Professional Documents
Culture Documents
Plumbing Services Design Guide
Plumbing Services Design Guide
,
f··
,-
' ..
-r·
'·
-
. ,--
Plurril~ing
services
' £7:\
,.
)
J
~u
design guide
~
..
··' i
'
....
27.9.77
Co ,- 1 ..L~
..:.1 ..L81'""
G Lo....,;
.. Pages
Index 169-17:
Preface
In 197 3 the I nst1tute published 1ts f1rsr comprehensive Acknowledgements
plumbing services text book. whrch incorporated most The Institute thanks Chairman. Mr. J. G. Rodoers and members
of the design leafiets previousiy published by the of the Revievv Pane: for their devotion tc, the task of compilmg
Institute. In addition to these. 1t contained a this oook. Their technical competence is reflected in the
considerable amount of data extracted from other frnished work which is a credit to the British plumbing industry.
sources which would be of use in the desig'n Acknowledgement is given to the co-operation of the British
processes. and due to this inclusion it was titled the Stendards Institution: the Director. Buildrr1;1 Research
E5tablishment for permission to reproduc: the BRE Digest 170-
'lOP Data Book'. The response from industry for this Ventilation of Internal Bathrooms and WC's in Dwellings.
book. with its easy reference. was such that within Thanks are also given to Mr. H. A Hawick for permission to use
nine months all copies had been sold. data from other Institute publications for w!"oich he holds the
copyright.
This revised text book. which still contains much In addition to the above the Institute would like to place on
record its appreciation for information supplied by the following
useful data. has now been extended to include the
individuals and companies which was used as a basis for items
fundamentals of plumbing design for all sections. It ftnally induded in the Guide:-
has also been enlarged and now includes additional E. James MIP
sections dealing with pumps and pumping. swimming
Applied Science Publishers Ltd.
pools. vacuum and medical gas. ventilation of internal
Edv;ards High Vacuum Ltd.
bathrooms and WC's in dwellings and a complete nev.·
Megaior Pumps ar.d Compressors Ltd.
section on fire protection services.
Paterson Candy International Ltd.
It is intended that this book should become the design Sha.-. Hathernware Lki.
guide for the Plumbing Industry and therefore it has Spirax Sarco Ltd.
been re-titled 'lOP Plumbing Services Design Guide' Finaliv ttte lnstrtute wishes to thank Mr. 8111 Field of WGF
in the hope that it may form the basis of all plumbing Designs for his high standard of layout and presentation.
design.
Members of the PLUMBING SERVICES DESIGN GUIDE
Review Panel:-
A panel of professional engineers. all members of the G. R. CRESPIN TEC;, (CEI) MIP
Institute. with considerable design and contractural Plumbing Engineer
experience. have collaborated to produce this most Building Design Partnership
comprehensive design guide. and the utmost care has J. HALLIDAY T ENG (CEI) FlOP
gone into its preparation to ensure. as far as possible. Projects Manager
Andrews Weatherfoil (Scotland) Ltd.
the accuracy and authenticity of its contents~
M. HARGREAVES MIP. MIPHE
Plumbing Engineer and Assocrate
We are grateful to all those who submitted comments Building Des1gn Partnership
on the first edition and for their constructive J. C. W. HILL TECH (CEI) MIP
suggestions. many of which we have been able to Plumbing Engineer
incorporate into this current guide. and we would Arup Associates
appreciate any further comments which may be useful H. A. HOWICK T.ENG (CEI) FIPHE. FlOP
to the panel when considering any future edit1ons. (from July 1975)
L. M. PHILIPS T.ENG (CEI) FlOP
Finally. I should like to pay my personal tribute and Plumbing Lecturer (Retired)
(from November 1974- July 1975)
extend my thanks to all concerned with the
J. J. PITE T.ENG (CEI) MIPHE. MASH. MIP
production of this book and in particular to tl:e
Plumbmg Manager
members of the review panel for their inspired help Matthew Hall Mechanical Services
which made it all possible. J. G. RODGERS T.ENG (CEI) FIPHE. MIP, MASPE
Senior Plumbing Engineer and Associate Building Design
Partnership (Chairman)
0 J. G. Rodgers T. Eng ccEil FIPHE. MJP. MASPE
Design Guide Co-ordinator:-
~
Chairman: ANDREW WATTS TECH (CEI) MIP. MASPE. RP
Plumbing Services Design Guide Review Panel. Executive Dorector The Institute of Plumb1ng
Past President:
The Institute of Plumbing.
November 1977.
we flushing
..
cistern
... .._._.;.._._... ____
foffices · ·' ---··- ._,.. ·--· ·- · -'"··· ··· ·
2
----
·- ·--~- -~-·--·-- -· · ·.o· ~ ....,.....,
...,_
.. __ . ..., . ~~--·------
cistern 1f 0 12
. (_:·:')" Wash basin (distributed use} 1t
·~ Wash basin 2 0·15
Wash basin (concentrated use) 3
Wash basin with spray taps l
I
0·04
Bath {private) 4 0·30 ~chools and_lndu_n._r~ai,_Bui~~-i~g_s_ ~-~~~..::·..~:=. :=--~~=
we flushing ci~tern 2
Bath (public) 8 0·60
Wash basin 3
Shower (with nozzle) 1.!.2 0·12
Wash basin _yvith spray tap
Sink with fin. taps 2t 0·20
Sink with ~in. taps 4 0'·30 Lab sink 1
Sink with 1 in. taps 8 0·60 Note: Certain sanitary appliances require a continuous flow of
water throughout the whole of the time that they are being used.
Lab sink iin. taps 1 0 08 Th.ese include ablution appliances fitted with spray taps._ umbrella
sprays. shower nozzles or similar fittings.
Assessment of probable demand In buildings where high peak demands occur, a loading unit
rating for such appliances is not applicable and 1 00 per cent of
the flow rate for these appliances as set out in Table A1 must be
In designing a hot or cold water supply system, an allowed for. The same applies to automatic flushing cisterns as
assessment must first be made of the probable maximum used for urinals.
demand at any particular time. In the majority of buildings
it rarely happens that the total number of appliances Example 7 Determrne the design flow rate for a distri-
installed are ever in use at any given time. For economic buting pipe feeding 8 wc's. 16 wash basins and 8 baths
reasons therefore, it is usual for a scheme to provide for in a block of flats.
a peak usage w.hich is less than the possible maximum. 8 wc's X 2 = 16 loading units
16 wash basins X 1! = 24 loading units
Probable demand Will depend upon the type of 8 baths X 10 = 80 loading units
sanitary appliance. the type of building in which it is 120 loading units
installed and the frequency of usage. In order to assess From Graph A 1. the flow rate reqwred for 120 loading
the probable demand, some designers total the possible units would be 1 · 5 1/s.
maximum demand and then take a percentage of this
figure, the percentage varying with the type of building Example 2 Determine the design flow rate for a distri-
in which the installation is fitted. The late W. Fretwell buting pipe feeding 24 wc·s. 24 wash basins. 16 urinals.
devised the formula m = vnwhere m = probable 4 showers and 4 cleaner's sinks in a factory where there
number of appliances in use and n = number of is a very high peak demand for use of the showers.
appliances installed. 24 wc's x 2 = 48 loading units
Mr. H. A. Hawick has devised a method based upon 24 wash basins x 3 = 72 loading units
.. the Theory of Probability. With this method a unit 4 sinks x 5 = 20 loading units
rating is devised for each type of sanitary appliance, 140 loading units
based on its rate of water delivery, time the taps are From Graph A 1. the flow rate requrred for 140 loading
open during usage, probable time the appliance is in units would be 1 · 65 litres per second. To this must
use and the simultaneous demand for the particular be added the water required for urinal flushing and
_. _type of _appliance, _continuous .use of ~rs.-
The urinals would require 16 x 4 ·50 = 72 litres every
Table A2 sets out the 'loading unit' rating for various 20 minutes or
appliances. A loading unit has no precise value in terms -20_7_x2_60- = 0·061/s
of litres per second. By multiplying the total number of
each type of appliance by the appropriate loading unit The 4 showers would require 4 x 0 ·12 = 0 · 48 1/s
number and adding the resultant totals together, the The total flow required would therefore be 1 · 65 0 · 06 +
recommended flow rate can be read from Graph A 1. + 0 · 48 =
2 ·19 1/s
--·--------··--·---------
. t .....
