Professional Documents
Culture Documents
Construction Project Management Graduati
Construction Project Management Graduati
2018 – 2019
Graduation Project
Prepared by:
Supervised by:
2018 – 2019
Summary
This Book outlines twelve chapters about ‘City Gate mall project’ including many
topics that we discussed, analysed and explained. Also we focused on the
methodology that we used in this book and how far we observed the civil works that
matters in our study to present it in a fairly proper way to understand the ways of
engineering used in this project.
The first part content starts with an overview about the whole project, its detailed
location, size and budget. The following chapter analysed the projects Contract and
how fair it is to the project stakeholders. In addition to the criticism on couple of
sections in the contract and the suggestions that would make it more fair. Then the
WBS is explained in a way that would make the work flow easier. The next chapter
shows the method statement with an steps methods to explain the construction ways
that are used during the project time, then we reviewed the project layout in which
the whole project area and its surroundings are showed and the details of the site
facilities and construction areas .The quantity take-off chapter covers the manual
and revit take off in detailed tables and the activities are presented in a logical
sequence and the relationships are showed also in this study.
The second part starts with the cost, time and resource management in which our
study results are presented such as the labor, crews and their productivity. Then the
cost and duration are calculated for each activity. Then the Risk chapter contains our
study concerning the future possible hazards that may affect the project duration
cost and time using many methods like Brainstorming and other similar projects also
we highlighted the high severity risks on the project and the response plan is made
accordingly using primavera risk analysis program. Coming next is the Pricing
chapter in which the whole project pricing details from overheads(indirect cost) to
cash flow and Cost of finance(COF) calculations. And finally the researching
topics(Quality, Value Engineering and Health/Safety)
I
Table of contents
Sumarry………………………………………………….……..…………………………….I
1.1 Overvierw......................................................................................................................- 2 -
2.8 Obligors........................................................................................................................ - 17 -
4. METHOD STATEMENT - 26 -
5. QUANTITY TAKEOFF - 53 -
III
6. ACTIVITIES & RELATIONS - 111 -
IV
8.8 Case study ................................................................................................................... - 172 -
9. PRICING - 189 -
VI
List of figures
List of Tables
VIII
Table.( 5.8 ): RFT of ground beams ................................................. - 80 -
Table.( 5.9 ): RFT of ground slabs ................................................... - 82 -
Table.( 5.10 ): Revit foundation schedule ......................................... - 86 -
Table.( 5.11 ): Revit columns' schedule ........................................... - 97 -
Table.( 5.12 ): Revit structural framing schedule ............................ - 101 -
Table.( 5.13 ): Revit wall schedule ................................................. - 105 -
Table.( 5.14 ): Revit floor schedule ................................................ - 106 -
Table.( 5.15 ): Revit Foundation Takeoff for Zone B ...................... - 109 -
Table.( 6.1 ): List of activities for building A2 .................................. - 112 -
Table.( 8.1 ): checklist of project risk .............................................. - 161 -
Table.( 9.1 ):overhead calculations ................................................ - 192 -
Table.( 10.1 ): Follow up frequency guide ...................................... - 207 -
Table.( 10.2 ): Tests frequency guide:............................................ - 209 -
Table.( 11.1 ): Cost model ............................................................. - 217 -
Table.( 11.2 ): Alternatives ............................................................. - 219 -
Table.( 11.3 ): Cost saving by using AAC blocks ........................... - 220 -
Table.( 12.1 ): Job Hazard Analysis (JHA) ..................................... - 224 -
IX
1. PROJECT DEFINITION
& SCOPE
-1-
Chapter (1) PROJECT DEFINITION & SCOPE Graduation Project 2019
ـــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــ
1.1 Overvierw
CityGate Mall is a mega project of a 57,135 square meters with decent parking
spaces destined between gate 12 and gate 14 of AL-Rehab City which will dominate
the area. Scheduled to open in 2021. The mall will be the largest in the city which will
be a new addition inside Al-Rehab City to maintain its sustainability while also
fulfilling the needs and requirements of its residents.
The main elements of construction within the project includes internationally
designed retail stores, entertainment areas, restaurants, cafes, food courts, clinics,
and offices.
The project consists of two phases. The first phase is the concrete work and the
other is the finishing phase with total budget 875,000,000 (875 million LE)
The total duration of the project is supposed to be 3 years which started at January
2018.
The standard of finishes for the mall will be of a quality to compete all
existing retail developments that are existing within the city and beyond.
1.2 Location
Third phase, Al-Rehab City, Cairo, Egypt
-2-
Chapter (1) PROJECT DEFINITION & SCOPE Graduation Project 2019
ـــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــ
Owner:
Arabian company for projects & urban development
(Talaat Mostafa Group)
Contractor:
Atrium
-3-
Chapter (1) PROJECT DEFINITION & SCOPE Graduation Project 2019
ـــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــ
Architecture Consultant:
Raafat Miller Consulting (RMC)
HHCP,inc
MEP Consultant :
Raafat Miller Consulting (RMC)
-4-
Chapter (1) PROJECT DEFINITION & SCOPE Graduation Project 2019
ـــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــ
-5-
2. CONTRACT ANALYSIS
-6-
Chapter (2) CONTRACT ANALYSIS Graduation Project 2019
ـــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــ
2.1 General information
Contract participants
The owner: Tatweer (TMG)
Main contractor: Atrium quality contractor
Contract type: lump sum contract
Contract price: 875,000,000 EGP
Project delivery method: EPC (engineering, procurement and construction)
Project duration: 3 years (from 1st Jan, 2018 to 31 of Dec, 2021)
Selection Method: Direct order tendering
Currency: Egyptian pounds
Percent of retention: 10%
Advanced payment: 10% of the contract price
The delay fine: 1% of contract price for each month or part of it to a maximum
penalty of 10% from contract price.
- Contract documents
• Contract Agreement.
• Letter of Acceptance.
• Conditions.
• Appendix to Tender.
• Tender.
• The Schedules.
• Drawings.
• Specifications.
• Bills of Quantities.
This contract type is based on anticipated quantities of items which are counted in
the project in addition to their unit prices. The final price of the project depends upon
the quantities required to carry out the work. Unit price contracts are seldom used for
an entire major construction project, but they are frequently used for agreements
with subcontractors which involve accurate identification of different types of items,
but not their numbers, in the contract documents. They are also often used for
maintenance and repair work.
-7-
Chapter (2) CONTRACT ANALYSIS Graduation Project 2019
ـــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــ
Unit price characteristic:
Owner is aware of the details of the project to a large extent and know
financial requirements.
Common in more than 80% of construction projects.
Execution period is often defined.
-8-
Chapter (2) CONTRACT ANALYSIS Graduation Project 2019
ـــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــ
The project delivery method is: EPC
-9-
Chapter (2) CONTRACT ANALYSIS Graduation Project 2019
ـــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــ
1. The owners seldom participate in the project, and the control degree is also low
for the owners.
2. EPC companies are responsible for risk, so it's important to choose the right EPC
companies. As if the EPC companies have the serious financing problems, the
project will be at risk.
3. The cost of EPC companies will be higher for the owner due to risk responsibility.
4. More information about EPC companies could be found in this site as the owners
of the traditional construction mode will be more difficult to understand the works of
the EPC companies.
- 10 -
Chapter (2) CONTRACT ANALYSIS Graduation Project 2019
ـــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــ
2.5 Financial conditions compared to FIDIC
1- Changes in cost
FIDIC
clause Not mentioned
The contract is not shown to use this ratio to reverse reference model
Comment
contractor obligation.
FIDIC
clause The same clause
Comment The contract is not shown to use this ratio to reverse reference model
contractor obligation.
- 11 -
Chapter (2) CONTRACT ANALYSIS Graduation Project 2019
ـــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــ
2.6 Legal conditions compared to FIDIC
1- Amicable Settlement and Arbitration
(i) the sole member of the “DB” and, where this is the case, all
references
(ii) one of the three persons who are jointly called the “DB” (or “Dispute
Board”) and, where this is the case, the other two persons are called
the
“Other Members”.
- 12 -
Chapter (2) CONTRACT ANALYSIS Graduation Project 2019
ـــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــ
2- Contractor's Entitlement to Suspend Work
Contract Price
If the Contractor suffers delay and/or incurs Cost from complying with the
Engineer’s instructions under Sub-Clause 8.8 [Suspension of Work]
and/or from resuming the work, the Contractor shall give notice to the
Engineer and shall be entitled subject to Sub-Clause 20.1 [Contractor’s
Claims] to:
The Contractor shall be entitled to payment of the value (as at the date of
suspension) of Plant and/or Materials which have not been delivered to
Site, if:
(a) the work on Plant or delivery of Plant and/or Materials has been
suspended for more than 28 days, and
- 13 -
Chapter (2) CONTRACT ANALYSIS Graduation Project 2019
ـــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــ
(b) the Contractor has marked the Plant and/or Materials as the
Employer’s
Comment
Same as FIDIC
The difference:
- 14 -
Chapter (2) CONTRACT ANALYSIS Graduation Project 2019
ـــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــ
set out in the Contract if, in the opinion of the Contract Administrator,
the same shall be applicable.
If the Contract does not contain any rates or prices applicable to the
varied work, the rates and prices in the Contract shall be used as the
basis for valuation so far as may be reasonable, failing which, after
due consultation by the Contract Administrator the Employer and the
Contractor, suitable rates or prices shall be agreed upon between the
Contract Administrator and the Contractor. In the event of
agreement, the Contract Administrator shall fix such rates or prices
as are, in his opinion, appropriate and shall notify the Contractor
accordingly, with a copy to the Employer. Until such time as rates or
prices are agreed or fixed, the Contract Administrator shall determine
provisional rates or prices to enable on-account payments to be
included in certificates I issued in accordance with Clause 60.
Comment
Varied quantity doesn’t exceed 10%
2. Inspection of Site
- 15 -
Chapter (2) CONTRACT ANALYSIS Graduation Project 2019
ـــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــ
and methods which the Contractor proposes to adopt for the execution
of the Works.
Unless the engineer - within (21) days from the date of receipt of the
program - to comment upon and inform the contractor about the extent
of non-matching program for a decade, then equal right to the
implementation of which, considering its other obligations under the
contract. As members of the employer is entitled to base on that
program when planning to perform their activities
Comment Contract pilot was not clear in this clause. There is a condition in the
Contract is an obligation on insurance companies
- 16 -
Chapter (2) CONTRACT ANALYSIS Graduation Project 2019
ـــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــ
2.8 Obligors
4.3 Subcontractors
- 17 -
Chapter (2) CONTRACT ANALYSIS Graduation Project 2019
ـــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــ
(ii) the Contractor shall remain totally responsible for thecompletion
of the Subcontract Works in accordance with the requirements of the
Contract;
If the Contract does not contain any rates or prices applicable to the
varied work, the rates and prices in the Contract shall be used as the
basis for valuation so far as may be reasonable, failing which, after
due consultation by the Contract Administrator the Employer and the
Contractor, suitable rates or prices shall be agreed upon between
the Contract Administrator and the Contractor. In the event
of disagreement the Contract Administrator shall fix such rates or
prices as are, in his opinion, appropriate and shall notify the
Contractor accordingly, with a copy to the Employer. Until such
time as rates or prices are agreed or fixed, the Contract
Administrator shall determine provisional rates or prices to enable
on-account payments to be included in certificates issued in
accordance with Clause 60.
- 18 -
Chapter (2) CONTRACT ANALYSIS Graduation Project 2019
ـــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــ
Administrator, Should the Contractor fail to agree the value within the
stipulated period, the Contract Administrator, shall determine the value
as noted above, which value shall be final and binding.
2.9 Beneficial
Payment of Subcontractors
4.7 ii) The Contractor shall pay its Subcontractors in accordance with
the terms of their respective subcontracts.
(b) The Employer shall deduct any payment made pursuant to Clause
4.7(a) from any sums owing to the Contractor and such payment shall
be considered to have been a payment made to the Contractor in
respect of the part of the Works to which it relates.
(c) The Contractor agrees that any payment made pursuant to this
Clause will be without any risk to the Employer and shall not create
any contractual relationship between the Employer and the
Subcontractor. The Contractor indemnifies the Employer in respect
of any claims made by any Subcontractor as a result of the Employer
exercising its right pursuant to Clause 4.4 and this Clause 4.7.
- 19 -
Chapter (2) CONTRACT ANALYSIS Graduation Project 2019
ـــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــ
2.10 Collateral/Security
Disruption of Progress
6.3 The Contractor shall give, not less than twenty eight (28)
calendar days, written notice to the Contract Administrator whenever
planning or progress of the Works is likely to be delayed or
disrupted unless any further drawings or order including a direction,
instruction or approval, is issued by the Contract Administrator within a
reasonable time. The notice shall include details of the drawing or
order required and of why and by when it is required and of any delay
or disruption likely to be suffered if it is late. Failure to comply with
this clause shall relieve the Contract Administrator from the
obligation to consider any claim by the Contractor.
This notice shall describe the physical conditions, so that they can be
inspected by the Contract Administrator, and shall set out the reasons
why the Contractor considers them to be Unforeseeable. The
Contractor shall continue executing the Works, using such proper
and reasonable measures as are appropriate for the physical
conditions, and shall comply with any instructions which the Contract
Administrator may give.
(b) the amount of any costs which may have been incurred by the
Contractor by reason of such obstructions or conditions having been
encountered, which shall be added to the Contract Price, and shall
notify the Contractor accordingly, with a copy to the Employer.
Such determination shall take account of any instruction which
the Contract Administrator may issue to the Contractor in
connection therewith, and any proper and reasonable
measures acceptable to the Contract Administrator which the
- 20 -
Chapter (2) CONTRACT ANALYSIS Graduation Project 2019
ـــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــ
Contractor may take in the absence of specific instructions from
the Contract Administrator.
42.2 If the Contractor suffers delay and/or incurs costs from failure
(b) the amount of such costs, which shall be added to the Contract
Price and shall notify the Contractor accordingly, with a copy to the
Employer.
- 21 -
3. WORK &
ORGANIZITIONAL
BREAKDOWN
STRUCTURE
- 22 -
Chapter (3) WBS & OBS Graduation Project 2019
ـــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــ
3.1 WBS definition
The Project Management Institute PMI (2001) define the WBS as “a hierarchical
structure that defines and organizes the total project scope based on deliverables,
with each descending level in the hierarchy representing an increasingly detailed
definition of the project work”.
The aim is to ensure complete and proper definition of the entire work. The highest
level of the structure represents the entire project. This is then subdivided into
smaller elements that represent the next level in the hierarchy. The process
continues until such a level when the entire project is deemed to have been
sufficiently decomposed to allow for effective and efficient project control. The last
level entries in the structure are referred to as work packages and represent the level
where responsibility for the performance of the work in
each work package is assigned to an individual or organization as shown in Fig 1.
- 23 -
)Chapter (3 WBS & OBS Graduation Project 2019
ـــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــ
- 24 -
Chapter (3) WBS & OBS Graduation Project 2019
ـــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــ
3.2 OBS definition
Organization Breakdown Structure or OBS is a hierarchical model describing the
established organizational framework for project planning, resource
management, time and expense tracking, cost allocation, revenue/profit reporting,
and work management.
- 25 -
4. METHOD STATEMENT
- 26 -
Chapter (4) METHOD STATEMENT Graduation Project 2019
ـــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــ
4.1 Method statement definition
This method of construction is intended to inform the Principal Contractor and other
contractors how the work will be delivered in the site associated with risks and the
precautions to be taken when the Company is working on the site. It provides the
basis for the control of operations whilst the Company is on the site.
- The purpose of this statement:
- To outline how the work will be achieved in the site.
- To provide a document that worker must read and understand before
starting a job.
- To meet legal requirements.
- To predict possible problems.
- To make a program for work, materials and time.
Program
The construction sequence is driven mainly by the contractual milestones, the
phased commissioning with respect to the handing over of mall defined areas and
detailed requirements.
The allocations of the milestones define a general working sequence for the whole
project.
The program is divided into 2 phases as per the contract agreement as follow:
- The pre-permit construction period
- The permanent works
- 27 -
Chapter (4) METHOD STATEMENT Graduation Project 2019
ـــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــ
After soil replacement, the concrete works will start (PC footings, RC footings,
smells, columns and ceiling for basement) then columns and ceiling of 1st floor
reaching the roof.
Insulation of RC footings starts after de shuttering the ceiling of the 1st floor followed
by backfilling.
Brick works start after finishing concrete works and followed by plastering.
- 28 -
Chapter (4) METHOD STATEMENT Graduation Project 2019
ـــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــ
-Surveying:
Prepare the Land surveying Studies
Setting control points
Determination of site natural average level
- 29 -
Chapter (4) METHOD STATEMENT Graduation Project 2019
ـــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــ
Excavating to 7m under ground level for each zone depending on the sequence of
works.
Transfer the result of excavation out of the site.
