Download as docx, pdf, or txt
Download as docx, pdf, or txt
You are on page 1of 2

Individual Assignments

1. Suppose that the following data is the Activities and Predecessors of a given project I

Immediate Time in
Activity
Predecessors Week
A — 2
B — 3
C A 2
D A, B 4
E C 4
F C 3
G D, E 5
H F, G 2

a) Draw the network diagram?


b) Determine the critical path

2. Suppose that the following data is the Activities and Predecessors of a given project II

Time Estimates
Activit Preceding
y Activity Most
Optimistic Pessimistic
likely
A - 1 2 3
B - 8 10 12
C A 2 4 6
D B 1 2 3
E C,B 6 8 10
F D 4 3 8

a. Determine the critical path


b. Detriment the average estimated duration of the project?
c. What is the probability of finishing the project within 20 weeks?

1
3. Given the following list of activities, precedence relationships, normal and crash time
and cost of a project, when the indirect cost is birr 120 per day

Preceding Time Cost


Activity
activity Normal Crash Normal Crash
A _ 6 4 500 620
B _ 4 2 300 390
C A 7 6 650 680
D A 3 2 400 450
E B,C 5 3 850 1000

a. Calculate the cost slope?


b. Draw the network diagram?
c. Determine the project completion time?
d. Determine the critical path?
e. Construct a least cost schedule for the network (Crash it)?

You might also like