BAR BENDING SCHEDULE FOR ABIJO FENCE (RAFT AND COLUMN) 200m

Prepared by Clérg
No. OF LENGTH
NO. OF NO. LENGTH TOTAL LENGTH
MEMBER BAR MARK TOTAL SHAPE OFFCUT(mm) REMARK
ITEMS THUS (mm) (mm) Y10 Y12 Y16 Y20 Y25

COLUMN Y1201A 4 58 232 2000 464000 STRAIGHT 39 8000x1


Y1201B 4 58 232 2460 570720 STRAIGHT 58 2160x58
150

Y1002 11 58 638 800 510400 150 150 43 5600x1

150
Y1603/04/
RAFT 266 1 266 12000 3192000 STRAIGHT 266
05
670

Y1006 1000 1 1000 2000 2000000 230 230 167 4000x1

670
1430
150 150 334 1920x333 +
Y1007 1000 1 1000 3360 3360000
8640x1
1430
Y1608/09 114 1 114 12000 1368000 STRAIGHT 114
TOTAL 544 97 380 0 0

TONNAGE FROM APP TONNAGE


REINFORCEMENT
SCHEDULE REQUIRED
Y10 4.814159292 5
Y12 1.043010753 1
Y16 7.307692308 8
Y20 0
Y25 0
13.16486235 14