Pipe sizing
Table A4 Loss of head through draw-off taps expressed as equivalent pipe lengths
Discharge rate Equivalent length of pipe of
tap fully open same diameter as tap (metres)
~F,;.;it;.;;ti;.;.;n~g~(;;:.B;;:.S..;.1.;;.01.;..0;.:)._•--=-....-.·---'----'--'-;,....;._ _ ya .Q!_l./_m_ln._......___~PJ't&l' Galvanised mifthteel
}in. (15 mm nominal) bibt...:ap~or....:p::...il_la_r_ta..:.p_ _ _o~_·.:;;20~----=2~!_ _ _----:2_·__ 7o_. 4 · 00
fin. (20 m~~~mina.!)_bibt~e~pillar tap 0 · 30 4 8 · 5...::.0_ _ _...;__...::.5_-7;_5;;...__ __
1 in. (_25_m_r:n_no_m_ina~~ bi_bt_a~_or _pil_latJ!!_p____0_·_6_0_._ _ _~-- ___ _?.Q.: 00_ _ _ _ _1_3;..._.O_O_ _ __
•The loss of head through some patented draw· off taps is much higher through BS 1010 fittings.
Permissible loss of-head per metre run of effective length By reference to Graph A2. a 25 mm ( 1 in.) diamett
of pipe would be: · copper tube under these conditions would convey 1 ·
Head 19 · 6 1/s so .that this size of pipe would satisfy requirement
- - = - - = 0·49 m/m
Length 40
Table AS Loss of head in metres t~rough draw-off taps
Discharge rate in 1/s
Fitting (BS 1010) ·075 0·12 0·15 0·20 0·22 0·30 0·35 0·47 0·55 0·60
fin. bibtap ·185 ·365 ·52 ·75 1 ·1 1·8
-J-in. bibtap ·21 ·33 ·45 ·75 1 ·1 1·4
1in. bibtap ·45 ·70 ·90 1·2 1 ·5
fin. pillar tap ·24 ·40 ·52 ·70 ·80
fin. pillar tap ·24 ·30 ·40 ·50 ·70
Relative discharging powers of pipes Table A6 Nominal diameter of main pipe .
:.•. ·: The relative discharging power of pipes are as the mm . 100 75 65 50 40 32 25 20 ' 11
··r-·
..
square root of the fifth power of their diameters in. 4 3 2f 2 1f H 1 f
N= (~J orN= v{W 1:::: 2 3
1= 2
6
3
12 18 32 66 18
6 9 15 32 a
where N = number of branches -~
t
..._;.c:--~ t J--~-
,;t'" I
A x P for blank ends and
i
!·
. 150 2471 3497 1890 961 484
645
175 3290 4652 2516 1284
200 4232 5967 .3239 . 1-&82 ·832.
.•.·-
225 5271 7452 4032 2058 1032
250 6426 9090 4916 2510. 1258
300 9374 13258 7174 3658 1839
350 12523 17710 9587 4884 2458
--·-----·--·-·-- ·-·-
'. ' ~
. .·~Jl~:;~~~ .
. u
}i Gt ......~
.. :: •''~ l··.'j .. •1•; .(.c.
~ •.
Pipe sizing
gT
L.t'E:" sec
~.f-
ct L0 X 14 = 22J =:.c
J
c.
'""· ..
.....
c
+- .
L.- e
1 x 14 " 2::2 ~.::.
c..·
..._.
"'
g
+- .. _ 16 >. 14 ~ 22.! 2.25
" .
"' t-
0'
c
... _ 14 l<. 14 =196 2.10
\
~o
"N!
c·
.j- ... _ 12 )( 14 = 162 ~.9D
R:
.I II
r•
e
c
~-.
"'
c·
+-
i- ... _
.. _
i0 Y.
8x14=112
14 = 140 1.65
1.40
I c
....
..... '
. ._
.,I
T .. 6 )( 14 = 84 1.20
o·
o:
- (I
I
.....
"'
ec· +-
:
•Ii
\ "Ni.i...
... _ 2 X 14 = 28 0.6:J
1. A tota: of 14 loading units fo~ ea::
flat has bee~ Liosd .
' • I 2. A flow ra:: of 0 · 6 l;s has beer. use:
20 20
on the bo!torr !•cor to allow for full flov
Estimated maximum demand {0 · 40 litres/sec per flat) - 8 · 0 litres/sec simultaneously a~ both batns.
Probable demand 35 per cent - 2 · 8 litres/sec 3. Piping r.as !Jeen assumed as cop;>~
Number of flats for which frictional allowances are provided is 35 per cent 7 flats tube.
'
1 2 3 4 5 6 7 8 9 10 11 12
;-~
;::_J CD
..•
c
u
•
•
......
.•
E
..
E ..
CD
c.
•c. •
-m
c. ..
"0 ... ..... ; ...
..::
Cl
"0
Ill
CD
..::
. -...
~ Gl
"0
Ill
Gl
..:: •
E
"0
.Ill
Ill
..::
-·
c
u :I Gl ';iu CD
\
... ..m•E ;ou
c >
c c
..- -
., -
.cc
..... c.,
..... :E •
Cl Gl Gl Ill
i
- ...Gl
CD
.:
.. = ...u .....
..Ee ;c Ql
.....
.E • Gl Ql
0 ~~ ..
-·
i Gl
. ''. "C
...
> E Gl c
~
-; Cl.!!!
•
Ill ..
0 ...
Gl
u ... 01111
o- 0 .,
CD :I .! -CD .. Gl .. Ill "i ~Ill
a: 0
..J 0 "C .tE :e2 C' ; . :
w_ .. CJE .tE Q..~ > <E
., ... ; 1 280 2·80 40 0·14 4·30 1·70 6·0 0·84 0·84 2·0
I
i 11 14 0·40 25 0·035 2·40 25·50 27·90 0·98 1 ·82 0·65 2·40
I
! 2 252 2·50 40 0·11 2·70 2·70 0·30 2·12 1·60
i
~
12 14 0·40 20 0·14 2·40 12·10 14·50 2·03 4·15 1 ·10 5·10
J i 3 224 2·25 40 0·10 2·70 2·70 0·27 4·42 1·60
II 13 14 0·40 20 0·14 2·40 12·10 14·50 2·03 6·45 1 ·10 7·80
4 196 2·10 32 0·20 2·70 2·70 0·54 6·99 2·10
l 14
5
14 0·40 20 0·14 2·40 12·10 14·50 2·03 0·02 1·10 10·50
168 1·90 32 0·18 2·70 2·70 0·49 9·51 2·00
i• 15 14 0·40 20 0·14 2·40 12·10 14·50 2·03 11 ·54 1 ·10 13·20
-,I 6 140 1·65 25 0·40 2·70 2·70 1·08 12·62 2·50
- , ·10
"
,..,t·
t 16
7
17
14
112
14
0·40
1·40
20
25
0·14
0·30
.. 2·40
2·70
12~10 14·50
2·70
·2·03
0·81
14·65
15·46 2·25
1 ·10 18·60
I
I
0·40 20 0·14 2·40 12·10 14·50 2·03 17·49
;I 8 84 1·20 25 0·24 2·70 --. 2·70 0·65 18·14 1·80 21·30
24·00
9 56 0·90 20 0·55 2·70 2·70 1·49 19·63 2·25
JI 1.
10 28 0·60 20 0·30 2·70 2·70 9·81 20·44 1·5 26·70
···'·-,--.,!;····.:;·····
" ... ··-,,(, ,_.·'
.....
Section I1.. Hot and Cold water supplies
Pipe sizing
.r ..
Fig. A2 Pipe sizing of. hot water supply service to 3 storey block (3 flats)
.. ,-----,
I
I
~~_j
~1 1 b\' _j hwb
Loading Units L!tre~ sec
T 1x16=16 0.~2
g~i
2 1
""" 25..,
3
I I __]
ic:) .,
,V;J ~~
32
' e
. 8 7
2x 16=32 0.60
... 32,
4
L
'
I .J ·-~·
e
10
32, 5
9 ' 3x16=48 0.80
c
""" ___ ,
I
I
....