1. Total station
- 30 -
)Chapter (4 METHOD STATEMENT Graduation Project 2019
ـــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــ
2. Excavator
3. Loader
- 31 -
Chapter (4) METHOD STATEMENT Graduation Project 2019
ـــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــ
5. dump truck
6. plate compactor
- 32 -
Chapter (4) METHOD STATEMENT Graduation Project 2019
ـــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــ
Steel cage is raised up and prepared for installation
The steel cage is driven into drilled hole
Pile cap is formed
- 33 -
Chapter (4) METHOD STATEMENT Graduation Project 2019
ـــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــ
Anchors:
Anchored sheet pile walls are held above the driven depth by anchors provided at
suitable level. The anchors provide forces for the stability of the sheet pile, in
addition to the lateral passive resistance of the soil into which the sheet piles are
driven.
It includes an anchor or tieback at or near the head of the wall. More than one set of
anchors or tiebacks can be used. It increases wall stability and enables taller walls to
be built and sustained almost a necessity with vinyl, aluminium and fiberglass sheet
piles. It is not exclusive to sheet piling; also used with other types of in situ wall
systems. In case of cantilever sheet pile walls if the deflection at top point of the
sheet pile wall is very large, then settlement of soil takes place at top just behind the
sheet pile wall. So, to reduce the excessive deflections the anchors are provided.
The angle of internal friction, which is an empirical shear strength parameter of the
soil, plays a major role in the resistance of the load carried by the ground anchor.
Also, when it is installed to a greater depth, the frustum of cone of soil supporting the
anchor is also large, which gives more force-resistance.
Also, when small loads are applied the depth can be less. But if the load is of higher
range, sufficient additional anchors (or) greater length is to be provided. The
diameter of the anchor also plays a bigger part. The size and angle of the top
surface of ground anchor is a useful parameter in the installation and pull-out
resistance of the ground anchor.
Components and Principle of Ground Anchor in Construction
The following are the different components of the Ground Anchor
1. Wedge Plate
2. Individual Sheathing
3. Bearing Plate
4. Wedge
5. Strands
6. Spacer
7. Grout body
The stiffness of the wedge plate is useful in transmitting the anchor load to the
bearing plate closer to the ends of the plate’s span. This prevents the bending of the
bearing plate. If you have large size wedge plate, then the amount of bending of the
bearing plate is reduced. Strands are useful in tying up all the cables and act as one
unit. The wedge prevents the anchor part from sliding and thus keeps the ground
anchor in position. Grout body is useful in maintaining a bond between the anchor
and the soil.
- 34 -
Chapter (4) METHOD STATEMENT Graduation Project 2019
ـــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــ
How to Determine the
Reasonable Position and
Length of the Ground
Anchor
This problem arises in
slope reinforcement
projects. One of recent
method used to calculate
the above is the variable-
modulus elastoplastic
strength reduction method
or simply called as the
SRM. This method is used
to obtain the stress
variations, strain field,
factor of safety of the
slope.
In this method, slope-
stability done by anchor Fig.( 4.7 ): various types of anchoring for sheet pile walls
cables is modeled using
surface loading. To
represent the anchor
reinforcement system,
they are distributed in
different forms of surface
loading.
Types of Anchors
(a) - Anchor Plate or beam
(b)- Vertical Anchor Pile
(c)- Tieback Anchor
- 35 -
)Chapter (4 METHOD STATEMENT Graduation Project 2019
ـــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــ
- 36 -
Chapter (4) METHOD STATEMENT Graduation Project 2019
ـــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــ
Compact each layer using Soil compactors as shown in Fig (4.10)
Fig.( 4.11 ): Submerging soil with water Fig.( 4.10 ): Soil Compacting
-Foundation:
Plain concrete:
The formwork for the 400 mm high plain concrete foundations will consist of H20 and
soldier combined system fixed onto the blinding underlay.
Reinforced concrete:
The formwork system will consist of steel modular panels supported onto the below
plain concrete foundation. Similarly, for the ground connecting tie beams which will
be cast together. In the same phase, we are planning to pour from 9 to 12
foundations and connecting beams simultaneously
Shuttering works:
Locating the axis of footings according to survey works.
Construct the shuttering forms for all sides of the footings.
Steel Fixing Works:
prepare the required length and dimensions of steel bar.
put the reinforcement in its location according to reinforcement drawings.
Pouring concrete & curing works:
•Pouring the concrete and using the vibrator during pouring.
•Curing the concrete after pouring and dismantling the forms for 7 days
- 37 -
Chapter (4) METHOD STATEMENT Graduation Project 2019
ـــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــ
Isolation works:
used to isolate plain and reinforced concrete
protect steel from cores
protect structure element from infiltrated water
-Backfilling:
1st layer:
Make 1st layer (using sand)
Compact the layer well.
Spraying water above sand layer.
2nd layer:
Make 2nd layer (using sand)
Compact the layer well.
Spraying water above sand layer.
3rd layer:
Make 3rd layer (using sand)
Compact the layer well.
Spraying water above sand layer.
4th layer:
Make 4th layer (using sand)
Compact the layer well.
Spraying water above sand layer.
- 38 -
Chapter (4) METHOD STATEMENT Graduation Project 2019
ـــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــ
4.3.3 Super structure
-Concrete works:
Concrete will be brought from El-SWEDY batch plant located in 5th settlement (15
minutes away from the site)
Pre-pour check, check line & levels must be completed before pouring.
The dimensions and alignment of R.C components and formworks should be
inspected by the site engineer.
Steel reinforcement should be placed and its alignment & number of steel bars
should be revised according to the drawings.
Ensure that the concrete delivery vehicles have suitable access to the intended
areas in the suitable time.
Ensure that the quality of concrete is suitable and proper, tests such as slump test
should be made.
Concrete is poured using a pump followed by a worker with a vibrator for the
compaction of the concrete.
Surveying instruments and level should be set up during the pouring to ensure the
formwork states.
Cubes of the designed mix must be tested for compressive strength at 7 days and 28
days for the initial approval satisfying a 400 kg/cm2 compressive strength.
The structure should be checked after the pour, line and levels should also be
verified.
-Risk assessment:
Incidents that could happen as a result of poor planning.
Unsuitable equipment locations which can cause several accidents.
Collapse of work area.
Live electrical lines in working area.
Injury through failure of equipment.
Vehicle damage.
Personnel struck by hoses or concrete
Working in extreme weather conditions.
- 39 -
Chapter (4) METHOD STATEMENT Graduation Project 2019
ـــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــ
-Formwork:
After studying the structural drawings, the Project Engineer will plan for sizes,
numbers and type of formwork to be used in consultation with the Structural
Engineer, if required. Depending upon the program, the number of repetitions will be
decided.
Availability of formwork will be checked with the Procurement Manager and decision
will be taken to buy, hire or reuse formwork material.
During fabrication of formwork shutters, all dimensions shall be cross-checked with a
view to avoiding corrective action during erection.
Paint reference numbers on all panels to ensure their use in correct positions.
Ensure that the props, shores, waling, bearers, clamps and tie rods are the right size
and at the correct spacing. The Formwork designer shall check the false work
system with respect to load imposed on it and design parameters as laid down in the
specification.
Check that the false work is securely braced and is on a firm foundation.
Forms fastened to previously cast concrete must be tightly fixed to prevent grout
loss. Cellular foam plastic strips can be used to make a seal.
Check quality of shutter lining, tightness of bolts and wedges, built-in items, inserts
and other embedment.
Tie-rod holes to be made in the formwork shall be neat so that they can be patched
or plugged later on.
Particular attention will be paid to the rigidity and line of stop ends and joint formers.
Remove all tie-wire clippings and nails, which may stain both the formwork and the
concrete.
Ensure that adequate access and working platforms are in place for the concreting
gang and that toe boards and guardrails are provided.
A spreader or lifting beam shall be used to prevent distortion when placing formwork.
Adjustable steel props shall be erected in plumb and verticality of props checked
using a spirit level.
A prop should not be used if it is bent, creased or, rusted or has a bent head or base
plate, damaged pin etc.
Proper release of agent shall be used so that it can be removed without damaging
the surface finish of the concrete.
New timber and plywood forms shall be given first coat of the appropriate release
agent 36 hours in advance, then a second coat just before they are used.
- 40 -
Chapter (4) METHOD STATEMENT Graduation Project 2019
ـــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــ
Avoid excessive use of release agent as this can cause staining or retardation of the
concrete.
A close watch should be kept on all wedges and fastenings. Make sure that they do
not work loose. Grout loss is an indication that some movement has occurred.
4.3.4 Finishing
Brick works:
Lines and levels should be set out and datum's marked whenever possible.
Material should be stacked as close to working site as possible.
Materials used are: Perforated bricks, light bricks, cement hollow and solid blocks
connected using a binding mortar.
Binding mortar will be mixed on site to ensure consistency.
Levels and line checks will be performed periodically during works.
For masonry works underground bricks will be insulated using liquid bitumen.
-plastering:
Plastering will be done on three stages:
Spattering:
Cleaning the wall surface from dust, and other roughness, then sprinkle it with water
& smoothing the surface, with a steel brush, Sprinkle mortar cement to the walls
using trowel.
Level dots & strings:
It is made by gypsum.
Thickens of dots equals to the thickness of plastering layer.
Plastering:
Sprinkle the walls with water.
Fill between the strings with mortar Level the surface.
- 41 -
Chapter (4) METHOD STATEMENT Graduation Project 2019
ـــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــ
Construction
No Activity Man power Material Equipment
sequence
-Excavator
-Excavate Excavator
-dumping
-Disposal -(n)
1 Excavation truck
formation level -Tipper (n)
-bulldozer
&compaction -Surveyor (n)
-Roller
-Form work -Concrete -Concrete
Plain -Pouring n mixing truck
2
concrete -Compaction n -Pump
-curing -vibrator
-Form work -Concrete
-Reinforcement n mixing truck
Reinforced
3 -Pouring n -Concrete Pump
concrete
-Compaction n -vibrator
-Curing -Vibrator
Clean the
-surface
Apply a -Concrete
Thermal &
-Concrete primer
4 moisture -Heater
Primer n -Bituminous
protection
-Apply sheets
bituminous
Sheet
Dumping
-Tipper (n)
-truck
-Backfilling -Driver (n)
5 Backfilling -Coarse sand -Bulldozer
-Compaction Civil
-Roller
-overseer
-Rotary boring
-BAUER 25
Disposal of
-H
-wastes -Leader (n)
-Loader
6 Piling Concrete -Fixer (n)
-concrete
-pouring -Handling (n)
pump
-Reinforcement
-vibrator
-pile capping
-Import blocks
to site
-Transported it -CMU
Internal
7 to needed area -Mortar -Trucks
masonry
Building -Reinforcement
n
-process
-Cement paste
8 plaster mixing n -Mortar
-Plastering
- 42 -
Chapter (4) METHOD STATEMENT Graduation Project 2019
ـــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــ
4.5 STUDY OF ALTERNATIVES
4.5.1 Form Work
Alternative 1: Steel formwork
- 43 -
Chapter (4) METHOD STATEMENT Graduation Project 2019
ـــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــ
Weighted Analysis 1
For Steel Formwork:
Judgment Rating
Extremly Prefered 9
Very Strongly
Prefered 7
Strongly Prefered 5
Moderatly Prefered 3
Equally Prefered 1
Steel formwork is costly but can be used for large number of projects. Steel
shuttering give very smooth finishes to concrete surface. It is suitable for circular or
- 44 -
Chapter (4) METHOD STATEMENT Graduation Project 2019
ـــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــ
curved structures such as tanks, columns, chimneys, sewer, tunnel and retaining
wall.
The Timber formwork is easy to produce but time-consuming for larger structures.
Plywood facing has a short lifespan. Timber is easy to fix, remove and lightweight.
Timber Shuttering is most flexible type of shuttering; it can be used for any shape
and size
4.5.2 Masonry Work
Alternative 1: solid concrete blocks (light grey colored)
Uses of solid concrete blocks:
Solid concrete blocks are used for load-bearing as well as non-load bearing walls.
It is also used for constructing retaining walls, garden walls, chimney and fireplaces.
It is also used as a lintel.
Advantages of solid concrete blocks:
The design of solid concrete blocks is flexible and easy to construct.
Solid concrete blocks are ideal for foundation and basement wall.
Solid concrete blocks provide insulation against cold and hot weather.
The solid concrete blocks wall is long lasting, durable and requires less
maintenance.
The Solid concrete blocks have a smooth finish and have more decorative
surface.
The Solid concrete blocks are virtually soundproof.
Disadvantages of solid concrete blocks:
The cost of building with solid concrete blocks can be higher than traditional
framed construction.
Weight of solid concrete block is more than AAC Block
Due to the heavy weight of concrete structural cost is high.
It is difficult to make arrangements for concealed work for wiring, plumbing &
conduit.
- 45 -
Chapter (4) METHOD STATEMENT Graduation Project 2019
ـــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــ
Alternative2: Autoclaved Aerated Concrete Blocks (ACC blocks) (Lightweight
blocks) (Grey colored)
Uses of ACC concrete blocks:
AAC Blocks can be used to build internal as well as external walls.
It can also be used for both load bearing and non-load bearing walls.
Advantages of ACC concrete blocks:
Saves steel and concrete due to the reduction in dead weight.
Increase in floor area due to the reduction in the size of columns and
thickness of the wall.
AAC blocks are very easy to handle and ordinary tools are used for cutting.
AAC blocks are made from inorganic material which helps to avoid termites,
damages or losses.
Easy to transport on upper floors.
Time-saving in construction
AAC blocks are appropriate for fire rating application for desired safety.
There is minimal wastage in case of AAC blocks.
It is environment-friendly and also saves water. Hence it is popularly used as
a green product.
Though the production cost of AAC Blocks is high but on the whole the project
cost decrease.
- 46 -
Chapter (4) METHOD STATEMENT Graduation Project 2019
ـــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــ
As an Aesthetic and Finish Surface: Bricks are used as per its different colours, sizes
and orientations to get different surface designs. As an aesthetic material brick can
be used:
a) As Facing Bricks
b) Architectural Purposes
c) Exposed practice work
Advantages of clay bricks:
Raw material is easily and cheaply available. So it is economical.
Red Bricks are low maintenance, permanent, hard and durable building
material.
Compressive strength is good enough for ordinary construction.
Different orientations and sizes give different surface textures
Demolishing of brick structures is very easy and less time consuming.
It is reusable and recyclable.
Highly fire resistant.
Disadvantages of clay bricks:
Time consuming construction
Red Bricks cannot be used in high seismic zones for load bearing structures.
A red brick absorbs water easily so Efflorescence occurs due to the presence
of salt in water.
Rough surfaces of bricks may cause moulds growth if it is not properly
cleaned.
Continuous use of Red bricks in construction will lead to extensive loss of
fertile top soil and hence potential agricultural land.
Red bricks are heavy in weight so that the structure needs to withstand
greater weight, and hence construction cost increases.
Big damage to environmental and loss of fertile land due to use of clay soil
excavation for making of bricks
- 47 -
Chapter (4) METHOD STATEMENT Graduation Project 2019
ـــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــ
Weighted Analysis 2
Table.( 4.3 ): Weighted Analysis among Concrete, Lightweight & Red brick blocks
Judgment Rating
Extremly Prefered 9
Very Strongly
Prefered 7
Strongly Prefered 5
Moderatly Prefered 3
Equally Prefered 1
The analysis shows that the solid concrete blocks are used as an alternative of clay
bricks (Red Bricks) but concrete blocks are heavy in weight hence buildings
becomes heavy. The cost of concrete block masonry is also high hence AAC
- 48 -
Chapter (4) METHOD STATEMENT Graduation Project 2019
ـــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــ
(Lightweight concrete blocks) blocks are used in the construction of the wall. Using
AAC block (Lightweight concrete blocks) is very advantageous because it conserves
the environment, saves energy and provides safety to life.
4.6 LAYOUT
6.1 Site layout elements achieved as shown in (Fig 14).
Safety
Site Accessibility
Information Signs
Security
Offices
Water Supply and Sanitation
Craft Change-Houses
Material Handling
Storage and site cleaning
Fire prevention
Medical services
Construction safety clothing
Lighting
Fencing the boundary
- 49 -
Chapter (4) METHOD STATEMENT Graduation Project 2019
ـــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــ
- 50 -
Chapter (4) METHOD STATEMENT Graduation Project 2019
ـــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــ
Pipe jointing yard No
Pipe storage yard Yes
Welding shop No
Parking lot Yes
Tank Yes
Long term laydown storage Yes
Machine room No
Electrical shop No
Steel fabrication shop No
Sandblast shop No
Painting shop No
Scaffold storage yard No
Material warehouse Yes
- 51 -
)Chapter (4 METHOD STATEMENT Graduation Project 2019
ـــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــ
- 52 -
5. QUANTITY TAKEOFF
- 53 -
Chapter (5) QUANTITY TAKEOFF Graduation Project 2019
ـــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــ
5.1.Manual quantity takeoff
we have used excel sheets in calculating the quantities of material of the building
and here is the excel sheets used
Foundation Quantities
Foundations quantity and RFT takeoff was made for the zone B which
consists of 44 isolated footing type and 5 rafts and tie beams shown in
fig.(5.1) below ,sections of footings are located in the appendix
Excavation Quantities
Excavation and backfilling were measured with engineering dimensions from
the plan of foundation shown in fig.(5.1)
Ground columns
Concrete volume and RFT were measured from the plan of ground floor fig.
