use only.
Copyright and Licensing
• It may not be further reproduced – in any format – to create an additional copy. Tel: +44 20 8996 7070
This includes scanning of the document.
Email: copyright@bsigroup.com
If you need more than one copy of the document, or if you wish to share the
document on an internal network, you can save money by choosing a subscription BSI Group Headquarters
product (see ‘Subscriptions’).
389 Chiswick High Road London W4 4AL UK
@seismicisolation
@seismicisolation