COMMISSIONING & OPERATIONAL TEST PROCEDURE –
NCP ICSS MODIFICATION Revision : B Doc. Class : 1
This document is the property of COMPANY. It must not be stored, reproduced or disclosed to others without authorization from the COMPANY.
Document number
ID-TUN-NG-SME-011282
COMMISSIONING & OPERATIONAL TEST PROCEDURE –
NCP ICSS MODIFICATION Revision : B Doc. Class : 1
TABLE OF CONTENTS
1. TEST SUMMARY 4
1.1 AIMS OF THE DOCUMENT 4
1.2 TEST PROCEDURE 4
2. PLANNING & MAN POWER 5
2.1 DETAIL MODIFICATION 5
2.2 PLANNING / SEQUENCE 5
2.3 MAN-POWER ESTIMATION. 6
2.4 TEST DURATION ESTIMATION. 6
2.5 VENDOR ASSISTANCE. 6
3. TEST REQUIREMENTS 6
3.1 PRECOMMISSIONING ACHIEVEMENTS 6
3.2 COMMISSIONING ACHIEVEMENTS 6
3.3 STATUS OF OTHER SUBSYSTEMS 6
3.4 SPECIAL TOOL AND TEST EQUIPMENT 6
3.5 CONSUMABLES 7
3.6 SPARES 7
3.7 SAFETY 7
3.8 UTILITIES 7
3.9 REFERENCE DOCUMENTS 7
4. TEST PREPARATIONS 7
4.1 JUMPER LIST 7
5. STEP BY STEP TEST PROCEDURE 8
5.1 VERIFICATION OF TASK #1, #5, #15, #16, #17, #18 & #19 8
5.2 VERIFICATION OF TASK #8 9
5.3 VERIFICATION OF TASK #9 & #10 11
5.4 VERIFICATION OF TASK #11 & #12 12
5.5 VERIFICATION OF TASK #13 13
5.6 VERIFICATION OF TASK #14 14
5.7 VERIFICATION OF TASK #21 & #23 15
5.8 VERIFICATION OF TASK #7 16
5.9 VERIFICATION OF TASK #6 17
5.10 VERIFICATION OF TASK #4 18
5.11 VERIFICATION OF TASK #2, #20 & #22 19
5.12 VERIFICATION OF TASK #24 20
5.13 VERIFICATION OF TASK #3 21
6. POST TEST CONDITION 22
6.1 REMOVAL INHIBITS & JUMPERS 22
SUMMARY
Existing NCP ICSS (PCS display & SSS) are modified to accommodate new NCP-2
(LP platform). Also new shutdown philosophies are implemented as well such as
removal of common ESD-0 and become individual ESD 1.0 and interlock for
simultaneous blow down.
1. TEST SUMMARY
Test result will be checked on NCP SSS Maintenance Console, NCP ITR Yokogawa
console or NCR Yokogawa console (if available during the test), and new ESD Matrix
panel.
Commissioning FTS (Functional Test Sheet) will be used to record the result of both
commissioning & operational test. These FTS have been prepared in accordance with
the ESD and F&G Logic diagram, and engineering document.
Task
Description
No
1 Deletion of ESD 0 bar & PB-0001 (ESD 0-NCR).
2 Renaming of ESD 1.0B from ESD 0.1B with same action as ESD 0.1 and new PB-0001 (ESD 1.0B - NCR).
Modification of Simultaneous Depressurization ( PB0001 - ESD1.0.B, PB0002, PB0003, PB0004, PB0005,
3 PB0006 - ESD 1.B).
4 P2P signal to NCP2 - US 03201 from NCP ESD 1.B
5 Removal of GTS's automatic shutdown from NCP ESD1.2 B ESD (US0146 & US0134), ESD 3.1.1B
(US0138), ESD 3.2.1B (US0142 - US0147), ESD 3.3.1.B (US0139), ESD 3.4.1.B (US0140), ESD 3.5.1B
B (US0148 - US0143), ESD 3.6.1.B (US0141), ESD 3.11.1B (US0144), ESD 3.7.4B (US0149 - US0131).