(5.2) for one floor height
Ground beams
Rft of beams was measured for the sub-zone B1 shown in plan fig.(5.4)
Ground floor
Concrete of the floors was measured totally for Zone B shown in fig.(5.2) but
the RFT measures was made only for the first floor at sub-zone B ,see
fig.(5.4)
- 54 -
)Chapter (5 QUANTITY TAKEOFF Graduation Project 2019
ـــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــ
- 55 -
)Chapter (5 QUANTITY TAKEOFF Graduation Project 2019
ـــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــ
F86 1 1700 1700 300 0,867
F87 4 3700 2300 300 10,212
F88 1 3500 2100 300 2,205
F89 6 3200 1900 300 10,944
F90 4 1700 1600 300 3,264
F91 19 2100 1800 300 21,546
' F92 1 2300 2100 300 1,449
F106 1 2700 2400 300 1,944
F107 2 2200 1800 300 2,376
F109 1 2400 1500 300 1,08
F110 1 1400 1400 300 0,588
F111 6 2600 1600 300 7,488
' F111 7 2800 1400 300 8,232
' F123 1 3900 3400 300 3,978
F131 1 4100 3500 300 4,305
F132 5 5100 5100 300 39,015
F135 1 4400 4300 300 5,676
F140 2 3600 2100 300 4,536
RAFT 300 1 878,43
total 1393,614
- 56 -
)Chapter (5 QUANTITY TAKEOFF Graduation Project 2019
ـــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــ
reinforced concrete
footing no. length width thickness )volume(m³
F2 1 1500 1500 600 1,35
F6 1 2700 2700 600 4,374
F7 2 1900 1900 600 4,332
F10 1 3600 3600 600 7,776
F13 2 3000 3000 600 10,8
' F15 1 3200 3200 600 6,144
F17 1 3100 3100 600 5,766
' F17 1 3100 3100 600 5,766
F19 3 3900 3900 600 27,378
F20 2 3700 3700 600 16,428
' F21 1 4300 4300 600 11,094
F23 3 3400 3400 600 20,808
F27 2 2800 2800 600 9,408
F28 2 1500 1500 600 2,7
F34 16 1300 1300 500 13,52
F35 11 2400 2400 500 31,68
F38 45 2700 2700 500 164,025
F40 18 1500 1500 500 20,25
F42 11 1900 1900 500 19,855
' F42 3 1400 1400 600 3,528
F44 5 3300 3300 500 27,225
F45 1 2300 2300 500 2,645
F52 8 1700 1700 600 13,872
F65 2 2100 2100 700 6,174
F71 1 1500 1500 600 1,35
- 57 -
)Chapter (5 QUANTITY TAKEOFF Graduation Project 2019
ـــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــ
F86 1 1100 1100 500 0,605
F87 4 1700 1700 500 5,78
F88 1 1500 1500 600 1,35
F89 6 1300 1300 500 5,07
F90 4 1000 1000 500 2
F91 19 1200 1200 500 13,68
' F92 1 1500 1500 500 1,125
F106 1 1800 1800 500 1,62
F107 2 1200 1200 500 1,44
F109 1 900 900 500 0,405
F110 1 800 800 500 0,32
F111 6 1000 1000 500 3
' F111 7 800 800 500 2,24
' F123 1 2800 2800 600 4,704
F131 1 2900 2900 600 5,046
F132 5 4500 4500 600 60,75
F135 1 3700 3700 600 8,214
F140 2 1500 1500 500 2,25
slab 500 8 50,12
slab 600 6 793,22
slab 800 1 945,31
total 2346,497
- 58 -
)Chapter (5 QUANTITY TAKEOFF Graduation Project 2019
ـــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــ
Footing
Dimension Long Direction Short Direction
Ite N Leng Wid dep Volu di W/ Spaci di W/ Spaci
Steel
ms o th th th me a M ng a M ng
1 0,8 1 0,8
F2 1 1,5 1,5 0,6 1,35 0,15 0,15 50,6
2 89 2 89
1 1,5 1 1,5
F6 1 2,7 2,7 0,6 4,37 0,15 0,15 222,8
6 80 6 80
1 0,8 1 0,8
F7 2 1,9 1,9 0,6 4,33 0,125 0,125 170,7
2 89 2 89
1 2,0 1 2,0
F10 1 3,6 3,6 0,6 7,78 0,1 0,1 674,9
8 00 8 00
1 1,5 1 1,5
F13 2 3 3 0,6 10,80 0,1 0,1 779,0
6 80 6 80
F15 1 2,0 1 2,0
1 3,2 3,2 0,6 6,14 0,1 0,1 549,1
' 8 00 8 00
1 0,8 1 0,8
F17 1 3,1 3,1 0,6 5,77 0,125 0,125 191,1
2 89 2 89
F17 1 2,0 1 2,0
1 3,1 3,1 0,6 5,77 0,125 0,125 420,5
' 8 00 8 00
1 2,0 1 2,0 1883,
F19 3 3,9 3,9 0,6 27,38 0,125 0,125
8 00 8 00 6
2 2,4 2 2,4 1744,
F20 2 3,7 3,7 0,6 16,43 0,1 0,1
0 69 0 69 7
F21 1 2,0 1 2,0
1 4,3 4,3 0,6 11,09 0,1 0,1 925,8
' 8 00 8 00
1 2,0 1 2,0 1831,
F23 3 3,4 3,4 0,6 20,81 0,1 0,1
8 00 8 00 2
1 1,5 1 1,5
F27 2 2,8 2,8 0,6 9,41 0,125 0,125 561,1
6 80 6 80
1 0,8 1 0,8
F28 2 1,5 1,5 0,6 2,70 0,125 0,125 118,3
2 89 2 89
- 59 -
)Chapter (5 QUANTITY TAKEOFF Graduation Project 2019
ـــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــ
1 1 0,8 1 0,8
F34 1,3 1,3 0,5 13,52 0,15 0,15 601,3
6 2 89 2 89
1 1 0,8 1 0,8 1580,
F35 2,4 2,4 0,5 31,68 0,1 0,1
1 2 89 2 89 7
4 164,0 1 1,5 1 1,5 1122
F38 2,7 2,7 0,5 0,125 0,125
5 3 6 80 6 80 8,2
1 1 0,8 1 0,8
F40 1,5 1,5 0,5 20,25 0,15 0,15 841,0
8 2 89 2 89
1 1 0,8 1 0,8
F42 1,9 1,9 0,5 19,86 0,15 0,15 746,5
1 2 89 2 89
F42 1 1,5 1 1,5
3 1,4 1,4 0,6 3,53 0,125 0,125 276,4
' 6 80 6 80
1 2,0 1 2,0 2760,
F44 5 3,3 3,3 0,5 27,23 0,1 0,1
8 00 8 00 7
1 0,8 1 0,8
F45 1 2,3 2,3 0,5 2,65 0,1 0,125 121,4
2 89 2 89
1 0,8 1 0,8
F52 8 1,7 1,7 0,6 13,87 0,125 0,125 573,4
2 89 2 89
1 0,8 1 0,8
F65 2 2,1 2,1 0,7 6,17 0,125 0,125 212,9
2 89 2 89
1 2,0 1 2,0
F71 1 1,5 1,5 0,6 1,35 0,1 0,1 157,3
8 00 8 00
1 1,5 1 1,5
F86 1 1,1 1,1 0,5 0,61 0,15 0,15 50,1
6 80 6 80
1 2,0 1 2,0
F87 4 1,7 1,7 0,5 5,78 0,1 0,1 708,0
8 00 8 00
1 1,5 1 1,5
F88 1 1,5 1,5 0,6 1,35 0,125 0,125 102,3
6 80 6 80
1 1,5 1 1,5
F89 6 1,3 1,3 0,5 5,07 0,125 0,125 451,6
6 80 6 80
1 1,5 1 1,5
F90 4 1 1 0,5 2,00 0,15 0,15 174,6
6 80 6 80
1 1 1,5 1 1,5 1083,
F91 1,2 1,2 0,5 13,68 0,15 0,15
9 6 80 6 80 1
F92 1 1,5 1 1,5
1 1,5 1,5 0,5 1,13 0,15 0,15 80,2
' 6 80 6 80
- 60 -
)Chapter (5 QUANTITY TAKEOFF Graduation Project 2019
ـــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــ
F10 1 1,5 1 1,5
1 1,8 1,8 0,5 1,62 0,15 0,15 107,2
6 6 80 6 80
F10 1 1,5 1 1,5
2 1,2 1,2 0,5 1,44 0,15 0,15 114,0
7 6 80 6 80
F10 1 1,5 1 1,5
1 0,9 0,9 0,5 0,41 0,15 0,15 37,6
9 6 80 6 80
F11 1 1,5 1 1,5
1 0,8 0,8 0,5 0,32 0,15 0,15 32,0
0 6 80 6 80
F11 1 1,5 1 1,5
6 1 1 0,5 3,00 0,15 0,15 262,0
1 6 80 6 80
F11 1 1,5 1 1,5
7 0,8 0,8 0,5 2,24 0,15 0,15 224,0
'1 6 80 6 80
F12 1 1,5 1 1,5
1 2,8 2,8 0,6 4,70 0,15 0,15 236,9
'3 6 80 6 80
F13 1 1,5 1 1,5
1 2,9 2,9 0,6 5,05 0,15 0,15 251,4
1 6 80 6 80
F13 1 2,0 1 2,0 5023,
5 4,5 4,5 0,6 60,75 0,1 0,1
2 8 00 8 00 5
F13 2 2,9 2 2,9
1 3,7 3,7 0,6 8,21 0,125 0,125 850,2
5 2 88 2 88
F14 1 1,5 1 1,5
2 1,5 1,5 0,5 2,25 0,15 0,15 160,4
0 6 80 6 80
557,8 3917
5 2,3
- 61 -
)Chapter (5 QUANTITY TAKEOFF Graduation Project 2019
ـــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــ
NO. NO.
BAR LENGT TOT A B C
T OF IN TOTA
TYPE MAR H AL (mm (mm (mm SHAPE & SIZE
)(mm MEM EAC L WT.
K )(mm Qty ) ) )
. H )(TON
140
01 2200 T 16 1 15 15 400 400 0,05
0
200
02 2800 T 16 1 11 11 400 400 0,05
0
100 200
04 3000 T 22 1 20 20 0,18
0 0
05 2200 T 08 1 4 4 500 500 100 0,00
06 1450 T 08 2 4 8 500 125 100 0,01
F125/C73
250
11 3300 T 16 2 21 42 400 400 0,22
0
250
12 3300 T 16 2 21 42 400 400 0,22
F39/C73
0
- 62 -
)Chapter (5 QUANTITY TAKEOFF Graduation Project 2019
ـــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــ
200
14 2200 T 16 2 16 32 200 0,11
0
15 2200 T 08 2 6 12 500 500 100 0,01
16 1700 T 08 4 6 24 500 250 100 0,02
17 1270 T 08 4 6 24 500 35 100 0,01
160
21 2400 T 16 1 21 21 400 400 0,08
0
250
22 3300 T 16 1 14 14 400 400 0,07
0
250
24 3000 T 22 1 20 20 500 0,18
F89/C73
0
- 63 -
)Chapter (5 QUANTITY TAKEOFF Graduation Project 2019
ـــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــ
25 2200 T 08 1 6 6 500 500 100 0,01
26 1450 T 08 2 6 12 500 125 100 0,01
160
31 2400 T 16 1 21 21 400 400 0,08
0
250
32 3300 T 16 1 14 14 400 400 0,07
0
228
34 3000 T 25 1 4 4 720 0,05
0
350
35 4000 T 08 1 16 16 500 0,03
0
36 2200 T 08 1 6 6 500 500 100 0,01
F89/C74
- 64 -
)Chapter (5 QUANTITY TAKEOFF Graduation Project 2019
ـــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــ
37 1450 T 08 2 6 12 500 125 100 0,01
TO
Bar T1
T8 T10 T12 T14 T18 T25 TA 1,50
Dia 6
L
- 65 -
)Chapter (5 QUANTITY TAKEOFF Graduation Project 2019
ــــــــــــــــــــــ
STARTER BARS ـــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــ
N
N Le
S o
o ng
ite Diame T STR.Le of
No of W/M th steel W/M dist, steel
ms ter R. ngth sti
ba ba
D rru
r r
ps
1,58 12,5
C1 86 16 16 2 4.348,84 8 0,395 7,92 0,15 4
0 2
2,00
C2 4 12 18 2 192,00 8 0,395 4,45 0,15 4 7,03
0
1,58 12,5
C7 16 16 16 2 809,09 8 0,395 7,93 0,15 4
0 3
C2 1,58
45 20 16 2 2.844,44 8 0,395 5,87 0,15 4 9,28
4 0
C2 2,00 16,1
2 18 18 2 144,00 8 0,395 10,2 0,15 4
6 0 2
C2 1,58
9 20 16 2 568,89 8 0,395 5,9 0,15 4 9,32
7 0
C2 1,58
8 20 16 2 505,68 8 0,395 5,9 0,15 4 9,32
8 0
C2 1,58
9 20 16 2 568,89 8 0,395 5,9 0,15 4 9,32
9 0
C3 2,00
12 14 18 2 672,00 8 0,395 4,5 0,15 4 7,11
0 0
C3 1,58
7 16 16 2 353,98 8 0,395 1,87 0,15 4 2,96
1 0
C5 1,58
1 10 16 2 31,60 8 0,395 1,15 0,15 4 1,82
6 0
C7 2,00 10,8
1 24 18 2 96,00 8 0,395 6,86 0,15 4
1 0 4
C7 1,58 12,5
7 16 16 2 353,98 8 0,395 7,92 0,15 4
2 0 2
C7 2,98
52 20 22 2 6.214,32 8 0,395 5,05 0,15 4 7,98
4 8
C7 2,98
1 20 22 2 119,51 8 0,395 5,51 0,15 4 8,71
5 8
- 66 -
)Chapter (5 QUANTITY TAKEOFF Graduation Project 2019
ـــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــ
C8 1,58 12,5
16 16 16 2 809,09 8 0,395 7,92 0,15 4
6 0 2
C8 2,98 19,1
4 32 22 2 764,84 8 0,395 12,1 0,15 4
7 8 2
C9 1,58
2 20 16 2 126,42 8 0,395 2,8 0,15 4 4,42
3 0
C
spe 2,00 16,0
1 24 18 2 96,00 8 0,395 10,15 0,15 4
cial 0 4
1
CP 1,58
6 8 16 2 151,70 8 0,395 0,95 0,15 4 1,50
L5 0
149,
18.632,30
89
CON
STEEL RATIO
C.
557,8 57954, 103,88
5 50 96
- 67 -
Chapter (5) QUANTITY TAKEOFF Graduation Project 2019
ـــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــ
Table.( 5.4 ): RFT of tie beams
BOTTOM STL
NO.b
tie axes NO. ott.R Lst.
