Which of the following is charged with high voltage in ESP collecting electrode | Discharge electrode | Collecting frame GD screen 2
Flue gas enters ESP after which equipment: Economiser APH LTSH Aeheater 2
Mechanical hitting for dislodging ash inside ESP is termed as: Disintegration Impact Rapping Driving 3
Which dass of Insulation is most common for Electrical induction
motor? F ¥ 4 E i
A combination of eddy current and hysteresis losses within stator is
known as? stator losses Core Losses rotor losses stray losses 2
Which type of loss remains constant with increase in percentage
loading of motors ? stator losses Core Losses rotor losses stray losses 2
How do we select the rating of a motor? slightly higher than matching the Slightly lowerthan |25% higher than
highest load highest load. highest load lowest load. 3
Which i ine device i itch > circuit Bresk. Current Potential
ich is nota sensing device in switchgear ? ircuit Breaker
é e Transformer Transformer cvT 1
Ultra high Voltage level starts from 1100 kW and higher. 785 kW and higher 345 kV and Higher 2200 kV and higher. 1
Which medium is treated as the ideal for Circuit breaker? ail Air sre Vacuum 3
Breaker Operates on fault current and isolator operates on Load
Current TRUE FALSE i
. o. . Transmit the Control &
Which of the following is not a purpose of switchyard? electricity Protection communication Frequency control |a
. Bogie Open Bogie |Bogie GpenBogie |Bogie OpenBogie Bogie Out Bogie
What is the full form of BOBR ? Return Direction Reverse Discharge |Rewerse Discharge |Aetum Direction 3
Coal size in Crusher Output is 25mm 15 mm 20mm 22mm 3
The equipment responsible for transferring Coal from Conveyor
to
Bunkers is called Paddle Feeder ‘Grizzly Feeder Stacker Tripper 4
. Emergency Push Early Protection Emergency Pausing
The full Form of EB is Button Bell Button End Protection Bell |1
Linear Heat Sensing Linear Heat Shorting Linear Heat shunt Linear Heat Sensing
In Conveyor fire fighting system LHSC Stands for
cable Cord Cable Cord 1
Protect Conveyor
Full form of Conveyor protection PCS is Part Control System |Post Card System = Pull Cord Switch Switch 3
oo . Increase loading on | Decrease loading on|Crushing Coal Prior |Coal Quality
The purpose of vibrating Screen Feeder is to Crushers ‘Crushers to Crusher Improvement 2
ESP hoppers emptiness to be ensured in every shift True FALSE i
In NTPC Dadri Ash Handling system, what isthe mode of ESPhoppers |Wetmodesystem |Drymodesystem = |Wetmode
& Dry none ofthe above |2
evacuation? mode both
The equipment/system which works both under vacuum as well as Wacuum Purp Airlock Tank Vacuum conveying |Buffer Hopper 2
pressure ash conveying systems is pipeline
Ina vacuum ash conveying system pneumatic operated MHV([material | Installed below Installed at the end | Installed below ESP | installed before 3
handling valve) is buffer hopper ofvacuum hopper WaCcUUM PUP
conveying pipeline
Where is the first area in the boiler system that fly ash is collected for .
Bottom ash hopper | Economizer hopper |E5P hopper APH hopper 2
disposal?
Capacity of a conveyor is designed based on the coal consumption of 16 hours at rated 12 hours at rated 24 hours at rated 10 hours at rated
the boilers and per day working of conveyor upto capacity capacity capacity capacity
Dry fly ash is conveyed from plant area to main loading silo By conveyor belts | By trucks conveying conveying
pneumatically pneumatically
throurh mings throush nino:
Submerged Scraper Chain Conveyor System used to remove bottom . . . 1
ash generated in furnace is run continuously intermittently
Total slurry Total slurry Total slurry Total shurry 2
ifin aash slurry pump disposal series, there are four pumps in a series |disposal shall be disposal shall be disposal shall be disposal shall be
and each pump is of 600 m3/hr capacity and developing 4 ke/cmz 600 m3/hrata 600 m3/hrata 2400 m3/hrata 2400 m3/hr ata
pressure pressure of 4 pressure of 16 pressure of4 pressure of 16
bef leoienn> kecicen> keofcrn?
Which electrical parameters stay constant for both primary and Frequency and Frequency and MVA.|MVA rating and 3
. P ¥ m ¥ quency Current and Voltage eal ¥ E
secondary windings of transformer. Current rating Current.
An auxiliary ofa transformer which is used to cater te volumetric pressure Relief +
expansion of transformer oil resulting due to increase / decrease in Conservator Buccholz Relay . Breather
. - - . device (PRD)
ambient temperature and loading condition of the transformer is:
“ - oe . 4
Core Type and Shell type construction are types. of construction of... Winding Tank Bushing Core
. - - . - . . - High Breakd 4
A transformer oil has a desirable quality of: High viscosity Low Viscosity ‘gn Breekeown Both (b) and [c)
Voltage strength
i
The following transformer accessory operates on account of are .
Buccholz Relay. Conservator Silica Gelbreather = |Bushings
development of gases and surges on an event of transformer fault:
The-trarsformes that is used to provide power to unit's auxiliary station Transformer Unit Auxiliary Unit Service Rectifier 1
Lequipment before synchronizing of generator is: Transformer Transformer Transformer.
The following test conducted on transformer oil is used to determine Dea Moisture Content leo Furan analysis 1
the type of fault in the transformer:
Differential a
Fuse is used for which protection ? Over current Distance protection | protection None of above
Which of the following protection device senses the fault? Fuse isolator Circuit breaker Relay 4
Step Down the 3
Transformers are used for: Step up the voltage |voltage All of the abowe None of the above
CT (Current Transformer) is used for: Protection Metering Both | & il None of above 3
The equipment consuming highest Auxiliary power is Coal Crusher motor |Mill motor Seilet Feed Pump |tp fan motor 3
Provide insulation
What is the function of the Bushing iin a Transformer? Support the _ {te the conductor Sesling the Prevent moisture
external connection | exiting the transformertank = jentry
enclosure 2
Carbon mono oxide
Hydrogen gas purging inside the generator is to be accomplished by Low DO DM water |Nitrogen gas Bas Carbon dioxide gas ja
reduce hysteresis reduce eddy current | reduce copper reduce all the listed
A transformer core is laminated to loss losses losses losses 2
In alternators, cylindrical pole type roters are generally used with Both low and high
prime movers of High speed Low speed Medium speed speed i
Seal oil system can be stopped when generator is filled with Air Nz coz Both coz and N2 1
LABYRINTH GLAND
GENERATOR ROTOR SHAFT IS SEALED BY STUFFING BOX SEAL MECHANICAL SEAL |SEAL OIL 4
The SOOMW alternator stator core is cooled by DM water Air Hydrogen Nitrogen 3
Ensur ne the
Turbo-generators in thermal power plant has how many poles? 2 4)can be any number |None of these i
In large size alternators, the stator winding and rotor winding carries? JAC & Dc Dc & Ac Ac & AC None ofthe above ja
‘Gravity sand filter
Coagulation, flocculation, and sedimentation take place in clarifier [G5F) Bothofthe above |Nomeofthe above |1
Which of the following isa coagulant? chlorine Ferric alum Bothoftheabove |None of the above
Dissolved salts,
Turbidity and Turbidity and living | Living organisms turbidity and living
What impurities are removed in pretreatment? dissolved salts ‘organisms and dissolved salts jorganisms z
Turbidity and Residual chlorine Turbidity and Both cations and
Activated carbon filter (ACF) removes residual chlorine and cations anions anions 1
Dissolved CO), is removed in Degasser ACF SAC MB a
LP dozing is done at; condenser outlet LP heater outlet HP heater outlet Boiler drum 1
Silica limit in steam is: 10 ppb <20 ppb <30 ppb <40 ppb z
Metal temperature
Rate of Heat transfer from hot gas to cold steam is proportional to Surface area of Mean Temp Diff. b/w hot gas & Both 1&3
of tubes
heat transfer Cold Gas. 4
Device attached to Boiler for automatically relieving the pressure of steam is Economiser Safety Valve Drains Vents 2
N f th
Which of the following is desirable in boiler? Film boiling Nucleate boiling Botha &b Bese, e 2
LRSB(Log Retractable Soot Blowers) is used to clean Water walls Air preheaters SH/RH/Economiser tubes All of the above 3
Economiser
Water inlet to furnace waterwalls is from Boiler drum Bottom Ring Header |Riser tubes outlet 2
Boiler Tube leakage may occur due to Overheating Corrosion Erosion |All of the above 4
Drum internals consist of - Primary separators |Cyclone separators |Screen Dryers |All of the above 4
In evaporation process steam volume increase by ........! times of water
volume 1000) 1200) 1600 2000 3
Economiser preheates feedwater by utilising residual heat of Exit Flue gas (Combustion air Extraction steam Primary air 1
From low temp
Main steam comes out from the boiler super heater Platen super heater |Final super heater Reheater 3
Raw coal feeder
Coal feed rate to the pulveriser is controlled by Bunker feedrate _|speed Pulveriser speed Crusher speed 2
(On load cleaning of the furnace is done by Soot blowers Boiler washing Air blowing Non of the Above 1
Coal Crusher
Mill motor Boiler Feed pump motor ID fan motor
The equipment consuming highest Auxiliary power is motor
Turbine Barring gear]
Purpose of Lube oil System is Cooling of Bearings Joperation Lubrication of Bearings |All of the above
Which of these device boosts suction of Main oil Pump Foot Valve Extractor Injector Exhauster
Which of these pump
starts and
pomp el provide lubrication in
extend supply to emergency bus-
case of Total AC failure until DG
mop AOP EOP JOP
MOP is coupled with AC Motor (Turbine shaft IDC motor None of these
Lube oil supply Governing oil supply
Barring Gear takes oil supply from - header header Seal oil supply header None of these
JOP(Jacking Oil Pump) lifts rotor during Rolling Costing down Barring gear operation All of the above
What is the source of Steam for TDBFP IP Exhaust Steam =| Auxiliary Steam ICRH |All of the above
None of the
Which of the following hasa Barrel Type Casing HP Turbine IP Turbine LP Turbine above
Aerofoil: Workin,
Which of the following is a part of Blade Root part ® |shrouds All of the above
How many anchor points are there in Turbine Rotor 1 2 3 4
ICEP(Condensate Extraction Pump takes suction from ? Deaerator Hotwell Makeup water Tank Non of the above
The RPM of regenerative APH are in the range of 1to2 2toS 5 to 10 10 to 20
Oil carry probe in Regenerative APH is installed at Air Inlet side Air Outlet side Gas Inlet side Gas Outlet side
Circumferential
Which types of seals are not used in Air Preheaters Radial Seals Axial Seas Longitudinal Seals Seals
Which fan creates highest discharge pressure ID Fan FD Fan PA Fan Exhaust Fan
Variable Blade Pitch
The system fitted for flow control in Fan Inlet Guide Vane [Control Speed control All the above
Text Subject | Module Difficulty Correct | Option1 Option2 Option3 Option4
Option
In impulse turbine pressure drop occurs in ....... PPF PPF VSTPS-2 LEVEL1 2 moving blades nozzles guide blade all of theses
in reaction turbine pressure drop occurs in....... PPF PPF VSTPS-2 LEVEL1 moving blades nozzles guide blade moving blades & nozzles
In nozzles of impulse turbine, Velocity of steam jet .... PPF PPF VSTPS-2 LEVEL1 INCREASES decreases None of these
NF
remain constant
In moving blade of impulse turbine, Velocity of steam jet .... PPF PPF VSTPS-2 LEVEL1 INCREASES decreases remain constant None of these
In nozzles of impulse turbine, Pressure of steam jet .... PPF PPF VSTPS-2 LEVEL1 INCREASES decreases remain constant None of these
NWN N
In moving blade of reaction turbine, pressure of steam jet .... PPF PPF VSTPS-2 LEVEL1 INCREASES decreases remain constant None of these
Compounding is required in Turbine to control... PPF PPF VSTPS-2 LEVEL1 pressure temperature speed None of these
Velocity compounded impulse turbine is known as ...... PPF PPF VSTPS-2 LEVEL1 RateauTurbine Curtis Turbine Moore Turbine None of these
Pressure compounded impulse turbine is known as ...... PPF PPF VSTPS-2 LEVEL1 RateauTurbine Curtis Turbine Moore Turbine None of these
pressure & velocity compounded impulse turbine is known as ...... PPF PPF VSTPS-2 LEVEL1 RateauTurbine Curtis Turbine curtis & Moore Turbine None of these
Purpose of balancing drum in casing is to PPF PPF VSTPS-2 LEVEL1 Thrust balance temperature balance Flow balance all of theses
PB
Purpose of lacing wire in last stages in turbine rotors PPF PPF VSTPS-2 LEVEL1 enhance natural frequency damping vibrations thrust balencing option 1&2
Alignments of Turbine rotors caters... PPF PPF VSTPS-2 LEVEL1 Axial alignment radial alignment both option 1 &2 swing check
ww
Barring gear is required for... PPF PPF VSTPS-2 LEVEL1 uniform cooling Uniform heating both option 1 &2 None of these
During shut down, barring gear is required for PPF PPF VSTPS-2 LEVEL1 uniform cooling Uniform heating both option 1 &2 None of these
RB
during start up / light up of power plant unit, barring gear is required for PPF PPF VSTPS-2 LEVEL1 uniform cooling Uniform heating both option 1 &2 None of these
RN
Seal steam system incorporated in system to ..... In turbine casing PPF PPF VSTPS-2 LEVEL1 avoid air ingress venting reduction of bearing vibration all of theses
Labyrinth gland seals used for... PPF PPF VSTPS-2 LEVEL1 step be step drop of vacuum step be step drop of pressure magnification of temperatur None of these
RN
Effect on Specific volume of steam when propagated through various stages of turbine PPF PPF VSTPS-2 LEVEL1 INCREASES decreases remain constant None of these
Size of turbine blades increases from inlet to exit of steam turbine to accommodate... PPF PPF VSTPS-2 LEVEL1 increased pressure of steam increased temperature of steam increased sp. Volume of steam None of these
What is FGD? PPF PPF VSTPS-2 LEVEL1 Full Gas Disposal Full Gas Desulphurisation Flue Gas Desulphurisation & Disposal Flue Gas Desulphurisation
What is the purpose of installing of FGD plant? PPF PPF VSTPS-2 LEVEL1 Disposal of Ash Disposal of NOx Removal of SOx All of the above
FGD plant at Vindhyachal is designed for treatment of... PPF PPF VSTPS-2 LEVEL1 90% flue gas Up to 100% flue gas as per requirement 25% flue gas 50% flue gas
What input is required in absorber tank to absorb Sulphur from flue gas? PPF PPF VSTPS-2 LEVEL1 Gypsum powder Gypsum slurry Limestone powder Limestone slurry
The temp of inlet flue gas is reduced below 80 deg before entering inside absorber... PPF PPF VSTPS-2 LEVEL1 For cooling of flue gas duct To prevent heating of lime slurry To prevent the rubber lining of absorber tank For better chemical reaction
GGH in FGD plant is... PPF PPF VSTPS-2 LEVEL1 Gas to Gypsum Heater Gas to Gas Heater Gypsum to Gas Heater Gas to Gas Header
The size of crushed limestone used as input in wet type ball mill is approximately... PPF PPF VSTPS-2 LEVEL1 100mm & less 60mm & less 40mm & less 20mm & less
lf FGD plant is kept in service for treatment of 100% flue gas then... PPF PPF VSTPS-2 LEVEL1 The bypass damper will remain close The bypass damper will remain open The bypass damper doesn't have any relation with this It is never possible to open or
situation close the bypass damper
The quantity of gypsum produced per hour will depend on... PPF PPF VSTPS-2 LEVEL1 The quantity of lime slurry added in the absorber The quantity of sulphur in flue gas Both (Option 1 & 2) The quantity of ash in flue gas
Gypsum produced in FGD plant can be used in... LEVEL1 Textile industries Paper Industries Cement Industries Steel Industries
As per govt. regulations, the max. allowable SOx in chimney emmission of 500MW is... PPF PPF VSTPS-2 LEVEL1 200 mg/Nm3 2000 mg/Nm3 220 mg/Nm3 20 mg/Nm3
What is the function of gypsum bleed pump? PPF PPF VSTPS-2 LEVEL1 Remove excess water from gypsum Remove gypsum from absorber tank Remove lime slurry from absorber tank Remove chlorides from
N
absorber tank
What type of ball mills are installed in FGD plant? PPF PPF VSTPS-2 LEVEL1 Dry ball mill Semi dry ball mill Wet ball mill None of the above
Ww
Treated flue gas discharged in to environment through... PPF PPF VSTPS-2 LEVEL1 A separate chimney Same chimney i.e. boiler chimney Chimney is not reauired Directly from absorber tank
NBN
In which equipment, main reaction of SOx removal takes place? PPF PPF VSTPS-2 LEVEL1 Ball mill Booster fan GGH Absorber tank
What is the function of absorber re-circulation pumps? PPF PPF VSTPS-2 LEVEL1 Re-circulate gypsum slurry Re-circulate lime slurry Re-circulate water Re-circulate flue gases
How much NOx can be removed in FGD plant? PPF PPF VSTPS-2 LEVEL1 Zero % 50% 80% 100%
What is the main by-product of VSTPS FGD system? PPF PPF VSTPS-2 LEVEL1 Lime Calcium Carbonate Sodium Chloride Gypsum
The water used to cool lube oil coolers of turbine and genetor is called as a PPF PPF VSTPS-2 LEVEL1 CW water ECW water Service water Fire water
PPF PPF VSTPS-2
BE AN
The water used to cool ECW in PHE is called as LEVEL1 CW water ECW water Service water ACW water
SB) Boe
Which water is used for cooling of seal water in vacuum pump cooler ? PPF PPF VSTPS-2 LEVEL1 CW water ECW water Service water ACW water
Which water is used in condenser for cooling purpose? PPF PPF VSTPS-2 LEVEL1 Clarified water DM Water Raw Water drinking water
What is the type of cooling water system in 500 MW Units? PPF PPF VSTPS-2 LEVEL1 Open system Raw Water system DM Water system DM Water closed system
How many PHE are used in a unit of 500 MW PPF PPF VSTPS-2 LEVEL1 Two Three Four five
COOLING MEDIUM FOR THE GENERATOR EXCITER COOLER IS: PPF PPF VSTPS-2 LEVEL1 DM WATER AIR RAW WATER HYDROGEN
In which material PHE plates are made of ? PPF PPF VSTPS-2 LEVEL1 bronge brass stainless steal alloy steel
Capacity of Equipment Cooling Water overhead tank for T.G. auxiliaries. PPF PPF VSTPS-2 LEVEL1 1)30m3 2)20 m3 3)10m3 4)40 m3
Routine maintenance is not consist of PPF PPF VSTPS-2 LEVEL1 Performance of the pump should be observed The alignment of the pump unit should be Bearings should be lubricated Checking of impellers and shaft
daily Any abnormalities in operation should be checked occasionally
taken care of promptly
Conditions for Shutdown of the pump for trouble shooting, repair and possible overhaul PPF PPF VSTPS-2 LEVEL1 Poor in pump performance Excessive noise during pump operation Excessive vibration of pump all of the above
Which type of problem is found for trouble shooting in centrifugal pumps PPF PPF VSTPS-2 LEVEL1 mechanical driver related hydraulic all of the above
Mechanical troubles in centrifugal pumps is consist of PPF PPF VSTPS-2 LEVEL1 Failure to deliver water reduction in discharge Breakage of coupling loading of the prime mover
Hydraulic troubles in centrifugal pumps is consist of PPF PPF VSTPS-2 LEVEL1 Breakage of coupling Breakage of shaft Failure to deliver water Breakage of impeller
When will centrifugal pumps not able is discharge water. PPF PPF VSTPS-2 LEVEL1 Low discharge head Speed of electric motor or engine too low Bent shaft Gland Packing too tight
N
When will Overloading of Motor/ Engine is takes place PPF PPF VSTPS-2 LEVEL1 Gland Packing too tight Worn wearing rings Damaged impeller Defective foot valve
When will centrifugal pumps not able to provide enough discharge water PPF PPF VSTPS-2 LEVEL1 Bent shaft wearing rings wear out Pump speed too high Distorted casing
PN
Which among following is not a part of condensate system PPF PPF VSTPS-2 LEVEL1 BFP LP Heater CEP GSC
Condensate extraction pump is PPF PPF VSTPS-2 LEVEL1 Multistage centrifugal pump Single stage centrifugal pump Reciprocating pump Screw type pump
RP
Tubes of condenser are PPF PPF VSTPS-2 LEVEL1 U shaped tubes straight tube Spiral tube none of the above
WN
nos of tubes in stage-1 condenser of VSTPS PPF PPF VSTPS-2 LEVEL1 23938 24398 16700 19000
THE SPEED OF BOOSTER PUMP OF MOTOR DRIVEN BOILER FEED WATER PUMP IS PPF PPF VSTPS-2 LEVEL1 LESS THEN MOTOR SPEED. EQUAL TO MOTOR SPEED. MORE THAN MOTOR SPEED. NONE OF ABOVE.
PPF PPF VSTPS-2
BPN
Number of working and standby condensate extraction pumps LEVEL1 1 working & 2 standby 1 working & 1 standby 2 working & 2 standby 2 working & 1 standby
fuction of deaerator is/are PPF PPF VSTPS-2 LEVEL1 PROVIDE NPSH TO BFP BOOSTER PUMP. AS FEED HEATER & STORAGE TANK. REMOVES DISOLVED GAS. All of the above
Boiler feed pump is PPF PPF VSTPS-2 LEVEL1 Multistage centrifugal pump Single stage centrifugal pump Reciprocating pump Screw type pump
Were
Nos of Boiler feed pump in 500 MW units of NTPC VSTPS PPF PPF VSTPS-2 LEVEL1 1 MDBFP and 2 TDBFP 2 MDBFP & 1 TDBFP 3 MDBFP 3 TDBFP
WR
Which is not a part of BFP rotating assembly PPF PPF VSTPS-2 LEVEL1 Impeller Shaft Diffuser all of the above
Booster Pump of BFP is PPF PPF VSTPS-2 LEVEL1 Multistage centrifugal pump Single stage centrifugal pump Reciprocating pump Screw type pump
PPF PPF VSTPS-2
WEN
Which of the following zone is not a part of HP heater LEVEL1 Desuperheating zone condensing zone subcooloing zone none of the above
numbers and capacity of drip pumps PPF PPF VSTPS-2 LEVEL1 2 and 50% capacity each land 50% capacity 2 and 100% capacity each land 100% capacity
Function of booster pump is PPF PPF VSTPS-2 LEVEL1 To provide feed water to LPH To Ensure NPSH for BFP To Ensure NPSH for CEP None of the above
NN
Nos. of stages in boiler feed pump of 210 MW at NTPC VSTPS PPF PPF VSTPS-2 LEVEL1 9 11 14 7
Rotational speed of 500 MW CEP in VSTPS PPF PPF VSTPS-2 LEVEL1 3000 1485 4500 5200
WNYNY
Deaerator works on the following principle PPF PPF VSTPS-2 LEVEL1 carnot cycle henery's law pascal's law none of the above
The purpose of the balancing device in BFP is PPF PPF VSTPS-2 LEVEL1 TO provide NPSH to BFP To perform shaft sealing of BFP to balance the hydraulic axial thrust of the pump rotor none of the above
function of AOP in boiler feed pumps is to PPF PPF VSTPS-2 LEVEL1 Provide lubrication oil to bearing supply oil for scoop control of hydraulic Both 1 &2 None of the above
WwW
coupling
condensation of steam takes place in? PPF PPF VSTPS-2 LEVEL1 hotwell condenser vacuum pump PRDS
NY
CW flows through which ? LEVEL1 condenser shell hotwell condenser tubes none
Liquid Ring Vacuum Pump's impeller is ? PPF PPF VSTPS-2 LEVEL1 concentric eccentric both none
LP HEATER -1 IS SITUATED IN ? PPF PPF VSTPS-2 LEVEL1 CONDENSER HOTWELL SEPARATOR TANK NONE
NN
VACUUM IN CONDENSER IS CREATED BY? PPF PPF VSTPS-2 LEVEL1 VACUUM PUMP CONDENSATION HOTWELL NONE
LOCATION OF VACUUM PUMP? PPF PPF VSTPS-2 LEVEL1 TGOM T68.5 M TG17M NONE
PPF PPF VSTPS-2
WNP
HOW MANY AOP IN KWU TURBINE 500 MW? PPF PPF VSTPS-2 LEVEL1 1 2 3 4
HOW MANY JOP IN KWU TURBINE 500 MW? PPF PPF VSTPS-2 LEVEL1 4 3 2 1
HOW MANY EOP IN KWU TURBINE 500 MW? PPF PPF VSTPS-2 LEVEL1 1 2 3 4
NFP
LOCATION OF MOT ROOM? PPF PPF VSTPS-2 LEVEL1 TGOM T68.5 M TG17M NONE
HOW MANY VAPOUR FANS FOR TURBINE LUBE OIL SYSTEM? PPF PPF VSTPS-2 LEVEL1 2 3 1 NONE
WR
THE RECOMMENDED SPECIFICATION OF TURBINE LUB OIL? PPF PPF VSTPS-2 LEVEL1 SERVO PRIME - 36 SERVO PRIME - 56 SERVO PRIME - 46 SERVO PRIME - 16
MOP COMES IN SERVICE when turbine speed reaches ? PPF PPF VSTPS-2 LEVEL1 210 2800 540 none
WWNYN
FUNCTION OF JOP IS ? PPF PPF VSTPS-2 LEVEL1 LUBRICATION OF ROTOR ROTATION OF ROTOR LIFTING OF ROTOR NONE
LOCATION OF MOT CENTRIFUGE? PPF PPF VSTPS-2 LEVEL1 TG FLOOR FRONT PEDESTAL MOT ROOM TGOM
What type of boilers are used at 500 MW units of VSTPS? PPF PPF VSTPS-2 LEVEL1 Forced circulation dry bottom Water Tube All of the above
PPF PPF VSTPS-2
NPP
Which of these pressure parts components are located in second pass of the boiler? LEVEL1 Water wall Reheater Platen Super heater LTSH
Which of these is a common weld defect PPF PPF VSTPS-2 LEVEL1 Overheating Porosity Corrosion none
Text Subject | Module Difficulty Correct | Option1 Option2 Option3 Option4
Option
Size of coal after crushing in Crusher is (-)...... mm PPF PPF VSTPS-3 LEVEL1 3 250 400 20 100
Condition based monitoring by measurement of operating parameters that detect the beginning PPF PPF VSTPS-3 LEVEL1 3 Reactive Preventive Predictive none of the above
of degradation of critical equipment and routine checks of general equipment is
termed...................miantenance.
Snub Pulley is provided to ..............the wrap angle of belt. PPF PPF VSTPS-3 LEVEL1 Increase Decrease Both none of the above
Which type of bearings in idler is supposed to give better life-: PPF PPF VSTPS-3 LEVEL1 Seize Resistance Seize resistant and double sealed bearings Simple Ball Bearings none of the above
seeeaeeeaeeeeeeneee type idlers are installed adjacent to all pulleys to permit proper support of loaded belt PPF PPF VSTPS-3 LEVEL1 Transition Impact Self Cleaning none of the above
near the pulleys to prevent excessive stretch of the belt edges.
seeneeeeee idlers have a number of resilient type rubber discs for absorbing the shock of free PPF PPF VSTPS-3 LEVEL1 Transition Impact Self Cleaning none of the above
falling material at loading point
In order to clean carrying side of belt on return side, belt scrappers and rubber disc type ... PPF PPF VSTPS-3 LEVEL1 Transition Impact Self Cleaning none of the above
idlers are installed just after snub pulley.
Pulley Lagging Sheet is made from natural rubber and should have thickness of PPF PPF VSTPS-3 LEVEL1 10 12 14
Minimum angle of wrap for head pulleys is........ Degree. PPF PPF VSTPS-3 LEVEL1 180 200 220 240
The ..........is the most important structural section of the belt, as it contains tensile member to PPF PPF VSTPS-3 LEVEL1 Top Cover Caracaas Bottom Cover none of the above
handle the load of coal carried on the conveyor
Pull chord switches are installed only on one side of conveyor belt: true/false PPF PPF VSTPS-3 LEVEL1 True FALSE
Zero speed switches are also referred as under speed switches: true/false PPF PPF VSTPS-3 LEVEL1 True FALSE
Load Cells are an integral part of: PPF PPF VSTPS-3 LEVEL1 In Line Magnetic Separator Cross Belt Magnetic Separator Metal Detector Belt Weigher
Wheel mounted .............are provided below the track hopper for evacuating the coal from the PPF PPF VSTPS-3 LEVEL1 Mobile Trippers belt feeders Paddle feeders Fixed Tripers
hopper.
The wagon tippling system consists of wagon tippler, Side arm charger, underground hopper; and PPF PPF VSTPS-3 LEVEL1 Mobile Trippers Apron Feeders Paddle feeders Fixed Tripers
wees. /Vibrating feeder below the hopper for evacuating the material unloaded into the
hopper.