:to
I
1....-. I
I
I
I I
1 2 3 4 5 6 7 8 9 10 11 12
..
Ill
·c
E
E
CD
.... ..
Q.
Q.
.:
..
.c
.:
"C
Cll CD.C
"C
Ill
Gl
u
"C
Ill
Gl
.c
..
... ~:
CD CD Gl > CD
-·. -=..
... .c CD
-
~
u
...
u CD Cou c iiu >. CD
c ::» Gl
•
CD c .. OGI .!•c Gl
c. • c
..... ~--. ::c •
......
CD c 0 CD .c!: lll.c Ill CD Ill
ID :0 •CD...
ID
E o::E .. CD > ..... • Gl
... ...
.2CD ulll
0 ... ~~
CD
Cll
0
Cll u ...
"l:GI
g'E -CD II
~cii
0 ...
._CD
u .. CD Ill
...
o·- ., Ill ..
> CD
a: Q Ill c C'GIGI
w_ ... oE .tE c..f >E <E
1
..J
11 ·5
=
0·35 20
LL.Q.
0·11
..J-
:"- :. :: I
I i
I I ' 0
. ; :
! t i ..
0
g
:! i :
i!;
. I-; I
I
I i
• :II 0
0
-
V)
I I
I en
; :; !i
:. i I
II ·c:::I
I II I! I
:I: I
I; I
I.
; i l i r I, I I C)
r::
iI:
I
:.0
cu
.9
. II II II o·
N
0
.,'
; I
' ·'-
.;11 ~: ;
~) 'I''
0 I:
.
j
llo.:
''I
I
I
I ,,J!,j~· ! I I 0
i l!!i[!~ I
g
! !
i i!! i i ! r~ ;
I ! I:! I I ~
I
I
. r ~·
, I •
:! : ' I 1 I
, . I
!i
;
' 1
IIi; l II iI II
'I:' . ! N 0
V)
Ill i ! I I i I I N.
I I
i
I iI I
I I I!!
I L'
i! IIi II
l I ]\.
lI
I
'
i
I;
I
\
I ; i ' i
I!illIiII I I II
I I
I
I ~ l I
t
I ~ 0
N
;
'
~
- •
I
I
I
.. '-I ·~ !
Tl
''
! I I i I
I.
II' I I j I I '\ M-
0
c
!":
0
N
= g: ..c ....
'""
'0 9 '? <? '0 "'!
Pipe sizing
2n---,......--..~~---.---~~~21
-~co
-/--,--~~-~--------,Y---1 ~ Qi
Ql
u;
·----1-.::·;:
- - - - : - - .....--1 -: ~
";3
I
x~
c
~~~·-·':·:
~
n-'V"''.---T-:.,---.---'V
....
1·0
"0
r::::
0
t.)
CD
·6
...
Cl)
CD
c.
Cl)
CD
~· .t,
·=
CD
...
iO
~
0
u::
) ·2
·1
·t. ·8 1·0
Pipe sizing
•..
Graph A4 Head loss through stopvalves
10
6 . '
'
~, 2
d
l·C:
·8
"C
c
0
C)
G)
fl)
·6
'-
G)
c.
fl)
G)
·..:
:E
.!:
G)
-
iii
~
0
- u:
"")
1"":.,
·2
I
I
·06r--t--r-t-t-~~~r----r-----4----~~~---~~-+--~~------+----+----~~--~--+--1
I
.......... I
'1
i
-~4
1-
I
I
I
I
.
·2 a:: •.! ·5 ·6 ·S 1·0
~~:~ater Byelaws require that. where a storag:3~:~~?~ ~t:eavie~t_d;~and cJ_:Mrinf!_~d~h_e1-. e~:~_d'"""H.\ . ~t6rag; wd.
· "d d · h · · ·ed 1 . ax. a• y eman requ1rement
rs prov~ e rn a ~use,_r.e. premrses separate y occ~pr of. building . . per person. • •.. per person
as a prrvate dwelling, rt shall have a storage capacrty of .... -· ~-- ··~--"'·----·~· ~~ ____..._....,_,_ ·- -·~-:-·-·
not less than 25 gallons (114 litres).' Where such Colle~es and schools btres btres
cistern is also used as a feed cistern, it shall have a Boardmg 11 4 23
capacity of not less than 50 gallons (227 litres). If the Day 14 4·5
storage is provided by means of two or more cisterns, Dwelling houses
h · Low rental 114 see note• below
t err total capacity shall be the same as for a single Medium rental 1 14 45
storage cistern. High rental 136 45
All storage cisterns should be proviaed with a readily :::FI~a::.::ts..:..(7:-b::::lo:.:.c-=k-s-=-)_ _ _ _ _ ___..;..;:.:.._ _ _ _ _ _..;,:;__
removable cover, well fitting but not airtight, and should Low rental 68 23
be adequately protected against damage by frost. Medium rental 114 32
Every storage cistern must be fitted with an efficient High ren..t:::a:..,.l-------........:1:.::3~6 -------=37 2 -=
overflow pipe which should have as great a fall as FactC?!.!.~s · - - - - - - - - - ' 1 : . . :4:..___ _ _ _ ___..:4--=:·
5
practicable and preferably not less than 1 in 1 0. In Hospitalst
England and Wales, the byelaws require the overflow General 136 27
pipe to have an internal diameter greater than that of the :~;~~:~:s ~~ ~~
inlet pipe and in no case less than 1 in. (19 mm). In Infirmaries (with laundries) 90 27
Scotland, byelaws require the overflow pipe to have an Maternity 225 32
internal dia111eter not less than twice that of the inlet Mental 90 23
pipe and in no case less than 1f in. (32 mm). !.!N.::.urs:=_:es~·.!!h.::::om=es::..__ _ _ _ _ _...:.1.::.36::___ _ _ _ _ _4~5~
If the capacity of the storage cistern does not exceed !fos!!J:.::Is=---------....:1..!.1;:!.4_ _ _ _ _ _:;32 __
1000 gallons (4546 litres), the overflow pipe should be Hotels
arranged as a warning pipe, i.e. so that its outlet is in a First class 136 45
conspicuous position, . either inside or outside the Average 114 36
building, where the discharge of water therefrom may ~O:.!.ff!!ic::e::.::s:__-:::-------_;,·~14!,..:..·_ _ _ _ ___....;;4~·E
be readily seen. There should be no other overflow pipe. Sports pavilions
If the capacity of a~orage cistern exceeds"''OOO gallons- (with sp~ay_-type showers) · S6 as
(45461itres), it should have a warning pipe as previously Restaurants Per meal 61itres
d~scribecl or, alternatively, it should have an overflow ·s 1,.,,r:?<'· r.o'ma:!,. a rninim..:m cf 11.~ o.:·e! \',~t~. a 4-hour ha~t-u;
prpe not arranged as a warning pipe and, in addition, a pr~:?::.
warning pipe of not less than 1 in. (25 mm) diameter, +;::,;f: also tc• rl':e,·;m: Ho:pi:a! e..:;;::ng Nc:l's (Miniwy c
or some other device, which effectively indicates when Hea!1r: H.M.s.o.
,..