F dia W/M bott bott.steel
t29 (Xa:Xf) 32 4 16 1,580 9 56,888889
(Xa:Xb),(
t29 9 4,85
Ya:Yi) 4 16 1,580 30,65679
(Xb:Xc),(Y
t29 8 8,2
a:Yh) 4 16 1,580 51,832099
(Xc:Xd),(Y
t29 9 9
a:Yi) 4 16 1,580 56,888889
(Xd:Xe),(
t29 9 8,2
Ya:Yi) 4 16 1,580 51,832099
(Xe:Xf),(Y
t29 1 5,75
e) 4 16 1,580 36,345679
(Xa:Xb),(
t29 1 4,95
Yb) 4 16 1,580 31,288889
t29 (Ya:Yb) 1 4 16 1,580 4,6 29,076543
(Xc:Xe),(Y
t22 3 9,2
a:Yb) 7 16 1,580 101,7679
(Xc:Xd),(Y
t13 2 9,6
a:Yb) 4 16 1,580 60,681481
(Xb),(Yh:
t7 1 9,6
Yi) 9 16 1,580 136,53333
(Xa),(Ya:
t7 1 9,2
Yb) 9 16 1,580 130,84444
(Xb:Xc),(Y
t7 1 8,2
i) 9 16 1,580 116,62222
t7 (Xe),(Yi) 1 4 16 1,580 5,75 36,345679
(Xa),(Ya:
t1 1 9,2
Yb) 8 16 1,580 116,30617
(Xa:Xb),(
t30 1 4,6
Ya:Yb) 4 18 2,000 36,8
- 68 -
)Chapter (5 QUANTITY TAKEOFF Graduation Project 2019
ـــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــ
(Xe),(Yh:
t14 1 9,6
)Yi 6 16 1,580 91,022222
TOP STL stirrups
W/ Lst.t top.stee W/ Lst str.ste
NO.top.RF dia M op l NO. dia M r. el
1, 0,
58 9 56,888 61 1,7 90,17
4 16 0 889 83 10 7 6 284
1, 0,
58 4,85 30,656 61 1,7 45,62
4 16 0 79 42 10 7 6 963
1, 0,
58 8,2 51,832 61 1,7 81,48
4 16 0 099 75 10 7 6 1481
1, 0,
58 9 56,888 61 1,7 90,17
4 16 0 889 83 10 7 6 284
1, 0,
58 8,2 51,832 61 1,7 81,48
4 16 0 099 75 10 7 6 1481
1, 0,
58 5,75 36,345 61 1,7 55,40
4 16 0 679 51 10 7 6 7407
1, 0,
58 4,95 31,288 61 1,7 46,71
4 16 0 889 43 10 7 6 6049
1, 0,
58 4,6 29,076 61 1,7 42,37
4 16 0 543 39 10 7 6 037
2, 0,
98 9,2 329,83 61 6,6 346,8
12 22 8 704 85 10 7 1 2099
2, 0,
2 18 00 9,6 89 10 61 3,7 203,2
0 38,4 7 716
1, 0,
8 16 58 9,6 121,36 89 10 61 3,7 203,2
0 296 7 716
- 69 -
)Chapter (5 QUANTITY TAKEOFF Graduation Project 2019
ـــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــ
1, 0,
8 16 58 9,2 116,30 85 10 61 3,7 194,1
0 617 7 358
1, 0,
8 16 58 8,2 103,66 75 10 61 3,7 171,2
0 42 7 963
1, 0,
8 16 58 5,75 72,691 51 10 61 3,7 116,4
0 358 7 8148
3, 0,
3,6
7 25 85 9,2 248,45 85 10 61 190,9
4
8 679 7 8765
2, 0,
4 18 00 4,6 39 10 61 1,7 40,92
0 36,8 7 5926
2, 0,
10 18 00 9,6 89 10 61 3,8 208,7
0 192 7 6543
SHRINKAGE BARS
di
NO. a W/M Lbar. shr.steel total
6526,4
0
0 0 0,000 0 198
962,48
0
0 0 0,000 0 889
1481,1
0
0 0 0,000 0 654
1835,5
0
0 0 0,000 0 556
1666,3
0
0 0 0,000 0 111
128,09
0
0 0 0,000 0 877
109,29
0
0 0 0,000 0 383
100,52
0
0 0 0,000 0 346
- 70 -
)Chapter (5 QUANTITY TAKEOFF Graduation Project 2019
ـــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــ
2433,4
9,2
4 12 0,889 32,711111 111
638,83
2 12 9,6
0,889 17,066667 951
478,23
2 12 9,6
0,889 17,066667 457
457,64
2 12 9,2
0,889 16,355556 198
406,16
2 12 8,2
0,889 14,577778 049
235,74
2 12 5,75
0,889 10,222222 074
588,46
4 12 9,2
0,889 32,711111 173
114,52
0 0 0
0,000 0 593
508,85
2 12 9,6
0,889 17,066667 432
Total
concrete=1
28.31
= Steel
12809,36
= Ratio 12809,
99.77 857
columns' necks
- 71 -
Chapter (5) QUANTITY TAKEOFF Graduation Project 2019
ـــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــ
C29 9 700 700 100 0,441
C30 12 600 400 100 0,288
C31 7 600 100 8,51
C56 1 400 100 0,54
C71 1 800 800 100 0,064
C72 7 600 600 100 0,252
C74 52 600 600 100 1,872
C75 1 700 700 100 0,049
C86 16 600 600 100 0,576
C87 4 900 900 100 0,324
C93 2 700 700 100 0,098
C special 1 1 100 4,95
CPL5 6 300 100 1,82
total 26,668
(volume)
no. area height
m³
excavation 1 10622 7 74354
columns' necks 26,668
PC for
1393,614
foundation
RC for
2381,41
foundation
Smells 349,26
backfilling 6471,048
- 72 -
)Chapter (5 QUANTITY TAKEOFF Graduation Project 2019
ـــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــ
- 73 -
Chapter (5) QUANTITY TAKEOFF Graduation Project 2019
ـــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــ
Table.( 5.6 ): concrete quantities for ground floor
ground
ground slab
columns
n len wid hei volume are volume
column no. depth
o. gth th ght (m³) a (m³)
8 164,08 Slab on 106 1699,5
C1 0,6 0,6 5,3 1 0,16
6 8 grade 22 2
C2 4 0,6 0,3 5,3 3,816
1
C7 0,6 0,6 5,3 30,528 1st floor slab
6
4 116,86 are volume
C24 0,7 0,7 5,3 slab no. depth
5 5 a (m³)
- 74 -
)Chapter (5 QUANTITY TAKEOFF Graduation Project 2019
ـــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــ
C
28,953
special 1 5,3 4,95 total
75
1
CPL5 6 0,3 5,3 1,82
tota 590,76 total 4118,2
l 4 slabs 4625
- 75 -
)Chapter (5 QUANTITY TAKEOFF Graduation Project 2019
ـــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــ
- 76 -
)Chapter (5 QUANTITY TAKEOFF Graduation Project 2019
ـــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــ
2,98
C75 1 20 22
0,7 0,7 5,8 2,842 8 7,5
1,58
C86 16 16 16
0,6 0,6 5,8 33,408 0 7,1
2,98
C87 4 32 22
0,9 0,9 5,8 18,792 8 7,5
1,58
C93 2 20 16
0,7 0,7 5,8 5,684 0 7,1
C special 2,00
1 4,95 24 18
1 0 0 5,8 0 7,2
1,58
CPL5 6 1,82 8 16
300 5,8 0 7,1
645,00
4
STIRRUPS
No of weight of
STR.d STR.Leng dist, )stirrup steel (kg
ia W/M th s
28.354,4
8 0,395 7,92 0,15 48 3
8 0,395 4,45 0,15 48 1.028,74
8 0,395 7,93 0,15 48 5.278,28
15.106,8
8 0,395 5,87 0,15 48 4
8 0,395 10,2 0,15 48 905,24
8 0,395 5,9 0,15 48 3.026,49
8 0,395 5,9 0,15 48 2.690,21
8 0,395 5,9 0,15 48 3.026,49
8 0,395 4,5 0,15 48 3.443,20
8 0,395 1,87 0,15 48 1.504,84
8 0,395 1,15 0,15 48 134,00
8 0,395 6,86 0,15 48 475,69
8 0,395 7,92 0,15 48 2.307,92
- 77 -
)Chapter (5 QUANTITY TAKEOFF Graduation Project 2019
ـــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــ
28.490,8
8 0,395 5,05 0,15 50 6
8 0,395 5,51 0,15 50 556,99
8 0,395 7,92 0,15 48 5.275,24
8 0,395 12,1 0,15 50 3.824,20
8 0,395 2,8 0,15 48 554,98
8 0,395 10,15 0,15 48 538,07
8 0,395 0,95 0,15 48 646,64
CON 107.169,
C. STEEL RATIO 36
645,0 107169,3 166,153
0 6 02
- 78 -
)Chapter (5 QUANTITY TAKEOFF Graduation Project 2019
ـــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــ
- 79 -
Chapter (5) QUANTITY TAKEOFF Graduation Project 2019
ـــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــ
Table.( 5.8 ): RFT of ground beams
BOTTOM STL
NO NO.bott.R di Lst.bot bott.stee
beam axes W/M
. F a t l
B8(300x80 (Xa),(Ya:Yb,Yd:Y 1,58 104,612
2 4 16 16,55
0) e) 0 3
B8(300x80 1,58
(Xa:Xb),(Yb:Yd) 2 4 16 15,8 99,8716
0) 0
B2(200x90 1,58 43,1407
(Xa:Xb),(Ya:Yb) 3 6 16 4,55
0) 0 4
B2(200x90 1,58 33,1851
(Xa:Xb),(Ya:Yb) 1 6 16 3,5
0) 0 9
top
steel
B8(300x80 0,00
on (Xa:Xb),(Yb:Yd) 2 0 0 0 0
0) 0
column
s
- 80 -
)Chapter (5 QUANTITY TAKEOFF Graduation Project 2019
ـــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــ
SHRINKAGE BARS
1547,524
- 81 -
Chapter (5) QUANTITY TAKEOFF Graduation Project 2019
ـــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــ
Table.( 5.9 ): RFT of ground slabs
ADDITIONAL
Bar total
Mark Dia W/M Spacing Distr. Lenth weight
1 12 0,8888888 0,25 19,8 4 109824
2 12 0,8888888 0,25 28,2 6 19251,2
3 16 1,5802469 0,25 3 2 37,92592
bottom
4 16 1,5802469 0,25 3 2 37,92592
5 16 1,5802469 0,25 3 2 37,92592
6 16 1,5802469 0,25 3 2 37,92592
top 7 16 1,5802469 0,125 210 3 7964,444
137.191,3
CHAIR
slab Dia W/M area Lenth total weight
S400 10 0,6172 2485,2 1,1 1687,481
volume
slab no. area depth
(m³) TOTAL
S400 1 2485,2 0,4 994,08 CONC. STEEL RATIO
994,08 237.093,9 238,5058
- 82 -
)Chapter (5 QUANTITY TAKEOFF Graduation Project 2019
ـــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــ
- 83 -
)Chapter (5 QUANTITY TAKEOFF Graduation Project 2019
ـــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــ
- 84 -
Chapter (5) QUANTITY TAKEOFF Graduation Project 2019
ـــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــ
5.2.Revit quantity takeoff
we have made a revit 3D model shown in (fig.21) to calculate the quantities of
material of the building to check the manual Quantity takeoff made and the results
were as below shown in the tables
- 85 -
Chapter (5) QUANTITY TAKEOFF Graduation Project 2019
ـــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــ
Table.( 5.10 ): Revit foundation schedule
- 86 -
)Chapter (5 QUANTITY TAKEOFF Graduation Project 2019
ـــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــ
F3 2 24 m² 10.05 m³
- 87 -
)Chapter (5 QUANTITY TAKEOFF Graduation Project 2019
ـــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــ
- 88 -
)Chapter (5 QUANTITY TAKEOFF Graduation Project 2019
ـــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــ
F60 2 13 m² 5.27 m³
- 89 -
)Chapter (5 QUANTITY TAKEOFF Graduation Project 2019
ـــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــ
- 90 -
)Chapter (5 QUANTITY TAKEOFF Graduation Project 2019
ـــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــ
F 38 1 18 m² 6.91 m³
- 91 -
)Chapter (5 QUANTITY TAKEOFF Graduation Project 2019
ـــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــ
- 92 -
)Chapter (5 QUANTITY TAKEOFF Graduation Project 2019
ـــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــ
F 64 6 169 m² 72.04 m³
- 93 -
)Chapter (5 QUANTITY TAKEOFF Graduation Project 2019
ـــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــ
- 94 -
)Chapter (5 QUANTITY TAKEOFF Graduation Project 2019
ـــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــ
F 134 16 78 m² 28.34 m³
- 95 -
)Chapter (5 QUANTITY TAKEOFF Graduation Project 2019
ـــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــ
- 96 -
Chapter (5) QUANTITY TAKEOFF Graduation Project 2019
ـــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــ
Structural
Column
Schedule
Total Total
Type
Type Count Volume Count Volume
- 97 -
)Chapter (5 QUANTITY TAKEOFF Graduation Project 2019
ـــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــ
'C63
C4 BASE,GR,FIRST
'C63 37.30
C4 4 13.50 m³ BASE,GR,FIRST 4 m³
C64
C5 BASE,GR,FIRST
C64 17.66
C5 8 40.15 m³ BASE,GR,FIRST 2 m³
C65
c5 250 x 700 BASE,GR,FIRST
C65 18.03
c5 250 x 700 8 58.22 m³ BASE,GR,FIRST 2 m³
*C5 C66
*C5 10 54.65 m³ C66 1 8.97 m³
C7 C69
352.58 263.06
C69
C7 67 m³ 32 m³
C8 C70
73.45
C70
C8 14 69.11 m³ 8 m³
C9 'C70
12.47
'C70
C9 5 24.32 m³ 3 m³
C10 C71
10.54
C71
C10 2 17.19 m³ 2 m³
C21 C72
173.27
C72
C21 21 12.82 m³ 86 m³
C22 C73
59.15
C73
C22 12 59.11 m³ 29 m³
C23 C74
97.67
C74
C23 8 75.31 m³ 54 m³
- 98 -
)Chapter (5 QUANTITY TAKEOFF Graduation Project 2019
ـــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــ
C24 C75
1161.52
C75
C24 128 m³ 2 5.92 m³
C76
C26 BASE,GROUND
C76
C26 2 15.81 m³ BASE,GROUND 1 9.14 m³
C27
C83
GROUND,SEC
C27
C83
GROUND,SEC 9 49.29 m³ 2 8.46 m³
C28 C86
369.18 47.64
C86
C28 51 m³ 17 m³
C29 C87
149.90 17.79
C87
C29 31 m³ 4 m³
C30 'C90
29.98
'C90
C30 14 31.36 m³ 6 m³
C31 C92
C31 7 22.96 m³ C92 10 7.57 m³
C93
C32 BASE,GROUND
C93 14.15
C32 6 23.44 m³ BASE,GROUND 2 m³
C96
C39 BASE,GROUND
C96
C39 6 56.89 m³ BASE,GROUND 1 3.23 m³
C40 C100
20.90
C100
C40 4 38.51 m³ 9 m³
C41 C special 1
- 99 -
)Chapter (5 QUANTITY TAKEOFF Graduation Project 2019
ـــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــ
16.58
C special 1
C41 9 76.78 m³ 1 m³
C41 2 CF
164.01
CF
C41 2 1 1.83 m³ 10 m³
C42 CPL5
C42 1 9.53 m³ CPL5 6 1.70 m³
C43 special1 rvt
191.97
special1 rvt
C43 2 8.99 m³ 18 m³
C44
special1 rvt 2
GROUND,FIRST
C44 18.47
special1 rvt 2
GROUND,FIRST 9 85.34 m³ 6 m³
Structural Framing
Schedule
- 101 -
)Chapter (5 QUANTITY TAKEOFF Graduation Project 2019
ـــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــ
Wall Schedule
Type Count Area Volume
Floor Schedule
Type Count Area Volume
- 106 -
)Chapter (5 QUANTITY TAKEOFF Graduation Project 2019
ـــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــ
Generic 300mm 1 824 m² 247.09 m³
03- Ground floor 235.3
100 2 356 m² 35.64 m³
150 7 410 m² 61.57 m³
150 stairs 81 46 m² 6.93 m³
160 mm 3 1039 m² 166.22 m³
250 1 1096 m² 274.08 m³
250 MM 12 90 m² 22.50 m³
300 5 1956 m² 586.80 m³
400 17 12669 m² 5067.72 m³
500 60 518 m² 259.15 m³
550 59 581 m² 319.58 m³
600 1 16 m² 9.60 m³
Generic 300mm 2 3781 m² 1134.28 m³
04- First 240.7
140 mm 1 7 m² 1.00 m³
150 1 26 m² 3.85 m³
150 stairs 81 46 m² 6.93 m³
160 mm 6 1167 m² 186.72 m³
200 mm 7 1216 m² 243.21 m³
250 1 1096 m² 274.08 m³
250 MM 13 159 m² 39.68 m³
300 5 1885 m² 565.41 m³
300 mm 5 8341 m² 2502.24 m³
500 61 527 m² 263.65 m³
600 1 16 m² 9.60 m³
drop 500 51 443 m² 221.41 m³
Generic 300mm 2 4598 m² 1379.38 m³
05- Second 244.8
- 109 -
)Chapter (5 QUANTITY TAKEOFF Graduation Project 2019
ـــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــ
F111 6 1,25 0,50 7,49 3,00
' F111 7 1,18 0,32 8,23 2,24
' F123 1 3,978 4,704 3,978 4,704
F131 1 4,305 5,046 4,305 5,046
F132 5 7,803 12,15 39,015 60,75
F135 1 5,676 8,214 5,676 8,214
F140 2 2,268 1,125 4,536 2,25
RAFT 300 1 878,43 878,43
slab 500 8 6,265 50,12
slab 600 6 132,2033 793,22
slab 800 1 945,31 945,31
Grand Totals 1394 2347
- 111 -
Chapter (6) ACTIVITIES & RELATIONS Graduation Project 2019
ـــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــ
6.1 List of activities
Table.( 6.1 ): List of activities for building A2
Activity
Key Dates
start of work
finish of concrete work
finish of work
PROJECT SKELTON
Engineering
shopdrawings submitals
shopdrawings approvals
Side Support System
excavate 2 m
soil investgation
site clearance
excavation for anchors level
excavation for buiding A
backfilling for building A (1st layer)
backfilling for building A (2nd layer)
backfilling for building A (3rd layer)
backfilling for building A (4th layer)
soil replacement (1st layer)
soil replacement (2nd layer)
soil replacement (3rd layer)
- 112 -
Chapter (6) ACTIVITIES & RELATIONS Graduation Project 2019
ـــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــ
soil replacement (4th layer)
piles work
piles excution
caping beams
anchors work
procurement
formwork procurement
steel bars procurement
bricks procurement
concrete procurement
substructure
formwork shuttering for PC footings
concrete pouring for RC footings
deshuttering of PC footings
formwork shuttering for RC footings & smells
steel fixing for RC footings & smells
Pouring for RC footings & smells
deshuttering for RC footings & smells
isolation for RC footings & smells
PC for SOG
formwork shuttering for SOG
steel fixing for SOG
pouring for SOG
deshuttering for SOG
isolation for SOG
superstructure(ground floor)
column formwork (3 faces)
column steel fixing
isolation for columns under ground
- 113 -
Chapter (6) ACTIVITIES & RELATIONS Graduation Project 2019
ـــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــ
column formwork (4 faces)
columns pouring
deshuttering of columns formwork
slabs & beams formwork
slabs & beams steel fixing
slabs & beams pouring
slabs & beams deshuttering
isolation of bathrooms
superstructure(roof)
slab roof excution
isolation of roof slab
sloping of roof slab
stairs & elevators covering
finishing
internal brickwork
external brickwork
isolation of brickwork
internal plastering
fallcieling
حلوق اﻻبواب و الشبابيك
windows & doors fixing
external gate
handrill of stairs
MEP
preliminary elictrical work for slab
elictrical panels fixing
preliminary plumbing works
plumbing works fixing
mechanical works
- 114 -
Chapter (6) ACTIVITIES & RELATIONS Graduation Project 2019
ـــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــ
6.2 Calendar
The Project Calendar is based on a six working days per week, with Friday’s
as a national weekend and National Holidays Off as shown below. The work
day is Eight Hours.