Slewing, Luffing and Long travel Motion are associated with which equipment PPF PPF VSTPS-3 LEVEL1 Mobile Trippers Stacker Reclaimers Paddle feeders Fixed Tripers
Normal Carrying Idlers/Troughing Idlers are installed at a gap of ....M PPF PPF VSTPS-3 LEVEL1 0.6 0.8 1.2 2
In emergency best option for a local operator to stop a belt conveyor is to PPF PPF VSTPS-3 LEVEL1 inform the control room run upto the local start/stop push bottom and push pull the cord of a pull cord switch run upto one pull cord switch
bottons and operate it
ROM coal stands for PPF PPF VSTPS-3 LEVEL1 Return of Mine Coal Run of Mine Coal Running of Mined Coal Rate of Mined Coal
Marshaling equipment used to pull a complete rake of 58 wagons is called Side Arm Charger : PPF PPF VSTPS-3 LEVEL1 TRUE FALSE
True/False
Impact Idlers are installed at gap of 0.6 m (True/False) PPF PPF VSTPS-3 LEVEL1 TRUE FALSE
Side Arm Charger is used to PPF PPF VSTPS-3 LEVEL1 Tipple the wagon tippler table for unloading Push empty wagons after unloading only Place loaded wagon wagon tippler table and push empty Support wagon from side with
coal from it wagons after unloading its Arm during unloading
Dribble conveyor d. Feeds coal from apron feeder to receiving conveyor: T/F PPF PPF VSTPS-3 LEVEL1 TRUE FALSE
A bulldozer in a coal handling plant is used for PPF PPF VSTPS-3 LEVEL1 feeding coal from heap into underground leveling the coal stock piles compacting coal in the coal stockpiles All three of above
hopper
A Switch Is Means For PPF PPF VSTPS-3 LEVEL1 Opening Closing Both None Of The Above
A Switch Should Always Operate PPF PPF VSTPS-3 LEVEL1 Manually During Short Circuit During Any Electrical Fault Manually And Fault Condition
an
Both
A Switchgear Include PPF PPF VSTPS-3 LEVEL1 Switching Device Control & Regulation Accessories Measurement And Protection All Of Above
Be) A) A) A) A
Function Of Switchgear PPF PPF VSTPS-3 LEVEL1 Carry Normal Load Current Make Or Break Fault Current Clearing Fault Current All Of Above
Parts Of The Switchgear PPF PPF VSTPS-3 LEVEL1 Power Switch Control And Protection System Measurement And Display All Of Above
Parts Of Protection System PPF PPF VSTPS-3 LEVEL1 Current Transformer (Ct) Potential Transformers (Pt) Protection Relay All Of Above
Surge Arrestor Is Provided In Switchgears To Protect From PPF PPF VSTPS-3 LEVEL1 Over Voltage Transient Over Current Short Circuit Earth Fault
MCB Stands For PPF PPF VSTPS-3 LEVEL1 Moulded Circuit Breakers Miniature Circuit Breaker Master Circuit Breaker Main Circuit Breaker
EN
Medium Voltage Stands For Voltages PPF PPF VSTPS-3 LEVEL1 2400V To 69000V 115Kv To 230Kv 345kv To 745Kv 745kv To 1100Kv
Switchgears Are Classified According To PPF PPF VSTPS-3 LEVEL1 Insulating Medium Current Rating Contruction Type All Of Above
SB) Bl woB
Which Chamber Of Switchgear Is Houses Low Voltage Components PPF PPF VSTPS-3 LEVEL1 Breaker Chamber Busbar Chamber Control And Protection Chamber CT/ PT Chamber
Chractrictics Of The Protection System PPF PPF VSTPS-3 LEVEL1 Speedly Clear The Fault Select The Faulty Zone Sentitive To The Fault All Of Above
Fault Clearing Time Does Not Include PPF PPF VSTPS-3 LEVEL1 Relay Pick Up Time Circuit Breaker Opening Time Relay Reset Time CB Arcing Time
During Any Electrical Fault In System PPF PPF VSTPS-3 LEVEL1 Fault Impedence Will Be Low Fault Current Increases Relay Sense The Fault All
NS
Short Time Rating Of Breaker PPF PPF VSTPS-3 LEVEL1 Current Which Breaker Can Carry Continuously Fault Current Which Can Be Break Maximum Current For Which The Fault Current Can Be Max Current During Closing Of
Handled Breaker
Auxiliary Power Supply System Includes PPF PPF VSTPS-3 LEVEL1 Stand By Power Control And Protection Supply Changeover Scheme All Above
Components Of Auxilary Power Supply Systems Are PPF PPF VSTPS-3 LEVEL1 DG Set Control Supply Tie Connection Among Switchgears All Of Above
Design Of Switchgears For Motor Are Decided On PPF PPF VSTPS-3 LEVEL1 Current Rating Kw Rating Power Factor None Of The Above
Normally Medium Voltage Switchgears Have Maximum System Fault Level PPF PPF VSTPS-3 LEVEL1 40 KA (Rms) 25 KA (Rms) 15 KA (Rms) 21 KA (Rms)
Normally System Neutral Earthing Of Medium Voltage Limits The Fault Current To PPF PPF VSTPS-3 LEVEL1 100 Ampere 200 Ampere 300 Ampere 400 Ampere
Bw
Which Is Not A Dc Motor Application In Power Plant PPF PPF VSTPS-3 LEVEL1 Seal Oil Pump Jacking Oil Pump Scanner Air Fan ID Fan
Emegency Mcc Supplied Power To PPF PPF VSTPS-3 LEVEL1 FD Fan ID Fan Jacking Oil Pump Ash Slurry Pump
PPF PPF VSTPS-3
Www
220V Charger Recieves Incoming Power From LEVEL1 Unit Service Switchgear Emergency Switchgear Both UPS
Which Is Not A Battery Manufacturer PPF PPF VSTPS-3 LEVEL1 Exide Amco Kirloskar HbI Knife
Capacity Of The Battery Bank Are Rated In PPF PPF VSTPS-3 LEVEL1 Ampere-Hour Volt Ampere None Of The Above
Be
MAIN FUNCTION OF THE SWITCHGEAR IS PPF PPF VSTPS-3 LEVEL1 CARRY NORMAL CURRENT MAKE OR BREAK NORMAL CURRENT FAULT PROTECTION SR NO 1 AND 2
WHICH IS NOT A PART OF SWITCHGEAR PPF PPF VSTPS-3 LEVEL1 CABLE POWER CIRCUIT CONTROL CIRCUIT MEASUREMENT
FB
CT/PT USED IN SWITCHGEARS ARE MAINLY PPF PPF VSTPS-3 LEVEL1 SWITCHING DEVICES PROTECTION DEVICES MEASURING DEVICES CONTROL DEVICES
WN
IN A SWITCHGEAR, MAIN POWER INTURRUPTING DEVICE IS PPF PPF VSTPS-3 LEVEL1 cT PT CIRCUIT BREAKER CONTROL TRANSFORMER
IN LT SWITCHGEARS FEEDING < 90 KW LOADS, CONTROL SUPPLY VOLTAGE IS PPF PPF VSTPS-3 LEVEL1 220V AC 110V AC 415V AC 24V DC
WN
FOLLOWING IS USED TO PROVIDE REMOTE MONITORING OF CURRENT IN SWITCHGEARS PPF PPF VSTPS-3 LEVEL1 cT PT CURRENT TRANSDUCER AMMETER
NORMALLY USED CONTROL VOLTAGE IN HT SWITCHGEARS IS PPF PPF VSTPS-3 LEVEL1 220V DC 24V DC 110V AC 110V DC
Nye
OPERATION OF FOLLOWING IS DONE DURING POWER SUPPLY DEAD CONDITION IN ANY PPF PPF VSTPS-3 LEVEL1 CONTACTOR ISOLATOR FUSES SURGE ARRESTORS
SWITCHGEAR
AIR BREAK CIRCUIT BREAKERS ARE USED UPTO PPF PPF VSTPS-3 LEVEL1 1000V 3300V 6600V 11000V
Bl Ww AB
WHICH CB IS NOT SUITABLE FOR FREQUENT SWITCHING OPERATIONS PPF PPF VSTPS-3 LEVEL1 ACB ABCB VACUUM CB MOCB
BPN)
THE MAIN FUNCTION OF FUSE IN SWITCHGEARS IS TO PPF PPF VSTPS-3 LEVEL1 PROTECT THE LINE OPEN THE CIRCUIT PREVENT EXCESSIVE CURRENT NONE OF THE ABOVE
RELAYS ARE DESIGNED TO RESPOND TO CHANGES IN PPF PPF VSTPS-3 LEVEL1 RESISTANCE VOLTAGE AND CURRENT TEMPERATURE ALL OF THE ABOVE
THERMAL OVER LOAD RELAYS ARE PROVIDED FOR PEOTECTION AGAINST PPF PPF VSTPS-3 LEVEL1 SHORT CIRCUIT OVERLOAD GROUND FAULT ALL OF THE ABOVE
The voltage appearing across the contacts after the opening of the circuit breaker is called PPF PPF VSTPS-3 LEVEL1 RECOVERY SURGE OPERATING ARC
IP PROTECTION IN CASE OF SWITCHGEARS STANDS FOR PPF PPF VSTPS-3 LEVEL1 INSULATION PROTECTION INGRESS PROTECTION INLET PROTECTION NONE OF THE ABOVE
Ny
SF6 GAS USED IN CIRCUIT BREAKER IS PPF PPF VSTPS-3 LEVEL1 VIOLET COLOR YELLOW COLOR COLOR LESS NONE OF THE ABOVE
Ww
MAX VOLTAGE LEVEL UPTO WHICH VACUUM CB ARE USED PPF PPF VSTPS-3 LEVEL1 6.6 KV 11 KV 33 KV 66 KV
BB
CB USED FOR EHV APPLICATIONS ARE PPF PPF VSTPS-3 LEVEL1 ACB OcB VCB ABCB
DURING ANY FAULT, FAULT IMPEDENCE IS PPF PPF VSTPS-3 LEVEL1 HIGH LOW DEPEND ON TIME NONE OF THE ABOVE
WN
MAXIMUM FAULT CURRENT AT WHICH A CB IS CAPABLE OF SWITCH OFF THE CIRCUIT IS CALLED PPF PPF VSTPS-3 LEVEL1 MAKING CAPACITY SHORT TIME RATING BREAKING CAPACITY NONE OF THE ABOVE
WHICH IS NOT PRODUCED DURING ARCING IN OIL CB PPF PPF VSTPS-3 LEVEL1 HYDROGEN NITROGEN METHANE ETHYLENE
PPF PPF VSTPS-3
BRN
FIXED AND MOVING CONTACTS IN OIL CB ARE OF LEVEL1 COPPER ALUMINIUM TUNGUSTUN CHROMIUM
DIELECTRIC STRENGTH OF AIR IS PPF PPF VSTPS-3 LEVEL1 30 KV /MM 0.3 KV /MM 0.03 KV / MM 3KV/MM
WHICH CB IS WELL SUITED FOR SWITCHING OF TRANSFORMERS AND REACTORS PPF PPF VSTPS-3 LEVEL1 ACB MOCB SF6 CB OIL CB
WwW
CB OPERATION TIME IS GENERALLY PPF PPF VSTPS-3 LEVEL1 1 SEC 50 m SEC 500 m SEC 200 m SEC
NY
THE ARC VOLTAGE PRODUCED BY AN AC CIRCUIT BREAKER IS ALWAYS PPF PPF VSTPS-3 LEVEL1 IN PHASE WITH ARC CURRENT 90 DEGREE LAGGING WITH ARC CURRENT 90 DEGREE LEADING WITH ARC CURRENT NONE OF THE ABOVE
PPF PPF VSTPS-3
BWR
INSULATION RESISTANCE OF HV CB IS LEVEL1 1 MEGA OHM 10 MEGA OHM 100 MEGA OHM 1000 MEGA OHM
ARC IN ACB IS INTERUPTED AT PPF PPF VSTPS-3 LEVEL1 MIN VOLTAGE MAX VOLTAGE MAX CURRENT ZERO CURRENT
A FUSE RATING IS GENERALLY EXPRESSED IN TERMS OF PPF PPF VSTPS-3 LEVEL1 CURRENT VOLTAGE KVA KW
FF
A FUSE IS CONNECTED IN THE CIRCUIT IN PPF PPF VSTPS-3 LEVEL1 PARALLEL SERIES EITHER SERIES OR PARALLEL NONE OF THE ABOVE
PPF PPF VSTPS-3
WNNY
Power transformers are designed to have maximum efficiency at PPF PPF VSTPS-3 LEVEL1 Full load 50% load 80% load no load
&
Lamination of transformer core is made of PPF PPF VSTPS-3 LEVEL1 Cast lron Silicon Steel Aluminium Cast Steel
PN
Breather is provided in a transformer to PPF PPF VSTPS-3 LEVEL1 Absorb moisture of air during breathing provide cold air in the transformer The filter of transformer oil None of above
Which of the following losses varies with the load in the transformer PPF PPF VSTPS-3 LEVEL1 Core loss Copper loss Both core & copper loss None of the above
WN
Transformer core are laminated in order to PPF PPF VSTPS-3 LEVEL1 reduce hysteresis loss reduce hysteresis & eddy current loss minimize eddy current loss Copper loss
The open circuit test in a transformer is used to measure PPF PPF VSTPS-3 LEVEL1 Copper loss Winding loss Total loss Core loss
NB
A star connected three phase transformer is provided with tertiary delta connected winding PPF PPF VSTPS-3 LEVEL1 Second harmonic of exciting current Third harmonic of exciting current Fifth harmonic of exciting current Seventh harmonic of exciting
which allows the flow of current
The size of a transformer core will depend on PPF PPF VSTPS-3 LEVEL1 Frequency Area of the core Flux density of the core material All of the above
Natural oil cooling is used for which transformers rating PPF PPF VSTPS-3 LEVEL1 3MVA 20 MVA 25 MVA 5SOMVA
BWRre
For Generating Transformer ,which type of connection is used PPF PPF VSTPS-3 LEVEL1 Delta/star star/delta star/star delta/delta
Noise level test in a transformer is a PPF PPF VSTPS-3 LEVEL1 Special test Routine test Type test None of the above
The chemical used in breather is PPF PPF VSTPS-3 LEVEL1 Asbestos fiber Silica sand Sodium chloride Silica gel
Ifa transformer is continuously operated the maximum temperature rise will occur in PPF PPF VSTPS-3 LEVEL1 Core Windings Tank Any of the above
WwWrhyY
Part of the transformer which is most subject to damage from overheating is PPF PPF VSTPS-3 LEVEL1 lron core Copper winding Winding insulation Frame or case
A transformer transforms PPF PPF VSTPS-3 LEVEL1 Voltage Current Current and voltage Frequency
Which of the following does not change in a transformer PPF PPF VSTPS-3 LEVEL1 Current Voltage Frequency All of the above
BW
The transformer ratings are usually expressed in terms of PPF PPF VSTPS-3 LEVEL1 Volts Amperes kw kVA
Bucholz relay give warning and protection against PPF PPF VSTPS-3 LEVEL1 electrical fault inside the transformer Electrical fault outsidethe transformer for both inside & outside none of the above
NF
Two transformer share the load depends upon PPF PPF VSTPS-3 LEVEL1 leakage reactance per unit impedence efficiences rating
Text Subject Module Difficulty |Correct |Option1 Option2 Option3 Option4
Option
Under speed switch operates PPF PPF VSTPS-4 LEVEL1 1 When the belt speed falls When the belt speed falls When the belt speed When the belt speed increases
by 85% of rated speed by 15% of rated speed increases by 15% of by 85% of rated speed
rated speed
Separation of magnetic metal pieces from coal at the conveyor belt discharge pulley PPF PPF VSTPS-4 LEVEL1 Suspended Magnet CBMS ILMS Metal Detector
is done by
Coal Sampling equipment consists of PPF PPF VSTPS-4 LEVEL1 primary sampler, primary sampler, primary sampler, mini primary sampler, secondary
secondary sampler, VGF, secondary sampler, mini crusher, small conveyors, sampler, small conveyors, screw
small conveyors, screw crusher, small conveyors, screw conveyors conveyors
conveyors screw conveyors
Slippage of belt at drive pulley, other pulleys cannot be due to PPF PPF VSTPS-4 LEVEL1 Presence of oil or water Belt overloading Belt underloading Inadequate tension on take up
on non-carrying surface pulley
of belt
Belt running out of centre with sway cannot be due to PPF PPF VSTPS-4 LEVEL1 Coal not falling in the Self aligning idlers jammed, Belt Joint not aligned More than required tension on
centre of the belt not functioning, their side take up pulley
rollers missing
If a motor takes start but belt conveyor does not take start, the possible reason can PPF PPF VSTPS-4 LEVEL1 Inadequate oil in the Failure of gear coupling Belt overloaded Any of the above reasons
be due to fluid coupling
High vibration of crusher bearings, foundation, floor cannot be due to PPF PPF VSTPS-4 LEVEL1 Broken crusher hammers Loose bolts of plummer Misalignment of drive High temperature of oil in fluid
blocks of its bearings coupling coupling
In order to prevent fugitive dust emission from coal stock piles PPF PPF VSTPS-4 LEVEL1 Coal stockpiles should be Compaction of coal Provision of green belt All the above mentioned steps
sprayed with water stockpiles should be done and buffer zones around should be taken
during stacking and layer by layer coal stockpiles should be
afterwards made
While tightening a nut with an adjustable wrench... PPF PPF VSTPS-4 LEVEL1 The wrench should be The wrench should be The Wrench can be The Wrench to be operated
pulled toward you pushed away fromyou operated eitherway only from adistance
In emergency best option for a local operator to stop a belt conveyor is to PPF PPF VSTPS-4 LEVEL1 inform the control room run upto the local start/ pull the cord of a pull run upto one pull cord switch
stop push bottom and push cord switch and operate it
bottons
Gas cylinder should never be handled holding from their PPF PPF VSTPS-4 LEVEL1 Body Base Handle Valve
Which of the following is a fire hazard in coal conveyors PPF PPF VSTPS-4 LEVEL1 Fluid coupling failures Overfilled Gearbox Loosely laid wires/cables All of the above
with exposed joints
Which of the following is a fire hazard in coal conveyors PPF PPF VSTPS-4 LEVEL1 Maintenance activities Friction caused by Jammed Self ignition of All of the above
involving welding / gas idler accumulated coal dust at
cutting leading to weld concave contours of
spatter on coal/ conveyors.
conveyor.
Cooling tower Effectiveness is the Ratio of PPF PPF VSTPS-4 LEVEL1 Range/(Range + Approach /(Range + Range/Approach Approach/Range
Approach) Approach)
A Cooling tower reduces the water temperature close to PPF PPF VSTPS-4 LEVEL1 Dry bulb temp. Ambient wet bulb Dew point temperature None of the above
temperature.
L/G Ratio in a Cooling tower is the ratio of PPF PPF VSTPS-4 LEVEL1 Water flow rate and air Length and girth Length and temperature air mass flow rate Water flow
mass flow rate gradient rate and
Ratio of dissolved solids in circulating water to the dissolved solids in makeup water is PPF PPF VSTPS-4 LEVEL1 Liquid gas ratio Capability Effectiveness Cycle of concentration.
termed as
Purpose of blowdown is to PPF PPF VSTPS-4 LEVEL1 Remove the heat from Maintain the Cold Water Limit the increase in the To reduce the entrainment of
Hot water outlet temperature concentration of solids Water droplets in Air
in the water due to
evaporation
The Purpose of fill is PPF PPF VSTPS-4 LEVEL1 To prevent the water To provide the required To reduce the To change the direction of Air
droplets splashing out of surface area for heat entrainment of Water inlet flow in the uniform manner
the tower transfer between air and droplets in Air
the water
FRP fan blades are used in cooling tower applications because PPF PPF VSTPS-4 LEVEL1 It needs low starting Easy handling and Energy Efficient than All of these
torque maintenance Metal blades
Cooling tower acceptance testing procedures are recommended by PPF PPF VSTPS-4 LEVEL1 CTl API ASME ISO
Better indicator for cooling tower performance is PPF PPF VSTPS-4 LEVEL1 WBT DBT Range Approach
A Cooling tower is said to be performing well when PPF PPF VSTPS-4 LEVEL1 Approach is closer to Range is closer to zero Approach is larger than Range is larger than design
zero design
On which principle cooling tower works PPF PPF VSTPS-4 LEVEL1 Mass Transfer Heat Transfer Both of these None of these
Which one of the following has maximum effect on Cooling tower performance PPF PPF VSTPS-4 LEVEL1 Fill media Drift Louvers Casing
Which one of the following fill material is more energy efficient for cooling tower: PPF PPF VSTPS-4 LEVEL1 Splash fill- PP Grid type Film-fill Splash fill- V bar type None of the above
Approximately about of cooling in cooling tower is through the sensible PPF PPF VSTPS-4 LEVEL1 20% 5% 80% 40%
cooling:
The Cooling Water Temperature leaving a tower increases as the Wet Bulb PPF PPF VSTPS-4 LEVEL1 Increases Decreases Remains same Data not sufficient
Temperature
In cross flow cooling towers, the air moves through the fill across the PPF PPF VSTPS-4 LEVEL1 vertically upward horizontally vertically downward None of the above
downward fall of the water:
The Purpose of Drift eliminators in cooling towers is PPF PPF VSTPS-4 LEVEL1 To prevent the water To provide the required To increase the To change the direction of Air
droplets splashing out of surface area for heat entrainment of Water inlet flow in the uniform manner
the tower transfer between air and droplets in Air
the water
Travelling water screens are used in CW system to PPF PPF VSTPS-4 LEVEL1 To guide the direction of To remove the debris from To prevent cavitation in None of the above
water flow towards the water flowing towards the pumps.
pump pump suction
For high flow requirement, pumps are generally operated in PPF PPF VSTPS-4 LEVEL1 Parallel Series Botha &b None of the above
What is the principle of measurement in Thermocouple PPF PPF VSTPS-4 LEVEL1 RAMAN EFFECT SEEBECK EFFECT PELTIER EFFECT Aharonov-Bohm effect
K Type thermocouple comprises of which 2 metals PPF PPF VSTPS-4 LEVEL1 Copper-Constantan Chromel-Constantan Chromel-Alumel Platinum-Rhodium
What is recommended pH for Drum Water (at 25 DEG C) PPF PPF VSTPS-4 LEVEL1 8.8-9.3 7,2-8.0 8.0-8.6 6.4-7.2
How is Air Flow measured in Boiler Ducts? PPF PPF VSTPS-4 LEVEL1 Pitot Tube Orifice Venturi Aerofoil
Which instrument provide correct monitoring of Bearing health? PPF PPF VSTPS-4 LEVEL1 Bearing Temperature Bearing Vibration Oil Flow Oil Temperature
A pointer of an instrument once deflected returns to zero position, when the current PPF PPF VSTPS-4 LEVEL1 Action of gravity Mass of the pointer Controlling Torque Damping Torques
is removed due to
If Eddy current damping is to be used, the disc of the instrument should be PPF PPF VSTPS-4 LEVEL1 Conducting and Non conducting and non conducting and non conducting and non mangetic
Magnetic magnetic magnetic
The function of a transducer is to PPF PPF VSTPS-4 LEVEL1 Modify the input signal Convert primary signal into Codify/Decodify Input Amplify the input signal
a more useful quantity, signal
usually an electrical
impulse
In a measuring system what is the term used to specify difference between higher PPF PPF VSTPS-4 LEVEL1 Threshold Range Drift Span
and lower calibration values
Accuracy and Precision are dependent on each other, comment true or false PPF PPF VSTPS-4 LEVEL1 TRUE FALSE
In a measuring system, quantity under measurement is termed as PPF PPF VSTPS-4 LEVEL1 Sonsors Measurand Indicators Controllers
In a measurement what is the term used to specify the closeness of two or more PPF PPF VSTPS-4 LEVEL1 Threshold Fidelity Accuracy Precision
measurements
Which of the following conversions takes place in Bourdon tubes PPF PPF VSTPS-4 LEVEL1 Pressure to Voltage Pressure to Strain Pressure to Force Pressure to displacement
Which of the following converts flow into rotational motion PPF PPF VSTPS-4 LEVEL1 Rotameter Flow system Rotating vane system None of the above Both a and b
What of the following conversions takes place in Float element PPF PPF VSTPS-4 LEVEL1 Level to Voltage Level to force Level to Displacement none of the above
In a closed container type level measuring system, pressure at top of container is due PPF PPF VSTPS-4 LEVEL1 Atomospheric Pressure Vacuum Pressure Liquid Pressure Vapor Pressure
a
to
Seismic displacement transducers are not suitable for measuring PPF PPF VSTPS-4 LEVEL1 Vibrating Velocities Dynamic Velocities Static Velocities none of the above
Damper system is used to PPF PPF VSTPS-4 LEVEL1 For indication Limit oscillation Produce displacement Produce oscillations
BNN
Output of bimettalic element will be PPF PPF VSTPS-4 LEVEL1 Strain Displacement Voltage Pressure
Functions of Governing System are PPF PPF VSTPS-4 LEVEL1 To control the initial run To control the turbine load To provide protective ALL
up and synchronization when running in parallel gears to ensure the safe
of the machine with other generating sets operation of the turbine
Function of Jacking Oil PPF PPF VSTPS-4 LEVEL1 Jacking of TG shaft Lurication For Protection circuit ALL
Control Oil in 200 MW provided by PPF PPF VSTPS-4 LEVEL1 AOP AOP/MOP MOP None
RNN
Control Oil in 500 MW provided by PPF PPF VSTPS-4 LEVEL1 AOP FRF pump MOP None
Function of start up oil is PPF PPF VSTPS-4 LEVEL1 to reset HP/IP stop valves Jacking of TG shaft Lurication All
Function of Aux start up oil is PPF PPF VSTPS-4 LEVEL1 to reset HP/IP stop valves To reset Trip gear Lurication All
No
Hydraulic Governor Speed Feedback is PPF PPF VSTPS-4 LEVEL1 start up oil Primary oil secondary oil Aux secondary
oil
RN
Function of RTS is PPF PPF VSTPS-4 LEVEL1 Trip the turbine to provide oil reset the turbine all
Aux trip oil drain through PPF PPF VSTPS-4 LEVEL1 RTS Hyd trip devices Stop valves None
NM
Hydraulic Governor consists of PPF PPF VSTPS-4 LEVEL1 Starting device Speeder gear Both 1 and 2 none
Bw
Hydraulic trip device consists of PPF PPF VSTPS-4 LEVEL1 OS trip device Low Vacuum trip Axial shift All
Function of Trip Oil is PPF PPF VSTPS-4 LEVEL1 TO HOLD STOP V/V TO PRODUCE SECONDARY Both 1 and 2 none
Ww
OIL
Function of Hydraulic Amplifier is PPF PPF VSTPS-4 LEVEL1 Amplify oil pressure Decrease oil pressure Control oil pressure None
Ne
Plunger Coil used in PPF PPF VSTPS-4 LEVEL1 Hydraulic converter ElectroHydraulic converter starting device All
Starting device is operated by PPF PPF VSTPS-4 LEVEL1 Motor solenoids Plunger coil None
Re
Type of Governing Used in 500 MW KWU turbine PPF PPF VSTPS-4 LEVEL1 Throttle Governing Nozzel Governing Bypass Governing None
RRP
In normal operation mode of Governing used PPF PPF VSTPS-4 LEVEL1 EHTC Hydraulic Starting device Speeder gear
Secondary oil is used to operate PPF PPF VSTPS-4 LEVEL1 RTS Control valves Stop valves All
Primary oil pressure is propotional to PPF PPF VSTPS-4 LEVEL1 Control valve postion Load Turbine Speed None
What is not true statement regarding ash PPF PPF VSTPS-4 LEVEL1 Ash is mineral matter Ash requires a large Ash is an inert waste Ash increases the heating value
that is released during investment for collection, material of the fuel
the combustion process storage & disposal
at high temperatures
A high ash fusion temerature indicates that the ash will cool quickly to produce a PPF PPF VSTPS-4 LEVEL1 Fluid Sticky Dry Wet
were aS deposit
What is clinker PPF PPF VSTPS-4 LEVEL1 Ash that breaks down Ash that melts and remain Ash that partially melts Ash that is collected as fine
into very small particles fluid until it reaches the & then solidifies particles in the pollution controll
that is carried up the bottom ash hopper equipment hoppers
stack
Where is the first area in the boiler that ash ash is collected for disposal PPF PPF VSTPS-4 LEVEL1 Economiser hoppers Bottom ash hoppers Baghouse hoppers ESP hoppers
What are the two boiler furnace designs used to handle bottom ash PPF PPF VSTPS-4 LEVEL1 Dry bottom and wet Clinker and granular High ash fusion and low Pressurized and vacuum
bottom ash fusion
The bottom of the boiler is sealed With ..........cccessessesceeees PPF PPF VSTPS-4 LEVEL1 Flexible bellows A seal skirt and seal trough A labyrinth seal A rupture diaphragm
What is used to crush the bottom ash to suitable size for sluicing PPF PPF VSTPS-4 LEVEL1 Ball mill Pulverizer Roller mill Clinker grinder
Of the total ash produced in the combustion process, what is the percentage of fly PPF PPF VSTPS-4 LEVEL1 20
- 30 40 - 50 30 - 40 70 - 80
ash collection in a dry bottom boiler/ furnace
What is the name of the component attached to the side of a slag tank that receives PPF PPF VSTPS-4 LEVEL1 Sluice hopper box Slag feeder Slag conveyor Seal trough
slag from the tank and directs the slag to the clinker grinder
How does a drag chain conveyor system seal the boiler PPF PPF VSTPS-4 LEVEL1 A flexible bellow expands A skirt along the bottom of The conveyor is located A labyrinth seal creates a
and contracts alongwith the boiler immersed in a in a basin that forms a tortuous path that prevents air/
boiler water trough water seal on the gas flow
bottom of the boiler
Where is the ash water mixture from the bottom ash hoppers directed PPF PPF VSTPS-4 LEVEL1 Plant sewer system ash water surge and Cooling tower Hydrobin or slurry sump
settling tank
Of the total ash produced in the combustion process, what is the percentage of ash PPF PPF VSTPS-4 LEVEL1 20 - 30 40
- 50 30 - 40 70 - 80
collected in bottom ash hoppers of a wet bottom boiler/ furnace
When is dry bottom boiler or furnace used PPF PPF VSTPS-4 LEVEL1 When water is scarce When water quenching When burning high ash When burning low ash fusion
would produce steam that fusion temperature coal temperature coal
interferes with the
combustion process
When is wet bottom boiler or furnace used PPF PPF VSTPS-4 LEVEL1 When burning low ash When burning high ash When burning high When buring coal that produces
fusion temperature coal fusion temperature coal sulphure coal high quantity of Nox
Which function is not associated with a bottom ash hopper filled with water PPF PPF VSTPS-4 LEVEL1 Cool the ash Store the ash Fracture the ash Dissolve the ash
Which of these stores clarified water for the bottom ash removal system PPF PPF VSTPS-4 LEVEL1 Final ash setttling basin Primary ash settling basin RO system Hydrobins
Of the total ash produced in the combustion process, what is the percentage of ash PPF PPF VSTPS-4 LEVEL1 20
- 30 40
- 50 30 - 40 70
- 80
collected in bottom ash hoppers of a dry bottom boiler/ furnace
Of the total ash produced in the combustion process, what is the percentage of fly PPF PPF VSTPS-4 LEVEL1 20
- 30 40
- 50 30 - 40 70
- 80
ash collection in a wet bottom boiler
/ furnace
What is the usual particle size of ash after clinker grinder PPF PPF VSTPS-4 LEVEL1 lesss than 10 mm less than 25 mm less that 40 mm less that 60 mm
Which of the following is not considered an ash mineral compound group PPF PPF VSTPS-4 LEVEL1 Silica & silicates Carbonates Hydrocarbons pyrite
MANY DIGITAL CONTROL SYSTEMS UTILIZE ETHERNET AS A COMMUNICATIONS PPF PPF VSTPS-4 LEVEL1 SPEED IS NOT AFFECTED IT 1S A WIRELESS IT IS FULLY IT IS ROBUST AND INEXPENSIVE
NETWORK, BECAUSE BY TRAFFIC NETWORK STANDARD DETERMINISTIC
WHAT IS THE FULL FORM OF SCADA? PPF PPF VSTPS-4 LEVEL1 SUPERVISORY CONTROL SUPERVISORY CONTROL SUPERVISORY COLUMN SUPERVISORY COLUMN AND
AND DOCUMENT AND DATA ACQUISITION AND DATA ASSESSMENT DATA ASSESSMENT
ACQUISITION
WHAT IS SCADA? PPF PPF VSTPS-4 LEVEL1 SOFTWARE PROCESS SYSTEM HARDWARE
WHICH IS NOT TRUE IN CONTEXT OF ADVANTAGES OF ATRS? PPF PPF VSTPS-4 LEVEL1 INCREASES THE NEED MINIMIZES THE POSSIBLE PROTECTS VARIOUS PROVIDES MAXIMUM
AND TASK OF HUMAN ERRORS DRIVES AND RELATED PROTECTION AGAINST
MONITORING VARIOUS AUXILIARIES. MALFUNCTIONS
PROCESS PARAMETERS
WHICH IS NOT A SUBGROUP OF ATRS? PPF PPF VSTPS-4 LEVEL1 SGC OIL SGC TURBINE SGC EVACUATION SGC FEEDWATER SYSTEM
HP BYPASS CONSIST OF HOW MANY OIL SUPPLY UNITS? PPF PPF VSTPS-4 LEVEL1 4
RATING OF VOLTAGE SUPPLY FOR MAIN PLANT UPS INPUT IS PPF PPF VSTPS-4 LEVEL1 415 V DC 415 VAC 230 V AC 230 V DC
TIME RESOLUTION OF SOE IS PPF PPF VSTPS-4 LEVEL1 1SEC 0.01 SEC 0.001 SEC 0.1 SEC
WHAT IS FULL FORM OF ATRS? PPF PPF VSTPS-4 LEVEL1 AUTOMATIC TURBINE AUTOMATIC TURBINE RUN AUTOMATIC TURBINE NONE OF THESE
RUNNING SYSTEM UP SYSTEM ROLL UP SYSTEM
Text Subject Module Difficulty |Correct Option1 Option2 Option3 Option4
Option
Percentage of Fly ash collected in ESP is PPF PPF VSTPS-5 LEVEL1 1 80-90% 100% 10-20% 40-50%
What is the percentage of major constituents in Siliceous Fly ash PPF PPF VSTPS-5 LEVEL1 2 < 40% >70% 10-20% 99%
Gray or Black Color in Fly ash indicates PPF PPF VSTPS-5 LEVEL1 3 High Temp of Ash High Iron content Unburnt Carbon Silica Fusion
What is the percentage of major constituents in Calcareous Fly ash PPF PPF VSTPS-5 LEVEL1 1 >50% traces 10-20% 99%