Section~~ Rot and Ccld v:c:tcr EU}YpliE:~
I
a time when the building may be occupied and the ! I'- I-
engineering services in daily use. :3 r-t- 'I-~ r-
500
~;
Whatever the building under consideration a pattern of jO.;_ I
hot water usage can be projected, the actual usage rt- 9
being largely a function of the building population and rrg
the type of activity that takes place within. In determin-
ing the pattern of usage it is important to differentiate
between the maximum daily demand and the average
daily demand, so that the implications of the system not
I
0
0 -
J
0 12
Hours
18
TL
meeting the demands made upon it can be recognised,
and the maximum. requirements designed for where
necessary. Table A 11 Peak hourly loads
: 3 2 3
To project the demand pattern over the operating period Lit res
Peak Litres Peak Lit res Lit res
an hour by hour analysis of hot water usage should be Hours used per Hour Hours used per Hour
made. Taking into account the building population, the 1 3400 3400 13 27000 2130
level and type of activity and all other factors which 2 6600 3300 14 28300 2021
affect hot water demand, a quantitive assessment of 3 9600 3200 15 28800 1920
hourly usage should be tabulated for ever( hour of the 4 11600 2900 16 28900 1806
operating period. For offices and schools a continuous 5 13300 2660 17 29000 1705
12 hour operating period may be sufficient, but for other 6 16300 2716 18 29100 1616
buildings such as hospitals and factories a 24 hour 7 19300 2757 19 29200 1536
operating period may be necessary. The projected 8 22000 2750 20 29300 1465
demand pattern should be recorded in the form of a 9 24000 2666 21 29400 1400
histogram profile as illustrated in Fig. A3. 10 25600 2560 22 29500 1340
11 26400 2400 23 29600 1286
From the histogram a series of sequential peak hourly
loads should be calculated for groups of hours, from 1 12 27200 2266 24 29700 1237
hour through to the maximum number of hours in the
operating period. The total hourly loads should be Fig. A4 Storage make-up ratio curve
recorded as in Table A 11 together with the average
hourly load for each group of hours under consideration.
On completion of Table A 11 a graph should be set up
using Col. 3 co-ordinates as the 'y' axis and Col. 2
co-ordinates as the 'x' axis as in Fig. A4. Unking the
co-ordinates for each group of hours will produce a
curve any point of which establishes a specific
relationship of recovery to storage which satisfies the
system requirements, assuming of course these have
been predicted with sufficient accuracy in the demand
profile.
It should be noted that for groups of buildings in which
· simtler types of activities take place, andwhich have the
same operating period, the shape of the curves will be
closely related the only variable being the quantitive
values of the storage and recovery co-ordinates. It
should also be noted that the storage volumes represent
net usable volumes to which an allowance should be 30000
. added to compensate for stratification and heat losses.
Boosted cold water installations
..
In the majority of large building Gomplexes which enlarged pipework.
includes multi-storey blocks it is usually necessary to An allowance of 7 litres per flat served is considered a
-- augment the mains pressure available and for the design
to provide for pumps or boosters to ensure an adequate
suitable provision for the size of the header.
supply of water to meet all the requirements at the 3. Indirect boosting from break tanks at low
higher floors. ; level
There are basically four systems in common usa. In the Thames Water Authority area and in other parts of
1. The directly boosted system (to cold water tanks the country, break. tanks must be provided for in the
only) · installation. Tt.a pumps must befitted on the outlet of a
2 The directly boosted header or enlarged pipe system break tank to ensure that there is no direct pump
3. Indirect boosting from break tanks at low level to connection .to the incoming main. As there is no
high level storage tanks assistance possible from the mains pressure the pumps
4. The pneumatic or pressurized system must, in this case, be capable of overcoming the total
static lift, friction losses in the pipework and in the
1. The directly boosted system ballvalve and any other resistances.
Where the water regulations permit, the pumps can be The sizing of the break tank must be considered
connected directly to the incoming main thus enabling carefully to prevent stagnation of the water which could
: iTh -the pump head to be added to that of the mains. occur due to oversizing.
~·V Generally this simple system is suitable for use only in In many cases full consultation with the water authority
those cases ·where the mains pressure is sufficient to is necessary where the whole of the storage is to be
., serve drinking water points on the top floor but cannot provided at low level.
' " provide adequate residual head at the roof level storage Float or electrode probe control switches must be
tanks. The pump head required is therefore usually provided with thebreak tank to cut out the pumps when
small. Control of the pumps is affected by means of a the water level drops to about 250 mm above the pump
float switch or electrode probes in the roof level suction connection.
storage tank. The control is usually set to start the pump This precaution is necessary to prevent the pumps
when the· water storage drops to about half that running dry snould the incoming main be shut off for
provided and stops the pump about 50 mm below 1the any reason.
ballvalve shut-off level. In a directly boosted pumped
system consideration may also have to be given to Example Indirectly boosted cold water
pressure surges which can occur under certain installation 12 storeys - 48 flats Fig. A5
conditions. Assumed static height to overhead storage
tanks •..•..•••....•...................••.•. 34m
2. The directly boosted header or enlarged pipe Allowance for friction loss in pipework . . . . . . . . 5 m
system · Allowance for loss of head at stopvalve and
This system incorporates a small header or enlarged ballvalves etc . • . . • .. • .. .. . .. .. .. .. .. .. . .. .. • • 5 m
pipe to provide drinking water storage ar- high level Estimated total head to be overcome . . • . . • . . . . 44 m
between .pump.cycJes. Float or electrode pro~ control The minimum pump head to be provided for is therefore
is provided to the duplicate pumps to ensure that the 44 m
roof storage tanks are refilled at suitable intervals. The The pump output at a head of 44 m to give a refill time of
pumps are connected, where permissable direct to the 4 hours to overhead main storage tanks, can be
mains supply. , derived as follows:-
The upper limit of head provided for by the pumps is
usually about 50 m.
·. Drinking water points where possible at lower level ate . Pump output in 1/s = s~ora~e in litres
fed direct at mains pressure. The minimum head which t1me m seconds
should be provided for at any draw-off point is 2 m.
The pumps are controlled in two main ways:- At 3 persons per flat and 90 litres per person (Table AS)
(a) by means of the drinking water demand from the ' 3 x 90 = 270 litres per flat
header pipe.
(b) by the fall in the water level in the main storage
tanks. pump output in 1/s = 48 x 270
In the first case when the header pipe empties a pipe line · 4 X 3600
-~
switch which is fitted on the header bypass starts the .
pump. = o:9o 1/s
To give a pump run of say two minutes, a time delay is
normally fitted .to the switch. As the header pipe is In addition to the overhead storage demand there is the
normally refilled in a shorter time than this, the excess is drinking water demand to assess. See page 15.
fed into the main storage tanks. As centrifugal pumps
~an operate against a closed valve for a short period of
t1me no damage is likely to occur if the ballvalves are
-elesed during pan of some refill cycTes.
The water level in the main storage tanks is controlled
u~ually either by float switches or electrode probes. In
VIew of the fill and empty cycle of the drinking water
header care must be taken to provide for an automatic
air valve to allow air to enter and be-vented from the
.
Section ...:\ Hot and Cold water supplies
144
c-~:)
90 90
From LU /flow rate graph A 1
- -----
1 - 0·845
144 LU are equivalent t9 1 · 9 1/r,,
32mm
25mm
....... ./
supply
, 25mm
.... D2 i:::::2 X 700
3·142 X 1000
. 14
" = - - = 0·446 m 2
31·42
D = )0·446 = 0·66 m
Storage at low level Drinking
unboosted D = 660 mm
25mm mains 25mm
-...supply , t>\:.1e: /-.. pne:..:matic cylindc~ 20:~:: !'n:"'ri lc:;; and 670 mrr.
df;:rneter "'o~lC ft1Cet the gi·..·er. C=~:g:-. reG;.;i~t:-~cnt.
/ \.
Pipe sizing boosted rising main for 24 flats
From the J)ipe sizing chart graph A2 and 32 mm N
'• copper pipe can handle a flow of 1 · 3 1/s at a velocity t
1 · 5 m/s (a suitable velocity for pumped supplies ;
Fig. A6 between1 to 2 m/s).
Pneumatic boosted Boosted It can also be found from the pipe sizing chart that th
cold water supply supply
loss of head in metres per metre run at this flow rate an
./ pipe diameter is 0 · 12 m/m run.
Friction loss in pipework for 32 mm N B pipe
Unboosted 34 x 0·12= 4·1 m
mains supply Friction loss in fittings at 32 mm NB pipe
4 elbows - 4 x 1 · 4 = 5 · 6 m} = 9 . 6 x 0 . 1 2
- 2 x 2 ·0 = 4 ·0
Incoming
Break
tank
"" 2 tees
.. =1·15m
Friction loss in 32 mm stopvalve- 1 · 0 m
Friction loss in 32 mm ballvalve- 2 · 0 m
Static lift and total friction heads to be overcome.
mam
34 + 4 ·1 0 + 1 ·15 + 1 + 2 = 42 · 5 m
Provision w~s made for 44 m pump head which we:
therefore satisfactory.