January 25
- 115 -
Chapter (6) ACTIVITIES & RELATIONS Graduation Project 2019
ـــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــ
6.2.2 Movable holidays
The following holidays are public holidays but the date on which each occurs
varies, according to its corresponding Coptic or Islamic calendar, and thus
has no set date. In order in which they occur:
Name Description
Islamic New Year The new year based on the lunar islamic
calendar
- 116 -
City Gate Mall Classic Schedule Layout 10-Jun-19 19:36
Activity ID Activity Name Original Start Finish 2018 2019 2020 2021
Duration
D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J
City Gate Mall 940d 01-Jan-18 31-Dec-20
Actual Level of Effort Remaining Work Page 1 of 12 TASK filter: All Activities
Actual Work Critical Remaining Work © Oracle Corporation
Activity ID Activity Name Original Start Finish 2018 2019 2020 2021
Duration
D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J
Finishing 97d 27-Oct-18 16-Feb-19 16-Feb-19, Finishing
MEP 154d 26-Nov-18 23-May-19 23-May-19, MEP
roof 219d 13-Sep-18 26-May-19 26-May-19, roof
A3 325d 15-Mar-18 28-Mar-19 28-Mar-19, A3
Foundation 140d 15-Mar-18 25-Aug-18 25-Aug-18, Foundation
PC 8d 15-Mar-18 24-Mar-18 24-Mar-18, PC
RC 70d 21-Mar-18 10-Jun-18 10-Jun-18, RC
masonary, water proofing & SOG 65d 11-Jun-18 25-Aug-18 25-Aug-18, masonary, water proofing & SOG
Ground floor 193d 31-Mar-18 10-Nov-18 10-Nov-18, Ground floor
Civil Works 141d 31-Mar-18 11-Sep-18 11-Sep-18, Civil Works
Columns 29d 31-Mar-18 02-May-18 02-May-18, Columns
Slabs and Beams 112d 03-May-18 11-Sep-18 11-Sep-18, Slabs and Beams
Finishing 66d 26-Aug-18 10-Nov-18 10-Nov-18, Finishing
MEP 60d 30-Aug-18 07-Nov-18 07-Nov-18, MEP
1st floor 195d 04-Jun-18 16-Jan-19 16-Jan-19, 1st floor
Civil Works 100d 04-Jun-18 27-Sep-18 27-Sep-18, Civil Works
Columns 28d 04-Jun-18 05-Jul-18 05-Jul-18, Columns
Slabs and Beams 72d 07-Jul-18 27-Sep-18 27-Sep-18, Slabs and Beams
Finishing 90d 11-Sep-18 24-Dec-18 24-Dec-18, Finishing
MEP 80d 16-Oct-18 16-Jan-19 16-Jan-19, MEP
2nd floor 227d 07-Jul-18 27-Mar-19 27-Mar-19, 2nd floor
Civil Works 82d 07-Jul-18 09-Oct-18 09-Oct-18, Civil Works
Finishing 112d 27-Sep-18 04-Feb-19 04-Feb-19, Finishing
MEP 110d 20-Nov-18 27-Mar-19 27-Mar-19, MEP
roof 207d 31-Jul-18 28-Mar-19 28-Mar-19, roof
A5 355d 25-Mar-18 12-May-19 12-May-19, A5
Foundation 151d 25-Mar-18 16-Sep-18 16-Sep-18, Foundation
PC 9d 25-Mar-18 03-Apr-18 03-Apr-18, PC
RC 83d 01-Apr-18 05-Jul-18 05-Jul-18, RC
masonary, water proofing & SOG 62d 07-Jul-18 16-Sep-18 16-Sep-18, masonary, water proofing & SOG
Ground floor 220d 10-Apr-18 22-Dec-18 22-Dec-18, Ground floor
Civil Works 151d 10-Apr-18 03-Oct-18 03-Oct-18, Civil Works
Columns 42d 10-Apr-18 28-May-18 28-May-18, Columns
Slabs and Beams 109d 29-May-18 03-Oct-18 03-Oct-18, Slabs and Beams
Finishing 61d 17-Sep-18 26-Nov-18 26-Nov-18, Finishing
MEP 69d 03-Oct-18 22-Dec-18 22-Dec-18, MEP
1st floor 213d 27-Jun-18 02-Mar-19 02-Mar-19, 1st floor
Civil Works 97d 27-Jun-18 17-Oct-18 17-Oct-18, Civil Works
Columns 36d 27-Jun-18 07-Aug-18 07-Aug-18, Columns
Slabs and Beams 61d 08-Aug-18 17-Oct-18 17-Oct-18, Slabs and Beams
Finishing 83d 03-Oct-18 07-Jan-19 07-Jan-19, Finishing
MEP 99d 07-Nov-18 02-Mar-19 02-Mar-19, MEP
2nd floor 237d 08-Aug-18 11-May-19 11-May-19, 2nd floor
Activity ID Activity Name Original Start Finish 2018 2019 2020 2021
Duration
D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J
Civil Works 70d 08-Aug-18 28-Oct-18 28-Oct-18, Civil Works
Columns 32d 08-Aug-18 13-Sep-18 13-Sep-18, Columns
Slabs and Beams 38d 15-Sep-18 28-Oct-18 28-Oct-18, Slabs and Beams
Finishing 114d 17-Oct-18 26-Feb-19 26-Feb-19, Finishing
MEP 129d 12-Dec-18 11-May-19 11-May-19, MEP
roof 206d 15-Sep-18 12-May-19 12-May-19, roof
A6 369d 04-Apr-18 08-Jun-19 08-Jun-19, A6
Foundation 154d 04-Apr-18 30-Sep-18 30-Sep-18, Foundation
PC 7d 04-Apr-18 11-Apr-18 11-Apr-18, PC
RC 84d 10-Apr-18 16-Jul-18 16-Jul-18, RC
masonary, water proofing & SOG 65d 17-Jul-18 30-Sep-18 30-Sep-18, masonary, water proofing & SOG
Ground floor 234d 19-Apr-18 16-Jan-19 16-Jan-19, Ground floor
Civil Works 155d 19-Apr-18 17-Oct-18 17-Oct-18, Civil Works
Columns 35d 19-Apr-18 29-May-18 29-May-18, Columns
Slabs and Beams 120d 30-May-18 17-Oct-18 17-Oct-18, Slabs and Beams
Finishing 63d 01-Oct-18 12-Dec-18 12-Dec-18, Finishing
MEP 79d 17-Oct-18 16-Jan-19 16-Jan-19, MEP
1st floor 224d 10-Jul-18 27-Mar-19 27-Mar-19, 1st floor
Civil Works 100d 10-Jul-18 03-Nov-18 03-Nov-18, Civil Works
Columns 39d 10-Jul-18 23-Aug-18 23-Aug-18, Columns
Slabs and Beams 61d 25-Aug-18 03-Nov-18 03-Nov-18, Slabs and Beams
Finishing 82d 17-Oct-18 20-Jan-19 20-Jan-19, Finishing
MEP 109d 21-Nov-18 27-Mar-19 27-Mar-19, MEP
2nd floor 245d 25-Aug-18 05-Jun-19 05-Jun-19, 2nd floor
- 129 -
Chapter (7) COST,TIME&RESOURCES MANAGEMENT Graduation Project 2019
ـــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــ
price
ManPower General
Material Financial
overheads
In this project a data basebase of labors, materials and equipment is used as follow:
- 130 -
Chapter (7) COST,TIME&RESOURCES MANAGEMENT Graduation Project 2019
ـــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــ
Equipment
Code name cost/day cost/day2
basic gross
LABOR table
Code name cost/day cost/day-
basic gross
L1 excavating labor 200 220
L2 surveyor 250 275
L3 labor 150 165
L4 rock breaker 150 165
- 131 -
Chapter (7) COST,TIME&RESOURCES MANAGEMENT Graduation Project 2019
ـــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــ
MATERIAL table
Code name unit cost/unit cost/unit-
basic gross
The labors and materials forms the following crews list used in
estimatimg the time and cost of the project
Crews table
crew
production
labor Equipment cost/
rate
Code name day
cod cost/da cod no cost/ unit/d
no. rate
e y e . day ay
- 132 -
Chapter (7) COST,TIME&RESOURCES MANAGEMENT Graduation Project 2019
ـــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــ
soil L3 5 825 E1 1 1100 450
replacement
C3 and m3 2035
compacting L6 1 110
crew
0,
p.c formwork L9 1 192,5 E8 1100
5
C4 for foundation 100 m2 1650
L10 2 220
crew
L2 0,5 137,5
R.c formwork 0,
L9 1 192,5 E8 1100 1402
C5 for footings 5 3 m3
,5
crew L10 1 110
Concrete
C6 L3 20 3300 200 m3 3300
pouring crew
footings & L11 1 220
C7 smells Steel 3 m3 440
works L12 2 220
L9 1 192,5
columns L10 1 110
C8 1,2 m3 605
formworks L3 1 165
L2 0,5 137,5
columns steel L11 1 220
C9 0,15 ton 385
works L3 1 165
L9 1 192,5
floors & L10 1 110 522,
C10 beams 7,5 m2
L3 0,5 82,5 5
formwork
L2 0,5 137,5
floors & L11 1 220
C11 beams steel 0,4 ton 440
works L12 2 220
L9 1 192,5
RC walls 467,
C12 L10 1 110 9 m2
formwork 5
L3 1 165
RC walls L11 1 220
C13 2,25 m3 440
steel works L12 2 220
foundation
C14 L13 2 330 75 m2 330
isolation
floors
C15 moisture L14 4 880 E7 2 2000 200 m2 2880
isolation
L8 1 110 E7 4 4000
temprature L16 1 165
C16 isolation for 100 m2 4110
floors L3 2 330
L18 5 1100
C17 L19 1 165 4 m3
- 133 -
)Chapter (7 COST,TIME&RESOURCES MANAGEMENT Graduation Project 2019
ـــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــ
masonry L20 2 165
412,
works
L21 1 82,5 5
)(25*12*6
internal L22 2 440
plastering L21 2 165
C18 140 m2 440
طرطشة و بؤج و (
)أوتار L3 1 165
external L22 2 440
plastering L21 2 165
C19 105 m2 770
طرطشة و بؤج و (
)أوتار L3 1 165
walls L22 1 220
467,
C20 roughing L21 1 82,5 37 m2
5
plastering L3 1 165
floors L22 1 220
467,
C21 roughing L21 1 82,5 30 m2
5
plastering L3 1 165
L22 1 220
L21 1 82,5
C22 البطانة 20 m2 825
L3 2 330
L9 1 192,5
L22 1 220
632,
C23 الضهارة L21 1 82,5 32 m2
5
L3 2 330
L11 1 220
L3 2 330 756,
C24 حدادة الشبك الممدد 5 m2
L7 0,5 110 25
L9 0,5 96,25
L22 1 220
C25 بياض الشبك الممدد 10 m2 220
L3 2 330
تركيب مواسير L23 1 550
C26 0,5 حمام 880
داخلية L3 2 330
تركيب اﻷجهزة L23 1 550
C27 0,5 حمام 880
الصحية L3 2 330
L23 1 550
سباكة خارجية مد و 1512
C28 L3 5 825 15 'm
تركيب خطوط ,5
L2 0,5 137,5
L24 8 2200
C29 piles 5 piles 6655
L3 27 4455
The cost and time estimation is calculated using the following Excel
sheet and here is a sample of activities calculated
quantity crew
Activity ID Activity Name cost/ production
unit quantity code no day rate
CGM(Project)-2.2.3 Zone A
CGM(Project)-2.2.3.3 A2
CGM(Project)-2.2.3.3.5
Foundation
CGM(Project)-2.2.3.3.5.1 PC
formwork shuttering
m2 1827 C4 5 8250 500
CGM2260 for pc footings
concrete pouring for
m3 548,1 C6 2 6600 400
CGM2270 pc footings
deshuttering of pc
m2 1827 C4 5 8250 500
CGM2280 footings
CGM(Project)-2.2.3.3.5.2 RC
formwork shuttering
for RC footings & m3 100,914 C5 5 7012,5 15
CGM2290
smells
steel fixing for RC
m3 100,914 C7 5 2200 15
CGM2300 footings & smells
pouring for RC &
m3 100,914 C6 1 3300 200
CGM2310 smells
deshuttering of RC
m3 100,914 C5 5 7012,5 15
CGM2320 footings & smells
isolation of RC
m2 2627,4 C14 5 1650 375
CGM2330 footings & smells
CGM(Project)-2.2.3.3.5.3
masonary, water proofing & SOG
masonary work m3 24 C17 1 412,5 4
CGM2336
backfilling m3 1000 C2 1 2310 200
CGM2339
Pc for SOG m3 2000 C6 1 3300 200
CGM2340
formwork shuttering
m2 30 C10 1 522,5 7,5
CGM2350 for SOG
steel fixing of SOG ton 2,5 C11 1 440 0,4
CGM2360
pouring of SOG m3 600 C6 1 3300 200
CGM2370
deshuttering of SOG m2 30 C10 1 522,5 7,5
CGM2380
isolation works for
m2 400 C15 1 2880 200
CGM2390 SOG
- 135 -
Chapter (7) COST,TIME&RESOURCES MANAGEMENT Graduation Project 2019
ـــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــ
CGM(Project)-2.2.3.3.3
Ground floor
CGM(Project)-2.2.3.3.3.1
Civil Works
CGM(Project)-2.2.3.3.3.1.1
Columns
Coloumn Formwork
m3 54,5238 C8 3 1815 3,6
CGM3480 (3 faces) for ground
Coloumn steel fixig
ton 15,26 C9 10 3850 1,5
CGM3490 for ground
Coloumn Formwork
m3 4,54365 C8 3 1815 3,6
CGM3510 (4 faces) for ground
columns pouring for
m3 90,7695 C6 2 6600 400
CGM3520 ground
desuttering of column
m3 90,7695 C8 4 2420 4,8
CGM3530 formwork for ground
CGM(Project)-2.2.3.3.3.1.3
Slabs and Beams
Slabs and Beams
m2 1354,4 C10 5 2612,5 37,5
CGM3600 Formwork for ground
Slabs and Beams
ton 54,2233 C11 12 5280 4,8
CGM3610 steel fixing for ground
Slaps and Beams
m3 402,224 C6 2 6600 400
CGM3620 Pouing for ground
slabs formwork
deshuttering for m2 402,224 C10 3 1567,5 22,5
CGM3630
ground
isolation of bathrooms
bulk 1
CGM3640 for ground
CGM(Project)-2.2.3.3.3.2
Finishing
internal brickwork for
m3 19,0697 C17 3 1237,5 12
CGM3790 ground
external brickwork for
m3 6,35656 C17 3 1237,5 12
CGM3800 ground
internal plastering for
m2 1764,05 C18 3 1320 420
CGM3820 ground
fallceiling for ground bulk 1
CGM3830
for ground حلوق ابواب و
bulk 1
CGM3840 شبابيك
windows & doors
bulk 1
CGM3850 fixing for ground
handrill of stairs for
bulk 1
CGM3870 ground
- 136 -
)Chapter (7 COST,TIME&RESOURCES MANAGEMENT Graduation Project 2019
ـــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــ
material Duratio
cost/un cod cost/un cost/un n Cost
code Q/m no code no
it e it it
4 33000
M2 1 750 2 424275
4 33000
7 49087,5
172826,1
M5 0,13 1560 7
5
M3 1 65 1 9859,423
7 49087,5
M12 1 20 M13 1 49 8 194490,6
12 8250
M5 0,13 1560 11 225470
2 3630
M1 1 900 1 88292,55
5 12100
12 31350
147948,2
M5 0,13 1560 12
8
375201,3
M1 1 900 2
9
4 6270
4 80000
- Man Power:
- Equipment:
- 139 -
Chapter (7) COST,TIME&RESOURCES MANAGEMENT Graduation Project 2019
ـــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــ
- Equipment total cost = Excavator total cost+ Dump Truck total cost+ Bulldozer
Total Cost+ Roller total cost = 8418750+5994150+4445100+1448025=
20,306,025 EGP
Excavation total cost = man power total cost + equipment total cost = 1070350
+20306025 = 21,376,375 EGP
- 140 -
Chapter (7) COST,TIME&RESOURCES MANAGEMENT Graduation Project 2019
ـــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــ
Without proper resource management, projects can fall behind schedule, or can
become unprofitable. The objective is to ensure the adequate and timely supply of
resources, whilst at the same time maximising the utilisation of resources between
projects.