6 P2P signal to NCP2 - US 03216 from NCP - ESD 1.2B
7 P2P signal to NCP2 - US 03111 from NCP - ESD 1.3B
FCW Case 6 from NCP ESD 3.1.1.B, ESD 3.2.1.B, ESD 3.3.1.B, ESD 3.4.1.B, ESD 3.5.1B, ESD 3.6.1B,
8 ESD 3.11.1.B
9 P2P signal to NMP3 - US03122 from NCP - ESD 3.7.2.B
10 New PSDV113100 connected to existing NCP - ESD 3.7.2.B.
11 P2P signal to NMP3 - US03123 from NCP - ESD 3.8.2.B
12 New PSDV113101 connected to existing NCP - ESD 3.8.2.B.
13 FCW Case 7 from NCP - ESD 3.7.4.B
14 FCW Case 4 from existing US0235 or US0335. FCW Case 5 from existing US0235 and US0335.
15 Deletion of ESD 0 Back-up signal (USS).
16 Renaming of existing ESD bar 0.2.B to ESD 1.0.2.B
B 17 Renaming description 8US9710 to Electrical Isolation HV/Control Supply OWT ESD 1.X.C
18 Renaming Description of US0115 from ESD 0.1.C OWTP to ESD 1.0.C OWTP
19 Renaming of existing ESD bar 0.3.B to ESD 1.0.3.B
20 Additional adjustable time delay on SSS outputs for 230 VAC UPS Electrical isolation. Set at 3 minutes.
21 P2P to NCP2, US03227 from NCP ESD 2.B
22 P2P to NCP2, US03206 from NCP ESD 1.0.B
23 Additional Loss of P2P on ESD 2 bar input.
24 Peer to peer points commissioning from NPU - NCP - OWT to validate Star networks.
PERSONNEL MANHOURS
PJC/CMS Instrument SPV 6 days 60 h
2 PJC/CMS Instrument Technicians 6 days 120 h
One Production Operator at NCR or NPU
ITR 6 days 60 h
One NPU CS Technician 6 days 60 h
B
One Triconex Vendor 6 days 60 h
One Yokogawa Vendor 6 days 60 h
TOTAL MANHOUR 420 h
3. TEST REQUIREMENTS
3.1 PRECOMMISSIONING ACHIEVEMENTS
• Verify that the Pre-Commissioning is completed.
• No Level A Punch list items are pending.
• NCP SSS modification is completed & downloaded
• NCP PCS modification is completed & downloaded
• Produce punch list as applicable
• Commissioning & Operational Test Procedure – NCP ICSS modification agreed
upon and signed
3.5 CONSUMABLES
N/A
3.6 SPARES
N/A
3.7 SAFETY
• Work permit shall be raised and issued prior to commencement of the test.
• Pre-job safety tool box meeting shall be conducted with all persons who involve in the
test.
• Site personnel shall maintain communication with control room by means of hand
held radio.
3.8 UTILITIES
N/A
4. TEST PREPARATIONS
4.1 JUMPER LIST
As per operations requirement (under NPU/MNT control & action).
Performed by Witnessed by
Name
Department
Signature
Date
Note:
- Full function of FCW will be commissioned separately during GTS transfer.
Performed by Witnessed by
Name
Department
Signature
Date
Performed by Witnessed by
Name
Department
Signature
Date
Performed by Witnessed by
Name
Department
Signature
Date
Note:
- Full function of FCW will be commissioned separately during GTS transfer.
Performed by Witnessed by
Name
Department
Signature
Date
Note:
- Full function of FCW will be commissioned separately during GTS transfer.
Performed by Witnessed by
Name
Department
Signature
Date
Notes:
- Peer to peer network may not ready. This verification to check if lost P2P with OWT,
NPU or NCP2, ESD 2 bar will trip.
- Peer to peer network status will be verified during verification of task #24. (§5.12)
- After verification of task #24 (§5.12), only Loss of P2P NCP2 will be inhibited until
NCP2 ready. Loss of P2P NPU & OWT can be removed.
Performed by Witnessed by
Name
Department
Signature
Date
Performed by Witnessed by
Name
Department
Signature
Date
Performed by Witnessed by
Name
Department
Signature
Date
Performed by Witnessed by
Name
Department
Signature
Date
Note:
- To avoid actual UPS trip, NPU/MNT shall isolate the UPS accordingly
Performed by Witnessed by
Name
Department
Signature
Date
Performed by Witnessed by
Name
Department
Signature
Date
Performed by Witnessed by
Name
Department
Signature
Date