1. Suppose that the following data is the Activities and Predecessors of a given project I
Immediate Time in
Activity
Predecessors Week
A — 2
B — 3
C A 2
D A, B 4
E C 4
F C 3
G D, E 5
H F, G 2
2. Suppose that the following data is the Activities and Predecessors of a given project II
Time Estimates
Activit Preceding
y Activity Most
Optimistic Pessimistic
likely
A - 1 2 3
B - 8 10 12
C A 2 4 6
D B 1 2 3
E C,B 6 8 10
F D 4 3 8
1
3. Given the following list of activities, precedence relationships, normal and crash time
and cost of a project, when the indirect cost is birr 120 per day