Which equipment converts fly ash into ash slurry PPF PPF VSTPS-5 LEVEL1 2 ash intake valve / MHV wetting head vaccum breaker Silo
Vaccum pump capacity is measured in PPF PPF VSTPS-5 LEVEL1 3 MWC (Meter Water Column) Kg/Cm2 mmHg (mercury Column PSI (Pascal
/ Sq. Inch)
in mm)
Which phenonmenon drastically reduces the fly ash flow PPF PPF VSTPS-5 LEVEL1 1 Moisture Low temperature Low Vaccum / Pressure Particle Size
In Vaccum Graph, straight line indicates PPF PPF VSTPS-5 LEVEL1 4 Major leakage vaccum breaker remain very poor ash flow All of these
open
In fly ash, chocking takes place in PPF PPF VSTPS-5 LEVEL1 (4 ESP Hopper Wetting Tower Buffer Hopper All of these
Vaccum Breaker opens at PPF PPF VSTPS-5 LEVEL1 3 100mmHg 300mmHg 450mmHg 650mmHg
Which equipment is used to prevent Silo from pressurizing PPF PPF VSTPS-5 LEVEL1 1 Vent Fan Air Blower TAC Rotory Feeder
Which is not a part of fly ash system PPF PPF VSTPS-5 LEVEL1 4 Wetting Head Buffer Hopper Fly Ash Mill Reject
Fly ash particle shape is PPF PPF VSTPS-5 LEVEL1 3 Cubic Cylindrical Spherical lregular Crystal
Rotory Feeder is used for loading ash in PPF PPF VSTPS-5 LEVEL1 2 Open Trains Closed trucks Open Trucks Jute Bags
Which is not related to vaccum pump PPF PPF VSTPS-5 LEVEL1 3 Rotor Silencer Seal Box Bearings
Dead Vaccum / VBO is PPF PPF VSTPS-5 LEVEL1 1 <100mmHg >450mmHg 580 mmHg 0 mmHg
Main shut off vaccum is PPF PPF VSTPS-5 LEVEL1 4 OmmHg 760mmHg <100mmHg >450mmHg
Main Drawback of Fly Ash is PPF PPF VSTPS-5 LEVEL1 4 Erosion Corroion Health Hazard All of these
Ash Lump formation takes place due to PPF PPF VSTPS-5 LEVEL1 4 Moisture Low temperature Large Particle Size All of these
Which is not a part of dry mode system PPF PPF VSTPS-5 LEVEL1 1 Wetting Head Buffer Hopper Bag Filter Ash Loading Tanks
Where is used hydrogen in power plant. PPF PPF VSTPS-5 LEVEL1 1 Cooling of generator Cooling of Turbine Cooling of conenser Cooling of motor
Mixuter of air with hydrogen is formed PPF PPF VSTPS-5 LEVEL1 3 Water Non toxic gas Explosive Toxic gas
Air Quality to be measured by PPF PPF VSTPS-5 LEVEL1 4 Dew point oil content Temp of air All of above
How capacity of compressor is measured. PPF PPF VSTPS-5 LEVEL1 2 M3 NM3/min Pressur Temp
Efficiency of compressor is measured by PPF PPF VSTPS-5 LEVEL1 4 Volumetic efficiency Isothermal efficiency Adiabatic efficiency All of above
How much PH is maintened in drinking water. PPF PPF VSTPS-5 LEVEL1 3 3 to 4 4.5 to 6.5 6.5 to 8.4 7 to 10
What is the function of drier in power plant. PPF PPF VSTPS-5 LEVEL1 1 Improve dew point Heating of air Cooling of air none of above
What is Source of water at VSTPS. PPF PPF VSTPS-5 LEVEL1 |4 Pond Ground water Lake Rihand dam
What is the compressor ratio in Reciprocating compressor PPF PPF VSTPS-5 LEVEL1 3 01 to 03 02 to 05 04 to 07 05 to 09
What is the used of HFO in coal fire plant. PPF PPF VSTPS-5 LEVEL1 4 Ignition Initial starting Low load operation All of above
Most commonly used compressor aFe .........06 in Power plant. PPF PPF VSTPS-5 LEVEL1 4 Centrifugal compressor Diaphragm type Vane type Reciprocating Type
What is the use of compressed air in power plant. PPF PPF VSTPS-5 LEVEL1 4 Cleaning purpose run air motor Open/close valve All of above
For safety purpose-Which tools is used in Hydrogen plant. PPF PPF VSTPS-5 LEVEL1 2 Normal tool Non sparking tool Electric tool Pnumatic tool
What is the speed of reciprocating compressor PPF PPF VSTPS-5 LEVEL1 1 Low Medium High Very high speed
What is the speed of Screw compressor PPF PPF VSTPS-5 LEVEL1 4 Low Medium High Very high speed
How much pressure maintened of compressed air header. PPF PPF VSTPS-5 LEVEL1 3 Less than 4 Less than 5 In between 5 and 6 More than 6
What is the purpose of Receiver tank in compressed air system. PPF PPF VSTPS-5 LEVEL1 4 Storage Load fluctuation Intermittent operation All of above
Why Hydrogen is used for cooling of generator. PPF PPF VSTPS-5 LEVELL 4 Light Low density High thermal All of above
conductivity
For how many years, H2 cylinder testing to be carried out. PPF PPF VSTPS-5 LEVEL1 4 Every year 2 year 4 year 5 year
For how many years, Hydro test to be carried out of receiver tank PPF PPF VSTPS-5 LEVEL1 3 Every year 2 year 4 year 5 year
Use of in power generation leads to the major environmental PPF PPF VSTPS-5 LEVEL1 3 High level of Nitrogen in coal High level of Sulphur in High level of ash content High CV of coal
problems in India coal in coal
Specific water consumption allowed for Thermal Power Plants established before PPF PPF VSTPS-5 LEVELL 4 2.0 3.5 3.2 3.0
2017, as per present norms, is
SPM limit for Stage 1 Units of VSTPS as per EC is PPF PPF VSTPS-5 LEVEL1 4 100 50 30 75
As on today, SO2 limit for Stage 2 Units of VSTPS, as per present norms, is PPF PPF VSTPS-5 LEVEL1 3 100 600 No Limit 200
Applicable limit for Nox from Dec'22 for Stage 3 Units of VSTPS, as per present PPF PPF VSTPS-5 LEVEL1 1 200 600 300 100
norms, is
What is the plan for achieving Nox limits in 500 MW Units at VSTPS PPF PPF VSTPS-5 LEVEL1 2 SNCR Combustion chamber SCR FGD
modification
Which figure is closest to the annual ash generation at VSTPS PPF PPF VSTPS-5 LEVEL1 3 1 Million Tonne 4 Million Tonne 8 Million Tonne 6 Million Tonne
Who issues the EC for a Thermal Power Project ? PPF PPF VSTPS-5 LEVEL1 1 MoEF & CC SPCB CPCB CEA
What is the PM10 annual limit {in micrograms/m3)? PPF PPF VSTPS-5 LEVEL1 2 10 60 100 80
What is the approximate capital expenditure incurred on Environment Protection at PPF PPF VSTPS-5 LEVEL1 4 1000 1100 4000 2300
VSTPS (Rs in crores)
ESP Efficiency at VSTPS is of the order of_ PPF PPF VSTPS-5 LEVEL1 2 70% 99% 95% 90%
Which figure (in lac) is closest to the total tree plantation done by VSTPS till Mar'20 PPF PPF VSTPS-5 LEVEL1 2 26 24 21 20
Which is not currently a part of 100 % Ash Utilisation at VSTPS PPF PPF VSTPS-5 LEVEL1 3 Ash dyke construction Ash Issue to Cement Fly ash-Gypsum plaster Ash filling in mines
Manufacturers
Which facility is used for treating process water in the plant area PPF PPF VSTPS-5 LEVEL1 1 ETP STP AWRS PTP
Which facility is not used for ensuring ZLD? PPF PPF VSTPS-5 LEVEL1 1 DFDS ETP STP AWRS
Which system is used for on-line monitoring of Flue Gas Emissions? PPF PPF VSTPS-5 LEVEL1 3 AAQMS EQMS CEMS CQMS
In which city has VSTPS set-up an Ash Park? PPF PPF VSTPS-5 LEVEL1 3 Varanasi Jabalpur Rewa Bhopal
Which is not an avenue for large scale consumption of ash at present PPF PPF VSTPS-5 LEVEL1 1 Use as soil conditioner in agriculture Cement manufacturing Mine Filling Road construction
Treated ETP water is used in PPF PPF VSTPS-5 LEVEL1 2 Horticulture Equipment Cooling DM water Condensor cooling
is a Hazardous Waste PPF PPF VSTPS-5 LEVEL1 4 Ferrous waste Kitchen Waste Sanitary Waste Used Oil
The major field(s) of application of gas turbine is (are) PPF PPF VSTPS-5 LEVEL1 (4 Aviation Oil and gas industry Power Generation All of the above
The percentage of total energy input appearing as net work output of the cycle PPF PPF VSTPS-5 LEVELL (1 Thermal efficiency Combustion efficiency Engine efficiency Compression efficiency
The following method(s) can be used to improve the thermal efficiency of open PPF PPF VSTPS-5 LEVEL1 (4 inter-cooling Reheating Regeneration All of the above
cycle gas turbine plant
In gas turbine, the function of Re-heater is to PPF PPF VSTPS-5 LEVEL1 4 Heat inlet air Heat exhaust gases Heat air coming out of Heat gases coming out of high
compressor pressure turbine
The ‘work ratio’ increases with PPF PPF VSTPS-5 LEVEL1 4 increase in turbine inlet pressure decrease in compressor decrease in pressure all of the above
inlet temperature ratio of the cycle
In the heat transfer takes place between the exhaust gases and cool air PPF PPF VSTPS-5 LEVEL1 3 Intercooler Re-heater Regenerator Compressor
Gas turbine power plant is....... efficient than steam turbine plant PPF PPF VSTPS-5 LEVEL1 1 More Less Same None of the above
Capital cost of a gas turbine plant........ than that of a steam power plant of same PPF PPF VSTPS-5 LEVEL1 2 Same Lower More None of the above
capacity
In a gas tirbine,high thermal efficiency is obtained in PPF PPF VSTPS-5 LEVEL1 1 Closed cycle Open cycle In both the cycles All the above cycles
The gas turbine works on this cycle PPF PPF VSTPS-5 LEVEL1 3 Otto Cycle Diesel Cycle Brayton Cycle Rankine Cycle
Heat Rejection in Gas Turbine takes place at PPF PPF VSTPS-5 LEVEL1 1 Constant Pressure Constant Entropy Constant Volume Constant Temperature
Work Ratio in Gas Turbines can be improved by PPF PPF VSTPS-5 LEVEL1 2 Increasing Compressor inlet temp. Decreasing Compressor Decreasing Turbine inlet Decreasing exhaust
inlet temp. temperature temperature
Two stage combustion in Gas turbine is known as PPF PPF VSTPS-5 LEVEL1 2 Regeneration Re-heating Intercooling All of the above
Multiple stages of variable inlet guide vanes are provided to improve PPF PPF VSTPS-5 LEVEL1 3 Base load efficiency Peak Load Efficiency Part Load Efficiency All of the above
Combined cycle efficiency of gas plant is of efficiency of gas turbine and PPF PPF VSTPS-5 LEVEL1 4 Sum Difference Multiplication None of the above
steam turbine
Cooling of Blades and vanes is done by PPF PPF VSTPS-5 LEVEL1 4 Compressed Air Steam None of 1&2 Both 1&2
Approximate percentage share of solar power in India's total generation capacity PPF PPF VSTPS-5 LEVEL1 2 7% 9% 11% 13%
Total installed capacity (in MW) of NTPC Solar plants as on 31.03.2020 PPF PPF VSTPS-5 LEVEL1 1 870 770 820 720
How much solar energy received at earth (Percentage) PPF PPF VSTPS-5 LEVEL1 2 30-40 40-50 50-60 60-70
NTPC Biggest solat power plant is PPF PPF VSTPS-5 LEVEL1 1 Bhadla Mandsour Anantapuramu Rajgarh
NTPC Singrauli solar power plant capacity is PPF PPF VSTPS-5 LEVEL1 3 5 MW 10 MW 15 MW 20 MW
The ratio of the beam radiation flux falling on a tilted surface to that falling on a PPF PPF VSTPS-5 LEVEL1 2 Radiation shape factor Tilt factor Slope None of the above
horizontal surface is called the
Solar radiation flux is usually measured with the help of a PPF PPF VSTPS-5 LEVEL1 2 Anemometer Pyranometer Sunshine recorder All of the above
Absorption of Solar radiations at earth’s surface occur due to presence of PPF PPF VSTPS-5 LEVEL1 4 Ozone Water vapours Carbon di-oxide All of the above
Mostly widely used solar material is PPF PPF VSTPS-5 LEVEL1 3 Arsenic Cadmium Silicon Steel
A Pyranometer is used for measurement of PPF PPF VSTPS-5 LEVEL1 3 Direct radiation only Diffuse radiation only Direct as well as Diffuse All of the above
radiation
Reflecting mirrors used for exploiting solar energy are called PPF PPF VSTPS-5 LEVEL1 4 Mantle Ponds Diffusers Heliostats
Photovoltaic cell or solar cell convers PPF PPF VSTPS-5 LEVEL1 2 Thermal energy into electricity Electromagnetic radiations Solar radiation in to Solar radiation in to kinetiv
dirtectly in to electricity thermal energy energy
For satelite the source of energy is PPF PPF VSTPS-5 LEVEL1 2 Cryogenic storage Solar cell Battery All of the above
Solar energy is used in PPF PPF VSTPS-5 LEVEL1 4 water heating Generate elctricity In electric cars All of the above
Solar PV plant is solar modules are connected PPF PPF VSTPS-5 LEVEL1 3 Only series Only paraller Series and paraller None of these
combination
Maximum temparature is reached in which technology PPF PPF VSTPS-5 LEVEL1 2 Parabolic Trough Power Tower Parabolic dish Solar PV
For Solar PV plant, which solar radiation data is used PPF PPF VSTPS-5 LEVEL1 1 Global Horizontal Irradiance only Direct Normal Irradiance GHI & DNI both None of these
only
For Solar thermal plant, which solar radiation data is used PPF PPF VSTPS-5 LEVEL1 2 Global Horizontal Irradiance only Direct Normal Irradiance GHI & DNI both None of these
only
Solar plant generation affect with PPF PPF VSTPS-5 LEVELL 4 Clouds Rain Fog All of the above
Renewable energy consists PPF PPF VSTPS-5 LEVEL1 4 Hydro plants Solar plants Wind plants All of the above
What is meaning of a Carbon Positive Area? PPF PPF VSTPS-5 LEVEL1 4 Area with carbon emissions more than Area with carbon Area with carbon Area with more renewable
carbon sequestration emissions balanced with emissions are zero energy generation than
carbon sequestration needed to sustain the area
The first Pilot-cum- demonstration project of Small Wind Solar Hybrid System of 25 PPF PPF VSTPS-5 LEVEL1 1 Tamil Nadu Gujarat Rajasthan Maharashtra
KW capacity will be installed at
Which energy accounts for largest share in the renewable energy basket of India? PPF PPF VSTPS-5 LEVEL1 3 Wind Nuclear Hydro Solar
Which of the following is not a renewable source of energy? PPF PPF VSTPS-5 LEVEL1 1 Nuclear Energy Energy from Waste Hydropower Biomass
Text Subject Module Difficulty | Correct Option Option1 Option2 Option3 Option4
FSSS IS RESPONSIBLE FOR Control Prot & Perf Ctrl Prot. & Perf-19 LEVEL2 3 TURBINE PROTECTION GENERATOR PROTECTION BOILER PROTECTION NONE OF THE ABOVE
FURNACE PR VERY HIGH PROTECTION ACT AT Control Prot & Perf Ctrl Prot. & Perf-19 LEVEL2 +125 MMWC +100 MMWC +150 MMHG +150 MMWC
PURPOSE OF BOILER PURGING IS Control Prot & Perf Ctrl Prot. & Perf-19 LEVEL2 REMOVING ANY FUEL FROM THE COOLING OF SH TUBES CLEANING OF ASH FROM ESP HOPPERS NONE OF THE ABOVE
FURNACE
MILL -A CAN BE TAKEN I/S WHEN Control Prot & Perf Ctrl Prot. & Perf-19 LEVEL2 FEEDER B IS AT 50% LOAD 3 AB GUN I/S ALWAYS BOTH 1&2
MFT CAUSES Control Prot & Perf Ctrl Prot. & Perf-19 LEVEL2 TOTAL FUEL CUT OFF FD/ID FAN TRIPPING PA FAN TRIPPING BOTH 1 &3
OIL GUN ELEVATION MODE IS ACTIVE WHEN Control Prot & Perf Ctrl Prot. & Perf-19 LEVEL2 ANY FEEDER IS I/S ADAJECENT FEEDER 1|/S BOILER LOAD IS >30% MFT ACTED
WN)
BOILER PURGE CYCLE TIME IS Control Prot & Perf Ctrl Prot. & Perf-19 LEVEL2 7 MIN 5 MIN 9 MIN 10 MIN
HOTV CLOSE IN AUTO IF Control Prot & Perf Ctrl Prot. & Perf-19 LEVEL2 MFT ACTS OIL GUN TRIPS PA FAN TRIPS TURBINE TRIPS
NIBP
LDO/HFO GUN- BOTH ,ARE AVAILABLE AT Control Prot & Perf Ctrl Prot. & Perf-19 LEVEL2 cD EF HJ AB ELEVATION
WE CAN TAKE ANY MILL 1/S Control Prot & Perf Ctrl Prot. & Perf-19 LEVEL2 ALWAYS WHEN IGNITION PERMIT IS WHEN BOILER IS ON WHEN LOAD IS TO BE INCREASED
AVAILABLE
RH PROTECTION GETS ARMED WHEN Control Prot & Perf Ctrl Prot. & Perf-19 LEVEL2 BOILER IS LIGHTED UP DRUM PR >30 KSC ANY FEEDR |/S 283
BONS
LOSS OF ALL FUEL TRIP WILL ACT WHEN Control Prot & Perf Ctrl Prot. & Perf-19 LEVEL2 <3 GUN I/S ALL FEEDER OFF & NO GUN I/S 1 GUN I/S NO GUN I/S
WHY WE NEED TO TRIP BOILER WHEN ALL ELEVATION VOTE NO Control Prot & Perf Ctrl Prot. & Perf-19 LEVEL2 THIS IS AN ABNORMAL BOILER MAY GET DAMAGED STATUS OF FURNCE FLAME IS NOT CLEAR ALL
FLAME CONDITION
DRUM LEVEL LOW PROTECTION IS FOR Control Prot & Perf Ctrl Prot. & Perf-19 LEVEL2 SAVING RH SAVING WW TUBES SAVING TURBINE NONE
WwW) BN
APHIS USED IN BOILER FOR Control Prot & Perf Ctrl Prot. & Perf-19 LEVEL2 SAFTEY EFFICIENCY PROPER COMBUSTION 2,3
TURBINE TRIP CAUSES DIRECT TRIPPING OF BOILER Control Prot & Perf Ctrl Prot. & Perf-19 LEVEL2 ALWAYS SOMETIMES WHEN HP/LP BP DOES NOT OPEN NONE
WE NEED PROTECTION FOR ANY EQUPMENT FOR Control Prot & Perf Ctrl Prot. & Perf-19 LEVEL2 LEGAL REQUIREMENT IMPROVING EFFCIENCY MINIMISING DAMAGES TO MAN AND NONE
Wi
MACHINE
SCANNER AIR FAN IS USED FOR Control Prot & Perf Ctrl Prot. & Perf-19 LEVEL2 COOLING SCANNER COOLING BOILER SEALING OF MILL NONE
BE
SEAL AIR FAN GET AUT OFF Control Prot & Perf Ctrl Prot. & Perf-19 LEVEL2 MFT ACTS BOTH PA FANS OFF TURBINE TRIPS NONE
SCANER FAN EMERGENCY SUCTION DAMPER OPENS WHEN Control Prot & Perf Ctrl Prot. & Perf-19 LEVEL2 BOTH PA OFF BOTH FD OFF SINGLE FD OFF OPEN COMMAND IS GIVEN
WHICH SOLENOID OPERATES FOR OPENING OF CW BFV Control Prot & Perf Ctrl Prot. & Perf-19 LEVEL2 S1 $2 $3 S4
WHICH SOLENOIDS OPERATE FOR NORMAL CLOSING OF CW BFV Control Prot & Perf Ctrl Prot. & Perf-19 LEVEL2 $1&S5 $2&S5 $3 &S5 $1 &S2
WHICH SOLENOID ARE RESPONSIBLE FOR EMERGENY CLOSING OF CW Control Prot & Perf Ctrl Prot. & Perf-19 LEVEL2 $1&S2 $2&S3 S$3&S4 S4
BFV
WHICH SOLENOID IS RESPONSIBLE FOR SLOW CLOSING OF CW BFV IN Control Prot & Perf Ctrl Prot. & Perf-19 LEVEL2 $2 $5 $3 S1
LAST 10%
PROTECTION FOR CW WINDING TEMP IS ON TEMP GREATER THAN Control Prot & Perf Ctrl Prot. & Perf-19 LEVEL2 80 90 100 120
CW BRG TEMP HIGH PROTECTION ARE FOR Control Prot & Perf Ctrl Prot. & Perf-19 LEVEL2 MOTOR DE MOTOR NDE THRUST BRG ALL
CW sump level very low , what will happen after passing of preset Control Prot & Perf Ctrl Prot. & Perf-19 LEVEL2 Half of running CW will trip All runningCWw will trip Only One CW WILL TRIP NONE OF THESE
delay time
CW VIBRATION PROTECTION IS ON Control Prot & Perf Ctrl Prot. & Perf-19 LEVEL2 Horizontal vertical Both NONE OF THESE
CW RUNNING AND BFV OPEN LESS THAN 90% , CW Will Control Prot & Perf Ctrl Prot. & Perf-19 LEVEL2 Trip immediately Trip after preset time delay Keep running 90% opening is not critical
CW STARTED AND BFV NOT OPEN MORE THEN 90% , THEN CW WILL Control Prot & Perf Ctrl Prot. & Perf-19 LEVEL2 Trip immediately Trip after preset time delay Keep running 90% opening is not critical
CW PUMP CAN BE TRIPPED FROM LOCAL EMEGENCY PUSH BUTTON Control Prot & Perf Ctrl Prot. & Perf-19 LEVEL2 TRUE FALSE NOT ALLOWED ONLY FROM REMOTE
IF BFV PANEL SELECTION IS IN LOCAL IT WILL NOT CLOSE DURING Control Prot & Perf Ctrl Prot. & Perf-19 LEVEL2 TRUE FALSE IT MUST BE IN REMOTE ONLY PUMP WILL TRIP
TRIPPING FROM REMOTE
IN PLANT RUNNING CONDITION , STOPPED CW BFV ARE ALLOWED TO Control Prot & Perf Ctrl Prot. & Perf-19 LEVEL2 TRUE FALSE FOR SHORT DURATION NOTHING WILL HAPPEN
OPEN
AHU Fan will be tripped immediately if fire signal exist Control Prot & Perf Ctrl Prot. & Perf-19 LEVEL2 TRUE FALSE NOT REQUIRED WITH TIME DELAY
WHAT WILL HAPPENED IF CHILLED WATER PUMP ON & DISCHARGE Control Prot & Perf Ctrl Prot. & Perf-19 LEVEL2 Trip immediately Trip after preset time delay keep running NONE OF THESE
PRESS < 2KSC, IT WILL
AC CT FAN HAVE TRIPPING ON VERY LOW TEMP (<27 C) Control Prot & Perf Ctrl Prot. & Perf-19 LEVEL2 TRUE FALSE NOT REQUIRED NONE OF THESE
LDO PUMP PROTECTION IS ON Control Prot & Perf Ctrl Prot. & Perf-19 LEVEL2 TANK LEVEL VERY LOW SUC PRESSURE LOW DISCHARGE VALVE NOT OPEN ALL
NS
IF ON FEEDBACK NOT COMES AFTER LDO START COMMAND GIVEN , IT Control Prot & Perf Ctrl Prot. & Perf-19 LEVEL2 Trip immediately Trip after preset time delay keep running NONE OF THESE
WILL
HFO PUMP PROTECTION IS ON Control Prot & Perf Ctrl Prot. & Perf-19 LEVEL2 TANK LEVEL VERY LOW TANK LEVEL HIGH BOTH NONE OF THESE
Bl RB
Highest no. Of fault occurence is in Control Prot & Perf Ctrl Prot. & Perf-19 LEVEL2 O.H. Lines CTs & PTs Transformer switchgear
Symbol "52" in protection system is used for Control Prot & Perf Ctrl Prot. & Perf-19 LEVEL2 Ciruit Breaker Isolator Earth fault Relay Overcurrent relay
NR} RP
In overhead lines highest percentage of fault occurence is in Control Prot & Perf Ctrl Prot. & Perf-19 LEVEL2 L-L fault L-G fault L-L-G fault L-L-L fault
Essential qualities of a power sytem protection is Control Prot & Perf Ctrl Prot. & Perf-19 LEVEL2 Reliability Selectivity Fastness of operation All
B®
Attracted armature tyoe relay is a type of realy Control Prot & Perf Ctrl Prot. & Perf-19 LEVEL2 Electromagntic Static Numerical None
earthing of motor body is atype of earthing Control Prot & Perf Ctrl Prot. & Perf-19 LEVEL2 System Earthing Equipment earthing Neutral earting None
NM) BLN
Main function of protection system is to Control Prot & Perf Ctrl Prot. & Perf-19 LEVEL2 Isolate the faulty sytem Continue the system Do nothing None
Which type of protection Fuse provide Control Prot & Perf Ctrl Prot. & Perf-19 LEVEL2 Secondary Primary Both None
Most fault on transmission line is of Control Prot & Perf Ctrl Prot. & Perf-19 LEVEL2 Permanent type Transient tyoe Both None
NIN
Pickup value of a relay is the value of actating quantity at which relay Control Prot & Perf Ctrl Prot. & Perf-19 LEVEL2 Resets Operates Both None
Following is not a measure of APH overall performance Control Prot & Perf Ctrl Prot. & Perf-19 LEVEL2 Boiler Load Index (BLI) GSE Flue Gas DP X ratio
NF
In running unit APH thermal performance terms can be checked by Control Prot & Perf Ctrl Prot. & Perf-19 LEVEL2 MS PRESSURE FGET Total coal flow Feedwater flow
visulaising
Mill dirty air flow test is carried out for checking Control Prot & Perf Ctrl Prot. & Perf-19 LEVEL2 Mill Currents Mill Power Coal Air mixture velocity Mill Bowl DP
Air heater leakage percentage for oxygen level of 2.8 % at inlet and Control Prot & Perf Ctrl Prot. & Perf-19 LEVEL2 12.28 15.31 8.42 17.05
5.7% at outlet comes out to be
Increased flue gas pressure drop across APH indiactes Control Prot & Perf Ctrl Prot. & Perf-19 LEVEL2 Choked baskets Seal wear Air leakage Poor X ratio
Increased High Energy Drain passing will lead to Control Prot & Perf Ctrl Prot. & Perf-19 LEVEL2 Poor condenser vacuum Improved Condenser vaccum No effect on Condenser Vacuum
Higher Coal air velocity than design through coal pipes can lead to Control Prot & Perf Ctrl Prot. & Perf-19 LEVEL2 Increased wear and tear of coal Poor heat pick up in water wall High FGET at APH All of the above
pipes
TTD in feed water heater is a reflection of its Control Prot & Perf Ctrl Prot. & Perf-19 LEVEL2 Thermal Expansion Heat Transfer Drip level None of above
Which of the following is not a cause of poor condenser vacuum Control Prot & Perf Ctrl Prot. & Perf-19 LEVEL2 High CW Inlet Temp High Air ingress Low cooling water flow None of above
Poor Condenser vacuum results in Control Prot & Perf Ctrl Prot. & Perf-19 LEVEL2 Increased coal consumption Reduced Heat Rate Financial Gain All of the above
Flue Gas duct circuit air ingress results in Control Prot & Perf Ctrl Prot. & Perf-19 LEVEL2 Higher ID fan power consumption Inceased APC Unit Capability restrictions All of the above
Feed water heater performance can be optimized in unit by Control Prot & Perf Ctrl Prot. & Perf-19 LEVEL2 Maintaining optimum heater level Bypassing the heater Increasing extraction steam flow None of above
Truly representative coal sample for sieving obtained by Control Prot & Perf Ctrl Prot. & Perf-19 LEVEL2 Clean Air flow test Dirty Air flow test lsokinetic Sampling Draft power Testing
Coal Fineness analysis has to be carried after collecting sample Control Prot & Perf Ctrl Prot. & Perf-19 LEVEL2 Two Hour Four Hour Eight Hour Immediately
p
Increased APH seal leakage affects Control Prot & Perf Ctrl Prot. & Perf-19 LEVEL2 Flue gas outlet temp Draft Power Both A and B None of these
WwW
Heater performance is judged by Control Prot & Perf Ctrl Prot. & Perf-19 LEVEL2 TTD DCA Feed water Temp Gain All of the above
BR
Low Flue Gas temperature at APH outlet can be due to Control Prot & Perf Ctrl Prot. & Perf-19 LEVEL2 High APH performance Increased seal leakage Both A and B None of these
Bw
Condenser vacuum is affected by Control Prot & Perf Ctrl Prot. & Perf-19 LEVEL2 Dirty Condenser Tubes Air Ingress CW Inlet temperature All of the above
Mill Performance tests consists of Control Prot & Perf Ctrl Prot. & Perf-19 LEVEL2 Clean Air flow test Dirty Air flow test lsokinetic Sampling All of the above
WwW) BB)
Optimimum condenser performance is ensured by Control Prot & Perf Ctrl Prot. & Perf-19 LEVEL2 COLTCS operation Opportunity backwashing Normal drip circuit in heaters All of the above
What is the purpose of transformer Protection Control Prot & Perf Ctrl Prot. & Perf-19 LEVEL2 To Prevent the faults in To limit the extent of damage in Both (1) & (2) None of these
transformer faulted transformer
What are the mechanical protection of Transformers Control Prot & Perf Ctrl Prot. & Perf-19 LEVEL2 Buchhloz Protection Sudden Pressure Relay OTI & Thermal Protection All of the Above
BS
Buchholz relay operates on the basis of Control Prot & Perf Ctrl Prot. & Perf-19 LEVEL2 Accumlated Gases Current Voltage Transformer Oil
Which type of transformer is Generator Transormer(GT) Control Prot & Perf Ctrl Prot. & Perf-19 LEVEL2 Power Transformer Distribution Transformer Stepup Transformer Both (1)& (3)
WBF
What are the major reasons of transformer failures Control Prot & Perf Ctrl Prot. & Perf-19 LEVEL2 Core insulation failure Bushing Cracking Overheating All of the above
What are the electrical protection of transformers Control Prot & Perf Ctrl Prot. & Perf-19 LEVEL2 Thermal Overload Protection Restricated Earth Fault Protection Both (2) & (4) Differential Protection
Differential protection of transformer protects Control Prot & Perf Ctrl Prot. & Perf-19 LEVEL2 Transformer winding only Zone outside the transformer Protection is not applicable or transformers None of these
What is the requirement of Tap changer in transformer Control Prot & Perf Ctrl Prot. & Perf-19 LEVEL2 To protect the HV winding To protect the LV winding To raise or lower the volatge of HV winding To raise or lower the volatge of LV winding
Transformer Restricted Earth fault protection is used Control Prot & Perf Ctrl Prot. & Perf-19 LEVEL2 To protect Delta winding of To protect Star winding of To protect both star and delta winding of None of these
transformer transformer transformer
Transformer Oil is used for Control Prot & Perf Ctrl Prot. & Perf-19 LEVEL2 Lubrication Cooling Sealing Insulating
Gases formerd in transformer during internal faults because of Control Prot & Perf Ctrl Prot. & Perf-19 LEVEL2 Transformer Oil Winding insulation Core Insulation None of these
Differential protection of transformer operates on the basis of Control Prot & Perf Ctrl Prot. & Perf-19 LEVEL2 Difference of current Difference of voltage Both (1) & (2) None of these
Thermal protection senses the Control Prot & Perf Ctrl Prot. & Perf-19 LEVEL2 Winding temperature Oil temperature Both (1) & (2) None of these
Fe Bw
Overfluxing protection operates on the basis of Control Prot & Perf Ctrl Prot. & Perf-19 LEVEL2 Transformer current Transformer Voltage Transformer frequency Both (2) & (3)
NIM
Differential Protection is used for transformers rating Control Prot & Perf Ctrl Prot. & Perf-19 LEVEL2 more than 5 MVA More than 1 MVA More than 2 MVA None of these
Transformer bushing size is longer for Control Prot & Perf Ctrl Prot. & Perf-19 LEVEL2 LV winding HV Winding same for both windings None of these
Sudden Pressure relief relay is used in transformers to Control Prot & Perf Ctrl Prot. & Perf-19 LEVEL2 isolate the faulty transformer from Limit the extent of damage Both (1) & (2) None of these
healthy transformer
Current have following components Control Prot & Perf Ctrl Prot. & Perf-19 LEVEL2 Positive Sequence component Negative sequence component Zero sequence component All of the above
Woe)
Which protection of Transformer operates fast Control Prot & Perf Ctrl Prot. & Perf-19 LEVEL2 Electrical Protection Mechanical protection Both (1) & (2) None of these
Which type of relays used in power transformer protection are most Control Prot & Perf Ctrl Prot. & Perf-19 LEVEL2 Electro mechanical Relay Static Relay Numerical Relay None of these
advanced
Motor Failure may result in Control Prot & Perf Ctrl Prot. & Perf-19 LEVEL2 Cost of Replacement Cost of Repairing Generation Loss All of the above
Motor may fail due to Control Prot & Perf Ctrl Prot. & Perf-19 LEVEL2 Over temperature Bearing failure Insulation failure All of the above
AS
Short Cicuit fault in motors results in Control Prot & Perf Ctrl Prot. & Perf-19 LEVEL2 high current Over heating motor failure All of the above
SAP
Locked Rotor Protection Operates when there is Control Prot & Perf Ctrl Prot. & Perf-19 LEVEL2 Mechanical jamming low load high vibration All of the above
PrP wre
Single phasing may be due to Control Prot & Perf Ctrl Prot. & Perf-19 LEVEL2 High vibration abnormal sound Fuse failure All of the above
Single phasing results in Control Prot & Perf Ctrl Prot. & Perf-19 LEVEL2 high current High vibration High torque All of the above
In Locked rotor condition Control Prot & Perf Ctrl Prot. & Perf-19 LEVEL2 motor don’t rotates high vibration abnormal sound All of the above
Motor must be protected from Control Prot & Perf Ctrl Prot. & Perf-19 LEVEL2 high current Under Voltage high temperature All of the above
Motor must be protected from Control Prot & Perf Ctrl Prot. & Perf-19 LEVEL2 Short Circuit Single phasing Locked rotor All of the above
Motor may fail due to Control Prot & Perf Ctrl Prot. & Perf-19 LEVEL2 Short Circuit fault Earth fault Over-current fault All of the above
B/S
Parts Of Protection System Control Prot & Perf Ctrl Prot. & Perf-19 LEVEL2 Current Transformer (Ct) Potential Transformers (Pt) Protection Relay All Of Above
Text Subject Module Difficulty | Correct Option Option1 Option2 Option3 Option4
What is the meaning of SAP in PTW system? Operation Operation-VSTPS 1 Level1 3 Senior Associate Person Safety Appointed Personnel Senior Authorised Person Supervisory Associate Personnel
What kind of permit should be taken for cutting/welding Operation Operation-VSTPS 1 Level1 2 Permit To Work Hot Work Permit Confined Space Permit Work At Height Permit
in fire prone areas like oil station?