- 141 -
Chapter (7) COST,TIME&RESOURCES MANAGEMENT Graduation Project 2019
ـــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــ
7.3.3 Resources management plan:
A resource management plan can be used to:
• Type of activity.
• Start date and duration of the activity.
• Activity owner.
• Resource type and quantity required.
• Source/supplier of each resource type.
• Equipment required.
• Cost estimates for each of the resources to be supplied.
• Risk mitigation.
• Access to the up-to-date project plan with clear definition of the different
phases of work and activity scheduling.
• Understanding the types of resources that are needed.
• Understanding the availability and optimum utilisation of resources.
• Understanding the potential for developing resources for new uses.
• Understanding of the lead time required to ensure that resources are available
when needed.
• The ability to redeploy resources if works need to be accelerated, or if works
are completed.
- 142 -
Chapter (7) COST,TIME&RESOURCES MANAGEMENT Graduation Project 2019
ـــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــ
7.3.4 Resource management plan steps
First, identify the different types of resources needed to complete the project.
You then need to quantify the amount of each type of resource required. And finally,
you need to schedule the consumption of each resource within the project. Let’s
describe each step in a little more detail.
You should start by listing the resources required to complete the project.
Labor. Identify all the roles involved in performing the project, including all full-
time, part-time and contracting roles.
More…
As much as possible, also indicate the date the resources are needed and the
consumption rate per day, week or month.
You have now collated all the information required to build a detailed Resource
Schedule. Create a resource schedule which specifies the:
basic gross
- 144 -
Chapter (7) COST,TIME&RESOURCES MANAGEMENT Graduation Project 2019
ـــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــ
• Crews working in the project and their productivity / day.
Crews table
crew
production
labor Equipment cost/da
rate
Code name y
cod cost/ unit/da
no. cost/day code no. rate
e day y
mechanical L1 1 220 E1 2 2200
excavation + L2 0,5 137,5 E3 1 1650
C1 150 m3 5307,5
waste
transportation E8 0,5 1100
mechanical L6 1 110 E1 1 1100
C2 200 m3 2310
backfilling E2 1 1100
soil L3 5 825 E1 1 1100 450
replacement
C3 and m3 2035
compacting L6 1 110
crew
p.c formwork L9 1 192,5 E8 0,5 1100
C4 for foundation L10 2 220 100 m2 1650
crew L2 0,5 137,5
R.c formwork L9 1 192,5 E8 0,5 1100
C5 for footings 3 m3 1402,5
crew L10 1 110
Concrete
C6 L3 20 3300 200 m3 3300
pouring crew
footings & L11 1 220
C7 smells Steel 3 m3 440
works L12 2 220
L9 1 192,5
columns L10 1 110
C8 1,2 m3 605
formworks L3 1 165
L2 0,5 137,5
columns steel L11 1 220
C9 0,15 ton 385
works L3 1 165
L9 1 192,5
floors & beams L10 1 110
C10 7,5 m2 522,5
formwork L3 0,5 82,5
L2 0,5 137,5
floors & beams L11 1 220
C11 0,4 ton 440
steel works L12 2 220
L9 1 192,5
RC walls
C12 L10 1 110 9 m2 467,5
formwork
L3 1 165
- 145 -
)Chapter (7 COST,TIME&RESOURCES MANAGEMENT Graduation Project 2019
ـــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــ
Carpenter
- 147 -
)Chapter (7 COST,TIME&RESOURCES MANAGEMENT Graduation Project 2019
ـــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــ
Labor
- 151 -
Chapter (8) RISK MANAGEMENT Graduation Project 2019
ـــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــ
8.1 Introduction
Risk is the probability of occurrence of a defined hazard and the magnitude of the
consequences or an uncertain event or condition that results from the work, having
an impact that contradicts expectations.
*Risk source: things that can cause variation from what is planned or expected.
- 152 -
Chapter (8) RISK MANAGEMENT Graduation Project 2019
ـــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــ
- 153 -
Chapter (8) RISK MANAGEMENT Graduation Project 2019
ـــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــ
8.3.2 Risk Management Process:
- 154 -
Chapter (8) RISK MANAGEMENT Graduation Project 2019
ـــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــ
• Risk Monitoring and Control : The process of monitoring the implementation of
agreed-upon risk response plans, tracking identified risks, identifying and
analyzing new risks, and evaluating risk process effectiveness throughout the
project
8.3.3 Risk Management Planning:
- Deciding how to approach, plan and execute the risk management
activities for the project.
Methodology: Defines the approaches, tools, and data sources that may be used to
perform risk management on the project.
- 155 -
Chapter (8) RISK MANAGEMENT Graduation Project 2019
ـــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــ
Roles and responsibilities: Defines the lead, support, and risk management team
members for each type of activity in the risk management plan, and clarifies their
responsibilities.
Budgeting: Assigns resources, estimates funds needed for risk management for
inclusion in the cost performance baseline, and establishes protocols for application
of contingency reserve.
Timing: Defines when and how often the risk management process will be
performed throughout the project life cycle, establishes protocols for application of
schedule contingency reserves, and establishes risk management activities to be
included in the project schedule.
Definition of risk probability and impact: The likelihood that events will occur, it can
be assigned using a simple High-medium-low scale that ranks the probability for each
risk.
Probability and impact matrix: Each identified risk is fed into a probability-impact
matrix, as seen in The figure. The matrix maps out the risk, its probability and
possible impact. The risks with higher probability and impact are a more serious
Threat to the project objectives than the risks with lower impact and Consequences.
The risks that are threats to the project require
Quantitative analysis to determine the root of the risks, the methods to
Control the risks, and effective risk management.
- 156 -
Chapter (8) RISK MANAGEMENT Graduation Project 2019
ـــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــ
Consequences
Almost
0.9 Medium Medium High High Extreme
certain
- 157 -
Chapter (8) RISK MANAGEMENT Graduation Project 2019
ـــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــ
Reporting format:
A Risk Form is a document which is completed by a member of a project to raise
with management a new project risk. Risk Forms may be used to formally log any
type of risk; however, the most frequent
• Design change.
• Wages problem.
• permits delays.
• Equipment breakdown.
• Scope change.
Brainstorming:
This is probably the most often used technique of the risk identification process.
You have probably used this many time for many purposes. Brainstorming involves
getting subject matter experts, team members, risk management team and anyone
else who might benefit the process in a room and asking them to start identifying
possible risk events. The trick here is that one person’s idea might spawn another idea
and so on, so that by end of the session you would have identified all the possible
risks. The facilitator could start the group off by going through the categories of risks
to get everyone thinking in the right direction.
- 159 -
Chapter (8) RISK MANAGEMENT Graduation Project 2019
ـــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــ
Documents reviews:
SWOT
• CHECKLIST ANALYSIS:
Checklists used during the Risk identification processes are usually developed based
on historical information and previous project experience. If you typically work on
projects that are similar in nature, begin to compile a list of risks. You can't hen convert
this to a checklist that will allow you to identify risks on future projects quickly and
easily. You can also use the lowest level of the RBS as a checklist. However, don’t
rely solely on checklists for Risk Identification because you might miss important risks.
It isn’t possible for a single checklist to be an exhaustive source or all projects. You
can improve your checklists at the end of the project by adding the new risks that were
identified or modifying old ones if need be.
- 160 -
)Chapter (8 RISK MANAGEMENT Graduation Project 2019
ـــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــ
The important thing to note about the project assumptions is that all assumptions are
tested against two factors:
All assumptions that turn out to be false should be evaluated and scored just as risks.
This method shows relationship between effects of problems and their causes.
This diagram depicts ever potential cause and sub cause of the problem and the
effect that each proposed solution will have on the problem. The diagram is also
called fishbone diagram or Ishikawa diagram after its developer Kaoru Ishikawa.
- 162 -
Chapter (8) RISK MANAGEMENT Graduation Project 2019
ـــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــ
Process flowcharts
This method shows logical steps needed to accomplish an objective how the elements
of a system relate to each other, and what actions cause what responses. This
flowchart it’s probably the one you are most familiar with. It’s usually constructed with
rectangles and parallelograms that step through a logical sequence and follow for
“Yes” and “No” branches.
Influence Diagrams
- 163 -
Chapter (8) RISK MANAGEMENT Graduation Project 2019
ـــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــ
8.4.2 Risk Register
Risk Activities
Risk triggers
ID Risk Statement Cause Impact
Quick Soil
change in replacement
prices Concrete
pumping
Plastering
Increase in availability of MEP
R1 materials price materials cost increase
Cancel MEP
government
Increase in the fuel support
R2 rate exchange rate cost increase
Protests & All activities
R3 Revolution political issues delay strikes
Traffic Jam and procurement
R4 problems traffic problems delay
Over Execution of
increase in activities
labors &
delay & cost equipment
R5 Accident in site poor site layout increase in site
shortage of skilled delay & cost All activities
R6 subcontractor low profit increase
Subcontractor All activities
failing to deliver task delay & cost
R7 on time financial problems increase
Conflict between Conflict procurement
designed and
R8 suppliers inaccurate design delay
Delay in material problems with procurement
R9 delivery suppliers delay
Theft of the Execution of
R10 materials poor security cost increase activities
Delay in Execution of
Drop of labor delay &poor labors activities
R11 productivity poor HSE quality tasks
labor wages Increasing Execution of
R12 increase inflation cost increase in prices activities
import/export governmental delay & cost MEP
R13 restriction routine increase
unexpected or Soil work
unforeseen earth delay & cost
R14 problems natural disaster increase
R15 Currency exchange exchange rate cost increase All activities
- 164 -
Chapter (8) RISK MANAGEMENT Graduation Project 2019
ـــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــ
Equipment Excavation
Malfunction in the delay & cost problems Backfilling
R16 equipment poor maintenance increase replacement
delay & cost Execution of
R17 Fire poor HSE increase activities
poor site Execution of
R18 Labor Strikes supervision delay activities
delay & cost Execution of
R19 Wars political issues increase activities
conflict Activities
Delay of consultant poor communication delay & cost delivery
R20 inspection between parties increase
inflation and All activities
R21 interested rate exchange rate cost increase
R22 Safety issue poor HSE poor quality All activities
- 165 -
Chapter (8) RISK MANAGEMENT Graduation Project 2019
ـــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــ
8.5.1 Qualitative Risk Analysis:
Prioritizing risks for subsequent further analysis or action by assessing and
combining their probability of occurrence and impact.
The qualitative analysis process is quick and cheaper. It gives us some feel about
the risks, and then we can determine which risks needs to be analyzed further by
using
- 166 -
Chapter (8) RISK MANAGEMENT Graduation Project 2019
ـــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــ
Risk urgency assessment
- In some qualitative analyses the assessment of risk urgency can be combined
with the risk ranking determined from the probability and impact matrix to give a
final risk sensitivity rating. Example- a risk requiring near-term responses may
be considered more urgent to address.
Expert judgment
– Individuals who have experience with similar project in the not too distant
past may use their judgment through interviews or risk facilitation workshops.
A quantitative analysis:
- quantifies the possible outcomes for the project and assesses the probability
of achieving specific project objectives
- provides a quantitative approach to making decisions when there is
uncertainty
- creates realistic and achievable cost, schedule or scope targets
- 167 -
Chapter (8) RISK MANAGEMENT Graduation Project 2019
ـــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــ
8.5.2.1 Tools and Techniques for Quantitative Analysis
Pert
Mont Carlo Simulation
Decision Analysis (Decision Tree)
Interviewing
- This technique is used to collect the data for assessing the probabilities of
achieving specific project objectives. You are looking for results such as: We have a
70% probability of finishing the project within the schedule desired by the customer.
Or: We have a 60% probability of finishing the project within the budget of LE.
100,000. The goal is to determine the
scale of probabilities for a given
objective; for example, there is a 20%
probability that the project will cost LE.
50,000, a 60% probability that it will
cost LE. 100,000 and a 20% probability
that it will cost LE. 150,000.
Probability distributions
- After you have collected the data on meeting the project objectives, you can
present it in a probability distribution for each objective under study. Note that a
distribution represents uncertainty, and uncertainty represents risk. For example, if
you know for sure the project will cost LE. 25,000 there will be no distribution
because it is only one data point. Distribution comes into the picture when you have
several possible values with a probability assigned to each value. There are
distributions of different shapes in which the data can be presented
- 168 -
Chapter (8) RISK MANAGEMENT Graduation Project 2019
ـــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــ
Sensitivity analysis
- This is a technique used to determine which risk has the greatest impact on
the project. You study the impact of one uncertain element on a project
objective by keeping all other uncertain elements fixed at their baseline
values. You can repeat this analysis for several objectives, one at a time. You
can also repeat this study for several uncertain elements (creating risks), one
element at a time. This way, you can see the impact of each element (or risk)
on the overall project separate from other elements (or risks).
Transference
– Shifting the negative impact of a threat, along with the ownership of the
response, to a third party.
Mitigation
Avoidance
- 170 -
Chapter (8) RISK MANAGEMENT Graduation Project 2019
ـــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــ
plans have been carried out successfully. Problems that have been found out in
the risk plan can help us adjust the plans for future risk activities.
The level of risk tolerance should be monitored as well. The attitude of the
stakeholders will change during the course of the project. Communication with all
stakeholders is important since it gives us a means of assessing changes in their
risk tolerance.
Activities:
The following activities will be undertaken to identify, review and control risks on the
project. These activities together form the "Risk Management Process.
Roles:
While any member of the project team may identify a project risk, the following staff
will have key responsibilities for the ongoing risk management within the project:
Team Members will be responsible for:
Identifying project risks and completing Risk Forms
Forwarding all Risks Forms to their Project Leader for review
Team Leaders will be responsible for:
Reviewing all Risk Forms to determine whether they are "likely" to adversely
affect the project.
Working with the team member to approve a set of preventative and
contingent actions.
Forwarding a prioritized set of Risk Forms to the Project Manager for action.
The Project Manager will be responsible for:
Confirming the priority level of Risk Forms received.
Taking immediate actions to resolve all low and medium priority level risks.
Making the Project Board immediately aware of new high priority risks.
Implementing actions approved by the Project to resolve High Priority Risks.