.
Volume
:Of
air .
Stop
{V2- _p.~~~~g
V,- -Start--
pumping
-
A
r 'C{>
ight glass .
---------
--------
f:'Pressure
relief
The drinking water demand of the 24 flats to be serve
from the high level storage has been assessed c
follows:-
On page 1 table A2 the L.U rating for a sink is given c:
3 to 5 LU. Taking a mean figure of 4 LU.
The 24 X 4 = 96 LU
From the LU flow rate graph A 1 page 7 this is show
'
I Drain
valve as being equivalent to a 1 · 3 1/s flow rate.
I• The high level storage refill flow rate and the drinkin
from pump to boosted supply water demand can now be added to provide th
--{\)-+-+---
maximum demand.
. - ·_f!g: A7- Pneumatic pressure vessel Total demand 0·90+T·3 = 2:2011s.
In practice the two demands on the rising pumped mai ·
(E) Working volume ----------~------ will occur simultaneously ver)C rarely.
To provide some working margin- say 20% becomes, The larger demand of the two can safely be taken as th
then the actual working volume to be provided. rated pump output to meet either demand.
v, = 580+ 20% The rated pump output should therefore be not les
say V,. = 700 litres than 1 · 3 1/s at a head of not Jess than 44 m.
Sectjc,n A Hot and Cold ·wate1· supplies
I ~o metres
where Dr= density of water in return pipe
and Df = density of water in flow pipe.
Not exceeding ·19 mm
Exceeding 19 mmbut not-exceeding 25 mm
12 · 0
7·6
I Exceeding 25_ mm 3 ·0
r .· As low pressures are usually expressed in millibars and
l·
i • 1· mbar = 100 N/m2, the expression becomes: In the case of a compound pipe of differing diameters
! Cp .m mb ar = 9 · 81 (Dr- Dt). x _circulating height
.
· ·
100
the largest diameter is to be taken.
For a spray tap the maximum length should be 0 · 9 m.
Example Determine the circulating pressure in a system Water quality
designed lor a flow temperature. of 82°C and a return
temperature of 60c C if the circulating head is 5 m. The quality of water is defined by chemical and bacterial
analysis and where the end usage is directly or indirectly
CP= 9·81 (983·2-970·6) X 5 9·81 X 12·6 X 5 for human consumption .it should comply with the
100 100 recognised standards to ensure freedom from harmful
bacteria. acute and long term toxic substances. In
CP= 6·18mbar= 618·00Pa addition the water should be clear, odourless, tasteless
Fig. AS Recircu~ation deionisation system and wholesome.
Ring main return
i
J -
1. Hand isolation valve 11. Solenoid valve
2. Break tank for raw water 12. Break tank for recirculation water
3. Low level float switch 13. Recin:ulatton pUmp
·--4: 9elitllf PUftlll - --14: ·Oaioniwt corlindet ·
5. Pump motor staner 15. Una ceH Raw
6. Non return valve 16. Conductivity controll11
7. Pressure relief valve 17. Conductivity meter water in
I
B. lmegrattng water meter 1B. Water condition alarm
... 9. Rate of flow meter 19. 0 2u Panicle filler
10. Two bed automatic detoniser 20. Pressure sustaining/relief valve
! .
'
;··i
---.--- -~~----------· -··-··-. -.. - ... ' . ,.
t: '' ''·. 1·4'~~
Water quality
i ,
..
The 'International Standards for ·Drinking Water' treated water is therefore not necessarily pure or sterile.
produced by the World Health Organisation defines the Centralised recirculating systems, local units, and
toxic limits for substances frequently found in water both in combination where terminal polishing is
supplies and in the UK, the Ministry of Housing required, can produce water up to 18 megohms at
Report No. 71 {4th edition 1969) recommends the 25 'C which is close to theoretical maximum.
bacterial purity standards for water suppli-ed by public Fig. AS shows a two bed recirculation system suitable
water authorities in addition to establishing procedures for providing 3 M 3/HR of deionised water up to 1
to be followed in obtaining samples. microsiemen centimetre quality.
Waters which satisfy the quality standards for human
consumption are not always suitable for certain medical. Softened water
industrial and commercial uses and may contain levels Water softening in large quantities for commercial use
of trace elements, high total dissolved solids contents, and distribution is usually carried out using one or more
non pathogenic bacteria. gases and suspended matter of the Lime or Lime/Soda processes. For domestic
which necessitates some form of treatment before the application, however, the base exchange system of
water can be used in activities such as food and softening is more commonly used and only this method
pharmaceutical preparation. brewing, research. is described. Base exchange softening operates on a
medicine and in many areas where heat generation and similar principle to the ion exchange described in
transfer take place. Deionised Water and functions by the process ·of
Chemically pure water has no free ions; its hydrogen exchanging Sodium salts for those of calcium.
ion concentration, usually known as pH value, is The action of softening can be expressed chemically as
equivalent to the hydroxyl ion concentration and on the follows:
pH scale has a value of 7 which represents neutrality. SODIUM CALCIUM CALCIUM SODIUM
This figure indicates the concentration of hydrogen ions + ,.- exchanges to +
in a litre of solution and for pure water the concentration ZEOUTE CARBuNATE ZEOUTE CARBONATE
for both types of ions being equal at 1 0 - 7 gram and that of re-generation:
molecules per litre. CALCIUM SODIUM SODIUM CALCIUM
The pH value usually being expressed as pH = log 10 + exchanges to +
1 ZEOLITE CHLORIDE · ZEOLITE CHLORIDE
+where H+ is the hydrogen ion concentration, hence · Because the base exchang1e system produces water of
H 1 zero hardness, it is often only necessary to soften part of
.•
the total wate requirement and blend the raw and
the pH of pure water is log 1o- = 7. softened water together. •
1Q-7
Water having a hydrogen ion concentration in excess of Operation of a base exchange water
10-7 gram molecules per litre will have a pH of less than softener ·
7 and will therefore tend to acidity and conversely The raw/hard water supply is connected into the top of
waters with pH of greater than 7 will tend to alkalinity. the softener tank and flows downwards under pressure
From the above it follows that pure water having no free through the bed of softening mineral {zeolite) where
· ions has poor conductivity and high resistance to the hardness is removed by the process of 'ion
electrical current. The conductivity, or its reciprocal exchange'. At the same time sediment in the water is
resistivity, of a, sample of water is a good measure filtered out and retained by the mineral bed. Clear soft
of its purity where this is concerned with dissolved water leaves the bottom of the tank into the water
ionisable solids or gases which is largely the case distribution system.
in research and laboratory applications. The softening mineral eventually becomes saturated
with hardness and no longer softens the water. ·
Deionised water Re-generation of the softening mineral is then necessary
Where water is required of a higher purity both and the process which consists of three stages is as
biologically and chemically than that supplied by the follows:
local Water Authority, single or mixed bed deionisers.
one capable of producing pure and ultra pure water (a) Backwash
approaching theoretical H 2 0. Purity being usually Reverse the water flow through the mineral bed to
measured by a conductivity moniter which measures remove accumulated sediment and wash to drain. A
the conductivity in microsiemens. backwash controller is necessary to limit the water flow
The operation of deionisation is based on using twin and thus prevent washing out the mineral bed.
bed or mixed bed columns of positive and negative
charged ionised resins such that the incoming water (b) Brine rinse
disassociates into positively charged ions such as Ordinary salt (sodium chloride) has the ability to fully
magnesium and calcium which exchange with the restore the softening capacity of the mineral. A measured
hydrogen ions of the acidic resins. amount of salt-brine is drawn from the brine tank
Likewise the negative ions of sulphate and bicarbonates through the brine injector and is rinsed slowly doyvn
<lr~ exchanged with the hydrcuyl. ions of the. alkaline
through the mineral bed to remove the hardness wh1ch .
resins. The resultant hydrogen and hydroxyl ions
·- 15 rinsed to drain. ·
combining to form theoretical H 2 0. The exhausted (c) Flushing · .
resin~ being replaced or regenerated with acid and . The water flow is again reversed to re-pack the mmeral
alkahne regenerants periodically. bed and any trace of sediment not removed by the
As the name of the process implies only ionisable backwash is flushed to drain. The softener can now be
dissolved solids and gases can be removed and the returned to normal service.