Who is Authorised to issue a Permit? Operation Operation-VSTPS 1 Level1 SAP CP AP Everybody
When should a permit be issued? Operation Operation-VSTPS 1 Level1 4 after completion of work before completion of work after starting maintenance work before starting maintenance work
What does LWC stand for? Operation Operation-VSTPS 1 Level1 1 Limited Work Certificate Limited Working Clearance Local Work Certificate Localised Work Clearance
What kind of permit should be taken for Chimney Painting Operation Operation-VSTPS 1 Level1 Hot Work Permit Floor Opening Permit Work At Height Permit Confined Space Permit
works?
What should be the priority of notification for jobs Operation Operation-VSTPS 1 Level1 4 A Priority B Priority C Priority E Priority
requiring immediate attention?
When two or more parties work on the same equipment Operation Operation-VSTPS 1 Level1 2 Nobody separate keys to each party any one Party None of the above
(cross permit), safe keys are issued to?
Notifications for jobs requiring shutdown should be raised Operation Operation-VSTPS 1 Level1 3 A Priority B Priority C Priority E Priority
in which priority?
What kind of permit should be taken if supply is to be Operation Operation-VSTPS 1 Level1 4 PTW LWC HWP ROMP
normalised during work?
Which of the following must be available before Boiler Operation Operation-VSTPS 1 Level1 4 Auxiliary Steam Fuel Oil Compressed Air All of the above
Lightup
Which of the following drives is run before the other three Operation Operation-VSTPS 1 Level1 2 FD Fan ID Fan PA Fan Pulveriser
during Boiler Startup
In addition to an Electric Motor, Air Motor is provided in Operation Operation-VSTPS 1 Level1 3 RC Feeder Pulveriser Air Pre-Heater BCW Pumps
which of these drives
Before Starting ID Fan, its IGV position should be Operation Operation-VSTPS 1 Level1 1 Minimum Maximum In auto mode Doesn't Matter
Which of the following is NOT a condition necessary for Operation Operation-VSTPS 1 Level1 2 Outlet Gate closed PA Fan running Blade pitch Minimum Lube Oil pump running
starting FD Fan
Which Gas is used for capping inside Primary Water Tank Operation Operation-VSTPS 1 Level1 2 Hydrogen Nitrogen Carbon Dioxide Air
Generator Excitation is used to control which of the Operation Operation-VSTPS 1 Level1 3 MW Output Rotor Speed MVAr Output Frequency
following
Hydrogen Gas is responsible for cooling of which of the Operation Operation-VSTPS 1 Level1 3 Stator Winding Rotor Only Stator and Rotor Exciter
following
Excitation is Controlled by which of the following Operation Operation-VSTPS 1 Level1 4 Pilot Exciter Main Exciter Bridge Rectifier DVR
Which of the following parameters of Primary Water need Operation Operation-VSTPS 1 Level1 4 Conductivity pH Dissolved Oxygen All of the above
to be controlled
NaOH dosing is done in Primary Water to maintain which Operation Operation-VSTPS 1 Level1 1 pH DO Conductivity Temperature
of the following
During Gen Gas purging, which of the following gases is Operation Operation-VSTPS 1 Level1 1 Carbon Dioxide Methane Argon Nitrogen
used as a barrier between H2 & Air
DPRVs are used to control which of the following Seal Oil Operation Operation-VSTPS 1 Level1 2 Temperature Pressure Tank Level H2 Purity
Parameters
What is the reason for using Hydrogen gas in Generator Operation Operation-VSTPS 1 Level1 1 High heat transfer capability Ease of handling Economical to produce Abundantly available
cooling
Which of the following Transformers supplies power to Operation Operation-VSTPS 1 Level1 2 Unit Transformer Unit Auxiliary Transformer Station Transformer Unit Service Transformer
3.3KV drives in 500 MW units
what is the full form of SLC? Operation Operation-VSTPS 1 Level1 2 Sequential Loop Control Sub Loop Control System Loop Control None of these
At what RPM AOP take start? Operation Operation-VSTPS 1 Level1 3 3000 2950 2840 2710
At what RPM barring valve opens? Operation Operation-VSTPS 1 Level1 2 240 210 540 2840
At what RPM JOP take start? Operation Operation-VSTPS 1 Level1 3 410 540 510 440
what is safe turbine load gradient for SOO MW unit? Operation Operation-VSTPS 1 Level1 3 25 MW/min 20 MW/min 15 MW/min 5 MW/min
at what RPM HPT valve closes? Operation Operation-VSTPS 1 Level1 3 1500 2810 2000 3000
At what HP shaft temp. barring can be stopped? Operation Operation-VSTPS 1 Level1 2 200 C 130 C 250C 350C
what is the frequency of SADC checking? Operation Operation-VSTPS 1 Level1 4 Daily per shift twice a week weekly
what is frequency of LRSB operation? Operation Operation-VSTPS 1 Level1 3 daily monthly weekly as per required
what is frequency of APH soot blowing? Operation Operation-VSTPS 1 Level1 1 Daily per shift weekly as per required
At what drum pr. SH drain should be opened? Operation Operation-VSTPS 1 Level1 1 8 Ksc 10 Ksc 12 Ksc 2 Kse
which gas is used for purging out H2 gas? Operation Operation-VSTPS 1 Level1 1 co2 Air N2 none of the above
what is the frequency of water wall soot blowing? Operation Operation-VSTPS 1 Level1 1 daily per shift weekly monthly
At what drum pr. Boiler vents are opened? Operation Operation-VSTPS 1 Level1 3 6 ksc 5 Kse 2 Ksc 8 Ksc
While killing Vacuum at what value Seal steam is isolated Operation Operation-VSTPS 1 Level1 1 0.2 Ksc 0.9 ksc 0.8 Ksc 0.4 Ksc
From where does Scanner Fan take Suction(Normal Operation Operation-VSTPS 1 Level1 2 Atmosphere FD FAN PA FAN ID FAN
Source)
At What Scan duct to furnace DP Auto On command goes Operation Operation-VSTPS 1 Level1 3 >150 MMWC 360 MMWC <150 MMWC None of these
to Scanner Fan
What is the duration of PURGE cycle Operation Operation-VSTPS 1 Level1 2 10 mins 9 mins 12 mins 6 mins
Minimum AIR Flow required for boiler purging Operation Operation-VSTPS 1 Level1 2 20% 30% 40% 50%
Which of these is not a purge permissive Operation Operation-VSTPS 1 Level1 3 NO MFT PA FAN OFF FD FAN OFF NO FLAME
Which of these is not a MFT Operation Operation-VSTPS 1 Level1 3 ALL IDs OFF ALL FDs OFF ALL PAPH OFF ALL SAPH OFF
What is adequate air pressure required for taking LDO in Operation Operation-VSTPS 1 Level1 2 2 Ksc 3 Ksc 4 Ksc 5 Kse
service
What is steam pressure required for taking HFO in service Operation Operation-VSTPS 1 Level1 4 2 Ksc 3 Ksc 4 Ksc 5 Ksc
What is the Scavenging time Operation Operation-VSTPS 1 Level1 3 340 sec 350 sec 360 sec 300 sec
What should be flue gas outlet temperature to start a PA Operation Operation-VSTPS 1 Level1 1 300C 100 C 200 C SO0C
FAN
Pa Fan Blade Pitch position to start a PA FAN Operation Operation-VSTPS 1 Level1 1 0 30 50 100
From where coes Seal Air Fan take Suction Operation Operation-VSTPS 1 Level1 1 Cold PA Hot PA FD FAN Atmosphere
Seal Air is mainly used for sealing of Which Equipment Operation Operation-VSTPS 1 Level1 1 Mills Oil Guns ECW Pumps IAC
Minimum Air Flow required to give start permissive to Operation Operation-VSTPS 1 Level1 3 60 tph 75 tph 80 tph 90 tph
Feeders
Which AIR is provided in Mills for lifting coal Operation Operation-VSTPS 1 Level1 1 Primary Air Secondary Air Scanner Air Seal Air
At what value of MILL Mtr vibn does MILL Trip Operation Operation-VSTPS 1 Level1 3 35 mm/s 20 mm/s 15 mm/s 25 mm/s
Most of the ASH gets collected at which hopper Operation Operation-VSTPS 1 Level1 1 First Hopper Last Hopper Fivth Hopper Same in All Hoppers
No. Of ESP per unit 500 MW Operation Operation-VSTPS 1 Level1 3 5 3 4 6
At What Gas Temp Transformers should be energised Operation Operation-VSTPS 1 Level1 3 230C 300 C 100 C 150C
ALI stands for Operation Operation-VSTPS 1 Level1 2 Air Level Indicator Ash Level Indicator Ash Level Inadequate None of these
ASH gets collected at which electrodes Operation Operation-VSTPS 1 Level1 2 Cathode Anode Both None of the above
DURING EHTC FAULT Operation Operation-VSTPS 1 Level1 4 THERE WILL BE LOAD THERE IS NO PROBLEM Take machine on HC 1 AND 3
HUNTIMG
EHC output zero WILL LEAD TO Operation Operation-VSTPS 1 Level1 3 Unit load reduced to zero as MS pressure increases, ERVS BOTH NONE OF THE ABOVE
all control valves close and safety valves lifted
IF CF PUMP TRIP Operation Operation-VSTPS 1 Level1 3 N2 bladders should take care If it drops then Turbine will trip BOTH NONE OF THE ABOVE
of the control fluid press on “trip oil press. Low”/
Closing of stopping of ESV
IF BFP TRIPPED Operation Operation-VSTPS 1 Level1 4 Drum level comes down Running TDBFP may get over FRS valves may close to maintain DP ALL
loaded across FRS
IF BFP RECIRCULATION VALVE GETS OPENED Operation Operation-VSTPS 1 Level1 1 Drum level come down Drum level GOES HIGH BOTH NONE OF THE ABOVE
THE REASON OF LOW/LOSS OF VACUUM IS/ARE Operation Operation-VSTPS 1 Level1 1 Steam ejector / Vacuum LOW level in condenser NO Air leak into system ALL
pump not functioning
properly
THE EFFECT OF LOW VACUUM IS Operation Operation-VSTPS 1 Level1 4 EFFICIENCY WILL INCREASE BOILER WILL TRIP NO PROBLEM Turbine will trip at -0.700 Ksc
IF DM make up pump have tripped. Operation Operation-VSTPS 1 Level1 2 HOTWELL LEVEL HIGH HOTWELL LEVEL LOW BOTH ANY
HOTWELL LEVEL HIGH Operation Operation-VSTPS 1 Level1 4 Malfunctioning of DM make Condensate pumps may have Hotwell set point too high. ALL
up valve. tripped
IF ONE ID FAN IS TRIPPED,IT WILL LEAD TO Operation Operation-VSTPS 1 Level1 1 FURNACE PR HIGH FURNACE PR LOW ANY THING CAN HAPPEN NONE OF THE ABOVE
FURNACE PRESSURE LOW Operation Operation-VSTPS 1 Level1 Sudden decrease in air input |.D. Fan vane control Sudden tripping of one or more mills ALL
or tripping of one F. D. fan. mechanism Failure causing or choking of mill/raw coal Feeder
vanes to open wide. pipe.
FSSS IS FOR SAFEGAURD OF Operation Operation-VSTPS 1 Level1 2 TURBINE FURNACE PUMPS ALL
EFFECT OF PA FAN TRIPPING IS Operation Operation-VSTPS 1 Level1 3 FURNACE PRESSURE HIGH PA HDR PR HIGH PA HEADER PRESSURE LOW ALL
WHICH IS NOT AN INDICATION OF FD or PA FAN STALLING Operation Operation-VSTPS 1 Level1 4 Stalled fan’s current will Vibration of fan will increase Other fan may get overloaded. normal sound in local
come down
ACTION ON FD or PA FAN STALLING Operation Operation-VSTPS 1 Level1 3 Reduce other fans loading Match both fans loading. BOTH NONE OF THE ABOVE
WHICH IS APH EMERGENCY Operation Operation-VSTPS 1 Level1 4 AIR PRE-HEATER ON FIRE. AIR PRE-HEATER ELECTRIC AIR PRE HEATER BEARING ALL
MOTOR TRIPPED. TEMPERATURE VERY HIGH.
BTL OR BOILER TUBE LEAKAGE WILL RESULT IN Operation Operation-VSTPS 1 Level1 3 DRUM LEVEL HIGH NO CHANGE DRUM LEVEL LOW ALL
LPBP CONNECTS Operation Operation-VSTPS 1 Level1 3 MS TO HRH HRH TO CRH HRH TO CONDENSER CRH TO CONDENSER
HPBP CONNECTS Operation Operation-VSTPS 1 Level1 1 MS TO CRH MS TO HRH MS TO CONDENSER CRH TO CONDENMSER
SPRAY FOR HPBP IS TAKEN FROM Operation Operation-VSTPS 1 Level1 2 CEP DISCH HDR BFP DISCH HDR ANY ONE NONE
SPRAY FOR LPBP IS TAKEN FROM Operation Operation-VSTPS 1 Level1 2 BFP DISCH HDR CEP DISCHARGE HEADER BOTH FROM ANY WHERE
MAIN TURBINE SEAL STEAM IS CHARGED AT Operation Operation-VSTPS 1 Level1 1 0.20 VACCUUM 0.30 Vaccum 0.10 vaccum 0.15 vaccum
FULL FORM OF TSE IS Operation Operation-VSTPS 1 Level1 1 TURBINE STRESS EVALUATOR TURBO STRESS EVALUATION BOTH NONE
FULL FORM OF TSI IS Operation Operation-VSTPS 1 Level1 1 TURBO SUPERVISORY TURBINE SUPERVISOR BOTH NONE
INSTRUMENTS INSTRUMENTS
X1 AND X2 CURVES ARE FOR Operation Operation-VSTPS 1 Level1 1 STOP VALVE OPENING FOR 360 RPM FOR 3000 RPM NONE
FOR RESETTING OF TURBINE ,STARTING DEVICE POSITION Operation Operation-VSTPS 1 Level1 1 0 42 56 100
IS
WHICH OF THE FOLLOWING IS INCORRECT Operation Operation-VSTPS 1 Level1 1 HPBP IS A PART OF MAIN BPE VALVES CONTROL BP VALVES ADJUST MS PRESSURE OF BD VALVES IS CONNECTED AHEAD OF
TURBINE GOVERNONG TEMPERATURE ON CRH LINE. TURBINE. BPE VALVE.
SYSTEM
WHICH COMES FIRST IN SEQUENCE Operation Operation-VSTPS 1 Level1 2 BOILER STOP VALVE MS STRAINER DRAIN OPENING HPBP CHARGING LPBP CHARGING
OPENING
HPBP WARM UP LINE DRAIN GOES TO Operation Operation-VSTPS 1 Level1 1 UFT SDFT FLASH BOX LP FLASH TANK
LPBP WARM UP LINE DRAIN GOES TO Operation Operation-VSTPS 1 Level1 2 UFT SDFT FLASH BOX NONE
TURBINE IS GENERALLY ROLLED IN GOVERNOR Operation Operation-VSTPS 1 Level1 1 EHTC HYDRAULIC BOTH NONE OF THE ABOVE
Which of the following is not a mode of operation in CMC Operation Operation-VSTPS 1 Level1 4 Co-ordinated mode Boiler-follow mode Turbine-follow mode Rehater mode
To put the system in CMC which of the loops has to be Operation Operation-VSTPS 1 Level1 3 Air master loop Fuel flow control loop Both1 &2 Niether 1 nor 2
kept in auto-mode
Unit Capability depends upon Operation Operation-VSTPS 1 Level1 1 Auxillaries in service Throttle pressure Unit Demand Actual load
Basic Task of EHTC is Operation Operation-VSTPS 1 Level1 1 Control steam flow to Control Boiler Parameters Control turbine speed None of the these
Turbine
Which of the following control loops is a part of EHTC Operation Operation-VSTPS 1 Level1 4 Pressure control Speed Control Load Control All
The Plunger coil feedback is measured by: Operation Operation-VSTPS 1 Level1 1 Collin Transmitter Level Transmitter Speed transmitter None
TSE is needed for which of the following Operation Operation-VSTPS 1 Level1 4 Reduce Thermal stress in To ensure safe operation Increase life of turbine All
turbine
Which controller Set point is affected by TSC Operation Operation-VSTPS 1 Level1 4 Pressure Controller Speed Controller Load Controller Speed and Load Controller
Text Correct Option1 Option2 Option3 Option4
BFP takes suction from 3 Condenser Gland drain tank Deaerator None of these
. . . ; Feed Regulating
The discharge of Boiler feed pumps goes first to : 1 HP heaters Station (FRS) Both of these None of these
When HP bypass valves opens,steam will be diverted to 2 Condenser Reheater Both None of these
The turbine of TDBFP is supplied steam at a pressure of 2 25 Kg/cm2 7 Kg/em2 15 Kg/cm?2 None of these
Steam exhaust from HP turbine goes to 2 IP Turbine Reheater Condenser None of these
Total number of bearings on which the turbine shaft in SOOMW is supported 3 Five Six Seven None of these
In IP turbine and LP turbines steam is admitted 2 At both ends At the centre At one end None of these
Steam leak off from the turbine glands is diverted to 2 Reheater Gland steam Deaerator None of these
Main oil pump is installed 2 On the turbine On the turbine shaft Both of these None of these
The process of drawing steam from intermediate stages of turbine and 1 Regeneration Reheating Both of these None of these
In the feed water heaters feed water flows through 2 Tubes Shell side Both None of these
In the case of Turbine driven Boiler Feed Pump (TDBFP) main pump is Between the At one end of the
2 booster pump and Both None of these
located ‘ shaft
turbine
HP heater — 6A normal drip (condensate) goes to 2 deaerator directly | HP heater-5A shell Both None of these
During initial starting/coast down the required upward thrust on turbine rotor 3 Barring gear Lub oil pump Jacking oil pump None of these
Thermodynamic cycle used in Thermal power plants is 2 Carnot cycle Rankine cycle Joule’s cycle None of these
BFPs supply water for the following 3 Super heater/ HP bypass spray Both the above None of these
The speed of drive turbine of TDBFP at full load is 3 3000-3500 RPM 3000-3500 RPM 5500-5700 RPM None of these
The minimum NPSH required for Boiler Feed Pump is 1 24 mts of WC 15 mts of WC 35 mts of WC None of these
Under normal conditions CEP discharge pressure is 3 30 kg/crmn2 40 kg/cm? 15 kg/cm? None of these
In case of LP heater— 2 level high, its drip gets diverted to 3 LP heater-1 Deaerator Condenser None of these
Low temperature
Feed water after passing through Economiser goes to: 1 super heater Bottom ring header Drum None of these
(LTSH)
500 MW boilers feed water is admitted into drum at a temperature of 2 250 deg C 315 deg C 400 deg C 450 deg C
The speed of drive turbine of TDBFP at full load is 3 3000 - 3500 RPM | 4000 - 4250 RPM 5500 - 5700 RPM 6100 - 6300 RPM
The rated speed of Boiler feed pump Booster pump is 2 1750 RPM 1494 RPM 1884 RPM 3000 RPM
TDBFP turbine can be supplied steam from 4 Extraction — 4 Auxiliary steam CRH line Any of these
In case of TDBFP, emergency lub oil pump supplies oil for 1 Lub oll Control oll Both (a) and (b) None of these
requirement requirement
HP Heaters 5A & 5B are supplied extraction steam at a pressure of 2 8.5 Kg/em2 18.5 Kg/cm2 28.5 Kg/cm2 None of these
i h i h -
HP heaters 6A & 6B are supplied steam from 3 HP turbine 6! IP turbine 8! IP turbine 8th stage IP-LP cross Over
stage stage pipe
Boiler feed pump main pump is having stages 1 4+1 (Kicker stage)| 5+1 (Kicker stage) | 3+1 (Kicker stage) | 6+1 (Kicker stage)
Condensate extraction pump (CEP) supplies water to 4 BFPs’ seals LP bypass spray PRDS spray All of these
Condensate outlet from Gland steam condenser normally goes to 2 LP Heater-1 Gland drain tank Gland Cooler None of these
LP Heater — 3 is supplied steam from LP turbine 5 th LP turbine 3 LP turbine 2 "4 stage None of these
w]o
When LP bypass valve opens steam bypasses LP turbine alone Both IP and LP IP turbine alone None of these
The steam after expansion in HP turbine goes to LP turbine IP turbine Reheater None of these
In Water treatment plant ,Lime is added for Controlling bacteria | Controlling PH Controlling Oxygen None of these
APM POMP
The unit of measurement of turbidity is Micro siemens ppb NTU None of these
In Indian coal ash content will be 5-15% 30-40% 60-70% None of these
The statutory limit for emission of Suspended Particulate Matter(SPM) 115mg/Nm3 15mg/Nm3 515mg/Nm3 None of these
In hydrogen plant the catalyst used is H2S04 K2Cr207 KOH None of these
APOlOINh]/ Alo, Apo, al Ol al aAy APR
In hydrogen plant the chemical added to water is NaOH KCl KOH None of these
For fly ash conveying systems of capacity <60 Tons the system used is Vacuume system |Pressurized system |Both 1&2 None of these
The disadvantage with pressurized fly ash evacuation sysytem is Double gates with Requires separating Limitation of capacity None of these
Bottom ash hopper is supplied with water to Cool the refractory Cool the hot bottom Both the Above None of these
Blow down = Evaporation loss / C.0.C / Evaporation Both the Above None of these
Ash consists of SiO2 Al203 Both the Above None of these
In the ESP voltage applied for the fields is 25 to 40 KV 10 to 15 KV 50 to 95 KV None of these
The gas injected into the ESP stream to improve ash collection is Carbon dioxide Helium Ammonia None of these
Normally HFO temperature is maintained in the range of 90 to 120 degree 70 to 80 degree 130 to 190 degree None of these
The cooling towers used in places with water shortage are Natural draft Forced draft cooling Both the Above None of these
The main disadvantage of reciprocating air compressor is High vibrations Wear and tear of Both the Above None of these
For measuring low temperatures the instrument used is Thermocouple RTD Pyrometer None of these
The output signal of analog instrumens is 4-20 mA DC 4-20 mAAC 4-20 VAC None of these
The thermo couples used for measuring -200 degree to 1200 degree are E-type K-type J-type None of these
OLN
The S-type thermocouples are made of Nickel-Chromium —|Copper-Nickel Platinum-Rhodium None of these
ESP fly ash size will be normally 100 to 600 microns TRUE FALSE
AlTALIM TMI
In a synchronous generator,which of the following statements is true? P is positive,Q is Both P and Q are P is negative,Q is Both P and Q are
Which statement is true for double layer winding? Onlyi Only iii All are true Both i and iii
In short pitched coils,which statement is true Copper per coil Less series/coils per More series/coils per Have larger end
For THDF generator,which statement is true Cooling gas in Stator core and Stator winding is Stator core is
Maximum hotspot temperature allowed in winding with class F insulation 130 deg C 140 degC 155 deg C 120 degC
The bushing chamber of a 5SOOMW generator,is located where on generator Exciter end Turbine end Middle None of these
How many hydrogen coolers are there in 500 MW generator and located in 3,TE end shield 4,EE end shield 4,TE end shield 2,TE end shield
The transposition angle of strands in straight end portion is 540 degree 360 degree 450 degree 270 degree
The rotor winding conductor material is Aluminium Copper Aluminium alloyed Copper alloyed with
The number of stages in cooling fan of 500 MW generator 4 6 5 1
The type of stator winding in 500 MW Generator star Delta Zig Zag Double star
The component in stator that interconnects different coil groups is Bushing Phase connector Flexible connector Teflon hose
NMP OlAlLNMI NIN] AlAlOlAl[NMITBRI NIN
The two poles of generator rotor are displaced by 90 degree 180 degree 120 degree 2/0 degree
The component of generator rotor to contain centrifugal forces due to end Rotor wedge Snap ring End ring Retaining ring
Gas used in 500 MW turbo generator for cooling of rotor and stator core is Nitrogen Hydrogen Helium Air
Inflammability range of Hydrogen in air is 4-74 % 8-98% 4-94 % None of the above
Gas used to purge out Hydrogen in generators is Argon Nitrogen CO2 Air
In 500 MW generators, low DO primary water system NAOH is dozed To maintain PH To maintain To maintain low DO _ |None of the above
The pumps used in seal oil system are Screw pumps Centrifugal pumps __| Negative Axial flow pumps
The element which maintains the diferential pressure between seal oil and Seal ring DPR valve Duplex filter Seal oil tank float
consider following statements ONLY | and Il Only | and Ill All 1,111 only Ill
The primary water conductivity in stator water cooling system is maintained 5 to 6 micro 2 to 3 micro 2 to 3 milli Siemens/ |There is no
Which of the following is used to remove moisture in generator hydrogen refrigeration drier |Vaccum pump Bearing exhaust fan |There is no
Rated casing hydrogen pressure of 500 MW BHEL generator is 6 KSC 2 KSC 3.5 KSC 10 KSC
In 500 MW BHEL double flow seal oil system, the air side seal oil goes to Mixes with bearing |goes to MOT directly |None of the above
In 500 MW BHEL double flow seal oil system,SOT overflow is connected to MOT directly SOST H2 side pump suction |To seals
MPA[ ALA] Ayal APA POPP sAPAL NM] ALO, Al A lOPNiR
The amount of water which is continuously treated in primary water system 10% 20% 2% 50%
Generator winding DP is increasing means choking of Conical filter Filter choking taking |Pump is
DC pump is provided in seal oil system Primary water In both of the above Bearing vapour
If a synchronous motor is running at a leading power factor, its excitation Equal to terminal Higher than the term Less than terminal volt Higher than the
Which type of excitation system has faster response to variation in Generato r terminal volta ge Static Excitation Brushless Both 1&2
Excitation None of these
excitation system is also known as self excitation system Static Excitation Brushless Excitation Both 1&2 None of these
Function of Automatic Voltage regulators are Regulate terminal |meet excitation powq Enable maximum All the above
Salient features of brushless excitation system are Minimum operating |Self generating Simple and reliable All the above
Automatic Voltage regulator is based on Open loop control |Closed loop control |None of these
Manual Mode of operation in voltage regulator is An open loop Voltage is controlled | Both 1&2 Only 2
Dc excitation generated by AVR is done through rectifiers using Thyristors GTOs IGBTs MOSFETs
Field flashing is required in type of Excitation System. Static Brushless
Generator is running with positive MVAr. This means Generator is over excited under excited
If the Generator is operating in leading power factor, the AVR response will be increase the decrease the Do Nothing None of the above
Functions of limiters in AVR is to Limits the Enable the stable Optimum utilization of all the above
Generator is operating in over excited condition. In such case which limiter Stator current Stator current Load angle limiter None of the above
Generator is operating in under excited condition. In such case which limiter Stator current Stator current Load angle limiter Both (b) and (c)
Limiter prevents the machine to operate in unstable region of the Stator current Load angle limiter Stator current
Field current
CONSIDER THE STATEMENT AND CHOOSE THE RIGHT OPTION: "HP TRUE FALSE PARTLY TRUE NONE OF THE
OPAL ALNM] OPO
HP BYPASS VALVE OPERATION IS ENABLED THROUGH WHICH MOTORISED PNEUMATIC HYDRAULIC ALL OF THE
SELECT THE CORRECT STEAM FLOW PATH IN HP BYPASS SYSTEM MS TO HRH MS TO CRH MS TO CONDENSER]JHRH TO
SPRAY FOR TEMPERATURE CONTROL IN HP BYPASS SYSTEM IS BFP DISCHARGE |JCEP DISCHARGE |SUPER HEATER REHEATER SPRAY
FUNCTIONS OF HP-LP BYPASS IN POWER PLANT IS/ARE__? IMPROVE STEAM JPROVIDES STEAM |PROTECTS ALL OF THE
CONSIDER THE STATEMENT AND CHOOSE THE RIGHT OPTION:"HP/ CORRECT PARTLY CORRECT | INCORRECT NONE OF THE
WHICH OF THESE IS NOTA PROTECTION FOR HP-BYPASS SYSTEM? HPBP HPBP CONDENSER ALL OF THE
AfAfRLOPMJAPM
HP BYPASS AUTO OPEN COMMAND IS INITIATED UNDER WHICH TURBINE TRIP GENERATOR TRIP J|EMERGENCY FAST |ALL OF THE
SPRAY FOR LPBYPASS IS TAKEN WHICH SYSTEM? BFP DISCHARGE |JCEP DISCHARGE |SUPER HEATER REHEATER SPRAY
HP AND LP BYPASS SYSTEM ARE USED FOR ? ONLY PRESSURE |JONLY BOTH NONE OF THE
LP BYPASS HELPS CONTROL RH STEAM FLOW DURING ? START UP LOW LOAD /PART |LOAD REJECTION/ JALL OF THE
SELECT THE CORRECT CONDITION WHEN LP BYPASS SYSTEM LPBP SPRAY CONDENSER HRH PRESSURE NONE OF THE
WHEN HP OR LPBYPASS SYSTEM OPERATES WHAT WILL HAPPEN CLOSES FULLY OPENS FULLY STAYS PUT INTHE JALL OF THE
WHICH BYPASS SYSTEM HAS STOP AND CONTROL VALVES FOR ITS HP BYPASS LP BYPASS BOTH HP/LPBP NONE OF THE
AlAs
LP BYPASS PROTECTION ACTS IF CONDENSER WALL TEMPERATURE TRUE FALSE Can't say None
The power consumed by Motor of MDBFP is 10 MW 2 MW 20 MW None
The maximum possible speed at which an alternator can be driven to generate 50 Hz and 15750 V is 2/3000 rpm.