- 171 -
Chapter (8) RISK MANAGEMENT Graduation Project 2019
ـــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــ
2-Risk Identification
3-Risk Analysis
Risk identification
- 172 -
)Chapter (8 RISK MANAGEMENT Graduation Project 2019
ـــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــ
- 176 -
Chapter (8) RISK MANAGEMENT Graduation Project 2019
ـــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــ
Quantitative Analysis
Risk Score
Risk Statement probability Impact Response Procedure
ID (p*I )
R01 Increase in materials price 0.9 0.9 0.81 Reduce
TO BE CONSIDERED
R13 Currency exchange 0.7 0.9 0.63 Reduce
R02 Increase in the fuel rate 0.7 0.7 0.49 Transfer
R18 inflation and interested rate 0.7 0.7 0.49 Reduce
R19 Safety issue 0.7 0.7 0.49 Reduce
R21 Design changes 0.6 0.8 0.48 Accept
eligabilities and
R22 regulatories 0.7 0.65 0.455 Reduce
R16 Labor Strikes 0.5 0.9 0.45 Reduce
R08 Theft of the materials 0.5 0.7 0.35 Reduce
WATCH LIST
R03 Traffic Jam and problems 0.5 0.5 0.25 Accept
Subcontractor failing to
R06 deliver task on time 0.3 0.7 0.21 Reduce
R10 labor wages increase 0.3 0.7 0.21 Accept
R15 Fire 0.3 0.7 0.21 Transfer
R04 Accident in site 0.3 0.5 0.15 Reduce
R07 Delay in material delivery 0.3 0.5 0.15 Transfer
R11 import/export restriction 0.3 0.5 0.15 Accept
Malfunction in the
R14 equipment 0.3 0.5 0.15 Transfer
R20 Design assumptions 0.2 0.7 0.14 Accept
Delay of consultant
R17 inspection 0.3 0.3 0.09 Avoid
unexpected or unforeseen
R12 earth problems 0.1 0.7 0.07 Accept NEGLECT
shortage of skilled
R05 subcontractor 0.1 0.5 0.05 Accept
R09 Drop of labor productivity 0.1 0.5 0.05 Reduce
Score response
Risk ID Risk Statement Probability Impact
(p*I )
subcontractor TO BE
R2 (back to back 0.7 0.7 0.49 CONSIDERED
agreement)
- 177 -
Chapter (8) RISK MANAGEMENT Graduation Project 2019
ـــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــ
decrease in
R1 material prices 0.5 0.9 0.45
early completion Watch list
R3 of works 0.5 0.7 0.35
no design
R4 changes 0.3 0.9 0.27
- 178 -
Chapter (8) RISK MANAGEMENT Graduation Project 2019
ـــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــ
Safety issue
Mitigation they decided that employee them in the security
precentage
consequnce
Id risk name Probability of total EMV
cost
value
Increase in materials
2% 10446235 8461450.35
R01 price 0.81
R13 Currency exchange 0.63 1.50% 7834676.25 4935846.038
Increase in the fuel 3% 15669352.5 7677982.725
R02 rate 0.49
inflation and interested
1.60% 8356988 4094924.12
R18 rate 0.49
R19 Safety issue 0.49 2% 10446235 5118655.15
R21 Design changes 0.48 1.50% 7834676.25 3760644.6
eligabilities and
5% 26115587.5 11882592.31
R22 regulatories 0.455
R16 Labor Strikes 0.45 0.50% 2611558.75 1175201.438
Cost 522311750
total threats EMV 47107296.73
total cost 569419046.7
ratio of risk 0.083
- 179 -
Chapter (8) RISK MANAGEMENT Graduation Project 2019
ـــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــ
Risk response for each risk
Response Scor
ID Risk name Explanation probability Impact EMV
Strategy e
By buying as
940161
much material
1.5
R01 Increase in materials price Reduce as possible 0.7 0.9 0.63
548427
R13 Currency exchange Reduce 0.7 0.9 0.63 3.375
by hiring
subcontractor
109685
Increase in the fuel rate s for
46.75
equipment
R02 Transfere and trucks 0.1 0.7 0.07
by studying
the inflation
trend to know
when to buy 584989
most of the 1.6
purchases
during the
R18 inflation and interested rate Reduce project lifetime 0.5 0.7 0.35
By hiring
731236
Securty
4.5
R19 Safety issue Reduce agency 0.2 0.7 0.14
by accepting
changes and
470080
push work to
5.75
get the lost
R21 Design changes Accept time 0.6 0.8 0.48
by starting in
issuing 182809
eligabilities and lisences in 11.25
R22 regulatories Reduce early time 0.4 0.65 0.26
By hiring well
130577
leading
9.375
R16 Labor Strikes Reduce supervisiors 0.2 0.9 0.18
- 180 -
Chapter (8) RISK MANAGEMENT Graduation Project 2019
ـــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــ
EMV after response
8461450.35 4230725.175
R01 Increase in materials price Reduce
R13 Currency exchange 4935846.038 Reduce 1974338.415
R02 Increase in the fuel rate 7677982.725 Transfer 3455092.226
R18 inflation and interested rate 4094924.12 Reduce 2047462.06
R19 Safety issue 5118655.15 Transfer 1535596.545
R21 Design changes 3760644.6 Accept 3760644.6
eligabilities and
11882592.31 5703644.31
R22 regulatories Reduce
R16 Labor Strikes 1175201.438 Reduce 740376.9056
cost 522311750
total
threats 23447880.24
EMV
total
545759630.2
cost
ratio of
0.043
risk
Monitor and control :In this stage we keep focused on the most expected risks to
take planned responses for them and detect any new pop up risks which may occur
during the project life cycle or secondary or residual out of risk responses.
- 181 -
Chapter (8) RISK MANAGEMENT Graduation Project 2019
ـــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــ
4. primavera risk analysis:
The purpose of using Primavera Risk Analysis is studying the effect of uncertainty
and possible risks effect using sensitivity analysis and Monte Carlo simulation, so we
imported our project activities and the time table from Primavera P6 and run
Schedule Check.
According to market status study we detect these values to recourse, equipment and
labors uncertainty cost and duration the next table shows the mean percentages of
cost uncertainty.
After running 10,000 iterations using " Monte Carlo Simulation " the result of cost and
duration is:
- 182 -
)Chapter (8 RISK MANAGEMENT Graduation Project 2019
ـــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــ
Based on above calculations and using primavera risk analysis the cost of risk after
metigation (risk allowance ) equals 545,622,977-522,651,237= 22,971,740 LE which
equals 3 % of total cost and the uncertinaty equals 370,356 LE so it can be
neglected and we take 1% for contingency to recover unknown risks so the risk
allowance is 4% of total cost added to profit of the project.
- 188 -
9. PRICING
- 189 -
Chapter (9) PRICING Graduation Project 2019
ـــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــ
9.1 Overview
The total price of a tender comprises the cost and the markup. The cost includes
direct and indirect costs. The markup, includes profit, financial charges (cost of
borrowing), and a risk allowance margin.
Total Price
Machines Money
Site overheads such as site accommodation, insurance, and so on, are generally
accounted for separately and in contractual terms are included in
the preliminaries element of the contract.
- 191 -
)Chapter (9 PRICING Graduation Project 2019
ـــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــ
Table.( 9.1 ):overhead calculations
- 193 -
)Chapter (9 PRICING Graduation Project 2019
ـــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــ
Price matrix:
Its is one of the most vital elements in the survival of a business. It can be
positive, or negative, which is obviously a most undesirable situation. The chapter
develops the concept of cash flow and then shows how the funds can be used in the
business. Funds are not only generated internally; they may be externally generated,
and so the chapter finishes with a discussion of externally generated funds.
We have made separate trails with different assumptions to reach the accurate
percentage of the cost of finance which is properly shows the best case for our
project cash flow during the whole project timeline.
In the first trial the Fig shows our assumptions in which we predict that the COF is
about 1% and other assumptions are the same in both trails.
- 195 -
)Chapter (9 PRICING Graduation Project 2019
ـــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــ
- 199 -
Chapter (10) QUALITY Graduation Project 2019
ـــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــ
-Project manager and project management team are responsible for determining and
delivering the required level of both quality and grade
- 200 -
Chapter (10) QUALITY Graduation Project 2019
ـــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــ
Quality
Engineer
Testers
- 202 -
Chapter (10) QUALITY Graduation Project 2019
ـــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــ
functional testing and managing the setup and assignment of the tests using Testing
Management tools.
10.4.4 Responsiblities of Testers:
Responsible for validating the test basis, designing and developing test cases/scripts
and data sets, executing tests, and reporting and diagnosing defects as well as
quality assurance of the tests cases and test execution.
-Materials:-
-Cement:
The contractor must supply the engineer with a report about the used cement
including its type, source and a certification with its components and
properties.
Tests must be carried out of prove it’s suitability for works before execution.
The cement must be delivered in the original closed bags, and it must be well
stored on an elevated wooden floor to protect it from humidity and rain.
The site must be provided with the amount of cement required to continue
work without stoppage.
-Aggregates:
The contractor must supply the engineer with a sufficient report about the
coarse and fine aggregates clarify the source, type and available dimensions.
Aggregates grading must allow the production of concrete with high
workability, without increasing its water content.
The contractor must carry out the required tests to prove the suitability of
aggregates for concrete and its correspondence to the specifications.
Gravel should be sprayed with water so as not to absorb part of the mixing
water.
Aggregate must be free of fine soft material so as not to affect the resistance
of concrete.
-Water:
The water used in mixing and curing must be from a source suitable for
drinking and clear of harmful materials like oils, acids, alkalis, salts, and
organic materials.
-Admixtures:
The engineer’s approval must be taken on any type of admixtures before
using it.
Used admixtures must correspond to one of the international specifications
and must not affect the fundamental concrete properties.
- 203 -
Chapter (10) QUALITY Graduation Project 2019
ـــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــ
-Reinforcement:
Reinforced steel shall be placed in concrete, as shown on the working draw
submitted by contractor and approved by owner engineer.
Forms to shape the concrete to the required lines shall be used whenever
necessary.
The forms shalt be of sufficient strength and rigidity to hold the concrete and
to withstand the necessary pressure of ramming without deflection from the
prescribed lines.
For concrete surface that will be exposed to view and for all other surfaces
that are to be finished smooth, the lagging for forms must be surfaced and
level edged, or notched.
Reinforcement bar:
1. Fabrication
• Cutting and bending of rebar will be done at site central steel workshop
according to the approved shop drawing.
• Fabricated rebar will be stored in designated floor covered area.
Each set of steel bars will be tied up after deforming and information card will
be stick on it.
2. Installation
- 204 -
Chapter (10) QUALITY Graduation Project 2019
ـــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــ
Approved spacers will be placed to maintain the cover of concrete.
Concrete cover will be 3.5cm for facing soil and 2.5cm on the other side as
stated in contract drawing.
Steel chairs will be used to maintain the gap in between top bar and bottom
bar.
All rebar installation work to be checked by QAQC and to be inspected by
PMCM
Mixing:-
Placing:-
No concrete shall be laid before an order has been optioned from the owner’s
engineer.
Concrete shall be used on the work immediately after the mixing, and any
concrete not laid at place within half an hour after mixing shall not be used in
the work and shall immediately be removed from the vicinity.
In case of R.C construction, concrete shall be placed in horizontal layers
stirred and
damped with suitable tools and mechanical vibrator until it completely fills the
forms,
closes enough against all surfaces and is in a perfect and complete contact
with all reinforcement.
During compaction must avoid crashing of immersion vibrators with steel bars.
Temperature requirements at the site should be taken into consideration.
-Finishing concrete surface:
- 205 -
Chapter (10) QUALITY Graduation Project 2019
ـــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــ
The surface of concrete finished against forms must be smooth, free form
protections thoroughly filled with mortar .immediately after the removal of the forms
all voids shall be neatly filled in with cement mortar of the same consistency as the
mortar in concrete.
Protection of concrete :
The contractor should protect all concrete against injury until final acceptance by the
owner. Exposed surfaces of concrete shall be protected from direct rays of the sun
and shall be kept damp for at least two weeks after the concrete has been placed.
- Slump test
- 207 -
Chapter (10) QUALITY Graduation Project 2019
ـــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــ
One test for each composite sample, but not less than
one test for each day's pour of each concrete mixture of
air-entrained, wet-mix shotcrete measured before
pumping.
-Compressive-Strength Test:-
- 208 -
)Chapter (10 QUALITY Graduation Project 2019
ـــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــ
Table.( 10.2 ): Tests frequency guide:
- 211 -
Chapter (11) VALUE ENGINEERING Graduation Project 2019
ـــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــ
11.1 Overview
VE (value engineering) was developed at General Electric Corp. during World War II
and is widely used in industry and government, particularly in areas such as defence,
transportation, construction and healthcare. VE is an effective technique for reducing
costs, increasing productivity and improving quality. It can be applied to hardware
and software; development, production and manufacturing; specifications, standards,
contract requirements and other acquisition program documentation; and facilities
design and construction.
VE is a technique directed toward analysing the functions of an item or process to
determine “best value”, or the best relationship between worth and cost. In other
words, “best value” is represented by an item or process that consistently performs
the required basic function and has the lowest life-cycle cost. In this context, the
application of VE in facilities construction can yield a better value when construction
is approached in a manner that incorporates environmentally-sound and energy-
efficient practices and materials. Because “costs” are measurable, “cost reduction” is
often thought of as the sole criterion for a VE application and indeed it is primarily
addressed in this document. However, the real objective of VE is “value
improvement” and that may not result in an immediate cost reduction.
Value engineering (VE) is systematic method to improve the "value" of goods or
products and services by using an examination of function. Value, as defined, is the
ratio of function to cost. Value can therefore be increased by either improving the
function or reducing the cost. It is a primary tenet of value engineering that basic
functions be preserved and not be reduced as a consequence of pursuing value
improvements.
Value Engineering define as “A specialized cost control technique, performed by a
group of experienced professionals. The technique involves an intensive, systematic
and creative study to reduce cost while enhancing reliability and performance. The
technique is used to achieve the best functional balance between cost, quality and
performance of a product, system or facility". Figure No. 1 to clarify that VE is a
functional balance between cost, quality and performance.
It may be successfully introduced at any point in the life-cycle of products, systems,
or procedures.
- 212 -
Chapter (11) VALUE ENGINEERING Graduation Project 2019
ـــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــ
- 213 -
Chapter (11) VALUE ENGINEERING Graduation Project 2019
ـــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــ
The team prepares alternative designs with capital and/or life cycle cost comparisons
of original designs and proposed alternatives. All recommendations are
supplemented with written descriptions, sketches, basic design concepts, technical
information and cost summaries. The selected ideas are developed into proposals
that are clearly written so that the owner and other project stakeholders understand
the intent of the proposal and how it benefits the project, and also to identify any
potential negative factors associated with the proposal.
E. Recommendation Phase
The recommendation phase is important, as the selected alternatives are presented
to top management with the full comparative position of costs as well as technical
ranking. The major changes in design are also described briefly with sketches,
drawings or models as appropriate.
- 214 -
)Chapter (11 VALUE ENGINEERING Graduation Project 2019
ـــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــ
Because construction process has many components such as concept, design and
drawing details of the project, construction etc., and it is a long-term production, the
risk of completion of construction in time, based on the estimated costs (first
investment + usage cost) by providing features such as quality, durability,
usefulness, continuity, feasibility, compliance, image and management convenience,
increases.
Suitable precautions are taken by predetermination of problematic areas via various
project planning and scheduling techniques. But none of these methods includes an
examination in terms of the “value”. After a building is completed or during the
construction stage, comparing the building value with the costs that occur during its
construction is not thought about. Although many buildings were built with high costs,
desired functions were not provided. There is absolutely no direct proportion
between a building’s costs and provided benefits. In value engineering rationalist
evaluation techniques are used considering the target features, and unnecessary
costs are determined to be eliminated from the project, so that a building’s value is
increased and resources (money, material and workforce) are not wasted.
Some methods that increase the value in construction sector are explained as
follows.
- 216 -
Chapter (11) VALUE ENGINEERING Graduation Project 2019
ـــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــ
1) Reducing construction production costs
2) Finishing the job before Time Schedule
3) Quality improvement and correction
4) Reducing mistakes and deficiencies in project drawings to minimum.
1) Cost Model
VE team applies uniformed cost model to determine the cost of each function. The
VE team has to find out the classification of the cost consumed in the overall project
and find out the most affected component in the building which has the higher value
compare to other materials and components. For each project, there is a cost model
depending on its component. Table 1 shows the cost of the all components of the
building described.
- 217 -
Chapter (11) VALUE ENGINEERING Graduation Project 2019
ـــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــ
- 219 -
Chapter (11) VALUE ENGINEERING Graduation Project 2019
ـــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــ
In the project there are large numbers of Red bricks are used for the construction of
project. So by changing the AAC blocks which are locally available and it serves the
all-purpose like Red bricks and having a less cost comparing the AAC bricks can
also minimize the project cost. Table (11.3).shows saving in cost by using AAC
blocks.
Materials used on
NO. Specification Replaceable materials
the Project site
Red bricks AAC Block
1 Material
(250 X 125 X 60) (600 X 200 X 150)
Numbers of
2 24335448 2552032
bricks
3 Price/bricks 0,5 4
4 Total cost 12167724 10208128
Saving 1959596 16,10%
11.5 Conclusion
Success of a project, deciding on where and how a project will be built, completion of
the structure according to desired design and building quality, within determined time
and cost limits, are all possible with good estimations and solutions. The purpose of
value engineering is not just reducing the costs, increasing the design standards,
making it easier to build the project and saving time and money. Value engineering is
a powerful tool in terms of the design improvements, performance of product and
service, solve problems and cost control. Now a day’s traditional cost control method
and modern cost control methods are used generally but these methods have a lots
of disadvantages compared with value engineering.