,w. ·,,
·,'
Section -~ Hot and Cold \Vater supplies
Water hammer
..
Water hammer is a pulsating type of noise which may, Basic design principles
on occasion, be heard emanating from a pipework The shock pressure waves which may be generated in
installation. The noise is caused mainly by shock waves pipes, travel at a velocity Vs which is affected both by the
which are set up when water, which is flowing at high compressibility of the water and the elasticity of the
velocity, is suddenly arrested. pipe walls.
The practical conditions which can create this adverse It can be shown mathematically that the velocity of the
effect are the too rapid closure of manual valves, or the shock wave is close to the velocity of sound under the
virtual instantaneous closure of automatic control same conditions.
valves. The time interval, in seconds, for a shock pressure wave
.. Pumped piped water supplies are also liable to water
hammer if provisions are not taken at the design stage.
to form. at the back of a valve or other arrest point is
given by:-
Plunger type pumps for example give a pulsating type of t = 2 x length of pipe
discharge which may require damping out. velocity of sound
Cases have occurred of water hammer damage
although little audible sound .was present. t= 2 XL
Premature failure of valves. joints and the loosening of ~ Vs
supports and clips are common types of damage The velocity of sound is 1450 m/s under perfect
t-:?\ associated with water hammer. ·
.v Gravity water installations do not as a rule give rise to
conditions. In the case of shock pressure waves this is
usually reduced somewhat by the conditions prevailing,
the problem but when water velocities exceed 3 m/s which must be taken into account.
water hammer conditons may exist.
The possible use on an increasing scale of pressurized Shockwave
domestic water systems in the UK could well lead to an
increase in the incidence of water hammer if proper
precautions at the design stage are not taken.
System protection .
Shock presscres in pipework supplied at high pressure
can be reduced to acceptable limits by incorporating Example
hydro-pneumatic accumulators or water hammer Calculate the time required for a shock wave to form at
arrestors in the pipeline at suitable points. a rapid closing valve in a pipe 14 · 5 metres long.
The earliest form of water hammer absorber was the Take Vs = 1450 m/s
simple air vessel or air bottle. In service these however
usually become water-logged and ineffective. unless t _ 2L
means was available to renew the air cushion. -1450
Modern hydro-pneumatic accumulators incorporate in _2 X 14·5
their design a pre-charged flexible gas bag which is - 1450
filled with air or nitrogen gas (Fig. A9}. Loss of air or gas
in service is thereby prevented. Their continuing t = 510 seconds
efficiency in service is in consequence satisfactory and
reliable. Solenoid valves of the type frequently fitted to auto-
Hydro-pneumatic "accumulators when used for this matic washing machines etc. have closure times of a
application absorb the Kinetic energy of the moving few milliseconds "i.e. 5/1000 or 2/200 seconds.
water and much of the initial shock pressure; this This type of valve can therefore be regarded as rapid
.• occurs when the nitrogen gas is compressed in the closing and liable, in some circumstances, to cause
flexible bag. shock waves to be set up when in operation particularly
2 3 .
Section_:\_ Hot and Cold water supplies
Water hammer
Fig. A 10 f!.ccumulator sizing (i) KE can vary with the square of the diameter (d 2 )
(ii) KE can vary with the square of the velocity (V 2 )
(iii) KE can vary with the length of the branch
From which we get the followrng relationships
V2 P3 • 524 + 720 - 1244 kN/m 2
(iii) New KE = KE x ~~
(ii) Compression due to shock pressures
= P2-v2n = P3-v3n These relationships have been applied to obtain the
volume of nitrogen gas for other pipe diameters,
(iii) Work done on gas = p 2 V 2 - p 3 V 3 velocities, pressures and lengths.
n-1
Aflowing for initial compression due to line pressure, Hydro-pneumatic accumulator sizing
and assuming T, = T 2 KE of 13 · 6 mm dia (15 mm N8} copper pipe when the
(constant temperature) velocity of the water .is 3 m/s and length of 15 m.
P, V, = P,·V 2 - KE = 10 Nm
470 X 100
=- For 20 mm NB
524 20 · 2 mm (actual)~
v2 = 90 em 3 2
eo-2)
Taking n = 1 · 4, (nitrogen) KE = 10 x 1_3 . 6 - 22·2 Nm
Main compression due to shock pressure
P 2 • V2 " = P 3 • V 3" I for 25 mm NB
26 · 2 mm (actual)
v2 (~:) n
0·71
v3 = = 90 X ( 524') 2
(26·2)
1244 KE = 10 x 1""J.6 - 37·0 Nm
-~90~~ =2Q_
2·38 0·71 1·854 For 32 mm NB
32·6 mm (actual)
v3 = 48·0 em 3
2
e2·6)
Work done on the nitrogen gas during compression KE = 10 x 13·6 - 57·5 Nm
stage
P 2 V 2 -P 3 V 3 For40mm NB
WD - n-1
39 · 6 mm (actual)
2
(524 90-1240 48 ·0) e9·6)
1""J.6
-
X X KE = 10 x - 85·0 Nm
(1· 4 ~ 1)10 3
For SOmm NB
(5·24 X 9-12·4 X 4·80) 51 · 6 mm (actual)
- 0·4 2
(51 ·6)
47·2-59·5 KE = 10 x .1""J.S - 144·0 Nm
- 0·4
Table A13 Accumulator sizing 1
= _12·3 cu-latelf42-m'lle8Ci~v ="'3-::m::;/::;os"'!'+"!"+""''~!'"'!',."!".-,-~(lr.I ="!!':Sj_!l!l;i.'t'""::·'i?''Pe~.~-·
6 NB
.......
0·4 Kinetic ... Volume , . Volume PDI · ·· .. ·
WD = - 30 · 6 Nm per 100 em 3 ~,P.!--!~!'.9Y ,: ···~, ~OP,,. > ;,.l.!SA/PDt..:;.·.42.m..~i,k
15 10 32 · 5 33 A
from example 3, KE for 15 m run of 15 mm pipe, 20 22·2 72·0 68 B
V = 3 m/s 25 37. 0 120 119 c
KE = 10 Nm 32 57· 5 186 187 0
Volume of nitrogen for 10 Nm of energy 40 85· 0 276 267 E
50 144 465 475 F
100
Volume= 10 x --
30·6
= 32· 6 cm 3
Volume say = 33 em 3
For 150 mm pipe, ~ = 80 (See graph A5) (ii) If thf: pipe length is altered then,
new KE ~· original KE · t
From the graph, A5 Vs= 925 m/s. V = 3 m/s
Pr = 925 X 3 Example 4
Pressure rise = 2775 kN/m 2 Calculate the volume of nitrogen gas in em 3 required to
be provided in a hydro-pneumatic accumulator which is
Example2 required to absorb the kinetic energy of water which is
Calculate the shock pressure rise when water is flowing flowing at 3 m/s through a 15 mm diameter pipe 15 m
through a 15 mm N B copper pipe at 3 m/s when the long. The line pressure is 414 kN/m 2 and the shock
water is suddenly arrested by the closure of a valve. pressure rise is not to exceed a further 620 kN/m 2 •
For 15 mm pipe. ~ = 20 (See graph AS) Note: Initial fill pressure of the gas is to be 90% of line pressure.
. Absolute. pressures have be11n 9Ptt~in!19 py i19c;ling 1 00
·- - From--the~h AS. · -vs =1125 m1s. V =. 3 m{s kN,'m; to gauge pressures.
Pr = 1225 X 3
Pressure rise = 3675 kN/m 2 (continued overleaf)
It_ will be seen from these two examples that thinner wall
ptpes reduce the pressure rise more than do rigid thick
wall pipes.
1.
l·
rv
I
-9 Its rating or in I.O.P. Lo&cEr,~ u~its.