Torque angle (Load Angle) of a synchronous machine operating from a constant voltage bus is usually 4 Rotor mmf wave and stator
In a synchronous generator seen in a power plant, field excitation is achieved by: 1 DC current sent to the
Fastest response time of generator excitation system in modern power plants is usually 4 20-100 milli seconds
Automatic mode of DVR (digital voltage regulator) is a control system, primarily observing which parameter 4 Generator terminal voltage
Which of the following is NOT a component of brushless excitation system 3/ Excitation transformer
Capability curve of a synchronous generator 2 Defines limits of safe
Which of the following is NOT a controlled electronic switch 2|Diode
Calculate the MVA rating of a 500 MW generator designed for operating at power factor of 0.85 3\588 MVA
What is effect of admitting more steam input quantity to turbine by governing valves? 4 Generator frequency
The brushes of electrical machines are made of 1| Carbon
Unbalance 3 - ph stator currents in a synchronous generator cause 4/all in the list
Hydrogen gas purging inside the generator is to be accomplished by 4| Carbon di oxide gas
In a transformer the energy is conveyed from primary to secondary 3 by the flux
Which of the following is not a part of transformer installation ? 4| Exciter
A transformer cannot raise or lower the voltage of a D.C. supply because 1 Faraday's laws of
Primary winding of a transformer 3 could either be a low voltage
Efficiency of a power transformer is of the order of 1 98 per cent
In a given transformer for given applied voltage, losses which remain constant irrespective of load changes 3 hysteresis and eddy current
Anot common method of cooling a power transformer is 4 WFAF
Transformer breaths in when 1} load on it decreases
The chemical used in breather for transformer should have the quality of 2 absorbing moisture
The chemical used in breather is 4 silica gel
Buchholz's relay gives warning and protection against 1 electrical fault inside the
In alternators, cylindrical pole type rotors are generally used with prime movers of 1 High speed
A synchronous generator is said to be overexcited when it is operating at 2} Leading power factor
What was the NTPC’s contribution in power generation in India in 2014-15: 2 0.25
Which is largest power plant in India: 2 Vindhyachal, NTPC
Eligibility Criteria for Maharatna in terms of average annual turnover during the last 03 years — 1/of more than Rs 25000 Crore
Both Navratna and Maharatna category CPSEs have the delegated power to incur CAPEX on purchase of 1, TRUE
Indian power sector is governed by: 2 Electricity Act, 2003
Current total Geneartion Capacity of NTPC is 3,51708 MW
Assessment of growth opportunities is part of 1 corporate planning
Choice of location of a thermal power plant depends on 4 all of the above
Land & water commitment is given by 2 State Govt
Zero date of a Project is defined by 1|Date of award of main plant
FQP is used during 3| Inspection of any item/activity
Chain pulley blocks are used as 1 Material lifting equipments
In case of alignment of rotating equipments, if shaft axes intersect each other, it is called 2) Angular off-set
Effects of misalignment are 4/All of the above
In erection sequence 1 TG box up’ precedes 'TG on
Main steam comes out from the boiler 3|Final super heater
Function of boiler drum is 4/All in the list
The use of primary air in a boiler is for 4 Carrying pulverized coal to
ESP work on the principal of 1|Corona Effect
What is the function of servomotor assy. in axial fans in modern boiler 4) To adjust the blade pitch
Secondary air in a pulverized fuel boiler is used to 2\ Assist in complete
How to control the load in ID fan NDZV47S in 500MW 3\/by IGV & VFD
The parameter used by ASME to define fans, blowers and compressors is 2| Specific r atio
Electrical Switchgear is consider as low voltage Switchgear if it is rated up-to 2)1kV
In Switchgears, isolators used for 3 Isolating the circuit under no
Which of the following circuit breakers has the lowest operating voltage 2 Air break
Thermal overload relay is used to protect the motor against 2 heavy loads
A circuit breaker is 3) a current interrupting device
Which among these is the least expensive protection for over currents in low voltage system 1\fuse
The Fuse rating is expressed in terms of 2 Ampere
Which principle is an important aspect in the good management of coal stack pile ? 4 First in Fi rst out
At NTPC Sipat,coal is received from which pithead mine? 3) Dipka Mines
Which is the equipment used to evacuate coal from Track Hoppers at Sipat? 1 Paddle Feeders
To pick & throw off any ferrous metal from running conveyor belt,which equipment is used? 4 ILMS(In line Magnetic
Arrange the correct sequence ,to transmit power from Motor to Belt Conveyors. 2 Motor--F luid Coupling--
In case of fire,to detect and spray water over conveyor belts ,which system is used? 3) Deluge Valves
Which is the Protection switch tied with pull cord (wire), to stop the conveyor in case of any hazard to 4 Pull Cord Switch
~
What are the four major types of coal found in India? 4 Peat, lign ite, semi-
What are the three components that are needed to form fossil fuels? 4 Organic material, heat,
What is the long term capacity addition target of NTPC 1,128 GW by 2032
Project Development phase / period is in the range of 3/18 to 24 months
otal number of coal mines in NTPC — 2 8.0
What is the solar installed capacity of NTPC: 4/870 MW
Text Correct Option1 Option2 Option3 Option4
BFP takes suction from 3 Condenser Gland drain tank Deaerator None of these
. . . ; Feed Regulating
The discharge of Boiler feed pumps goes first to : 1 HP heaters Station (FRS) Both of these None of these
When HP bypass valves opens,steam will be diverted to 2 Condenser Reheater Both None of these
The turbine of TDBFP is supplied steam at a pressure of 2 25 Kg/cm2 7 Kg/em2 15 Kg/cm?2 None of these
Steam exhaust from HP turbine goes to 2 IP Turbine Reheater Condenser None of these
Total number of bearings on which the turbine shaft in SOOMW is supported 3 Five Six Seven None of these
In IP turbine and LP turbines steam is admitted 2 At both ends At the centre At one end None of these
Steam leak off from the turbine glands is diverted to 2 Reheater Gland steam Deaerator None of these
Main oil pump is installed 2 On the turbine | On the turbine shaft Both of these None of these
The process of drawing steam from intermediate stages of turbine and 1 Regeneration Reheating Both of these None of these
In the feed water heaters feed water flows through 2 Tubes Shell side Both None of these
In the case of Turbine driven Boiler Feed Pump (TDBFP) main pump is Between the At one end of the
2 booster pump and Both None of these
located . shaft
turbine
HP heater — 6A normal drip (condensate) goes to 2 deaerator directly | HP heater-5A shell Both None of these
During initial starting/coast down the required upward thrust on turbine rotor 3 Barring gear Lub oil pump Jacking oil pump None of these
Thermodynamic cycle used in Thermal power plants is 2 Carnot cycle Rankine cycle Joule’s cycle None of these
BFPs supply water for the following 3 Super heater/ HP bypass spray Both the above None of these
The speed of drive turbine of TDBFP at full load is 3 3000-3500 RPM 3000-3500 RPM 5500-5700 RPM None of these
The minimum NPSH required for Boiler Feed Pump is 1 24 mts of WC 15 mts of WC 35 mts of WC None of these
Under normal conditions CEP discharge pressure is 3 30 kg/crmn2 40 kg/cm? 15 kg/cm? None of these
In case of LP heater— 2 level high, its drip gets diverted to 3 LP heater-1 Deaerator Condenser None of these
Low temperature
Feed water after passing through Economiser goes to: 1 super heater Bottom ring header Drum None of these
(LTSH)
500 MW boilers feed water is admitted into drum at a temperature of 2 250 deg C 315 deg C 400 deg C 450 deg C
The speed of drive turbine of TDBFP at full load is 3 3000 - 3500 RPM | 4000 - 4250 RPM 5500 - 5700 RPM 6100 - 6300 RPM
The rated speed of Boiler feed pump Booster pump is 2 1750 RPM 1494 RPM 1884 RPM 3000 RPM
TDBFP turbine can be supplied steam from 4 Extraction — 4 Auxiliary steam CRH line Any of these
In case of TDBFP, emergency lub oil pump supplies oil for 1 Lub oll Control oll Both (a) and (b) None of these
requirement requirement
HP Heaters 5A & 5B are supplied extraction steam at a pressure of 2 8.5 Kg/em2 18.5 Kg/cm2 28.5 Kg/cm2 None of these
j h j h -
HP heaters 6A & 6B are supplied steam from 3 HP turbine 9° IP turbine 8! IP turbine 8th stage IP-LP cross over
stage stage pipe
Boiler feed pump main pump is having stages 1 4+1 (Kicker stage)| 5+1 (Kicker stage) | 3+1 (Kicker stage) | 6+1 (Kicker stage)
Condensate extraction pump (CEP) supplies water to 4 BFPs’ seals LP bypass spray PRDS spray All of these
Condensate outlet from Gland steam condenser normally goes to 2 LP Heater-1 Gland drain tank Gland Cooler None of these
LP Heater — 3 is supplied steam from LP turbine 5 th LP turbine 3 ' LP turbine 2 "4 stage None of these
o
The statutory limit for emission of Suspended Particulate Matter(SPM) 115mg/Nm3 15mg/Nm3 515mg/Nm3 None of these
In hydrogen plant the catalyst used is H2S04 K2Cr207 KOH None of these
In hydrogen plant the chemical added to water is NaOH KCl KOH None of these
For fly ash conveying systems of capacity <60 Tons the system used is Vacuume system |Pressurized system |Both 1&2 None of these
The disadvantage with pressurized fly ash evacuation sysytem is Double gates with Requires separating Limitation of capacity None of these
Bottom ash hopper is supplied with water to Cool the refractory Cool the hot bottom Both the Above None of these
Blow down = Evaporation loss / C.0.C / Evaporation Both the Above None of these
NM] A]][ Osa] Oya
For measuring low temperatures the instrument used is Thermocouple RTD Pyrometer None of these
The output signal of analog instrumens is 4-20 mA DC 4-20 mA AC 4-20 VAC None of these
The thermo couples used for measuring -200 degree to 1200 degree are E-type K-type J-type None of these
iO
The S-type thermocouples are made of Nickel-Chromium —|Copper-Nickel Platinum-Rhodium None of these
PO
ESP fly ash size will be normally 100 to 600 microns TRUE FALSE
In ESP,AC voltage is applied across the fields TRUE FALSE
MI] ALAlLM TNO
The difference between cooled water temperature and wet bulb TRUE FALSE
Reciprocating compressors are positive displacement type TRUE FALSE
In stator water system NaOH IS added to maintain PH TRUE FALSE
For 50Hz system,if the speed of generator rotor is 500 RPM,what are the 14 poles, cylindrical 12 poles, salient 10 poles, salient 8 poles, cylindrical
In a synchronous generator,which of the following statements is true? P is positive,Q is Both P and Q are P is negative,Q is Both P and Q are
Al OPRTOPRINT
Which statement is true for double layer winding? Onlyi Only iii All are true Both i and iii
In short pitched coils,which statement is true Copper per coil Less series/coils per More series/coils per Have larger end
For THDF generator,which statement is true Cooling gas in Stator core and Stator winding is Stator core is
Maximum hotspot temperature allowed in winding with class F insulation 130 deg C 140 degC 155 deg C 120 degC
The bushing chamber of a 5SOOMW generator,is located where on generator Exciter end Turbine end Middle None of these
How many hydrogen coolers are there in 500 MW generator and located in 3,TE end shield 4,EE end shield 4,TE end shield 2,TE end shield
OPA] AO]
The transposition angle of strands in straight end portion is 540 degree 360 degree 450 degree 2/0 degree
The rotor winding conductor material is Aluminium Copper Aluminium alloyed Copper alloyed with
The number of stages in cooling fan of 500 MW generator 4 6 5 1
The type of stator winding in 500 MW Generator star Delta zig zag Double star
MIB
The component in stator that interconnects different coil groups is Bushing Phase connector Flexible connector Teflon hose
The two poles of generator rotor are displaced by 90 degree 180 degree 120 degree 270 degree
RIN
The component of generator rotor to contain centrifugal forces due to end Rotor wedge Snap ring End ring Retaining ring
Gas used in 500 MW turbo generator for cooling of rotor and stator core is Nitrogen Hydrogen Helium Air
hMP NM] OPAL NMI NIN] AlAlOl AlN
Inflammability range of Hydrogen in air is 4-74 % 8-98% 4-94 % None of the above
Gas used to purge out Hydrogen in generators is Argon Nitrogen CO2 Air
In 500 MW generators,low DO primary water system NAOH is dozed To maintain PH To maintain To maintain low DO _|None of the above
The pumps used in seal oil system are Screw pumps Centrifugal pumps _| Negative Axial flow pumps
The element which maintains the diferential pressure between seal oil and Seal ring DPR valve Duplex filter Seal oil tank float
consider following statements ONLY | and Il Only | and Ill All 1,111 only Ill
The primary water conductivity in stator water cooling system is maintained 5 to 6 micro 2 to 3 micro 2 to 3 milli Siemens/ |There is no
Which of the following is used to remove moisture in generator hydrogen refrigeration drier |Vaccum pump Bearing exhaust fan |There is no
Rated casing hydrogen pressure of 500 MW BHEL generator is 6 KSC 2 KSC 3.5 KSC 10 KSC
In 500 MW BHEL double flow seal oil system, the air side seal oil goes to Mixes with bearing |goes to MOT directly |None of the above
In 500 MW BHEL double flow seal oil system,SOT overflow is connected to MOT directly SOST H2 side pump suction |To seals
The amount of water which is continuously treated in primary water system 10% 20% 2% 50%
NM] APO, Al APO
Generator winding DP is increasing means choking of Conical filter Filter choking taking |Pump is
DC pump is provided in seal oil system Primary water In both of the above Bearing vapour
If a synchronous motor is running at a leading power factor, its excitation Equal to terminal Higher than the term Less than terminal volt Higher than the
Which type of excitation system has faster response to variation in Generato r terminal volta ge Static Excitation Brushless Excitation Both 1&2 None of these
excitation system is also known as self excitation system Static Excitation Brushless Excitation Both 1&2 None of these
Function of Automatic Voltage regulators are Regulate terminal |meet excitation powq Enable maximum All the above
A POPM PALA
Salient features of brushless excitation system are Minimum operating |Self generating Simple and reliable |All the above
Automatic Voltage regulator is based on Open loop control |Closed loop control |None of these
Manual Mode of operation in voltage regulator is An open loop Voltage is controlled | Both 1&2 Only 2
De excitation generated by AVR is done through rectifiers using Thyristors GTOs IGBTs MOSFETs
Field flashing is required in type of Excitation System. Static Brushless
[A] A [Ale
Generator is running with positive MVAr. This means Generator is over excited under excited
If the Generator is operating in leading power factor, the AVR response will be increase the decrease the Do Nothing None of the above
Functions of limiters in AVR is to Limits the Enable the stable Optimum utilization of all the above
Generator is operating in over excited condition. In such case which limiter Stator current Stator current Load angle limiter None of the above
OlOPNMsAPTA
Generator is operating in under excited condition. In such case which limiter Stator current Stator current Load angle limiter Both (b) and (c)
Limiter prevents the machine to operate in unstable region of the Stator current Load angle limiter Stator current Field current
CONSIDER THE STATEMENT AND CHOOSE THE RIGHT OPTION: “HP TRUE FALSE PARTLY TRUE NONE OF THE
HP BYPASS VALVE OPERATION IS ENABLED THROUGH WHICH MOTORISED PNEUMATIC HYDRAULIC ALL OF THE
SELECT THE CORRECT STEAM FLOW PATH IN HP BYPASS SYSTEM MS TO HRH MS TO CRH MS TO CONDENSER]HRH TO
ALM
SPRAY FOR TEMPERATURE CONTROL IN HP BYPASS SYSTEM IS BFP DISCHARGE |JCEP DISCHARGE |SUPER HEATER REHEATER SPRAY
FUNCTIONS OF HP-LP BYPASS IN POWER PLANT IS/ARE___? IMPROVE STEAM |PROVIDES STEAM |PROTECTS ALL OF THE
MOPAR
CONSIDER THE STATEMENT AND CHOOSE THE RIGHT OPTION:"HP/ CORRECT PARTLY CORRECT | INCORRECT NONE OF THE
WHICH OF THESE IS NOTA PROTECTION FOR HP-BYPASS SYSTEM? HPBP HPBP CONDENSER ALL OF THE
HP BYPASS AUTO OPEN COMMAND IS INITIATED UNDER WHICH TURBINE TRIP GENERATOR TRIP |EMERGENCY FAST {ALL OF THE
AlAlNMTAlTAPR LOMB
SPRAY FOR LPBYPASS IS TAKEN WHICH SYSTEM? BFP DISCHARGE |CEP DISCHARGE |SUPER HEATER REHEATER SPRAY
HP AND LP BYPASS SYSTEM ARE USED FOR ? ONLY PRESSURE |JONLY BOTH NONE OF THE
LP BYPASS HELPS CONTROL RH STEAM FLOW DURING ? START UP LOW LOAD /PART |LOAD REJECTION/ JALL OF THE
SELECT THE CORRECT CONDITION WHEN LP BYPASS SYSTEM LPBP SPRAY CONDENSER HRH PRESSURE NONE OF THE
WHEN HP OR LPBYPASS SYSTEM OPERATES WHAT WILL HAPPEN CLOSES FULLY |OPENS FULLY STAYS PUT IN THE |JALL OF THE
WHICH BYPASS SYSTEM HAS STOP AND CONTROL VALVES FOR ITS HP BYPASS LP BYPASS BOTH HP/LPBP NONE OF THE
LP BYPASS PROTECTION ACTS IF CONDENSER WALL TEMPERATURE TRUE FALSE Can't say None
The power consumed by Motor of MDBFP is 10 MW 2 MW 20 MW None
Text | Correct Option] Option1 Option2 Option3 Option4
BFP takes suction from 3 Condenser Gland drain ta] Deaerator None of these
The discharge of Boiler feed pumps goes first {1 HP heaters Feed Regulatin} Both of these |None of these
When HP bypass valves opens,steam will be dj/2 Condenser Reheater Both None of these
The turbine of TDBFP is supplied steam at a py2 25 Kg/cm2 7 Kg/cm2 15 Kg/cm?2 None of these
Steam exhaust from HP turbine goes to 2 IP Turbine Reheater Condenser None of these
Total number of bearings on which the turbing3 Five Six Seven None of these
In IP turbine and LP turbines steam is admitte{2 At both ends |At the centre |At one end None of these
Steam leak off from the turbine glands is diva 2 Reheater Gland steam c] Deaerator None of these
Main oil pump is installed | 2 On the turbine] On the turbing Both of these |None of these
The process of drawing steam from intermedi] 1 Regeneration |Reheating Both of these |None of these
In the feed water heaters feed water flows thiy2 Tubes Shell side Both None of these
In the case of Turbine driven Boiler Feed Pum Between the h At one end of t Both None of these
HP heater— 6A normal drip (condensate) goes deaerator dire HP heater-5A Both None of these
During initial starting/coast down the require Barring gear Lub oil pump Jacking oil pun None of these
Thermodynamic cycle used in Thermal power Carnot cycle
Rankine cycle Joule’s cycle None of these
BFPs supply water for the following Super heater/r] HP bypass spra Both the above None of these
The speed of drive turbine of TDBFP at full loa 3000-3500 RPI 3000-3500 RPN 5500-5700 RPN None of these
The minimum NPSH required for Boiler Feed F 24 mts of WC}15 mts of WC | 35 mts of WC | None of these
Under normal conditions CEP discharge press 30 kg/cm? 40 kg/cm? 15 kg/cm2 None of these
In case of LP heater— 2 level high, its drip gets LP heater-1 Deaerator Condenser None of these
Feed water after passing through Economiser|1 Low temperatu Bottom ring ha Drum None of these
500 MW boilers feed water is admitted into dy2 250 deg C 315 deg C 400 deg C 450 deg C
The speed of drive turbine of TDBFP at full loa3 3000 - 3500 RF 4000 - 4250 RA 5500 - 5700 RA6100 - 6300 R
The rated speed of Boiler feed pump Booster |2 1750 RPM 1494 RPM 1884 RPM 3000 RPM
TDBFP turbine can be supplied steam from = |4 Extraction — 4} Auxiliary stear] CRH line Any of these
In case of TDBFP, emergency lub oil pump sug Lub oil require Control oil req Both (a) and (h None of these
HP Heaters 5A & 5B are supplied extraction st{2 8.5 Kg/cm2 |18.5 Kg/em2 128.5 Kg/cm2 |None of these
HP heaters 6A & 6B are supplied steam from |3 HP turbine 54 IP turbine 81 /1P turbine 8] IP-LP cross ovd
Boiler feed pump main pump is having 1 4+1 (Kicker st{ 5+1 (Kicker st{3+1 (Kicker sta 6+1 (Kicker st
Condensate extraction pump (CEP) supplies w/4 BFPs’ seals LP bypass spr4 PRDS spray |All of these
Condensate outlet from Gland steam condeng2 LP Heater-1 | Gland drain ta] Gland Cooler | None of these
The statutory limit for emission of Suspended 115mg/Nm3 |15mg/Nm3 |[515mg/Nm3_ |None of these
In hydrogen plant the catalyst used is H2S04 K2Cr207 KOH None of these
In hydrogen plant the chemical added to wate NaOH KCl KOH None of these
For fly ash conveying systems of capacity <60 Vacuume syste Pressurized syg Both 1&2 None of these
The disadvantage with pressurized fly ash eva Double gates W Requires separ] Limitation of c None of these
Bottom ash hopper is supplied with water to Cool the refrac Cool the hot b Both the Abov None of these
Blow down = | Evaporation lo C.0.C / Evapor: Both the Abov None of these
Wp Ry
The gas injected into the ESP stream to impro Carbon dioxide Helium Ammonia None of these
Normally HFO temperature is maintained in th 90 to 120 degr 70 to 80 degre 130 to 190 deg None of these
Oo] MT]
The cooling towers used in places with water Natural draft c Forced draft cd Both the Abov None of these
The main disadvantage of reciprocating air co High vibrationg Wear and tear Both the Abov None of these
For measuring low temperatures the instrume Thermocouple] RTD Pyrometer None of these
Wt
The output signal of analog instrumens is 4-20 mADC |4-20mAAC_ [4-20 VAC None of these
GW) MTR]
The thermo couples used for measuring -200 E-type K-type J-type None of these
The S-type thermocouples are made of Nickel-Chromiu Copper-Nickel Platinum-Rhod None of these
ESP fly ash size will be normally 100 to 600 mi 1
Ny]
CO] ©
es
Which statement is true for double layer wind Onlyi Only iii All are true Both i and iii
In short pitched coils,which statement is true Copper per coi Less series/coi More series/ca Have larger en
For THDF generator,which statement is true Cooling gas in Stator core and Stator winding Stator core is c
Oo] By
Maximum hotspot temperature allowed in wi 130 degC 140 deg C 155 degC 120 degC
The bushing chamber ofa SOOMW generator, Exciter end Turbine end |Middle None of these
rR]
How many hydrogen coolers are there in 500 3,TE end shield 4,EE end shield 4,TE end shield 2,TE end shield
Wp
The transposition angle of strands in straight 4 540 degree 360 degree 450 degree 270 degree
BPR]
The rotor winding conductor material is Aluminium Copper Aluminium alld Copper alloyed
The number of stages in cooling fan of 500 M 4 6 5 1
Wo
The type of stator winding in 500 MW Genera star Delta zig zag Double star
BY]
The component in stator that interconnects d Bushing Phase connect} Flexible conned Teflon hose
BP RP my BP NMP NM
The two poles of generator rotor are displace 90 degree 180 degree 120 degree 270 degree
The component of generator rotor to contain Rotor wedge |Snap ring End ring Retaining ring
Gas used in 500 MW turbo generator for cooll Nitrogen Hydrogen Helium Air
Inflammability range of Hydrogen in air is 4-74% 8-98% 4-94% None of the ab
Gas used to purge out Hydrogen in generatorg Argon Nitrogen co2 Air
In 500 MW generators,low DO primary water To maintain PH To maintain co To maintain lov None of the ab
NMP RP RY]
The pumps used in seal oil system are Screw pumps Centrifugal pur Negative displa Axial flow pum
The element which maintains the diferential p Seal ring DPR valve Duplex filter Seal oil tank fla
consider following statements ONLY [and Il Only | and III only Ill
WP RE NMP MP
AIL LIU
The primary water conductivity in stator wate 5 to 6 micro Sig 2 to 3 micro Sig 2 to 3 milli Sier There is no req
Which of the following is used to remove moi refrigeration d Vaccum pump Bearing exhaug There is no me
Rated casing hydrogen pressure of 500 MW B 6 KSC 2 KSC 3.5 KSC 10 KSC
In 500 MW BHEL double flow seal oil system, goes to precha Mixes with bed goes to MOT d None of the ab
WP RP Ry WP BPN
In 500 MW BHEL double flow seal oil system, MOT directly SOST H2 side pump To seals
The amount of water which is continuously tr 0.1 0.2 0.02 0.5
Generator winding DP is increasing means choking of con Conical filter ch Filter chokingt Pump is malfu
DC pump is provided in | seal oil system Primary water In both of the Bearing vapou
If a synchronous motor is running at a leading| Equal to termin Higher than th Less than term Higher than th
Which type of excitation system has faster res Static Excitatio Brushless Excit! Both 1&2 None of these
BP RP Rp Rp Ry ep mp By BP MPR]
excitation system is also known as § Static Excitatio{Brushless Excit| Both 1&2 None of these
Function of Automatic Voltage regulators are Regulate termi] meet excitatioy Enable maximy All the above
Salient features of brushless excitation system Minimum opey Self generating Simple and reli] All the above
Automatic Voltage regulator is based on Open loop con| Closed loop co] None of these
Manual Mode of operation in voltage regulata An open loop § Voltage is cont|Both 1&2 Only 2
Dc excitation generated by AVR is done throug Thyristors GTOs IGBTs MOSFETs
Field flashing is required in___ type of Static Brushless
Generator is running with positive MVAr. This over excited |under excited
If the Generator is operating in leading power increase the ey decrease the e]Do Nothing None of the ab
Functions of limiters in AVR is to Limits the excit Enable the sta Optimum utiliz all the above
Generator is operating in over excited conditid Stator current Stator current Load angle lim None of the ab
BPR
Generator is operating in under excited condit Stator current Stator current Load angle lim Both (b) and {qd
Limiter prevents the machine to operd Stator current Load angle lim Stator current Field current nf
NM
HP BYPASS VALVE OPERATION IS ENABLED THA MOTORISED |PNEUMATIC |HYDRAULIC ALL OF THE AB
RP NM]
SELECT THE CORRECT STEAM FLOW PATH IN MS TO HRH MS TO CRH MS TO CONDEJHRH TO COND
SPRAY FOR TEMPERATURE CONTROL IN HP BY BFP DISCHARG| CEP DISCHARG]|SUPER HEATER] REHEATER SPR
FUNCTIONS OF HP-LP BYPASS IN POWER PLAN IMPROVE STEA PROVIDES STE4 PROTECTS REH| ALL OF THE AB)
BP
CONSIDER THE STATEMENT AND CHOOSE THE CORRECT PARTLY CORRE{INCORRECT NONE OF THE
WHICH OF THESE IS NOTA PROTECTI HPBP DOWNSTHPBP DOWNSJT CONDENSER V4 ALL OF THE AB)
By WP my BPM]
HP BYPASS AUTO OPEN COMMAND IS INITIAT TURBINE TRIP | GENERATOR THEMERGENCY F4 ALL OF THE AB)
SPRAY FOR LPBYPASS IS TAKEN WHICH SYSTEM BFP DISCHARG| CEP DISCHARG]|SUPER HEATER] REHEATER SPR
HP AND LP BYPASS SYSTEM ARE USED FOR___] ONLY PRESSUR| ONLY TEMPERA BOTH TEMPER] NONE OF THE
LP BYPASS HELPS CONTROL RH STEAM FLOW | START UP LOW LOAD /PAJLOAD REJECTIG ALL OF THE AB
SELECT THE CORRECT CONDITION WHEN LP B LPBP SPRAY W4 CONDENSER V4HRH PRESSURG NONE OF THE
MP RP}
WHEN HP OR LPBYPASS SYSTEM OPERATES W CLOSES FULLY OPENS FULLY |STAYS PUT IN T|ALL OF THE AB
WHICH BYPASS SYSTEM HAS STOP AND CONT HP BYPASS LP BYPASS BOTH HP/LPBP] NONE OF THE
LP BYPASS PROTECTION ACTS IF CONDENSER 1 0 Can't say None
PPR
BFP takes suction from 3 Condenser Gland drain tank Deaerator None of these
The discharge of Boiler feed pumps goes first to : 1 HP heaters Feed Regulating Both of these None of these
9 PUMPS g Station (FRS)
When HP bypass valves opens,steam will be diverted to 2 Condenser Reheater Both None of these
The turbine of TDBFP is supplied steam at a pressure of 2 25 Kg/cm? 7 Kg/em? 15 Kg/cm? None of these
Steam exhaust from HP turbine goes to 2 IP Turbine Reheater Condenser None of these
Total number of bearings on which the turbine shaft in 500MW is 3 Five Six Seven None of these
supported is
In IP turbine and LP turbines steam is admitted 2 At both ends At the centre At one end None of these
Steam leak off from the turbine glands is diverted to 2 Reheater Gland steam Deaerator None of these
condenser
The process of drawing steam from intermediate stages of turbine and 1 Regeneration Reheating Both of these None of these
using it for heating feed water is called
In the feed water heaters feed water flows through 2 Tubes Shell side Both None of these
: . : : : Between the
In the case of Turbine driven Boiler Feed Pump (TDBFP) main pump is 2 booster pump and At one end of the Both None of these
located shaft
turbine
HP heater-5A shell
HP heater — 6A normal drip (condensate) goes to deaerator directly Both None of these
side
Thermodynamic cycle used in Thermal power plants is Carnot cycle Rankine cycle Joule’s cycle None of these
Super
BFPs supply water for the following heater/reheater HP bypass spray Both the above None of these
spray
The speed of drive turbine of TDBFP at full load is 3000-3500 RPM 3000-3500 RPM 5500-5700 RPM None of these
The minimum NPSH required for Boiler Feed Pump is 24 mts of WC 15 mts of WC 35 mts of WC None of these
Under normal conditions CEP discharge pressure is 30 kg/cm?” 40 kg/cm? 15 kg/cm? None of these
In case of LP heater — 2 level high, its drip gets diverted to LP heater-1 Deaerator Condenser None of these
Low temperature
Feed water after passing through Economiser goes to: super heater |Bottom ring header Drum None of these
(LTSH)
500 MW boilers feed water is admitted into drum at a temperature of 250 deg C 315 deg C 400 deg C 450 deg C
(approx)
The speed of drive turbine of TDBFP at full load is 3000 - 3500 RPM 4000 - 4250 RPM 5500 - 5700 RPM 6100 - 6300 RPM
The rated speed of Boiler feed pump Booster pump is 1750 RPM 1494 RPM 1884 RPM 3000 RPM
TDBFP turbine can be supplied steam from Extraction -— 4 Auxiliary steam CRH line Any of these
Lub oil Control oil
In case of TDBFP, emergency lub oil pump supplies oil for Both (a) and (b) None of these
requirement requirement
HP Heaters 5A & 5B are supplied extraction steam at a pressure of 8.5 Kg/om 18.5 Kg/em2 28.5 Kgicm” None of these
Boiler feed pump main pump is having stages ee) ota) 3+1 (Kicker stage) O ege)
Condensate extraction pump (CEP) supplies water to BFPs' seals LP bypass spray PRDS spray All of these
Condensate outlet from Gland steam condenser normally goes to LP Heater-1 Gland drain tank Gland Cooler None of these
Both IP and LP
When LP bypass valve opens steam bypasses LP turbine alone IP turbine alone None of these
turbines
The steam after expansion in HP turbine goes to LP turbine IP turbine Reheater None of these
In Water treatment plant ,Lime is added for ronvolng Controlling PH Controlling Oxygen |None of these
The unit of measurement of turbidity is Micro siemens ppb NTU None of these
In Indian coal ash content will be 5-15% 30-40% 60-70% None of these
The statutory limit for emission of Suspended Particulate Matter(SPM) 415mg/Nm3 15mg/Nm3 515mg/Nm3 None of these
through stack is
In hydrogen plant the catalyst used is H2S04 K2Cr207 KOH None of these
In hydrogen plant the chemical added to water is NaOH KCl KOH None of these
For fly ash conveying systems of capacity <60 Tons the system used Vacuume system Pressurized Both 1&2 None of these
is system
Bottom ash hopper is supplied with water to Cool the refractory |Cool the hot Both the Above None of these
lining bottom ash
The gas injected into the ESP stream to improve ash collection is Carbon dioxide Helium Ammonia None of these
Normally HFO temperature is maintained in the range of 90 to 120 degree 70 to 80 degree 130 to 190 degree None of these
For measuring low temperatures the instrument used is Thermocouple RTD Pyrometer None of these
The output signal of analog instrumens is 4-20 mA DC 4-20 mA AC 4-20 V AC None of these
The thermo couples used for measuring -200 degree to 1200 degree E-type K-type J-type None of these
are
The S-type thermocouples are made of Nickel-Chromium Copper-Nickel Platinum-Rhodium None of these
ESP fly ash size will be normally 100 to 600 microns TRUE FALSE
temperature ic called "Renge" water temperature and wet bulb TRUE FALSE
For 50Hz system,if the speed of generator rotor is 500 RPM,what are 14
12 poles,salient 10 poles,salient 8 poles,cylindrical
the number of poles on rotor and what is type of rotor used? poles, cylindrical
Maximum hotspot temperature allowed in winding with class F 130 deg C 140 deg C 155 deg C 120 deg C
insulation
The bushing chamber ofa 500MW generator,is located where on Exciter end Turbine end Middle None of these
generator
The transposition angle of strands in straight end portion is 540 degree 360 degree 450 degree 270 degree
The rotor winding conductor material is Aluminium Copper Aluminium alloyed Copper alloyed
with silver with silver
The type of stator winding in 500 MW Generator star Delta Zig zag Double star
The component in stator that interconnects different coil groups is Bushing Phase connector |Flexible connector |Teflon hose
The two poles of generator rotor are displaced by 90 degree 180 degree 120 degree 270 degree
The component of generator rotor to contain centrifugal forces due to Rotor wedge Snap ring End ring Retaining ring
end winding are
Gas used in 500 MW turbo generator for cooling of rotor and stator
core is Nitrogen Hydrogen Helium Air
Inflammability range of Hydrogen in air is 4-74 % 8-98% 4-94 % None of the above
Gas used to purge out Hydrogen in generators is Argon Nitrogen CO2 Air
To maintain
In 500 MW generators,low DO primary water system NAOH is dozed To maintain PH conductivity To maintain low DO_ [None of the above
Negative
The pumps used in seal oil system are Screw pumps Centrifugal pumps displacement pumps Axial flow pumps
The element which maintains the diferential pressure between seal oil
and hydrogen at seals in seal oil system is Seal ring DPR valve Duplex filter Seal oil tank float
consider following statements
|.Generator tripping is provided if winding flow reduces 48 tph
||.Generator tripping is provided if bushing flow increases more than 1.6 ONLY land Il Only | and Ill All LILI only Ill
There is no
The primary water conductivity in stator water cooling system is 5 to 6 micro 2 to 3 micro 2 to 3 milli requirement to
maintained at Siemens/cm Siemens/cm Siemens/cm maintain
There is no
Which of the following is used to remove moisture in generator mechanism to
hydrogen refrigeration drier Vaccum pump Bearing exhaust fan remove moisture
Rated casing hydrogen pressure of 500 MVV BHEL generator is 6 KSC 2 KSC 3.5 KSC 10 KSC
goes to Mixes with bearing
prechamber and lube oil and goes
In 500 MW BHEL double flow seal oil system, the air side seal oil there to SOT to SOST goes to MOT directly [None of the above
In 500 MW BHEL double flow seal oil system,SOT overflow is H2 side pump
connected to MOT directly SOST suction To seals
If a synchronous motor is running at a leading power factor, its Equal to terminal Higher than the Less than terminal Higher than the
excitation induced voltage (Ef) is voltage V terminal voltage V voltageV terminal voltage V
Which type of excitation system has faster response to variation in Static Excitation |Brushless Both 1&2 None of these
Generator terminal voltage System Excitation System
Dc excitation generated by AVR is done through rectifiers using Thyristors GTOs IGBTs MOSFETs
If the Generator is operating in leading power factor, the AVR response increase the decrease the
will be excitation excitation Do Nothing None of the above
Enable the stable |Optimum utilization
Limits the operation of of Machine
Functions of limiters in AVR is to excitation Machine. capability all the above
Generator is operating in over excited condition. In such case which Stator current Stator current
limiter will become active if the excitation increases inductive limiter capacitive limiter Load angle limiter None of the above
Generator is operating in under excited condition. In such case which Stator current Stator current
limiter may become active inductive limiter capacitive limiter Load angle limiter Both (b) and (c)
Limiter prevents the machine to operate in unstable region of Stator current Stator current Field current
the capability curve capacitive limiter Load angle limiter inductive limiter maximum limiter
CONSIDER THE STATEMENT AND CHOOSE THE RIGHT
OPTION:"HP BYPASS SYSTEM IS USED ONLY FOR LIGHT UP NONE OF THE
ACTIVITY" TRUE FALSE PARTLY TRUE ABOVE
SPRAY FOR TEMPERATURE CONTROL IN HP BYPASS SYSTEM IS BFP DISCHARGE |CEP DISCHARGE |SUPER HEATER REHEATER
TAKEN FROM ? HEADER HEADER SPRAY LINE SPRAY LINE
IMPROVE STEAM|PROVIDES PROTECTS
TEMPERATURE/ |STEAM PATH REHEATER COILS JALL OF THE
FUNCTIONS OF HP-LP BYPASS IN POWER PLANT IS/ARE__? PRESSURE IN DURING LOAD FROM ABOVE
CONSIDER THE STATEMENT AND CHOOSE THE RIGHT
OPTION:"HP/LP BYPASS SYSTEMS CAN BE OPERATED IN THE PARTLY NONE OF THE
ABSENCE OF VACUUM IN CONDENSER" CORRECT CORRECT INCORRECT ABOVE
HPBP HPBP CONDENSER
WHICH OF THESE IS NOTA PROTECTION FOR HP-BYPASS DOWNSTREAM |DOWNSTEAM VACUUM PR ALL OF THE
SYSTEM? TEMP V.HIGH TEMP V.LOW V.HIGH ABOVE
HP BYPASS AUTO OPEN COMMAND IS INITIATED UNDER WHICH GENERATOR EMERGENCY FAST /ALL OF THE
CONDITIONS? TURBINE TRIP _|TRIP OPEN COMMAND _ [ABOVE
WHICH BYPASS SYSTEM HAS STOP AND CONTROL VALVES FOR 2 NONE OF THE
ITS NORMAL OPERATION? HP BYPASS LP BYPASS BOTH HP/LPBP ABOVE
1
The power consumed by Motor of MDBFP is 10 MW 2 MW 20 MW None
Correct : : : :
Text Option Option’ Option2 Option3 Option4
HP BYPASS VALVE OPERATION IS ENABLED THROUGH WHICH MEDIUM? 3}MOTORISED PNEUMATIC HYDRAULIC ALL OF THE ABOVE
SELECT THE CORRECT STEAM FLOW PATH IN HP BYPASS SYSTEM 2)]MS TO HRH MS TO CRH MS TO CONDENSER HRH TO CONDENSER
SPRAY FOR TEMPERATURE CONTROL IN HP BYPASS SYSTEM IS TAKEN FROM BFP DISCHARGE CEP DISCHARGE SUPER HEATER SPRAY |REHEATER SPRAY
_? 1]HEADER HEADER LINE LINE
IMPROVE STEAM PROVIDES STEAM PROTECTS REHEATER
TEMPERATURE/PRE |PATH DURING LOAD |COILS FROM
FUNCTIONS OF HP-LP BYPASS IN POWER PLANT IS/ARE___? 4|SSURE IN STARTUP |THROWOFF STARVATION ALL OF THE ABOVE
SELECT THE CORRECT CONDITION WHEN LP BYPASS SYSTEM TRIPS FROM LPBP SPRAY WATER |CONDENSER
OPERATION? 1|]PRESSURE LOW VACUUM PR OK HRH PRESSURE LOW _ {NONE OF THE ABOVE
STAYS PUT IN THE
WHEN HP OR LPBYPASS SYSTEM OPERATES WHAT WILL HAPPEN TO THE CLOSES FULLY OR PREVIOUS OPEN
BYPASS VALVES? ZERO PERCENT OPENS FULLY POSITIONN ALL OF THE ABOVE
BR
WHICH BYPASS SYSTEM HAS STOP AND CONTROL VALVES FOR ITS NORMAL
OPERATION? 2}]HP BYPASS LP BYPASS BOTH HP/LPBP NONE OF THE ABOVE
1
The power consumed by Motor of MDBFP is 10 MW 2 MW 20 MW
1 IP turbine
Steam exhaust from HP turbine goes to LP turbine Reheater
Total number of bearings on which the turbine shaft in 500MW is ale 7 8
supported is
3
In IP turbine and LP turbines steam is admitted At one end At both ends At the centre
On the turbine On the turbine
Main oil pump is installed main oil tank shaft itself None of the above
The process of drawing steam from intermediate stages of
turbine and using it for heating feed water is called Regeneration Reheating None of the above
In the feed water heaters feed water flows through Tubes Shell side Both
The discharge of Boiler feed pumps goes first to HP heaters FRS None of the above
In the case of Turbine driven Boiler Feed Pump (TDBFP) main booster pump At one end of the
pump is located and turbine shaft None of the above
Deaerator HP heater-5A
HP heater — 6A normal drip (condensate) goes to directly shell side None of the above
During initial starting/coast down the required upward thrust on
turbine rotor is provided by: Barring gear Lub oil pump Jacking oil pump
Boiler feed Pump takes suction from Condenser Gland drain tank De-aerator
Thermodynamic cycle used in Thermal power plants is Carnot cycle Rankine cycle Joule’s cycle
heater/reheater
BFPs supply water for the following spray HP bypass spray Both the above
The speed of drive turbine of TDBFP at full load is 3000-3500 RPM 4000-4250 RPM 5500-5700 RPM
The minimum NPSH required for Boiler Feed Pump is 24 mts of WC 15 mts of WC 35 mts of WC
LP exhaust hood
CEP supplies water to spray LP bypass spray Both the above
2 Gland Steam
Steam leak off from the turbine glands is diverted to Reheater Condenser Deaerator
2
HP heater — 5A alternate drip (condensate) goes to HP heater -6A Condenser Deaerator
Keeping Mrpine On
3|Bringing turbine _|barring
During shut down, bowing/sagging of the turbine rotor is avoided by to complete rest gear/turning gear None of the above
2
Re heater spray water is supplied by CEP BFP None of the above
2
Normal drip from LP Heater-3 goes to Condenser LP Heater-2 Deaerator
1
LP heaters are of Shell & tube type ‘|Plate type Direct-in-contact
3
TDBFP turbine can be supplied steam from Auxiliary steam CRH line Both the above
2)5+1 (Kicker
Boiler feed pump main pump is having stages stage) 4+1 (Kicker stage |3+1 (Kicker stage)
IP turbine 98"
N
HP heaters 6A & 6B are supplied steam from stage CRH line HP turbine 5” stage
Correct . . . .