In the Case study discussed above, there are value engineering concepts used
having a main focus to reduce the cost of the project by simply recommending the
other advanced replaceable materials which are locally available to improve the
value of the project.
- 220 -
12. HSE MANAGEMENT
- 221 -
Chapter (12) HSE MANAGEMENT Graduation Project 2019
ـــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــ
12.1 Overview
We are committed to providing a safe, accident-free, and healthy work environment
for everyone. However, excellent safe and healthy conditions do not occur by
chance. They are the result of diligent work and careful attention to all company
policies by everyone.
Safety demands cooperation on everyone's part. Thus, it is important that
communication be kept open at all times between the management and employees.
Workers who notice hazards or other safety problems, or feel that they need
additional training, must notify their supervisor. Supervisors and management at all
levels must address these concerns and take corrective action when warranted.
Everyone is obligated to know the safety standards for their area or job, and just as
important, to abide by them. Supervisors must instill a positive attitude and safety
awareness in their workers through personal adherence, personal contact, training,
and regularly scheduled safety meetings. It is the duty of all employees to perform
their work with maximum regard for the safety of themselves and co-workers.
Our safety policies are based on past experience and current standards, and are
also an integral part of the company's personnel policies. This means that
compliance with the policies is a condition of employment and must be taken
seriously. Failure to comply is sufficient grounds for disciplinary action or for
termination of employment.
Safety and health are a top priority in this organization and is every bit as important
as productivity and quality. In fact, they go hand in hand. Of course, the best reason
for you to observe these policies is because it's in your own self-interest to do so.
Conscientiously following them can help you stay safe, healthy, and able to work,
play, and enjoy life to its fullest.
12.2 Introduction
Health & Safety Risk is the chance that an event will occur, that will harm people,
property and the environment. It is measured in terms of likelihood & consequence.
Observation of Health & Safety conditions in projects:
Provide a safe working environment to employees.
Reduce workplace hazards.
Minimize the opportunities of job-related injuries & illnesses
Improve the cost effectiveness of the company operations by reducing the
cost paid in accidents.
Enhance the image of the company in society as a H&S conscious
organization.
The OHSAS 18001:-
A standard that defines the requirements for an Occupational Health & Safety
(OH&S ) system, needed to enable an organization to control its OH&S risks and
improve its performance. It also allows third-party certification. It was issued by the
international Organization for Standards.
- 222 -
Chapter (12) HSE MANAGEMENT Graduation Project 2019
ـــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــ
OHSAS 18001 is applicable to any organisation that wishes to:
Establish an OH&S system to eliminate / minimise risk to employees & other
parties who may be exposed to OH&S risks associated with its activities
Implement & continually improve an O&HS management system
Assure conformance with its OH&S policy & Demonstrate such conformance
to others
Seek certification of its OH&S management system by an external
organisation
What is a "hazard?"
An unsafe condition or practice injury or illness to an employee and it’s preventable
Some types of Hazards:
Fire
Noise Level.
Heat / Temperature.
Toxics.
Radiation.
Workplace Violence.
Mechanical.
Chemical.
Electrical contact.
Biological.
Explosives.
MEEP Matrix:
- 223 -
)Chapter (12 HSE MANAGEMENT Graduation Project 2019
ـــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــ
Hazard exist in 4 Areas
Material - Equipment - Environment - People
a. Employees scheduled for any safety and health training will attend such training.
b. New employees will be provided orientation training and will be furnished
information and literature covering the company health and safety policies, rules, and
procedures. This orientation training must be provided prior to the employee's
exposure to the work environment.
c. Individual job/task training will be provided to all employees. Included in this
training are the applicable regulations/standards for their job; the recognition,
avoidance, and prevention of unsafe conditions; areas and activities that require
personal protective equipment; and how to use protective equipment (such as
respirators, etc.).
d. Monthly/quarterly on-going safety training sessions will be conducted to provide
information and training on new equipment, new procedures, new chemicals,
refresher/remedial training in specific areas, or meet annual requirements. Such
training may be held in conjunction with the safety briefings/meetings addressed
elsewhere in this program.
e. Various individual Wyoming Workers' Safety programs specify that training be
provided to employees. Supervisors will ensure their employees are scheduled and
provided this training as required. Examples of specified training include but not
limited to:
Fire extinguisher training
Confined space entry
Respirator care and use
Hazard communication
Lockout/tagout procedures
Industrial truck/forklift operation
Electrical work
f. Training addressed above will be documented in the employees' personnel records
and/or in a master training record.
- 225 -
)Chapter (12 HSE MANAGEMENT Graduation Project 2019
ـــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــ
City Gate Mall Site Signs:
12.3 Responsibilities:
The goal is to protect employees from injury while working for the company. This
must receive top priority from everyone.
Duties and responsibilities of all personnel under our health and safety program are
in the following:
.2.1 Health and Safety Manager (Or management personnel if none assigned) :
a. Administers all aspects of the occupational health and safety program.
b. Develops programs and technical guidance to identify and remove physical,
chemical, and biological hazards from facilities, operations, and sites.
c. Assists management and supervisors in the health and safety training of
employees.
d. Conducts inspections to identify unhealthy or unsafe conditions or work
practices and completes written reports of inspections.
e. Recommends programs and activities that will develop and maintain
incentives for and motivation of employees in health and safety.
f. Recommends disciplinary action for repeat violators of health and safety
rules.
g. Maintains the state health and safety poster, emergency telephone numbers,
OSHA Form 300, and other notices required by Wyoming Workers' Safety.
Ensures this information is posted in places where employees can see them
on each job.
h. Develops and maintains accident and incident investigation and reporting
procedures and systems. Investigates serious or reportable accidents and
takes action to eliminate accident causes. Reportable incidents consist of
fatalities, lost work day cases, and without lost work days requiring medical
treatment. Keep management informed of findings.
i. Report accidents that result in an occupational fatality or three or more
hospitalized workers within eight (8) hours of occurrence.
a. Maintains all records and reports of accidents that have taken place during
company operations. These forms and reports may include the OSHA
Form 300 Injury/Illness Log, the OSHA Form 101 Supplementary Record of
Occupational Injury and Illnesses. The equivalent form, Wyoming
Workers' Safety and Compensation Division Report of Occupational Injury or
Disease, may be kept instead of the OSHA 101.
b. Ensures that employee's Report of Occupational Injury or Disease report is
filed with the Workers' Compensation office within ten days of employee's
notification of an occupational injury or disease.
c. Processes all paperwork associated with accidents, on-site inspections and
in-house audits. He also maintains permanent record for company files.
d. Maintains all medical records, evaluations and exposure monitoring records
for a period of 30 years.
e. Maintains all training records for a minimum of three (3) years.
- 229 -
Chapter (12) HSE MANAGEMENT Graduation Project 2019
ـــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــ
a. Be familiar with and comply with proper health and safety practices.
b. Use the required safety devices and proper personal protective safety
equipment.
c. Notify supervisor immediately of unsafe conditions/acts, accidents, and
injuries.
Personal protective equipment must be worn as required for each job in all
operations where there is an exposure to hazardous conditions. This
exposure is determined by a personal protective equipment hazard
assessment of the workplace by the supervisor. Equipment selection and
wearing requirements are determined from this assessment.
Safety glasses, goggles, or face shields will be worn in those areas where
there is a reasonable
probability of injury to the eye from flying particles, molten metal,
chemicals/acids/caustics, or light radiation, or other eye hazards.
Head protection (hard hats) will be worn for protection from falling objects or
work near energized electrical contact.
Foot protection will be worn where there is danger to the foot from
falling/rolling objects, objects piercing the sole or electrical hazards.
Hand protection is required when hands are exposed to severe
cuts/abrasions, chemical/thermal burns, or chemical absorption.
Appropriate gloves, aprons, goggles, and boots will be used when necessary
for protection against acids and other chemicals which could injure
employees.
Respiratory equipment in many cases is needed for protection against toxic
and hazardous fumes/dusts. Supervisors must verify which equipment meets
the need for breathing safety. Only MSHA/NIOSH approved equipment will be
used.
The use of safety harnesses and lanyards are required when working more
than ten feet above a floor or ground level and there are no guardrails or other
form of fall protection, and on certain suspended scaffolds. Each employee
will be on a separate safety line, and this line will be adjusted so that the
employee cannot fall more than six feet.
Guarding
1. All flywheels, shafting, pulleys, belts, gears, sprockets, chains, and fan
blades will be guarded/enclosed when located below seven feet above
the floor or work platform.
- 230 -
Chapter (12) HSE MANAGEMENT Graduation Project 2019
ـــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــ
Guards removed for servicing or other work on the machine or
equipment will be immediately replaced upon completion of the work.
3. Woodworking equipment, such as power saws, radial arm saws, table
saws, nor portable abrasive grinders, will not be operated unless all
required guards are in place. Feather boards and push boards will
be used when necessary.
Compressed Gas Cylinders
1. All gas cylinders shall have their contents clearly marked on the outside
of each cylinder.
2. Cylinders must be transported, stored, and secured in an upright
position.They will never be left laying on the ground or floor, nor used as
rollers or supports.
3. Cylinder valves must be protected with caps and closed when not in use.
4. Oxygen cylinders and fittings will be kept away from oil and grease.
Oxygen cylinders will be stored at least 20 feet from any fuel gas
cylinder, or separated by a fire barrier at least five feet high.
5. When cylinders are hoisted, they will be secured in a cradle, sling-board,
or pallet. Valve protection caps will not be used for lifting cylinders from
one vertical level to another.
Ladders
1. Ladders will be inspected frequently to identify any unsafe conditions.
Those ladders which have developed defects will be removed from
service, and repaired or replaced. They will be tagged or marked as
such.
2. Portable ladders will be placed as to prevent slipping, or if used on other
than stable, level, and dry surfaces, will be tied off or held. A simple rule
for setting up a ladder at the proper angle is to place the base from the
vertical wall equal to one-fourth the working length of the ladder.
a. Portable ladders will extend at least three feet above the upper
level to which the ladder is used to gain access.
b. The top of a stepladder will not be used as step.
- 231 -
Chapter (12) HSE MANAGEMENT Graduation Project 2019
ـــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــ
3. Only one person will be on a ladder at a time.
Cranes/Hoists
1. All cranes/hoists will be inspected prior to each use to make sure it is in
safe operating condition.
2. A monthly inspection of hooks, running ropes, and hoist chains will be
made and a certification record to include date, inspector signature, and
hook/rope/chain identifier will be maintained.
3. Inspections of frequent (daily-monthly) and periodic (1-12 months)
intervals, depending on severity of use, will be made of all cranes. See
1910.179(j) for inspection requirements.
4. The rated load of the crane/hoist will be plainly marked on each side of
the crane. If the crane has more than one hoisting unit, each rating will
be marked on the unit or its load block.
5. Loads will never be swung over the heads of workers in the area.
6. Tag lines must be used to control loads and keep workers away.
7. Loads, booms, and rigging will be kept at least 10 feet from energized
electrical lines rated 50 KV or lower unless the lines are de-energized.
For lines rated greater that 50 KV follow Wyoming Workers’ Safety Health
and Safety Rules and Regulations, 1910.180(j).
- 232 -
Chapter (12) HSE MANAGEMENT Graduation Project 2019
ـــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــ
8. Job or shop hooks or other makeshift fasteners using bolts, wire, etc. will
not be used.
9. All slings will be inspected each day before use. Damaged or defective
slings will be immediately removed from service. In addition, alloy chain
slings will receive a thorough inspection periodically (at least annually).
10. Alloy steel chain slings, metal mesh slings, and synthetic web slings will
have permanently affixed identification, markings, or coding to show rated
capacities.
- 233 -
Chapter (12) HSE MANAGEMENT Graduation Project 2019
ـــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــ
Safety Railings and Other Fall Protection
1. All open sided floors and platforms four feet or more above adjacent
floor/ground level will be guarded by a standard railing (top and mid rail,
toe board if required).
2. All stairways of four or more risers will be guarded by a handrail, or stair
rails on the open side. Handrails or stair rails will be provided on both
sides if the stairs are more than 44 inches wide.
3. When a hole or floor opening is created during a work activity, a cover or
a barricade must be installed immediately.
4. Safety harnesses, belts, lanyards, lines, and lifelines may be used in lieu
of other fall protection systems to provide the required fall protection.
5. Adjustment of lanyards must provide for a not more than a six foot fall,
and all tie off points must be at least waist high.
6.
Scaffolds
1. Scaffold platforms more than ten feet above the ground, floor, or lower
level will have standard guardrails (consisting of top rail, mid rail, and toe
board) installed on all open sides and ends of platforms .
2. Planking will be laid tight; overlap at least 12 inches, and extend over end
supports 6 - 12 inches.
3. Mobile scaffolds will be erected no more than a maximum height of four
times their minimum base dimension.
4. Scaffolds will not be overloaded beyond their design loadings.
Forklifts
1. Only authorized and trained employees
will operate forklifts and other industrial
trucks.
2. Safe speeds, load handling, turning, and
other safe driving practices will be
followed at all times.
3. Operators will ensure loads are stable
and/or secure before moving.
4. Employees will not operate any forklift
that is in need of repairs, defective, or
unsafe .Such forklifts will be removed
from service for repair. Fig.( 12.11 ): Forklifts safety sign
- 234 -
Chapter (12) HSE MANAGEMENT Graduation Project 2019
ـــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــ
Aerial Lifts
1. Only trained employees will operate aerial lifts
(cherry pickers, extensible and articulating boom
platforms).
2. A body belt or harness will be worn and a lanyard attached to the boom or
basket when working from an aerial lift.
3. Employees will stand firmly on the basket floor, and not sit/stand/ climb on
the edge of the basket. Planks, ladders, or other devices will not be used
for additional elevation.
4. Aerial lift trucks will not be moved with workers in an elevated basket.
5. Lift controls will be tested each day prior to use.
- 235 -
Chapter (12) HSE MANAGEMENT Graduation Project 2019
ـــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــ
diseases that can occur in a work-related environment. Those employees, who suffer
injuries while on the job, must file a claim to receive the benefits provided by the act.
12.7 Injury and Illness Prevention:
The workplace safety insurance act and similar forms of legislation are administered
by a board or administrative agency. These agencies possess multiple functions,
which are designed to reduce the occurrence of workplace illnesses and injuries.
The board or administrative agency will also develop standards regarding the
certification of individuals and the approval for the underlying programs that are
attached to the certification.
12.8 Safety Insurance Basics:
A typical safety insurance legislation will apply to only workers categorized by the
administrative agency. For example, in Ontario, the safety insurance act only applies
to workers of a Schedule 1 and Schedule 2; an employee of a Schedule 1 employer
is paid by the Insurance Fund from premiums paid into the fund by the underlying
business entity. Workers of Schedule 2 employers are paid directly by their employer
through a payment schedule that is determined by the board. If the board delivers a
payment to the underlying employer to provide coverage, the employer is required to
reimburse the board the full payment amount.
12.9 Claiming Benefits:
When a worker is involved in an accident a claim should be filed as quickly as
possible. A formal claim for benefits cannot be filed, in most instances, more than six
months after an accident or being diagnosed with an occupational disease. If the
individual sustained critical or severe injuries, the individual’s spouse or other
survivor who is eligible for benefits will need to file a claim within six months of the
serious injury or death of the employee.
12.10 Lock out/Tag out Permit
- 236 -
)Chapter (12 HSE MANAGEMENT Graduation Project 2019
ـــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــ
- 240 -
Chapter (13) BIM MODEL Graduation Project 2019
ـــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــ
- 241 -
)Chapter (13 BIM MODEL Graduation Project 2019
ـــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــ
1- 3D model
2- Quantity takeoff
3- Timeline programming
4- Cost estimation 5D
5- 4D, 5D visualisation
6- updating reports
- 246 -
REFRENCES Graduation Project 2019
ـــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــ
References:
- Google Earth
- Google Maps
- Lecture Notes of Construction Project Managment by Dr.Emad Elbeltagi
- Egyptian code for project management
- Passing the risk management (C.Yeomans, 2011)
- https://www.slideshare.net/jbucho/engineering-procurement-and-construction-
contracts-for-infrastructure-projects-in-east-africa-69363479 accessed on
(10/10/2018)
- Van Ness Feldman Law firm
- FIDIC contractual conditions book
- SlideShare
- Egyptian code of practice for design and construction of concrete structures 203
– 2007
- Google search Engine
- https://gharpedia.com/aac-blocks-vs-red-bricks/ accessed on (3-Nov-2018)
- https://gharpedia.com/solid-concrete-blocks-vs-aac-blocks/ accessed on (2-Nov-
2018)
- Work Health and Safety Act 2011
- Work Health and Safety Regulation 2011
- Approved Work Health and Safety Codes of Practice
- Additional information on these sources may be found at www.comcare.gov.au
- Construction project management 2006/18934
- OHSAS 18001
- 247 -