~ ~ 16~-~ ~ ~ 227 X 1 · 8~ · The nearest single size is 267 cm 3 or POl size 'E'.
lfl l'raetiee two smaller units coopted in iam:terrrwould
Pressure rise at switch off probably be used
For 75 mm steel pipe. ¥= 15 From which 1 ;o = 95 em 3
from the graph A5. Vs = 1315 m/s Nearest size to 95 em 3 is 119 em 3
Pr = Vs V = 1315 x 1 · 8 = 2370 kN/m 2 Therefore two 11 9 em 3 accumulators could be used
=
Pr 2·370 M N/m 2 = 2·37 M.Pa coupled POl size ·c·. ·
I
Section A Hot and Cold ,,·ater ~l~J-'Plie:::
l - Water hammer
'·
I
•
0
~-----~-----~-----~~-----~----------~--~-----~-------~-----~-----~-------~~-------~~r.~----;~
- I I)
........
,. 0
0
('I
-E
>
Q)
co
3:
!• ..
Q)
;:,
II)
en
0 Q)
-- c.
l.f')
-
-
0
>
·c:;
0
a;
0 >
~-----~~~~~~-----~-------+------~--~~-----~-----~-----~-----h~~----------+---------------;0
.;)
..
.Q
£
0
-
Q)
.c
~
0
..c
• I
I
I
I
I
II" II
I
0 0 0 0 S2
U") M
"<:
""
l •
. .•
....
--·----------~·-- --~---·--
..
Graph A.6 Hydro-pneumatic; accumulator selection chart (single units)
400
I ! ;
i
I ! !
i
i l I I
·300 :
I
I
I
I
;
I
I
.II
1
' ; ; '
; '
'
I
i I
I
'
20C - I
I
I
!
i
!
:
KE(Nm) x 1oo: I
!
; i
Volume cm 3 =
29·5 Nm
I i : I
I
I I
y
I
i : I
150 I ;
i
l '
I
}·G .. '
;
:
!
:
: I I
I'
i.
I
I : . ! I
II
i
!
.•
I
1 :
!
100 ;
90 ;
' .. i / i
:
80
i i / i
i !
l 1
/e i I
v
;
70
i
,.
60
: ' '
: i - . II
J.
E
z
c: 5C
; I
!I . /1'
...,
i I
I
!
>-
...
C)
Q)
c:
Q) 40
;
/ ;
:
!
I
I
I
I
fi I
i
-~ :
a; ~ ' '
:'
I
·y,
c: ;
~ 30 ~ :
'
. . ! I
i
:' I
--~
i;.:. ::
I '
,·~·
:
.
'
.
I I
I
'
'
. I
!
20 :
. '.
.
i I
I
i
'
;
/~ ..' .
'
i I
i : II
i
y
;
15 !
' I I !
' I !
!
i
: '
I i iI
I
I
i' I
i
!i ; l
10
!
.h
I
I
I
i
I
l I l
j
I
;
i ! - ! l
l
9
L ! I
I . il '
v
l I
8
,. I l !
I !
J
i
7
i I
I
I ! I i i
0
I
! i
!
II I
I
! l I i
I T Ii
I
l
i'll
5 i I
I
I !! I !
l l
i-
Section A Hot and Cold water supplies
Water hammer
500~------~----~~mmnn~~~~~~~+---~--r-~----+--------+~~~
I I
I VUIUIIIC 1..1
KEINm)x 100.
29 . 5 Nm i v L_
l ~
400~-------r----_,---------r-----+----~,---+---r--r----r-----.r--+-----;
foDFF _ -_.
.
·-.
-- ...
. .. :'·-:
j _ - kjFL . . 1· ·:
: - •.
' 200~---+-----+--,--------+--.,.,..
I j tl I 71 . "·j· ...
__,,__---l1--.rl"--t---+--___;.--+---l
.. +-1_
I I ymF . I .
tsot-'----------+----~:----------+------+----+:~,.h~c:!j!~F--~.~~----+--------+----~
.
i /!.A
t100~----'----~~----~~------~-r~~~~--F--~~~---+--~~r---~--------+-----;
~
-~
-~
90r-----~-----+-----~
/~'~.
! I
M_~~---~~--~~-1---~~---+-------~~~-;
80~-------r----~----~,/~~----~---+---+--~--r---~--------+---r-;
~ I I I I
~
~
/e ,
70r----+---~~v-~-___;.+:--~-__,,,__~_~__,,___-+-----r---1
I I I
1
60t---'-------+-----~~------~-----+----+---+-~:----t-----r-------~-+-----;
A
sor---~~1'~--~.------~----~.--~--+~--~4---4-------~--~
I . I
~I I I
40
1 / I I 1
3o~c ·· Ij ..
1
...
,I • ;
'l
i - ..
I ..
..
...!
.. .. ~ . -· .,
- . '
I
.
~ ...
·
•I .... :-~ .
l. 500
11
400
---300
·-
..E 200
"c:
...0
~
::I
-E
::I
""co
.E
c:
Cl)
C)
-...
0
·c:
-
0
Cl)
E
::I
10~--------------~--------~--------~------_.----------~------...
15 20 25 32 40 so . ·6s
• . . ..
~
.. .
• ; .
. ; ., ..,..
':
' ~.
Section 1i. Hot and Cold \Vater supplies
Table A16 Dimensions of galvanised mild steel cisterns· and covers·io BS 417: Part .2 : 1973 .
1 2 I3 I 4
Dimensions of cisterns
5 I 6
.•
. 7 ·r
.8
..
Minimum thickness of
9I 10 '. 11 12 1
"·
Capacity Distance stcaJ·belote galvani~ing·, --~ ~~-~-:t. &overs
. . . ..
.::_
.. ·-.··. ..........
...
y.. to of water for cisteti'ls ~rid co~ers . · .. .. ...
water line from
BS type Lengtht Width Depth line top; Grade A Grade B Covers No.• of·.. , ..si~e of pieces
reference•
L w ' D c WL ... .
cisterns cisterns · · .· for · pi~ces:
' :cisterns .·. - .. J. ength. Width
..
mm mm mm htres mm mm . ; ..mm: ·mm ·. .-mm mm
....
SCM 45 457 305 305 18 ·111 1 ·6 1··2 LO 1 482 330
SCM 70 610 ·305. 381' .. 36 111 1·6 1·2 ..1·0 1 -635 . .... 330_
SCM 90 610 406 371 111 1·6. 1·2 1·0 1 635 432
SCM 110 610 432 432 68 114 1·6 1·2 1·0 1 635 457
SCM 135 610 457 482 86 114 1 ·6 1·2 1 ;o 1 •• 0 -~35-· . .-:_ ·482
SCM 180 686 508 508 114 114 1·6 1·2 1·0 1 "71"1 533"
SCM 230 736 559 559 114 . 2··0 1·6 1·0 .
SCM 270 762 584 610 191 114 2·0 1 ·6 1 . () 1 . 787j /. {5.1 0
SCM 320 914 610 584 114 2·0 . 1 ·6 t·G
SCM 360 914 660 610 264 114 2·0 .. 1 ·6 1·0 , . ·;. 940 .. · ·. 6~6
SCM 450/1 1219 610 610 114 2·0 1 ·6 1·0
SCM 450/2 965 686 686 114 2·0 1 ·6 1·0
SCM 570 965 762 787 146 2·:5 :2·0 . 1':2.
SCM 680 1092 864 736 491 146. 2:5 2·0 .1-:b.'··
SCM 910 1168 889 889 709 146 2·5 .-2·0 . 1 '2
~ I SCM 1130 1524 914 813 . 841 146 2·5 9 2·0 ··1·2 1 .1549_.· .··· .940
r, SCM 1600 ·· .·914 :787 . ·. ::1'175§
1 I 1524 . 1143 1227 146 3·~ 2·5 1 ·6 2
H SCM 2270
·SCM 2720
1829
1829
1219
1219
1016
1219
1727 146 . 3·2 2·5 1 ·6
1 ·6.
2 9.40 .. :: ·1251 §
. 940 -~·.1251 §
2137 1.90 3·2 . 2·5
r 1-·
I" , 5eM4540
;;~~~e;i~~.should
2438 1oz.f. 1219 3354 - 254 ' 4·8 '3';2 1·6 · B3B· .-- 1551>§ .
1
r be ordered by the BS type reierence tc avo;d a :'These dimensions w_ere de.tcrmine'd.Jo; the dt:pths n.~c~r~r to
. ac~ommodate ballvalve. inte"t and overi)o,w~.kipf~ i,iJ\!IIea" sizet
, tFor welded cisterns. the length may be increased by net more m.ely to be used. pnd in th,e p~sitions. to sat,s!Y·:Wat.~r I?,YY.I~~s.