Text . Option1 Option2 Option3 Option4
Option
Gas turbine operates on 3 rankine cycle joule cycle brayton cycle None of these
which consumes more power in Gas turbine 2 Pump compressor fan None of these
In combined cycle Gas turbine exhaust is passed through 2 condenser steam generator atmosphere None of these
In gas turbine Gas is used in 2 steam generator combustor compressor None of these
advantage of gas turbine 2 low power cost environment friendly|Both 1&2 None of these
which is a gas power plant of NTPC 2 Jhajar kawas bhilai north karnapura
two const pressure |two const pressure |two const volume and |two const pressure
Gas turbine cycle consists of 4 and two contant and two contant two contant entropy |and two contant
temp process volume process process entropy process
In gas turbine compressor is directly coupled to TG YES NO
which is not a feature of Gas turbine ? quick start black start facility compactness high instalation time
Pricinciple of Sea back Effect is used in RTD Thermocouple Bourdon Gauge Accoustic pyrometer
Change over of
Change over valve is used for Primary oil SV change over Trip Device Blocking |RTS change over
Value of Atmospheric pressure is indepandant of Altitude Temperature Seasons of the year Day of the month
Thermal Stress is NOT calculated in which components HPS HPCV IPC IPS
Furnace temperature probe uses Thermocouple RTD Accoustic pyrometer |Coreolis Force
Differential
Flow measurement uses Temperature Differential Pressure |Differential Flow Differential Level
Apart from DP, Flow can be measured using Ultrasonic meter Accoustic pyrometer Bourdon Gauge Mercury Switches
Temperature
Mercury Switches are generally used in Pressure Switch Over Voltage Relay |Flow Switches Switches
Bimetallic Strip is generally used in Flow Switch Over Load Relay Pressure Switch Level Switch
Atmospheric Above Absolute
Gauge Pressure always shows Pressure Absolute Pressure Above Atmospheric Pressure
BOP in DCS means Boiler Project Balance Of Project Balance of Plant Balance of Payment
The major field(s) of application of gas turbine is (are) Aviation Oil and gas industry |Marine propulsion |All of the above
The percentage of total energy input appearing as net work output of the Combustion Compression
p 8 By Inpurapp 8 p Thermal efficiency . Turbine efficiency . P
cycle efficiency efficiency
The ratio of heat actually released by 1kg of fuel to heat that would be . Combustion . . Compression
_ Thermal efficiency . Turbine efficiency .
released by complete perfect combustion, is called efficiency efficiency
Combined Cycle power plant is....... efficient than steam turbine plant more less same None of the above
Capital cost of a gas turbine plant is ........ than that of a steam power plant of .
. same lower higher None of the above
same capacity
A gas turbine works on which cycle? Carnot Brayton Dual cycle Rankine cycle
Either Reciprocating
Reciprocating Multistage axial flow
Which type of compressor is used in a gas turbine plant? Screw compressor compressor & Screw
compressor compressor
compressor
Kerosene oil and
. . . . , . . Natural gas and
The gas turbine power plant mainly uses which among the following fuels? Coal and Peat diesel oil and Gas oil a
, . liquid petroleum fuel
residual oil
What part or % of power developed is utilised for driving the compressor? 25% 80% 65% 50%
Which is not a component of Combustion Chamber Combustion Liner |Flow Sleeve Fuel Nozzle Bleed Valve
Oil used in governing system lub oil FRF JACKING OIL None of these
. we . de-synchronised
Role of speed controller is when TG is in synchronised state state Both 1&2 None of these
RGMO or FGMO is influenced by grid frequency load set point grid voltage None of these
auxiliary secondary oil is generated from trip oil at starting device speeder gear barring gear None of these
pressure of this oil varries with the speed of the turbine test oil primary oil aux secondary oil None of these
control fluid pump is AC driven DC driven both AC and DC driven |None of these
What amount of steam can HP by pass valves can bypass 20% 70% 50% 100%
After HP bypass steam enters condenser IP turbine CRH line None of these
Pneumatic
Hp bypass is which type of valve Hydraulic Electrical None of these
What are the rated parameters of Main steam 150 kg,300deg 100 kg,300deg 170 kg,500deg 170 kg,540deg
BFP
Spray for LP bypass is from CEP CWP None of these
When HP bypass valves open they bypass HP turbine HP & IP turbine HP & LP turbine None of these
When HP bypass valve opens steam goes to Reheater Condenser LP turbine None of these
The standard interface between the command transmitters and None of these
receivers is called Sub group control Control Interface Sub loop control
MS pressure is <12
Automatic Control Interface (ACI) will be ON when HRH pressure is <12 HRH pressure is >12 None of these
Kg/cm? Kg/cm? Ke/em*
Unit level control consist of Sub group control | Sub loop contro! Control interface All of these
ATRS consists of SGC oil SGC turbine SGC evaculation All of these
SGC oil supply directly acts on SLC turning gear SLC AOP SLC EOP All of these
In which mode of ATRS, all the criteria for a particular step are Operator guide
Step-by- step mode Automatic mode None of these
simulated manually mode
. oe . . ¢Reduction of .
Higher Cycle thermal efficiency is for Conservation of fuel Low tariff All of the Above
resources
CO2,SO,& NOx
Cri Temp - 253.9 °C Cri Temp - 273.9 °C Cri Temp - 373.9 °C & CriTemp- 540°C &
At Critcal point the parameters of water are
& Crit Pres-215 bar & Crit Pres-125 bar Crit Pres-225 bar Crit Pres-165 bar
With increase in Absolute Pressure of feed water flow into boiler, which of the decrease in latent Increase in latent No change in latent
None of the above
following is corrrect heat addition heat addition heat of addition
Initially during startup in Once through design which Boiler auxiliary serves waterwall Outlet .
Storage tank Separator Economiser
the purpose of Drum Header
Major differences from Drum type boiler in comparision with Once through Low load Circulation
: Evaporator System Separator All of the above
boile System
In once through design during full load condition the state of fluid after Slightly Super Mixture of water and Fully superheated as
Hot water state
passing through water wall before going to Separator heated steam Main steam
In once through design the temp of fluid after passing through water wall
Not uniform Constant Can't Say Mostly uniform
tubes before going to Separator
Water walls & Water walls & Super Super heater & Economiser &
The alloy steel T91 Material is used in which Pressure parts Elements
Economiser Heater Reheater Tubes Reheater
What is the Principle of bottom ash evacuation from Boiler bottom ash hoper
at Simhadri? Centrifugal Ejection conveying displacement
How many clinker grinders are placed in bottom ash hoper at each 500 MW 5 3 4 2
unit of Simhadri?
Bottom ash hoper filled with water, which pump it caters? BAHP BALP FWP
Where Vacuum created during bottom de-ashing from BAH ? Ejector/jetpump feed gate clinker grinder none of these
Which pump is used to pump bottom slurry from BAH to Ash slurry sump ? Centrifugal pump = |jet pump reciprocating pump vertical pump
Which pump fed water to jet pump suction to transfer ash slurry from BAH to
Slurry sump? BAHP BALP FAHP FWP
2 1 3 4
Clinker grinder is having how many rollers to grind clinkers at simhadri ?
Clinker flow controlled by _ Ss to. enter in grinder Feed gate gate valve transmitter check valve
What is the percentage of bottom ash and dry ash generated in furnace of *20:80 *80:20 *30:70 *70:30
boiler?
Which pumps will pump lean ash slurry up to ash dyke from ash slurry sump.? Vertical pumps Centrifugal Pump Reciprocating pump none of these
from where dry ash will be issued to users ESP Economizer Ash silo BAH
Which System is installed for return of Water from Ash Dyke area to re-use Ash Water Re- Transport Water
main plant. circulation System Ash Slurry System Ash Water System System.
To control fugitive dust emission in Ash Dyke area, we use Sprinkler System Wind Barriers Water Spray All of the above
Which Insulation is used to Protect Bottom Ash Hopper ? Glass Wool Cement Refractory None
to protect Hopper
To quench and Insulation and to channelize flow
Why is Bottom Ash Hopper filled with Water? collect ash/ plates/ through grinders all of the above.
Of which Material is Clinker Grinder Rolls Generally made? Grey Cast Iron Stainless Steel Manganese Steel Mild Steel
Which Equipment is used to vary speed of Pump ina Ash Slurry Series? Gear Box Variable Pulley Fluid Coupling VFD
what is the use of FAHP pump flyash in to slurry to feed sump to feed boiler hopper none of these
Dry /fly ash used in manufacturing of & steel &plastic cement & brick carbon & lime none of these
Rail head plant near to mine far away from mine |near to railway station
None
UHV of Coal is more than GCV equal to GCV less than GCV
None
Pneumatic bottom
BOBR wagons unloaded by WAGON TIPLER Manually :
opening door
None
Coal size that is bypassed to crusher less than 20 mm less than 200 mm more than 20 mm
Coal having B-M index are highly prone to auto-oxidation >50 > 60 > 80
None
Loss in CV of coal increases with higher size of coal {smaller size of coal |indipendent of size
None
Conveyor tripping involved in case of Magnetic separator |Metal detector in both cases
None
Bucket wheel is used for stacking coal bunkering coal reclaiming coal watering coal
Boom conveyor is used in track hopper stacker reclaimer crusher house bunkering
Which are belt protection pull chord zero speed belt sway all option
Skirt board is located at belt tail end at belt head end return side of belt
None
take up pulley facilitate to rotate the belt belt tension adjust the belt sway
None
idlers used to absorb shock return idler troughing idler impact idler
None
crusher hammers are made of manganese steel cast steel stain less steel mild steel
vibrating screen placed after crusher before coal mill before crusher
None
coal from wagons unloaded at silo track hopper crusher coal bunker
Transformers does not vary Voltage Current frequency None of the above
Transformer humming is mainly due to Eddy current loss Copper loss Hysterysis loss Stray loss
More magnetic
In core type of transformers..... More copper . More steel More insulation
material
Which is not a Transformer rating? Power Voltage ratio Oil volume power factor
Indian Standard for Power Transformers IS: 2026 IS: 2062 IS: 6020 IS: 2620
Vector group rotation standard? does not rotate clock wise anti-clock wise both directions
Heat trasfer mode in case of Transformer oil? Conduction Convection Radiation Does not transfer
Maximum cooling efficiency is achieved in which cooling method? ONAN ONAF OFAF ODAF
Buchholtz Relay is type of? Electrical Mechanical Electrostatic Hydraulic
upto 50% of
Oil is filled in a transformer upto what level? upto Tank level only upto conservator full upto 50% of radiator
conservator
Which Oil test determines for oil replacement? Moisture test BDV test Acidic test Resistivity test
To the voltage levels from higher to lower level or vice versa, keeping the
power constant , What is used Transformer Circuit Breaker lsolator generator
What is used to Makes or breaks the electrical circuits under normal and
abnormal conditions Transformer Circuit Breaker lsolator generator
What is Used to connect the charged body (voltage on dead line) to ground to
discharge the trapped charge (to have a safe maintenance zone) Lightning Arrester |Circuit Breaker lsolator Earth Switch
Material used for conductors are Aluminum Copper ACSR All of the above
Generally, following clearances are adopted for outdoor Switchyards between
phases and phase to earth.
Minimum clearance required for 400KV Level between phase to earth 2.1Mtr 6.4Mtr 3.5Mtr 1.3Mtr
Minimum clearance required for 220KV Level between phase to earth 2.1Mtr 6.4Mtr 3.5Mtr 1.3Mtr
Minimum clearance required for 765KV Level between phase to earth 2.1Mtr 6.4Mtr 3.5Mtr 1.3Mtr
A device that detects the fault and initiates the operation of the Circuit
breaker to isolate the defective element from the rest of the system Relay CT CVT None of the above
What is used in Arc Quenching in Circuit Breakers SF6 Air Blast Vacuum All of the above
No Stability and
Step-up/Step-down synchronising Low cost due to less
Advantages of AC transmission over DC transmission is possible problems copper requirement Less Corona and RI
Requirement of
Step-up/Step-down Requires more Transposition of
Advantages of DC transmission over AC transmission is possible copper conductors Less Corona and RI
Provides path for
Protects from Provides return path Optical fiber through
Over head earth wire on transmission towers are used for Lightning strokes during faults ground wire All of the above
Where is VFD deployed in 500mw NTPC units PA fan FD fan Coal mills ID fan
What type of VFD is used in ID fan PWM type cycloconvertor LCI VSI
LCI VFD drives employs principle of variable voltage variabale frequency |both A&B none of the above
precise speed
what are the advantage of vfd Low capital cost control both 1&2 None of the above
IN a speed vs torque plot 1" quadrant represents forward motoring reverse motoring forward breaking reverse breaking
IN a speed vs torque plot 2nd quadrant represents forward motoring reverse motoring forward breaking reverse breaking
IN a speed vs torque plot 3rd quadrant represents forward motoring reverse motoring forward breaking reverse breaking
IN a speed vs torque plot 4th" quadrant represents forward motoring reverse motoring forward breaking reverse breaking
Which among the following will you advice where energy conservation is
crucial inlet guide vane VFD Outlet Damper control Scoop control
Does not require
commutation Size and cost of Can operate at higher
What are advantages of LCI drive circuits inverter is reduced power levels All the above
Large Synchronous motor does not self start TRUE False Both 1&2 None of the above
Applying low Slip ring induction
frequency and Damper windings
in [DC motor to start main}motor to start main
Technique used for starting motor in BHEL make LCI Drives is voltage motor motor motor
Purpose of fuel oil flame stability startup shutdown ignition support all
What is the BMCR of each oil elevation in 500 MW unit 7.50% 5% 30% 50%
Tracing steam is provided for HFO LDO Lube oil control fluid
Air is used for atomization of HFO LDO Lube oil control fluid
Non sparking tools are used in handling of HFO LDO Hydrogen all
Hydrogen is used for cooling of Fuel oil generator seal oil lube oil
high thermal
Advantage of h2 Gas low density conductivity both none
Hydrogen leak alarm activated at 40% of LEL 20%of LEL 40% HEL 20% HEL
Type of Circuit breakers used in EHV applications ACB VCB SF6 Oil
Earth switch can be closed only when Isolator is closed lsolator is opened In all cases Never
To reduce short circuit currents, these are used Resistors Reactors Capacitors None of the above
Reactor used in the switchyard is of which type? Series Shunt Series-Shunt All of the above
Low melting point Low melting point Low melting point
and high specific and Low specific High melting point and and any specific
Material used for fuse must have resistance resistance Low specific resistance resistance
Either in series or
A fuse is connected in Series with circuit Parallel with circuit parallel None of the above
The impurities in raw water are mainly classified into Dissolved solids Suspended solids Both 1 &2 None of the Above
Clarifier-Aerator-GSF-
Aerator-GSF- Aerator-DMP-GSF- Aerator-Clarifier-GSF-
DMP
Mark the correct process/steps followed in Pre-Treatment Plant Clarifier-DMP Carifier DMP
What are the main disinfectants and coagulants used in Pre-Treatment Plant
respectively EDTA- Alum Oxygen-Lime Chlorine-Alum None of the above
To increase To decrease
Lime is used mainly for conductivity To decrease pH conductivity To Increase pH
During Demineralization process the residual chlorine present in incoming Strong Acid Weak Acid Mixed Bed Activated Carbon
water is being removed by Exchanger Exchanger filter
The cations and anions are being exchanged in ACF and MB SAC and SBA SBA only SAC only
The regenerated resin in SAC(strong Acid Cation Exchager ) is in the form of OH- form Chloride form Both H+ and OH- form H+ form
Silica is mainly removed in Weak Base Anion Strong Acid cation Strong base Anion Both A and B
The Capacity of a battery is expressed in terms of Current rating Voltage rating ampere-hour rating None of the above
The specific gravity of a electrolyte is measured by Mano meter Hydrometer Mechanical gauge Psychometer
High current
Number of cells connected in series provide a carrying capacity Higher Voltage higher power None of the above
Manufactures of Lead acid batteries in India Amco shaft HBL Knife Exide batteries All of the above
Electrolyte used in lead acid cell is NaoH Only H2S04 Only Water Dilute H2S04
A Battery is a series or parallel combination of electrolytic cells. TRUE FALSE
Float mode in the battery charger Constant Current Constant Frequency Constant Voltage All of the above
High current
Number of cells connected in parallel provide a carrying capacity Higher Voltage higher power None of the above
Engine generator
Batteries are charged by Rectifiers sets Motor generator sets Any of the above
Text Subject Module Difficulty Correct Option) Option1 Option2 Option3 Option4
In impulse turbine pressure drop occurs in........ PPF PPF VSTPS-2 LEVEL1 2 moving blades) nozzles guide blade all of theses
in reaction turbine pressure drop occurs in....... PPF PPF VSTPS-2 LEVEL1 4 moving blades) nozzles guide blade moving blades
In nozzles of impulse turbine, Velocity of steam jet... | PPF PPF VSTPS-2 LEVEL1 1 INCREASES decreases remain constar None of these
In moving blade of impulse turbine, Velocity of steam jet) PPF PPF VSTPS-2 LEVEL1 2 INCREASES decreases remain constar None of these
In nozzles of impulse turbine, Pressure of steam jet..... | PPF PPF VSTPS-2 LEVEL1 2 INCREASES decreases remain constar None of these
In moving blade of reaction turbine, pressure of steam je PPF PPF VSTPS-2 LEVEL1 2 INCREASES decreases remain constar None of these
Compounding is required in Turbine to control.... PPF PPF VSTPS-2 LEVEL1 3 pressure temperature |speed None of these
RateauTurbin | Curtis Turbine
Velocity compounded impulse turbine is known as ...... PPF PPF VSTPS-2 LEVEL1 2 e Moore Turbine None of these
RateauTurbin | Curtis Turbine
Pressure compounded impulse turbine is known as ...... PPF PPF VSTPS-2 LEVEL1 1 e Moore Turbine None of these
RateauTurbin | Curtis Turbine
pressure & velocity compounded impulse turbine is knov PPF PPF VSTPS-2 LEVEL1 3 e curtis & Moore None of these
Purpose of balancing drum in casing is to PPF PPF VSTPS-2 LEVEL1 1 Thrust balance) temperature bi Flow balance | all of theses
Purpose of lacing wire in last stages in turbine rotors PPF PPF VSTPS-2 LEVEL1 4 enhance naturi damping vibrat thrust balencin option 1 & 2
Alignments of Turbine rotors caters... PPF PPF VSTPS-2 LEVEL1 3 Axial alignmeni radial alignmer both option 1 swing check
Barring gear is required for... PPF PPF VSTPS-2 LEVEL1 3 uniform coolin; Uniform heatir both option 1 § None of these
During shut down, barring gear is required for PPF PPF VSTPS-2 LEVEL1 1 uniform coolin; Uniform heatir both option 1 § None of these
during start up/ light up of power plant unit, barring gea PPF PPF VSTPS-2 LEVEL1 2 uniform coolin; Uniform heatir both option 1 § None of these
Seal steam system incorporated in system to ..... In turbir PPF PPF VSTPS-2 LEVEL1 1 avoid air ingres venting reduction of be all of theses
Labyrinth gland seals used for... PPF PPF VSTPS-2 LEVEL1 2 step be step dr step be step dr magnification ¢ None of these
Effect on Specific volume of steam when propagated thre PPF PPF VSTPS-2 LEVEL1 1 INCREASES decreases remain constar None of these
Size of turbine blades increases from inlet to exit of stear PPF PPF VSTPS-2 LEVEL1 3 increased pres! increased tem, increased sp. V None of these
What is FGD? PPF PPF VSTPS-2 LEVEL1 4 Full Gas Dispos Full Gas Desulp Flue Gas Desul) Flue Gas Desul
What is the purpose of installing of FGD plant? PPF PPF VSTPS-2 LEVEL1 3 Disposal of Ask Disposal of NO) Removal of SO) All of the abov:
FGD plant at Vindhyachal is designed for treatment of... | PPF PPF VSTPS-2 LEVEL1 2 90% flue gas |Up to 100% flu 25% flue gas |50% flue gas
What input is required in absorber tank to absorb Sulphu PPF PPF VSTPS-2 LEVEL1 4 Gypsum powdé Gypsum slurry | Limestone pow Limestone slur
The temp of inlet flue gas is reduced below 80 deg before PPF PPF VSTPS-2 LEVEL1 3 For cooling off To prevent hea To prevent the) For better cher
GGH in FGD plantis... PPF PPF VSTPS-2 LEVEL1 2 Gas to Gypsum Gas to Gas Hea Gypsum to Gas Gas to Gas Hea
The size of crushed limestone used as input in wet type b PPF PPF VSTPS-2 LEVEL1 4 100mm & less 60mm & less |40mm & less | 20mm & less
If FGD plant is kept in service for treatment of 100% flue | PPF PPF VSTPS-2 LEVEL1 1 The bypass dar The bypass dar The bypass dar It is never poss
The quantity of gypsum produced per hour will depend ¢ PPF PPF VSTPS-2 LEVEL1 3 The quantity oj The quantity oj Both (Option 1) The quantity o”
The function of GGH is to... PPF PPF VSTPS-2 LEVEL1 1 Reduce temp c Reduce temp c Increase temp | None of the ab
Hydrocyclones are used in... PPF PPF VSTPS-2 LEVEL1 2 Reaction tank |Gypsum handli Booster fans |Limestone han
Gypsum produced in FGD plant can be used in... PPF PPF VSTPS-2 LEVEL1 3 Textile industri) Paper Industrie Cement Indust| Steel Industrie:
As per govt. regulations, the max. allowable SOx in chimr PPF PPF VSTPS-2 LEVEL1 1 200 mg/Nm3_ | 2000 mg/Nm3) 220 mg/Nm3_ |20 mg/Nm3
What is the function of gypsum bleed pump? PPF PPF VSTPS-2 LEVEL1 2 Remove excess Remove gypsul Remove lime s| Remove chloric
What type of ball mills are installed in FGD plant? PPF PPF VSTPS-2 LEVEL1 3 Dry ball mill | Semi dry ball m Wet ball mill | None of the ab
Treated flue gas discharged in to environment through... | PPF PPF VSTPS-2 LEVEL1 2 A separate chir Same chimney) Chimney is not Directly from a
In which equipment, main reaction of SOx removal takes) PPF PPF VSTPS-2 LEVEL1 4 Ball mill Booster fan GGH Absorber tank
What is the function of absorber re-circulation pumps? | PPF PPF VSTPS-2 LEVEL1 2 Re-circulate gy| Re-circulate lin Re-circulate wz Re-circulate flu
How much NOx can be removed in FGD plant? PPF PPF VSTPS-2 LEVEL1 1 Zero % 0.5 0.8 1
What is the main by-product of VSTPS FGD system? PPF PPF VSTPS-2 LEVEL1 4 Lime Calcium Carboi Sodium Chloric Gypsum
The water used to cool lube oil coolers of turbine and ge| PPF PPF VSTPS-2 LEVEL1 2 CW water ECW water Service water | Fire water
The water used to cool ECW in PHE is called as PPF PPF VSTPS-2 LEVEL1 4 CW water ECW water Service water |ACW water
Which water is used for cooling of seal water in vacuum | PPF PPF VSTPS-2 LEVEL1 4 CW water ECW water Service water ACW water
Which water is used in condenser for cooling purpose? | PPF PPF VSTPS-2 LEVEL1 1 Clarified water), DM Water Raw Water drinking water
What is the type of cooling water system in 500 MW Uni! PPF PPF VSTPS-2 LEVEL1 4 Open system | Raw Water sysiDM Water syst] DM Water clos
How many PHE are used in a unit of 500 MW PPF PPF VSTPS-2 LEVEL1 4 Two Three Four five
COOLING MEDIUM FOR THE GENERATOR EXCITER COOLE PPF PPF VSTPS-2 LEVEL1 1 DM WATER AIR RAW WATER | HYDROGEN
In which material PHE plates are made of ? PPF PPF VSTPS-2 LEVEL1 3 bronge brass stainless steal | alloy steel
Capacity of Equipment Cooling Water overhead tank for PPF PPF VSTPS-2 LEVEL1 3 1)30m3 2)20 m3 3)10m3 4)40 m3
Routine maintenance is not consist of PPF PPF VSTPS-2 LEVEL1 4 Performance oj The alignment | Bearings shoul! Checking of im
Conditions for Shutdown of the pump for trouble shootir PPF PPF VSTPS-2 LEVEL1 4 Poor in pump f£ Excessive noise Excessive vibra| all of the abov
Which type of problem is found for trouble shooting in ¢ PPF PPF VSTPS-2 LEVEL1 2 mechanical driver related | hydraulic all of the abov
Mechanical troubles in centrifugal pumps is consist of | PPF PPF VSTPS-2 LEVEL1 3 Failure to deliv) reduction in dis Breakage of co) loading of the
Hydraulic troubles in centrifugal pumps is consist of PPF PPF VSTPS-2 LEVEL1 3 Breakage of co| Breakage of sk Failure to deliv Breakage of im
When will centrifugal pumps not able is discharge water.| PPF PPF VSTPS-2 LEVEL1 Low discharge | Speed of electr Bent shaft Gland Packing°
RN
When will Overloading of Motor/ Engine is takes place |PPF PPF VSTPS-2 LEVEL1 Gland Packing | Worn wearing | Damaged impe Defective foot'
When will centrifugal pumps not able to provide enough| PPF PPF VSTPS-2 LEVEL1 Bent shaft wearing rings v Pump speed tc Distorted casin
PORN)
Which among following is not a part of condensate syste| PPF PPF VSTPS-2 LEVEL1 BFP LP Heater CEP GSC
Condensate extraction pump is PPF PPF VSTPS-2 LEVEL1 Multistage cen| Single stage ce) Reciprocating ,¢ Screw type pur
Tubes of condenser are PPF PPF VSTPS-2 LEVEL1 U shaped tube! straight tube | Spiral tube none of the ab
WIN
nos of tubes in stage-1 condenser of VSTPS PPF PPF VSTPS-2 LEVEL1 23938 24398 16700 19000
THE SPEED OF BOOSTER PUMP OF MOTOR DRIVEN BOILE PPF PPF VSTPS-2 LEVEL1 LESS THEN MO) EQUAL TO MO) MORE THAN M NONE OF ABO\
BIN
Number of working and standby condensate extraction ¢ PPF PPF VSTPS-2 LEVEL1 1 working & 2 $1 working & 132 working & 2 $2 working & 1:
fuction of deaerator is/are PPF PPF VSTPS-2 LEVEL1 PROVIDE NPSH AS FEED HEATE REMOVES DISC All of the abov:
|B
Boiler feed pump is PPF PPF VSTPS-2 LEVEL1 Multistage cen| Single stage ce) Reciprocating ,¢ Screw type pur
WR
Nos of Boiler feed pump in 500 MW units of NTPC VSTPS PPF LEVEL1 1 MDBFP and 22 MDBFP & 1 1/3 MDBFP 3 TDBFP
Which is not a part of BFP rotating assembly PPF PPF VSTPS-2 LEVEL1 Impeller Shaft Diffuser all of the above
Booster Pump of BFP is PPF PPF VSTPS-2 LEVEL1 Multistage cen| Single stage ce) Reciprocating ,¢ Screw type pur
BIN
Which of the following zone is not apart of HP heater |PPF PPF VSTPS-2 LEVEL1 Desuperheatin| condensing zor subcooloing zo none of the ab
numbers and capacity of drip pumps PPF PPF VSTPS-2 LEVEL1 2 and 50% capi 1 and 50% capi 2 and 100% caj| 1 and 100% cay
WwW
Function of booster pump is PPF PPF VSTPS-2 LEVEL1 To provide fee To Ensure NPSk To Ensure NPSi None of the ab
ONIN)
Nos. of stages in boiler feed pump of 210 MW at NTPC V! PPF PPF VSTPS-2 LEVEL1 9 11 14 7
Rotational speed of 500 MW CEP in VSTPS PPF PPF VSTPS-2 LEVEL1 3000 1485 4500 5200
NIN
Deaerator works on the following principle PPF PPF VSTPS-2 LEVEL1 carnot cycle |henery'slaw |pascal'slaw | none of the ab
The purpose of the balancing device in BFP is PPF PPF VSTPS-2 LEVEL1 TO provide NP{ To perform sha to balance the| none of the ab
es)
function of AOP in boiler feed pumps is to PPF PPF VSTPS-2 LEVEL1 Provide lubrica supply oil for si Both 1 & 2 None of the ab
condensation of steam takes place in? PPF PPF VSTPS-2 LEVEL1 hotwell condenser vacuum pump | PRDS
WINN)
LP HEATER -1 IS SITUATED IN ? PPF PPF VSTPS-2 LEVEL1 CONDENSER > HOTWELL SEPARATOR TA) NONE
VACUUM IN CONDENSER IS CREATED BY? PPF PPF VSTPS-2 LEVEL1 VACUUM PUM| CONDENSATIO| HOTWELL NONE
PIN
LOCATION OF VACUUM PUMP? PPF PPF VSTPS-2 LEVEL1 TGOM TG 8.5 M TG 17M NONE
CW TEMPERATURE IN CONDENSER? PPF PPF VSTPS-2 LEVEL1 DECREASES INCREASES both NONE
WIN
HOW MANY MOP IN KWU TURBINE 500 MW? PPF PPF VSTPS-2 LEVEL1 2 3 1 4
LOCATION OF MOP? PPF PPF VSTPS-2 LEVEL1 MOT ROOM FRONT PEDEST EXCITER END | BEARING NO.2
NIN
HOW MANY AOP IN KWU TURBINE 500 MW? PPF PPF VSTPS-2 LEVEL1 1 2 3 4
HOW MANY JOP IN KWU TURBINE 500 MW? PPF PPF VSTPS-2 LEVEL1 4 3 2 1
PW
HOW MANY EOP IN KWU TURBINE 500 MW? PPF PPF VSTPS-2 LEVEL1 1 2 3 4
LOCATION OF MOT ROOM? PPF PPF VSTPS-2 LEVEL1 TGOM TG 8.5 M TG 17M NONE
RIN
HOW MANY VAPOUR FANS FOR TURBINE LUBE OIL SYSTE PPF PPF VSTPS-2 LEVEL1 2 3 1 NONE
THE RECOMMENDED SPECIFICATION OF TURBINE LUB OI PPF PPF VSTPS-2 LEVEL1 SERVO PRIME - SERVO PRIME - SERVO PRIME - SERVO PRIME -
NW
MOP COMES IN SERVICE when turbine speed reaches ? | PPF PPF VSTPS-2 LEVEL1 210 2800 540 none
FUNCTION OF JOP IS ? PPF PPF VSTPS-2 LEVEL1 LUBRICATION € ROTATION OF F LIFTING OF RO} NONE
WW
LOCATION OF MOT CENTRIFUGE? PPF PPF VSTPS-2 LEVEL1 TG FLOOR FRONT PEDEST MOT ROOM |TGOM
What type of boilers are used at 500 MW units of VSTPS; PPF PPF VSTPS-2 LEVEL1 Forced circulat) dry bottom Water Tube |All of the abov
BIB
Which of these pressure parts components are located ir PPF PPF VSTPS-2 LEVEL1 Water wall Reheater Platen Super hi LTSH
Which of these is a common weld defect PPF PPF VSTPS-2 LEVEL1 Overheating | Porosity Corrosion none
NM
Correct
Text Option Option1 Option2 Option3 Option4
BFP takes suction from 3 Condenser Gland drain tank Deaerator None of these
. : . : Feed Regulating
The discharge of Boiler feed pumps goes first to : 1 HP heaters Station (FRS) Both of these None of these
When HP bypass valves opens,steam will be diverted to 2 Condenser Reheater Both None of these
The turbine of TDBFP is supplied steam at a pressure of 2 25 Kg/cm? 7 Kgicmn? 15 Kglom? None of these
Steam exhaust from HP turbine goes to 2 IP Turbine Reheater Condenser None of these
Total number of bearings on which the turbine shaft in S500MW is : :
: 3 Five Six Seven None of these
supported is
In IP turbine and LP turbines steam is admitted 2 At both ends At the centre At one end None of these
Steam leak off from the turbine glands is diverted to 2 Reheater Gland steam Deaerator None of these
condenser
oo a On the turbine On the turbine
Main oil pump is installed 2 main oil tank shaft itself Both of these None of these
The process of drawing steam from intermediate stages of turbine and 1 Regeneration Reheating Both of these None of these
using it for heating feed water is called
In the feed water heaters feed water flows through 2 Tubes Shell side Both None of these
: . : : : Between the
In the case of Turbine driven Boiler Feed Pump (TDBFP) main pump is 2 booster pump and At one end of the Both None of these
located : shaft
turbine
HP heater — 6A normal drip (condensate) goes to 2 deaerator directly HP neater oA shell Both None of these
Thermodynamic cycle used in Thermal power plants is Carnot cycle Rankine cycle Joule’s cycle None of these
Super
BFPs supply water for the following 3 heater/reheater | HP bypass spray Both the above None of these
spray
The speed of drive turbine of TDBFP at full load is 3 3000-3500 RPM | 3000-3500 RPM 5500-5700 RPM None of these
The minimum NPSH required for Boiler Feed Pump is 1 24 mts of WC 15 mts of WC 35 mts of WC None of these
Under normal conditions CEP discharge pressure is 3 30 kg/om? 40 kg/cm? 15 kg/om? None of these
In case of LP heater — 2 level high, its drip gets diverted to 3 LP heater-1 Deaerator Condenser None of these
Low temperature
Feed water after passing through Economiser goes to: 1 super heater |Bottom ring header Drum None of these
(LTSH)
500 MW boilers feed water is admitted into drum at a temperature of 2 250 deg C 315 deg C 400 deg C 450 deg C
(approx)
The speed of drive turbine of TDBFP at full load is 3000 - 3500 RPM 4000 - 4250 RPM 5500 - 5700 RPM 6100 - 6300 RPM
The rated speed of Boiler feed pump Booster pump is 1750 RPM 1494 RPM 1884 RPM 3000 RPM
TDBFP turbine can be supplied steam from Extraction - 4 Auxiliary steam CRH line Any of these
Lub oil Control oil
In case of TDBFP, emergency lub oil pump supplies oil for
requirement requirement
Both (a) and (b) None of these
HP Heaters 5A & 5B are supplied extraction steam at a pressure of 2 8.5 Kg/om* 18.5 Kg/om2 28.5 Kg/om? None of these
. th . th . th -
HP heaters 6A & 6B are supplied steam from 3 HP turbine 5 IP turbine 8 IP turbine 8 IP-LP STOSS over
stage stage stage pipe
Condensate extraction pump (CEP) supplies water to 4 BFPs' seals LP bypass spray PRDS spray All of these
Condensate outlet from Gland steam condenser normally goes to 2 LP Heater-1 Gland drain tank Gland Cooler None of these
. th . rd : nd
LP Heater — 3 is supplied steam from 3 LP turbine & LP turbine 3 LP turbine 2 None of these
stage stage stage
In Water treatment plant ,Lime is added for 2 ronteling Controlling PH Controlling Oxygen |None of these
The unit of measurement of turbidity is 3 Micro siemens ppb NTU None of these
In Indian coal ash content will be 2 5-15% 30-40% 60-70% None of these
The statutory limit for emission of Suspended Particulate Matter(SPM) 1 415mg/Nm3 45mg/Nm3 515mg/Nm3 None of these
through stack is
In hydrogen plant the catalyst used is 2 H2S04 K2Cr207 KOH None of these
In hydrogen plant the chemical added to water is 1 NaOH KCl KOH None of these
For fly ash conveying systems of capacity <60 Tons the system used 1 Vacuume system Pressurized Both 1&2 None of these
is system
Double gates with |Requires Limitation of
The disadvantage with pressurized fly ash evacuation sysytem is 1 air lock are separating apaci None of these
required equipment capacity
Bottom ash hopper is supplied with water to 3 Cool the refractory) Cool the hot Both the Above None of these
lining bottom ash
_ Evaporation loss /|C.0.C /
Blow down = 1 (C.0.C-1) Evaporation loss Both the Above None of these
The cooling towers used in places with water shortage are 2 Natural draft Forced draft Both the Above None of these
coolinig towers cooling towers
The main disadvantage of reciprocating air compressor is 3 High vibrations Wear and tear of Both the Above None of these
components
For measuring low temperatures the instrument used is 3 Thermocouple RTD Pyrometer None of these
The output signal of analog instrumens is 1 4-20 mA DC 420 mA ACG 420 V AC None of these
The thermo couples used for measuring -200 degree to 1200 degree 2 E-type K-type J-type None of these
The S-type thermocouples are made of 3 Nickel-Chromium |Copper-Nickel Platinum-Rhodium |None of these
ESP fly ash size will be normally 100 to 600 microns 2 TRUE FALSE
In ESP,AC voltage is applied across the fields 2 TRUE FALSE
The difference between cooled water temperature and wet bulb 2 TRUE FALSE
temperature is called "Range
Reciprocating compressors are positive displacement type 1 TRUE FALSE
In stator water system NaOH IS added to maintain PH 1 TRUE FALSE
For 50Hz system,if the speed of generator rotor is 500 RPM,what are 14 : : oa
the number of poles on rotor and what is type of rotor used? 2 poles, cylindrical 12 poles.salient 10 poles,salient 8 poles.cylindrical
In a synchronous generator,which of the following statements is true? 2 Pis positive,Q is Both P and Q are |P is negative,Q is Both P and Q are
negative positive negative negative
Which statement is true for double layer winding?
i There are two coil sides per slot
i Both coil sides are in Top half of different slots : om : om
i i One coil side is in top half of one slot and other coil side in bottom 4 {Only | Only ii All are true Both | and il
half of another slot
iv Both coil sides are in Bottom half of different slots
The bushing chamber of a 500MW generator,is located where on 1 Exciter end Turbine end Middle None of these
|generator
How many hydrogen coolers are there in 500 MW generator and
located in which end shield
3 |3,TEendshield |4,EEendshield |4,7TEendshield — |2,TE end shield
The transposition angle of strands in straight end portion is 1 540 degree 360 degree 450 degree 270 degree
The rotor winding conductor material is 4 Aluminium Copper Aluminium alloyed Copper alloyed
with silver with silver
The number of stages in cooling fan of 500 MW generator 3 4 6 5 1
The type of stator winding in 500 MW Generator 4 star Delta zig zag Double star
The component in stator that interconnects different coil groups is 2 Bushing Phase connector [Flexible connector [Teflon hose
The two poles of generator rotor are displaced by 2 90 degree 180 degree 120 degree 270 degree
The component of generator rotor to contain centrifugal forces due to 4 Rotor wedge Snap ting End ring Retaining ring
end winding are
Gas used in 500 MW turbo generator for cooling of rotor and stator
: 2 , . .
core is Nitrogen Hydrogen Helium Air
Inflammability range of Hydrogen in air is 1 4-74% 8-98% 4-94 % None of the above
Gas used to purge out Hydrogen in generators is 3 Argon Nitrogen CO2 Air
1 To maintain
In 500 MW generators,
low DO primary water system NAOH is dozed To maintain PH conductivity To maintain low DO {None of the above
1 Negative
The pumps used in seal oil system are Screw pumps Centrifugal pumps |displacement pumps|Axial flow pumps
The element which maintains the diferential pressure between seal oil 2
and hydrogen at seals in seal oil system is Seal ring DPR valve Duplex filter Seal oil tank float
Which type of excitation system has faster response to variation in Static Excitation |Brushless Both 1&2 None of these
Generator terminal voltage System Excitation System
Minimum
operating and Self generating Simple and reliable
Salient features of brushless excitation system are maintenance cost |system excitation system All the above
SPRAY FOR TEMPERATURE CONTROL IN HP BYPASS SYSTEM BFP DISCHARGE|CEP DISCHARGE |SUPER HEATER JREHEATER
IS TAKEN FROM ? HEADER HEADER SPRAY LINE SPRAY LINE
IMPROVE
STEAM PROVIDES PROTECTS
TEMPERATURE/ |STEAM PATH REHEATER COILS
PRESSURE IN DURING LOAD FROM ALL OF THE
FUNCTIONS OF HP-LP BYPASS IN POWER PLANT IS/ARE___? STARTUP THROWOFF STARVATION ABOVE
CONSIDER THE STATEMENT AND CHOOSE THE RIGHT
OPTION:"HP/LP BYPASS SYSTEMS CAN BE OPERATED IN THE PARTLY NONE OF THE
ABSENCE OF VACUUM IN CONDENSER" CORRECT CORRECT INCORRECT ABOVE
HPBP HPBP CONDENSER
WHICH OF THESE IS NOTA PROTECTION FOR HP-BYPASS DOWNSTREAM |DOWNSTEAM VACUUM PR ALL OF THE
SYSTEM? TEMP V.HIGH TEMP V.LOW V.HIGH ABOVE
EMERGENCY
HP BYPASS AUTO OPEN COMMAND IS INITIATED UNDER WHICH GENERATOR FAST OPEN ALL OF THE
CONDITIONS? TURBINE TRIP [TRIP COMMAND ABOVE
LPBP SPRAY
SELECT THE CORRECT CONDITION WHEN LP BYPASS SYSTEM WATER CONDENSER HRH PRESSURE — |NONE OF THE
TRIPS FROM OPERATION? PRESSURE LOW|VACUUM PR OK_[LOW. ABOVE
seeeaeeeaeeeeeeneee type idlers are installed adjacent to all pulleys to permit proper support of loaded belt | PPF PPF VSTPS-3 | LEVEL1 1 Transition Impact Self Cleaning none of the above
near the pulleys to prevent excessive stretch of the belt edges.
seeneeeeee idlers have a number of resilient type rubber discs for absorbing the shock of free PPF PPF VSTPS-3 | LEVEL1 2 Transition Impact Self Cleaning none of the above
falling material at loading point
In order to clean carrying side of belt on return side, belt scrappers and rubber disc type ................ | PPF PPF VSTPS-3 | LEVEL1 3 Transition Impact Self Cleaning none of the above
idlers are installed just after snub pulley.
Pulley Lagging Sheet is made from natural rubber and should have thickness of ........ mm. PPF PPF VSTPS-3 | LEVEL1 2 10 12 14 8
Minimum angle of wrap for head pulleys is........ Degree. PPF PPF VSTPS-3 | LEVEL1 3 180 200 220 240
The ..........is the most important structural section of the belt, as it contains tensile member to PPF PPF VSTPS-3 | LEVEL1 2 Top Cover Caracaas Bottom Cover none of the above
handle the load of coal carried on the conveyor
Pull chord switches are installed only on one side of conveyor belt: true/false PPF PPF VSTPS-3 | LEVEL1 2 True FALSE
Zero speed switches are also referred as under speed switches: true/false PPF PPF VSTPS-3 | LEVEL1 True FALSE
Load Cells are an integral part of: PPF PPF VSTPS-3 | LEVEL1 4 In Line Magnetic Separator Cross Belt Magnetic Separator Metal Detector Belt Weigher
Wheel mounted .............are provided below the track hopper for evacuating the coal from the PPF PPF VSTPS-3 | LEVEL1 3 Mobile Trippers belt feeders Paddle feeders Fixed Tripers
hopper.
The wagon tippling system consists of wagon tippler, Side arm charger, underground hopper; and | PPF PPF VSTPS-3 | LEVEL1 2 Mobile Trippers Apron Feeders Paddle feeders Fixed Tripers
wees. /Vibrating feeder below the hopper for evacuating the material unloaded into the
hopper.
Slewing, Luffing and Long travel Motion are associated with which equipment PPF PPF VSTPS-3 | LEVEL1 2 Mobile Trippers Stacker Reclaimers Paddle feeders Fixed Tripers
Normal Carrying Idlers/Troughing Idlers are installed at a gap of ....M PPF PPF VSTPS-3 | LEVEL1 3 0.6 0.8 1.2 2
In emergency best option for a local operator to stop a belt conveyor is to PPF PPF VSTPS-3 | LEVEL1 3 inform the control room run upto the local start/stop push bottom and push pull the cord of a pull cord switch run upto one pull cord switch
bottons and operate it
ROM coal stands for PPF PPF VSTPS-3 | LEVEL1 2 Return of Mine Coal Run of Mine Coal Running of Mined Coal Rate of Mined Coal
Marshaling equipment used to pull a complete rake of 58 wagons is called Side Arm Charger : PPF PPF VSTPS-3 | LEVEL1 1 TRUE FALSE
True/False
Impact Idlers are installed at gap of 0.6 m (True/False) PPF PPF VSTPS-3 | LEVEL1 1 TRUE FALSE
Side Arm Charger is used to PPF PPF VSTPS-3 | LEVEL1 3 Tipple the wagon tippler table for unloading Push empty wagons after unloading only Place loaded wagon wagon tippler table and push empty | Support wagon from side with
coal from it wagons after unloading its Arm during unloading
Dribble conveyor d. Feeds coal from apron feeder to receiving conveyor: T/F PPF PPF VSTPS-3 | LEVEL1 TRUE FALSE
A bulldozer in a coal handling plant is used for PPF PPF VSTPS-3 | LEVEL1 4 feeding coal from heap into underground leveling the coal stock piles compacting coal in the coal stockpiles All three of above
hopper
A Switch Is Means For PPF PPF VSTPS-3 | LEVEL1 3 Opening Closing Both None Of The Above
A Switch Should Always Operate PPF PPF VSTPS-3 | LEVEL1 1 Manually During Short Circuit During Any Electrical Fault Manually And Fault Condition
Both
A Switchgear Include PPF PPF VSTPS-3 | LEVEL1 4 Switching Device Control & Regulation Accessories Measurement And Protection All Of Above
Function Of Switchgear PPF PPF VSTPS-3 | LEVEL1 4 Carry Normal Load Current Make Or Break Fault Current Clearing Fault Current All Of Above
Parts Of The Switchgear PPF PPF VSTPS-3 | LEVEL1 4 Power Switch Control And Protection System Measurement And Display All Of Above
Parts Of Protection System PPF PPF VSTPS-3 | LEVEL1 4 Current Transformer (Ct) Potential Transformers (Pt) Protection Relay All Of Above
Surge Arrestor Is Provided In Switchgears To Protect From PPF PPF VSTPS-3 | LEVEL1 1 Over Voltage Transient Over Current Short Circuit Earth Fault
MCB Stands For PPF PPF VSTPS-3 | LEVEL1 2 Moulded Circuit Breakers Miniature Circuit Breaker Master Circuit Breaker Main Circuit Breaker
Medium Voltage Stands For Voltages PPF PPF VSTPS-3 | LEVEL1 1 2400V To 69000V 115Kv To 230Kv 345Kv To 745Kv 745Kv To 1100Kv
Switchgears Are Classified According To PPF PPF VSTPS-3 | LEVEL1 4 Insulating Medium Current Rating Contruction Type All Of Above
Which Chamber Of Switchgear Is Houses Low Voltage Components PPF PPF VSTPS-3 | LEVEL1 3 Breaker Chamber Busbar Chamber Control And Protection Chamber CT/ PT Chamber
Chractrictics Of The Protection System PPF PPF VSTPS-3 | LEVEL1 4 Speedly Clear The Fault Select The Faulty Zone Sentitive To The Fault All Of Above
Fault Clearing Time Does Not Include PPF PPF VSTPS-3 | LEVEL1 4 Relay Pick Up Time Circuit Breaker Opening Time Relay Reset Time CB Arcing Time
During Any Electrical Fault In System PPF PPF VSTPS-3 | LEVEL1 4 Fault Impedence Will Be Low Fault Current Increases Relay Sense The Fault All
Short Time Rating Of Breaker PPF PPF VSTPS-3 | LEVEL1 2 Current Which Breaker Can Carry Continuously | Fault Current Which Can Be Break Maximum Current For Which The Fault Current Can Be Max Current During Closing Of
Handled Breaker
Auxiliary Power Supply System Includes PPF PPF VSTPS-3 | LEVEL1 4 Stand By Power Control And Protection Supply Changeover Scheme All Above
Components Of Auxilary Power Supply Systems Are PPF PPF VSTPS-3 | LEVEL1 4 DG Set Control Supply Tie Connection Among Switchgears All Of Above
Design Of Switchgears For Motor Are Decided On PPF PPF VSTPS-3 | LEVEL1 2 Current Rating Kw Rating Power Factor None Of The Above
Normally Medium Voltage Switchgears Have Maximum System Fault Level PPF PPF VSTPS-3 | LEVEL1 1 40 KA (Rms) 25 KA (Rms) 15 KA (Rms) 21 KA (Rms)
Normally System Neutral Earthing Of Medium Voltage Limits The Fault Current To PPF PPF VSTPS-3 | LEVEL1 3 100 Ampere 200 Ampere 300 Ampere 400 Ampere
Which Is Not A Dc Motor Application In Power Plant PPF PPF VSTPS-3 | LEVEL1 4 Seal Oil Pump Jacking Oil Pump Scanner Air Fan ID Fan
Emegency Mcc Supplied Power To PPF PPF VSTPS-3 | LEVEL1 3 FD Fan ID Fan Jacking Oil Pump Ash Slurry Pump
220V Charger Recieves Incoming Power From PPF PPF VSTPS-3 | LEVEL1 3 Unit Service Switchgear Emergency Switchgear Both UPS
Which Is Not A Battery Manufacturer PPF PPF VSTPS-3 | LEVEL1 3 Exide Amco Kirloskar Hbl Knife
Capacity Of The Battery Bank Are Rated In PPF PPF VSTPS-3 | LEVEL1 1 Ampere-Hour Volt Ampere None Of The Above
MAIN FUNCTION OF THE SWITCHGEAR IS PPF PPF VSTPS-3 | LEVEL1 4 CARRY NORMAL CURRENT MAKE OR BREAK NORMAL CURRENT FAULT PROTECTION SR NO 1 AND 2
WHICH IS NOT A PART OF SWITCHGEAR PPF PPF VSTPS-3 | LEVEL1 1 CABLE POWER CIRCUIT CONTROL CIRCUIT MEASUREMENT
CT/PT USED IN SWITCHGEARS ARE MAINLY PPF PPF VSTPS-3 | LEVEL1 2 SWITCHING DEVICES PROTECTION DEVICES MEASURING DEVICES CONTROL DEVICES
IN A SWITCHGEAR, MAIN POWER INTURRUPTING DEVICE IS PPF PPF VSTPS-3 | LEVEL1 3 CT PT CIRCUIT BREAKER CONTROL TRANSFORMER
IN LT SWITCHGEARS FEEDING < 90 KW LOADS, CONTROL SUPPLY VOLTAGE IS PPF PPF VSTPS-3 | LEVEL1 2 220V AC 110V AC 415V AC 24V DC
FOLLOWING IS USED TO PROVIDE REMOTE MONITORING OF CURRENT IN SWITCHGEARS PPF PPF VSTPS-3 | LEVEL1 3 CT PT CURRENT TRANSDUCER AMMETER
NORMALLY USED CONTROL VOLTAGE IN HT SWITCHGEARS IS PPF PPF VSTPS-3 | LEVEL1 1 220V DC 24V DC 110V AC 110V DC
OPERATION OF FOLLOWING IS DONE DURING POWER SUPPLY DEAD CONDITION IN ANY PPF PPF VSTPS-3 | LEVEL1 2 CONTACTOR ISOLATOR FUSES SURGE ARRESTORS
SWITCHGEAR
AIR BREAK CIRCUIT BREAKERS ARE USED UPTO PPF PPF VSTPS-3 | LEVEL1 1 1000V 3300V 6600V 11000V
WHICH CB IS NOT SUITABLE FOR FREQUENT SWITCHING OPERATIONS PPF PPF VSTPS-3 | LEVEL1 4 ACB ABCB VACUUM CB MOCB
THE MAIN FUNCTION OF FUSE IN SWITCHGEARS IS TO PPF PPF VSTPS-3 | LEVEL1 3 PROTECT THE LINE OPEN THE CIRCUIT PREVENT EXCESSIVE CURRENT NONE OF THE ABOVE
RELAYS ARE DESIGNED TO RESPOND TO CHANGES IN PPF PPF VSTPS-3 | LEVEL1 4 RESISTANCE VOLTAGE AND CURRENT TEMPERATURE ALL OF THE ABOVE
THERMAL OVER LOAD RELAYS ARE PROVIDED FOR PEOTECTION AGAINST PPF PPF VSTPS-3 | LEVEL1 2 SHORT CIRCUIT OVERLOAD GROUND FAULT ALL OF THE ABOVE
The voltage appearing across the contacts after the opening of the circuit breaker is called PPF PPF VSTPS-3 | LEVEL1 1 RECOVERY SURGE OPERATING ARC
IP PROTECTION IN CASE OF SWITCHGEARS STANDS FOR PPF PPF VSTPS-3 | LEVEL1 2 INSULATION PROTECTION INGRESS PROTECTION INLET PROTECTION NONE OF THE ABOVE
SF6 GAS USED IN CIRCUIT BREAKER IS PPF PPF VSTPS-3 | LEVEL1 3 VIOLET COLOR YELLOW COLOR COLOR LESS NONE OF THE ABOVE
MAX VOLTAGE LEVEL UPTO WHICH VACUUM CB ARE USED PPF PPF VSTPS-3 | LEVEL1 4 6.6 KV 11 KV 33 KV 66 KV
CB USED FOR EHV APPLICATIONS ARE PPF PPF VSTPS-3 | LEVEL1 4 ACB OCB VCB ABCB
DURING ANY FAULT, FAULT IMPEDENCE IS PPF PPF VSTPS-3 | LEVEL1 2 HIGH LOW DEPEND ON TIME NONE OF THE ABOVE
MAXIMUM FAULT CURRENT AT WHICH A CB IS CAPABLE OF SWITCH OFF THE CIRCUIT IS CALLED =| PPF PPF VSTPS-3 | LEVEL1 3 MAKING CAPACITY SHORT TIME RATING BREAKING CAPACITY NONE OF THE ABOVE
WHICH IS NOT PRODUCED DURING ARCING IN OIL CB PPF PPF VSTPS-3 | LEVEL1 2 HYDROGEN NITROGEN METHANE ETHYLENE
FIXED AND MOVING CONTACTS IN OIL CB ARE OF PPF PPF VSTPS-3 | LEVEL1 1 COPPER ALUMINIUM TUNGUSTUN CHROMIUM
DIELECTRIC STRENGTH OF AIR IS PPF PPF VSTPS-3 | LEVEL1 4 30 KV / MM 0.3 KV /MM 0.03 KV / MM 3KV/MM
WHICH CB IS WELL SUITED FOR SWITCHING OF TRANSFORMERS AND REACTORS PPF PPF VSTPS-3 | LEVEL1 3 ACB MOCB SF6 CB OIL CB
CB OPERATION TIME IS GENERALLY PPF PPF VSTPS-3 | LEVEL1 2 1 SEC 50 m SEC 500 m SEC 200 m SEC
THE ARC VOLTAGE PRODUCED BY AN AC CIRCUIT BREAKER IS ALWAYS PPF PPF VSTPS-3 | LEVEL1 1 IN PHASE WITH ARC CURRENT 90 DEGREE LAGGING WITH ARC CURRENT 90 DEGREE LEADING WITH ARC CURRENT NONE OF THE ABOVE
INSULATION RESISTANCE OF HV CB IS PPF PPF VSTPS-3 | LEVEL1 3 1 MEGA OHM 10 MEGA OHM 100 MEGA OHM 1000 MEGA OHM
ARC INA CB IS INTERUPTED AT PPF PPF VSTPS-3 | LEVEL1 4 MIN VOLTAGE MAX VOLTAGE MAX CURRENT ZERO CURRENT
A FUSE RATING IS GENERALLY EXPRESSED IN TERMS OF PPF PPF VSTPS-3 | LEVEL1 1 CURRENT VOLTAGE KVA KW
A FUSE IS CONNECTED IN THE CIRCUIT IN PPF PPF VSTPS-3 | LEVEL1 2 PARALLEL SERIES EITHER SERIES OR PARALLEL NONE OF THE ABOVE
Transformer oil is used for PPF PPF VSTPS-3 | LEVEL1 2 LUBRICATION COOLING SEALING INSULATING
If supply frequency of a transformer increases, the secondary output voltage of the transformer | PPF PPF VSTPS-3 | LEVEL1 3 Increase Decrease Remain the same Any of the above
Power transformers are designed to have maximum efficiency at PPF PPF VSTPS-3 | LEVEL1 1 Full load 50% load 80% load no load
Lamination of transformer core is made of PPF PPF VSTPS-3 | LEVEL1 2 Cast lron Silicon Steel Aluminium Cast Steel
Breather is provided in a transformer to PPF PPF VSTPS-3 | LEVEL1 1 Absorb moisture of air during breathing provide cold air in the transformer The filter of transformer oil None of above
Which of the following losses varies with the load in the transformer PPF PPF VSTPS-3 | LEVEL1 2 Core loss Copper loss Both core & copper loss None of the above
Transformer core are laminated in order to PPF PPF VSTPS-3 | LEVEL1 3 reduce hysteresis loss reduce hysteresis & eddy current loss minimize eddy current loss Copper loss
The open circuit test in a transformer is used to measure PPF PPF VSTPS-3 | LEVEL1 4 Copper loss Winding loss Total loss Core loss
A star connected three phase transformer is provided with tertiary delta connected winding PPF PPF VSTPS-3 | LEVEL1 2 Second harmonic of exciting current Third harmonic of exciting current Fifth harmonic of exciting current Seventh harmonic of exciting
which allows the flow of current
The size of a transformer core will depend on PPF PPF VSTPS-3 | LEVEL1 4 Frequency Area of the core Flux density of the core material All of the above
Natural oil cooling is used for which transformers rating PPF PPF VSTPS-3 | LEVEL1 1 3MVA 20 MVA 25 MVA 5SOMVA
For Generating Transformer ,which type of connection is used PPF PPF VSTPS-3 | LEVEL1 1 Delta/star star/delta star/star delta/delta
Noise level test in a transformer is a PPF PPF VSTPS-3 | LEVEL1 3 Special test Routine test Type test None of the above
The chemical used in breather is PPF PPF VSTPS-3 | LEVEL1 4 Asbestos fiber Silica sand Sodium chloride Silica gel
If a transformer is continuously operated the maximum temperature rise will occur in PPF PPF VSTPS-3 | LEVEL1 2 Core Windings Tank Any of the above
Part of the transformer which is most subject to damage from overheating is PPF PPF VSTPS-3 | LEVEL1 3 lron core Copper winding Winding insulation Frame or case
A transformer transforms PPF PPF VSTPS-3 | LEVEL1 3 Voltage Current Current and voltage Frequency
Which of the following does not change in a transformer PPF PPF VSTPS-3 | LEVEL1 3 Current Voltage Frequency All of the above
The transformer ratings are usually expressed in terms of PPF PPF VSTPS-3 | LEVEL1 4 Volts Amperes kW kVA
Bucholz relay give warning and protection against PPF PPF VSTPS-3 | LEVEL1 1 electrical fault inside the transformer Electrical fault outsidethe transformer for both inside & outside none of the above
Two transformer share the load depends upon PPF PPF VSTPS-3 | LEVEL1 2 leakage reactance per unit impedence efficiences rating
During Arc Inrupption Process, High Current Phase testing Mock test LEVEL2 1] Conductive Plasma Formation Take Place Start After Thermal Intruption Local Distortion Of Electrical Field Normalised Cooling Of Plasma Completes
During Arc Inrupption Process, Thermal Phase testing Mock test LEVEL3 1| Cooling Of Plasma Start Start After Thermal Intruption Vigorious Turbulance Effective Cooling Of Arc
During Arc Inrupption Process, Di-Electric Phase testing Mock test LEVEL4 3] Vigorious Turbulance Formation Of Metal Vapour No Longer Electricaly Conductive Medium High Tempreture
During Any Electrical Fault In System testing Mock test LEVEL2 4] Fault Impedence Will Be Low Fault Current Increases Relay Sense The Fault All
Maximum Current For Which The Fault Current Can Be Max Current During Closing Of
Short Time Rating Of Breaker testing Mock test LEVEL2 2| Current Which Breaker Can Carry Continuously | Fault Current Which Can Be Break Handled Breaker
Auxiliary Power Supply System Includes testing Mock test LEVEL1 4] Stand By Power Control And Protection Supply Changeover Scheme All Above
Components Of Auxilary Power Supply Systems Are testing Mock test LEVEL1 4|DG Set Control Supply Tie Connection Among Switchgears All Of Above
Design Of Switchgears For Motor Are Decided On testing Mock test LEVEL1 2| Current Rating Kw Rating Power Factor None Of The Above
Normally Medium Voltage Switchgears Have Maximum System Fault Level testing Mock test LEVEL1 1] 40 KA (Rms) 25 KA (Rms) 15 KA (Rms) 21 KA (Rms)
Normally System Neutral Earthing Of Medium Voltage Limits The Fault Current To testing Mock test LEVEL1 3] 100 Ampere 200 Ampere 300 Ampere 400 Ampere
Which Is Not A Dc Motor Application In Power Plant testing Mock test LEVEL1 4] Seal Oil Pump Jacking Oil Pump Scanner Air Fan ID Fan
Emegency Mcc Supplied Power To testing Mock test LEVEL1 3] FD Fan ID Fan Jacking Oil Pump Ash Slurry Pump
220V Charger Recieves Incoming Power From testing Mock test LEVEL1 3] Unit Service Switchgear Emergency Switchgear Both UPS
Which Is Not A Battery Manufacturer testing Mock test LEVEL1 3] Exide Amco Kirloskar Hbl Knife
Capacity Of The Battery Bank Are Rated In testing Mock test LEVEL1 1] Ampere-Hour Volt Ampere None Of The Above
Duration Of Discharge For Lead Acid Battery In Capacity Test Is testing Mock test LEVEL1 1] 10 Hrs 5 Hrs 8 Hrs Depends On Capacity
Breather is provided in a transformer to Transformer Mock test 1| Absorb moisture of air during breathing provide cold air in the transformer The filter of transformer oil None of above
Which of the following losses varies with the load in the transformer Transformer Mock test 2| Core loss Copper loss Both core & copper loss None of the above
Transformer core are laminated in order to Transformer Mock test 3| reduce hysteresis loss reduce hysteresis & eddy current loss minimize eddy current loss Copper loss
The open circuit test in a transformer is used to measure Transformer Mock test 4| Copper loss Winding loss Total loss Core loss
The leakage flux in a transformer depends upon the value of Transformer Mock test 3| Frequency Mutual Flux Load current Applied Voltage
Ina5kV/400V, 75 kVA single phase transformer, the current flowing in
the primary winding of transformer is 1OA. what will be the current flowing
in the secondary winding Transformer Mock test 3| 100A 120A 125A 130A
Astar connected three phase transformer is provided with tertiary delta
connected winding which allows the flow of Transformer Mock test 2| Second harmonic of exciting current Third harmonic of exciting current Fifth harmonic of exciting current Seventh harmonic of exciting cy
The size of a transformer core will depend on Transformer Mock test 4| Frequency Area of the core Flux density of the core material All of the above
The full-load copper loss of a transformer is 1600 W. At half-load, the
copper loss will be Transformer Mock test 4| 6400 W 1600 W 800 W 400 W
The changes in volume of transformer cooling oil due to variation of
atmospheric temperature during day and night is taken care of by which
part of transformer Transformer Mock test 1 | Conservator Breather Bushings Buchholz relay
Natural oil cooling is used for which transformers rating Transformer Mock test 1|3MVA 20 MVA 25 MVA S50MVA
For Generating Transformer ,which type of connection is used Transformer Mock test 1 | Delta/star star/delta star/star delta/delta
Noise level test in a transformer is a Transformer Mock test 3 |Special test Routine test Type test None of the above
The chemical used in breather is Transformer Mock test 4| Asbestos fiber Silica sand Sodium chloride Silica gel
If a transformer is continuously operated the maximum temperature rise
will occur in Transformer Mock test 2| Core Windings Tank Any of the above
Part of the transformer which is most subject to damage from overheating is| Transformer Mock test 3 | Iron core Copper winding Winding insulation Frame or case
A transformer transforms Transformer Mock test 3| Voltage Current Current and voltage Frequency
Which of the following does not change in a transformer Transformer Mock test 3| Current Voltage Frequency All of the above
The transformer ratings are usually expressed in terms of Transformer Mock test A| Volts Amperes kW kVA
Bucholz relay can be installed in Transformer Mock test 4} only auto transformer air cooled transformer welding transformer oil cooled transformer
No load current drawn by transformer is percentage of full load current Transformer Mock test 210.2 to 0.5 % 2-5% 12-15 % 25-30%
Bucholz relay give warning and protection against Transformer Mock test 1 | electrical fault inside the transformer Electrical fault outsidethe transformer for both inside & outside none of the above
Two transformer share the load depends upon Transformer Mock test 2| leakage reactance per unit impedence efficiences rating
Tranformer can be classified based on Transformer Mock test 4| Power level type of application voltage class all of the above
100 Volt DC applied to Transformer of tur ratio of 100/50, what is the
secondary voltage. Transformer Mock test 250 V 200 V 50 V None of the above.
S.NO. Text Module Difficulty Answer Option1 Option2 Option3 Option4
1 DGA is applicable to monitor the condition of MTP Easy 2 Gear Boxes Transformer Bearings Pumps
S.P.M. is a good condition monitoring tool to predict the MTP Easy 3 ' a
2 condition of Sleeve Bearings Motor abnormalities Anti-Friction Bearings Shaft crack
3 Amplitude of Vibration is measured in MTP Easy 4 G mm/Sec microns All the above
For pi inting th f vibrati bl hich of og . ae ae .
4 OF PHT PONTE Te SOURCE OF Wro raion. Prowrenas Winey o MTP DIFFICULT 3 Vibration amplitude Vibration phase Vibration frequency Vib. Tolerence
the following is essential
9 Ultrasound monitoring is used for detecting MTP Easy 1 Valve leakage wear particle analysis Oil condition Shaft Cracks
First Harmonic (IX) radical vibration and steady phase MTP DIFFICULT 3
10 indicate Gear problem Belt problem unbalance problem Bearing defect
The main objective of NTPC Maint management system is MTP Easy 3 - Maximize the plant
11 to Maximize plant efficiency _ [availability Both
12 The main function of maintenance planning is MTP Easy 1 Coordination execution Cooperation
13 Maintenance planning is service function to MTP Easy 1 Maintenance Operation Erection
14 Long Term Planning coordinate the activities of MTP Easy 2 Day to day breakdown Unit Overhauls Plant erection
15 Short Term Planning coordinate the activities of MTP Easy 1 Day to day breakdown Unit Overhauls Plant erection
MTP Easy 3 It is performance base
16 What is preventive maintenance? Itis condition based system_|It is situation base Itis time based system system
Which is the on-line condition monitoring technique for MTP DIFFICULT 2 —
17 steam turbine Wear debris analysis Shaft vibration Thermography Noise analysis
18 The most commonly used unit of noise measurement is MTP Easy 3 Pascales N.M2 Decibel Watl
When gas cutting and welding is there is the work, the MTP DIFFICULT 3 Take a limited work Keep more people at the
24 maintenance should certificate work spot Take a hot work permit
25 The person who is authorized to raise defect MTP DIFFICULT 4 Operation personnel Maintenance personnel Concerned person working _ [Any person having access to
26 Run out of a shaft indicated MTP DIFFICULT 4 Eccentricity Bend in the shaft Ovality All the above
MTP DIFFICULT 1
27 In case of only angular misalignment Axes of both shafts intersect | Axes will not intersect Axes are in line Axes are parallel
28 E priority work order cards are raised when MTP Easy 2 Manpower is not available Generation and safety is To call to maintenance To give stress in
29 Thermography in NTPC power stations are largely carried MTP DIFFICULT 3 Boiler Pumps Switch yard Turbo Generator
30 To pin point the causes for vibration, the following MTP DIFFICULT 2 Wear debris analysis EET analysis S.PM Motor current analysis
31 Predictive maintenance is MTP DIFFICULT 3 Preventive maintenance Trend maintenance Condition based Vibration based maintenance
32 The Overhauling of BOiler is required in MTP Easy | 2 year 4 year 6 year 8 year
33 8year rolling plan prepare for MTP Easy 4 one complete cycle of all It provides a guidelines for __ | It helps to estimate our spare __| All the above
34 OPI Preparation start before the OH MTP Easy 1 24 Month 18 Month 12 month 6 Month
35 who is the authority for approval for ABB MTP Easy 3 Head of O&M Head of Finance Head of project Regional Executive director
S.NO. Text Module Difficulty Answer Option1 Option2 Option3 Option4
1 DGA is applicable to monitor the condition of MTP Easy 2 Gear Boxes Transformer Bearings Pumps
S.P.M. is a good condition monitoring tool to predict the MTP Easy 3 ' a
2 condition of Sleeve Bearings Motor abnormalities Anti-Friction Bearings Shaft crack
3 Amplitude of Vibration is measured in MTP Easy 4 G mm/Sec microns All the above
For pi inting th f vibrati bl hich of og . ae ae .
4 OF PHT PONTE Te SOURCE OF Wro raion. Prowrenas Winey o MTP DIFFICULT 3 Vibration amplitude Vibration phase Vibration frequency Vib. Tolerence
the following is essential
9 Ultrasound monitoring is used for detecting MTP Easy 1 Valve leakage wear particle analysis Oil condition Shaft Cracks
First Harmonic (IX) radical vibration and steady phase MTP DIFFICULT 3
10 indicate Gear problem Belt problem unbalance problem Bearing defect
The main objective of NTPC Maint management system is MTP Easy 3 - Maximize the plant
11 to Maximize plant efficiency _ [availability Both
12 The main function of maintenance planning is MTP Easy 1 Coordination execution Cooperation
13 Maintenance planning is service function to MTP Easy 1 Maintenance Operation Erection
14 Long Term Planning coordinate the activities of MTP Easy 2 Day to day breakdown Unit Overhauls Plant erection
15 Short Term Planning coordinate the activities of MTP Easy 1 Day to day breakdown Unit Overhauls Plant erection
MTP Easy 3 It is performance base
16 What is preventive maintenance? Itis condition based system_|It is situation base Itis time based system system
Which is the on-line condition monitoring technique for MTP DIFFICULT 2 —
17 steam turbine Wear debris analysis Shaft vibration Thermography Noise analysis
18 The most commonly used unit of noise measurement is MTP Easy 3 Pascales N.M2 Decibel Watl
When gas cutting and welding is there is the work, the MTP DIFFICULT 3 Take a limited work Keep more people at the
24 maintenance should certificate work spot Take a hot work permit
25 The person who is authorized to raise defect MTP DIFFICULT 4 Operation personnel Maintenance personnel Concerned person working _ [Any person having access to
26 Run out of a shaft indicated MTP DIFFICULT 4 Eccentricity Bend in the shaft Ovality All the above
MTP DIFFICULT 1
27 In case of only angular misalignment Axes of both shafts intersect | Axes will not intersect Axes are in line Axes are parallel
28 E priority work order cards are raised when MTP Easy 2 Manpower is not available Generation and safety is To call to maintenance To give stress in
29 Thermography in NTPC power stations are largely carried MTP DIFFICULT 3 Boiler Pumps Switch yard Turbo Generator
30 To pin point the causes for vibration, the following MTP DIFFICULT 2 Wear debris analysis EET analysis S.PM Motor current analysis
31 Predictive maintenance is MTP DIFFICULT 3 Preventive maintenance Trend maintenance Condition based Vibration based maintenance
32 The Overhauling of BOiler is required in MTP Easy | 2 year 4 year 6 year 8 year
33 8year rolling plan prepare for MTP Easy 4 one complete cycle of all It provides a guidelines for __ | It helps to estimate our spare __| All the above
34 OPI Preparation start before the OH MTP Easy 1 24 Month 18 Month 12 month 6 Month
35 who is the authority for approval for ABB MTP Easy 3 Head of O&M Head of Finance Head of project Regional Executive director
Quiz on Generator Basic principles and construction
For 50Hz system,if the speed of generator rotor is 500 RPM,what are the number of poles on rotor and what is type of rotor used?
14 poles,cylindrical
nro
12 poles,salient
10 poles,salient
Qo
8 poles,cylindrical
P is positive,Q is negative
Both P and Qare positive
P is negative,Q is negative
Both P and Q are negative
Onlyi
7mwa
Only iii
All are true
ao
130 deg C
Qora
140 deg C
155 degC
120 deg C
Exciter end
Qou7ra
Turbine end
Middle
None of these
How many hydrogen coolers are there in 500 MW generator and located in which end shield
©
540 degree
Qonro
360 degree
450 degree
270 degree
Copper
Aluminium alloyed with silver
Copper alloyed with silver
The number of stages in cooling fan of 500 MW generator
4
6
5
1
The component of generator rotor to contain centrifugal forces due to end winding are
Rotor wedge
Snap ring
End ring
Retaining ring
Text Subject Module Difficulty | Correct Option Option1 Option2 Option3 Option4
Which document contains of commissioning test procedure Commissioning Commissioning VSTPS Levelt 3 SCL SRCC TS RIOC
Kerosene test is carried out for checking leakage in Commissioning Commissioning VSTPS Levelt 2 ESP ID fan inlet damper to stack Wind box ESP outlet to ID fan inlet gate
Hydro test of the drainable portion of boiler consists of Commissioning Commissioning VSTPS Levelt Water wall only Water wall, Drum, RH Water wall, drum, economiser, Water wall, drum, economiser, SH upto
fw
Air in leak test is related to Commissioning Commissioning VSTPS Levelt Wind box Boiler ID Fan ESP
GD test is performed with the help of Commissioning Commissioning VSTPS Levelt Anemometer Thermometer Flow meter Pressure Guages
=|]
The document issued prior to energisation of equipement/plant is called as Commissioning Commissioning VSTPS Levelt RIOC SRCC SCL All
N
Pressure reading during hydraulic test of boiler is to be taken at Commissioning Commissioning VSTPS Levelt Highest Point Lowest Point Middle Point Any Where
WANN
Gas Distribution test is carried out to Commissioning Commissioning VSTPS Levelt Detect Leakages in ESP Ensure correct gas flow inside Detect Flue gas leakage in Duct Ensure correct gas flow inside flue gas
Rodine is used in acid cleaning as a Commissioning Commissioning VSTPS Levelt Catalyst Substitute Inhibitor All of the above
Internals taking over certificate is issued to Commissioning Commissioning VSTPS Levelt GM by Contractor O&M dept C&l by Erection dept None of the above
ANN
Mills Air flow test is done to ensure Commissioning Commissioning VSTPS Levelt Proper PA air flow to mill Equal coal flow at each corner Adequate seal air flow to Proper Hot PA air flow to control
Furnace and Ducts Air tightness test is done at pressure Commissioning Commissioning VSTPS Levelt 100 mm wel & 300 mm wel 100 mm wel both 300 mm wel both 300 mm wel & 100 mm wel
Completion criteria of Mills Clean Air flow test is achieved by Commissioning Commissioning VSTPS Levelt adjusting the opening of providing orifice plates within coal adjusting the opening of BIG regulating the PA flow through Mills
NY
Insulation work is carried out Commissioning Commissioning VSTPS Levelt after Air Tightness Test before Air Tightness Test before hydro test after Steam Blowing
A]
pH & Hydrazine content of DM Water for Boiler Hydro is Commissioning Commissioning VSTPS Levelt 10 & 100 ppm 10 & 200 ppm 7 & 100 ppm 7 & 200 ppm
WN
Which method is adopted for steam blowing process Commissioning Commissioning VSTPS Levelt Flushing Hammering Puffing Steam flowing
Decouple trial run of HT motors is done for Commissioning Commissioning VSTPS Levelt 4hrs 8 hrs Till bearing temp reaches 10 hrs
WN
Hydrotest of Reheater circuit is carried out with Commissioning Commissioning VSTPS Levelt Boiler drainaible portion Boiler non drainaible portion Independently Both 1 & 2
Chemical used in Alkali flushing of Boiler is Commissioning Commissioning VSTPS Levelt Hydrazine & ammonia Sodium hydrate DSP & TSP Citric Acid
BAW
Acid cleaning of Boiler includes Commissioning Commissioning VSTPS Levelt Economiser, Waterwall & Economiser, waterwall, drum & Waterwall only Economiser & water wall only
First Boiler light up is done with Commissioning Commissioning VSTPS Levelt Oil & Coal firing Coal firing Any of the above Oil firing
Hydrotest of lube oil line is done Commissioning Commissioning VSTPS Levelt Prior to oil flushing Prior to acid cleaning After completion of oil flushing Not required
oO]
During steam blowing the standard practise to limit the number of blow Commissioning Commissioning VSTPS Levelt 10 9 8 12
Completion criteria for steam blowing Commissioning Commissioning VSTPS Levelt No of pitting on the target 8 no of blows Manual inspection of pipe line No of pitting on the target plate must
|]
Target Plate is located at Commissioning Commissioning VSTPS Levelt Boiler stop valve outlet End of line to be blown in the mid way any where
WM
Hydrotest of boiler is carried out with Commissioning Commissioning VSTPS Levelt Air Plain DM water DM water treated with Ammonia Clarified water
During hydrotest, the rate of pressure rise upto 80 % of test pressure is less than Commissioning Commissioning VSTPS Levelt 20 KSC / min 12 KSC / min 15 KSC / min 10 KSC / min
AR
Safety valve setting includes Commissioning Commissioning VSTPS Levelt Setting of Set Pressure Setting of Resetting Pressure Ensuring desired reliving steam All of the above
The activity to remove oil, grease and impurities adhering to interiors of pressure parts after erection of boiler is Commissioning Commissioning VSTPS Levelt Thermal flow test Alkali Boil out Steam Blowing All of the above
NY
After acid cleaning, passivation is done to form a protective layer on the surface. The layer is Commissioning Commissioning VSTPS Levelt Magnetite layer Acid layer Carbon layer None of the above
NM]
The process of removing weld slag, foreign material and loose pieces from steam lines is called as Commissioning Commissioning VSTPS Levelt Oil flushing Steam blowing Detergent flushing Acid cleaning
During safety valve floating, the order of valves floating in terms of pressure setting is Commissioning Commissioning VSTPS Levelt Ascending Descending Constant Pressure Any order
High Pressure pump are employed to Commissioning Commissioning VSTPS Levelt Fill the boiler upto test Only filling the boiler To raise the pressure to test To drain out the boiler at certain rate
pressure pressure only
Gas distribution screens are used in ESP for Commissioning Commissioning VSTPS Levelt Proper distribution of flue Screen out any foreign material To maintain constant temp at All of the above
=|
The gas used for wet preservation is Commissioning Commissioning VSTPS Levelt Nitrogen Helium Hydrogen C02
APM =|
Commissioning refers to the activities carried out Commissioning Commissioning VSTPS Levelt Soon after the award of Just before erection activities On regular basis in a power During later stages of erection activities
HR
RIOC is issued to intimate the erection dept & the contractor of the Commissioning Commissioning VSTPS Levelt intention to take the plant in completion of initial operation completion of guarantee or energising the supply of the equipment
The date at which certificate becomes operative is the start of the guarantee or maintainence period. The Commissioning Commissioning VSTPS Levelt RIOC SRCC FICCC ITOC
After the issue of plant becomes property of NTPC. Commissioning Commissioning VSTPS Levelt SRCC FICCC RIOC ITOC
NM
Trial operation is of Commissioning Commissioning VSTPS Levelt 14 days 72 hrs full load operation both 1 & 2 1 month
Ww
In ATT of ducts & furnace, air leakage is checked with the help of Commissioning Commissioning VSTPS Levelt Water Soap Solution Sound of air Smoke generator
ONY
ATT of Hot & Cold PA duct is done at mmwe Commissioning Commissioning VSTPS Levelt 100 300 500 800
In ESP gas distribution test the variation in flow among the ESP passes is +/- % of average flow Commissioning Commissioning VSTPS Levelt 5 10 15 20
BM
Governing body responsible for formulating the overall policy for safe & efficient commissioning of the plant is Commissioning Commissioning VSTPS Levelt Commissioning Panel Working Party Test Teams Steering Committee
is responsible to approve all detail commissioning documents and associated procedures. Commissioning Commissioning VSTPS Levelt Steering Committee Commissioning Panel Operation Services GM ( Project)
BD
is responsible for preparation of entire commissioning documentation. Commissioning Commissioning VSTPS Levelt Steering Committee Commissioning Panel Operation Services Working Party
Which of the following is a certificate in commissining documentation Commissioning Commissioning VSTPS Levelt PTW LWwc FICC ROMP
WD
ITOC stands for Commissioning Commissioning VSTPS Levelt Initial Trial Operation Initial Taking Over Certificate Internal Trial Operation Internal Test Operation Certificate
ANY
After the issue of this certificate, future work on the plant must be under permit to work Commissioning Commissioning VSTPS Levelt ITOC FICCC RIOC SRCC
Which process is done in Boiler to prevent corrosion of boiler Commissioning Commissioning VSTPS Levelt Acid cleaning of Boiler Steam Blowing Boiler Hydro Boiler ATT
In which process of boiler, Boiler light up is required to be done Commissioning Commissioning VSTPS Levelt Boiler Hydro Boiler ATT Acid Cleaning using EDTA Boiler Preservation
AWWW]
HYDRAULIC TEST OF LUBE OIL LINE AND JOP LINE IS DONE AT Commissioning Commissioning VSTPS Levelt 10 KSC AND 180 KSC 12 KSC AND 160 KSC 12 KSC AND 180 KSC 08 KSC AND 180 KSC
THE PROCESS OF REMOVING DIRT BY USE OF COMPRESSED AIR AND CARDBOARD IS Commissioning Commissioning VSTPS Levelt TG LUBE OIL FLUSHING DETERGENT FLUSHING CARDBOARD BURSTING RINSING
IN THE 1ST STAGE OF FLUSHING FILTER ELEMENT AND INJECTOR NOZZLE ARE Commissioning Commissioning VSTPS Levelt REMOVED NOT REMOVED REPLACED WITH OLDER NONE
INITIALLY FOR STARTING OF SEAL OIL FLUSHING, Commissioning Commissioning VSTPS Levelt AIR SIDE SEAL OIL PUMP AIR SIDE SEAL OIL PUMP -2 DC SOP STARTED EMERGENCY SEAL OIL LINE FROM
THE COMPLETION CRITERIA FOR TG LUB OIL FLUSHING IS MOISTURE AND MI LESS THAN Commissioning Commissioning VSTPS Levelt 50PPM 10PPM 100PPM 7OPPM
YO
DM WATER TURBIDITY AFTER HOT WATER RINSING FOR ACHIEVING COMPLETION CRITERIAIS Commissioning Commissioning VSTPS Levelt LESS THAN 10 NTU LESS THAN 5 NTU LESS THAN 15 NTU LESS THAN 20 NTU
WN
WHOSE PRESSURE IS SET AT MAXIMUM PR. Commissioning Commissioning VSTPS Levelt AIR SIDE SEAL OIL. H2 SIDE SEAL OIL RING RELIEF OIL ALL EQUAL
DP BETWEEN SEAL OILAND H2 1S SET AT, Commissioning Commissioning VSTPS Levelt 1.4 KSC. 1.5KSC 1.6 KSC 2.0 KSC
HAHNYNN
IN THE STARTING OF ANY LUB OIL FLUSHING ,GENERALLY BEARING IS IN Commissioning Commissioning VSTPS Levelt CHARGED CONDITION. BYPASSED CONDITION. PARTIALLY CHARGED. NONE OF ABOVE.
WHICH OF THE FOLLOWING EQUIPMENT WILL BE COMMISSIONED FIRST. Commissioning Commissioning VSTPS Levelt TGECW SYSTEM MDBFP SYSTEM TDBFP CEPs
WHICH OF THE FOLLOWING IS CORRECT SET OF DPRV AND ITS SIGNAL OIL. Commissioning Commissioning VSTPS Levelt AIR SIDE DPRV ,H2 PR. AIR SIDE DPRV ,H2 SIDE OIL H2 SIDE DPRV ,H2 PR. AND NONE OF ABOVE.
HA
DC SEAL OIL PUMP IS PROVIDED IN Commissioning Commissioning VSTPS Levelt BOTHAIR & GAS SIDE ONLY AIR SIDE BOTH SIDE NONE
Wj]HRWANN
N2 CAPPING IN STATOR WATER SYSTEM PROVIDED FOR Commissioning Commissioning VSTPS Levelt REDUCING H2 REDUCING DISSOLVE 02 REDUCING BOTH 02 & H2 NONE
DETERGENT FLUSHING COVERS THE CLEANING OF? Commissioning Commissioning VSTPS Levelt FEED WATER SYSTEM CONDENSATE SYSTEM DRIP SYSTEM ALL THE ABOVE
THERMAL SHOCK IS RELATED TO Commissioning Commissioning VSTPS Levelt HPH COMMISSIONING. DETERGENT FKUSHING. LUB OIL LINES FLUSHING ALL ABOVE
WHICH OF THE FOLLOWING IS COMMONLY USED FOR DETERGENT FLUSHING. Commissioning Commissioning VSTPS Levelt RINOPOL SUMISOL ANY DETERGENT (A). AND (B). BOTH
IN CONDENSER FLOOD TEST ,WATER IS FILLED , Commissioning Commissioning VSTPS Levelt UP TO THE TIP OF LP MORE THAN THE LEVEL OF TIP ONLY UPTO 8.5 METER. NONE.
GATT IS MEANT FOR Commissioning Commissioning VSTPS Levelt CHECHING H2 CHECKING SEAL OIL CHECKING ANY LEAKAGES NONE
During AC insulation test, change in capacitive current indicates Commissioning Commissioning VSTPS Levelt Carbon tracking Corona Degradation due to moisture Surface conduction
What action is required in case of Low IR of Stator winding, when stator winding is filled with water Commissioning Commissioning VSTPS Levelt Puffing Dryout Pl Both Option 1 & 2
HA
What action is required in case of Low IR of Stator winding, when water has been drained Commissioning Commissioning VSTPS Levelt Puffing Dryout Pl Both Option 1 & 2
HAHN
Generator rotor winding IR to be done at Commissioning Commissioning VSTPS Levelt 1KV 1.5KV 2.5KV 5SKV
ELCID test is conducted to assess the healthyness of Commissioning Commissioning VSTPS Levelt Insulation Core Wedges Ripple Springs
AN
GATT (Generator air tightness test) is done at Commissioning Commissioning VSTPS Levelt 6KSC for 0.5 Hr 6KSC for 6 Hr 4KSC for24 Hr 6KSC for24 Hr
This is an distructive testing Commissioning Commissioning VSTPS Levelt Wedge deflection test High pot test AC impedance test Purge test
ANYN
Stator winding haydraulic test is conducted at Commissioning Commissioning VSTPS Levelt 6KSC for 0.5 Hr 6KSC for 6 Hr 4KSC for24 Hr 6KSC for24 Hr
Recurrent surge Oscillograph (RSO) test is used to assess the healthyness of Commissioning Commissioning VSTPS Levelt Rotor winding interturn Stator winding interturn shorting Partial Discharge inside winding Inter-lamination shorting in core blocks
HH
Graph plotted between Genrator voltage and field current is known as Commissioning Commissioning VSTPS Levelt Open circuit characteristic Short circuit characteristic Full load curve Magnetizing curve
Hydraulic test of Hydrogen coolers are conducted at Commissioning Commissioning VSTPS Levelt 6KSC for 0.5 Hr 6KSC for 6 Hr 4KSC for24 Hr 6KSC for24 Hr
WHA
During commissioning, Hipot test was conducted on generator winding at 40KV. Then during first overhaul hipot Commissioning Commissioning VSTPS Levelt 40KV 38KV 32KV 21KV
Documents required before starting C&l Commissioning Commissioning Commissioning VSTPS Levelt Piping and Instrumentation Measuring Point list or Logic diagrams All of above
A
Equipment required for C&l system commissioning Commissioning Commissioning VSTPS Levelt MULTIMETER VIBRATION SHAKER TABLE CURRENT SOURCE All of above
WNNYP
For Commissioning of Pressure gauge it is true Commissioning Commissioning VSTPS Levelt Check that insertion depth Check that the isolation valves, Check that cable support, None of above
Vibration sensors is checked with the help of Commissioning Commissioning VSTPS Levelt MULTIMETER VIBRATION SHAKER TABLE CURRENT SOURCE All of above
Earth pit resistance / Earth resistance for control panels should be Commissioning Commissioning VSTPS Levelt more than 1 ohm less than 10 ohm less than 0.5 ohm any of above
To protect DCS system from voltage fluctuations following are provided in DCS panels Commissioning Commissioning VSTPS Levelt Under voltage relays Over voltage relays A&B None of above
WO
FOR COMMISSIONING OF PRESSURE TRANSMITTER FOLLOWING IS TRUE Commissioning Commissioning VSTPS Levelt Transmitter calibration as Termination of cables in junction G type cable should be used for All of above
WN
As per NTPC engineering practice DCS systems are powered with Commissioning Commissioning VSTPS Levelt 230 V AC 415 V Ac 24V DC Any of above
Following are the part of C&l Control system Commissioning Commissioning VSTPS Levelt Control/DCS Panels Network Panels HMI systems All of above
BR
Following is required to be checked before starting any HT drive Commissioning Commissioning VSTPS Levelt Protections Alarms SOE All of above
BR
Following statement is true for alarm checking Commissioning Commissioning VSTPS Levelt Alarms should be checked It should be punched properly in logic diagram is not required for A&B
Following is not part of C&l commissioning Commissioning Commissioning VSTPS Levelt Power cable checking of LT cles loop tuning protection and interlock Field instruments loop checking
OA
In C&l Panels following type of earth is provided Commissioning Commissioning VSTPS Levelt Electrial Earth Instrument Earth A&B NONE OF ABOVE
Following activity is part of C&l Commissioning Commissioning Commissioning VSTPS Levelt Panel Power supply Motor offline vibration Motor Alignment None of above
BA
Following are part of C&l field instruments Commissioning Commissioning VSTPS Levelt Level transmitter Pressure transmitter RTD all of above
For CEP suction valve position indication following field instrument is used Commissioning Commissioning VSTPS Levelt Pressure gauge Limit switch Relay RTD
NM
For Measurement of CEP motor thrust brg temp measurement in Control room following instrument is used Commissioning Commissioning VSTPS Levelt RTD TiC Temp Gauge All of above
OW]
For any change in Equipment Logics Commissioning Commissioning VSTPS Levelt No approval is required Verbal communication is required Approval as per LMI is required | Logics can not be changed
In P&ID diagram following information is available Commissioning Commissioning VSTPS Levelt Logics of equipment Ranges of instrument Correct location of installation of | all of above