, than 25 mm. The dimj!nsions have been used: in calculatintf the :1!,p.a~·~•.es.
§The _dimension i_s for'the lap~i~~pieee iJ;~~~~.~!.~~~~ ~:~!~~·
I :
r ~ . .. , ....
-
I
']
..2~.-
.....
. .
'>?
. ·•
.: .
.. ·'· ; ·. . . ·.. : : ·,:- :._:::.. :-t;·(~.~;:~·?i;:i:~~~~;.
"' ..
TableA17 Po/yolefin or Olefin Copolymer Cisterns (Polythene or Polypropylene) to BS 4213: 1975
BSType Capacity to Distance of water Minimum• Maximum Minimum
reference water line line from top thickness height weight
litres mm mm mm kg
PC 4 18 110 1·4 310 1·36
PC 8 36 110 1·4 '· 380 1 ~ 81
PC 15 68 115 2·1 430 2·95
I.
PC 20 91 115 2·1 510 3·18
PC 25 114 115 2·1 560 3·40
PC 40 182 115 2·1 610 6·35
PC 50 227 115 2·1 660 7·03
PC 60 273 115 2·1 660 ·7·26
. PC 70 318 115 2·1 660 9·07 .
PC100 455 115 2·1 760 12·70
I' "'In th~ cas€' of Cl~!!?rns c~ €S li:r;~ C.?::c:::-r·.· cr·= a:0ve m~-- ;,.·.:a:t:.:~:
ed from ~ohrtr.e;.t: o~ de~.!:.it:o- of C· &..: ;: ·:r.; i);'ld ct.: .. ::. ~~-~
rr1i:1in1:.:!·n tl,ickncss rr,ay be rtd~:C:-c t~ i C i:"",:r,.
I Thickness of steel
Grade A Grade B
Outside dimensions Test pressure Test pressure
• (hand hole at top) 69 kN/m 2 52 kN/m 2
BS type Length Width Depth Capacity Max. working head Max. working head
reference ofwater:4·5m* of water: 3·0 m•
mm mm mm litres mm mm
>•
TM 114/1 610 432 432 95 3·2 2·5
TM 114/2 610 9H> 305 3·2 - 4·~-
~
., TM 136/1 610 457 482 114 3·2 2·5
TM 136/2 610 610 381 123 3·2 2·5
TM 182 686 508 508 155 3·2 2·5 "
• •The working head is the vertica; distance b!tween the bottom
. ·.. , , .:. of the tank and the water line of the cistern supplying thi tanl...
1;: .-~:p:<:?t:::.~ -~
11 > ' 0 • .. '
.~ -.
.
·('
~~
..
· Cyliridars "
The method of calculating the capacity in litres of a that the dimension up to the shoulder of the cylinder is
cylinder with flat en.ds is as follows: taken as the height. . . . .
~ Internal diameter of cylinder -in metres squared Y Example Determine the capaCity in litres of an upright
0·7a~ x· heigHt in metres x 1000. . _· · cylinder 1200 mm high (to the shoulder) and 508 miT
As the capacity of the domed top and the dished bottom internal diameter. ·.
::::f>f an u~right cylinder are roughly_ equal, one com- Capacity·. 0·508 X 0·508 X 0·7854 X 1·2 X 1000
pensates· for the other and the above method can be = 243 litres. :
used to determine the approximate capacity, provided The sizes of standard cylinders are given in the follow-
~g~~- ' •
-
water: 3Dmt water: 11at water: !•t H L P ihread
B A
1I YM 491
mm
381
mm
762
litres
73
mm
2·0
mm mm mm
584 102 159
in.
,..
!
YM 114 381 991 100 3·2 2·5 762 102 159 1
:·;
I
YM 127 457 787 114 3·2 2-5 2·0 584 102 159
YM 141 457 838 123 2·0 635 102 159~
I YM 150 457 914 136 3·2 2·0 686 102 159 1
I YM177 '457 1067 159 813 102 159 H
813 102 159 H:
:i YM218
YM264
508
508
1067
1295
195
241 3·2 991 102 159 H
i
YM 355 · 610 1219 332 4-8 3-2 914 127 159 1!
YM 455 610 1600 441 2·5 1194 127 159 1!
I
l
i
•Cylinders shouid be ordered b\· tile SS type reference to avo'c
confusion.
§To obtain the approxim<=!e outside d:a:-neter, ,add 13 m:!' fc~
qhe workino head shall be the vertical a:stance between the
botton' cf th; cylinder and the water line ct the cistern supplyin2
the cylinder.
welded seams. and 25 mm for rivetifd seams.
*Th6 v·:od.l!"l£: ~ead is 1h~ ven;~a: C:;5tcr,ce bt:~\~t·t-::l'i the b:::c:n +E>:terna! BSP.F threads may be s;;p:>iied v:hen so crde~ed.
of the cy!ir.d~' and tht: water !ine oi the cistern s;.:pply'n; t~•& §Preferred sizes for new insta~istior.s in dwellings.
cylinder.
**The numeta~5 in these ccsicnatior.s rqm:sen: t!":<> nomina: s:ze
of the threacs. ' -
Table A22a Double feed copper indirect cylinders to BS 1566: Part 1: 1972
Test pressure Muimum working head• or pressure
Grade of cylinder Primary heater Complete Primary heater Complete
Coil Annular cylinder Coil Annular cylinder
kPa• kPa kPa kPa m m
700 220 350 350 15 15
700 145 145 350 10 10
...
. :.' .·.··
··-~~~----~.-f.~~~-~:~::;,;~::;.;;:~ki~·f~il~~:E~;-------
Section ~A;,. Hot and Cold v.Tater supplies
:-
Cylinders
..
., " Table A23 Single feed copper indirect cylinders to BS 1566: Part 2 1972 (Drawing 'A·;
mm mm lilres m2 mm mm mm mm mm mm mm mm in in
31 400 1050 104 '0·63 0·9 1·6 0·55 0·7. 1·2 0·55 140 100 G1 G1 B
5 450 750 86 0·52 1·0 1·6 0·55 · 0·7 1·2 0·55 140 100 G1 G1 B
71 450 900 108 0·66 1·0 1·6 0·55 0·7· 1·2 0·55 140 100 G1 G1 8
) -
81 450 ;o5o 130 0·78 1-0 1·6 o-55 ·. 0·7 1-2 0·55 150 100 G1i GliB
.SJ 450 1200 152 0·91 1·0 1·6 0·55 ·. 0·7 1·2 0·55 150 100 GH GHB
,1 _ ....... __ .•. 10 ... _.soo 1200 1so 1·13 1-2 1·8 o-55 0'9 :1-e 0·5s 180 150 G1i
i · t.:'\ . •Cylinders should be ordered by the ES type referer>ces. . :te:2ss 5 exterr>a: thruos ma; ~supplied-when so o•oe•ed.
: \ij ·
~ ~Ttoe"":'rking·heal>is tM Ytrtical oostance t!F'" the bonom !'llhe-1:-;iindet-to the -:· .•--t?reiefree sized or n~w-installr.icms m ttwel!mgs ··- -:- --·· .. - . .:...•___ · ; "7.~
[" -~ · --···:water ltne.of the.~ost~.s~;:p!y.ns.;_.r. 11. m'i'O •..1.0 ~J\:m'-J--~-,- .. .·.. ;----:7. ::>· .- -c -·: .'.. . · .... · · ·· ,. ·' ....... C: · ·· · ::- -.......
·-·~--c·":-.--.,......,,-
· . .·' -~ .. ~..:..:-- .......
_;,...
~- A ··> :-
.lndir~ct :&.
... --·
\
cv!·nO!!r . ___ :~....
- ·a..,.ang~d'
for combined
immersion
.~ -· ~~:-
~at&• and ·,
. ~ ~-
.
thermostat
.,.
-, -mounted ..
··.· ~
"K--..._...1..-T-Ij"--A+--""'"I~-...-~ h~rizontalfy ..
·--. i.."
-~ .
.' .. . . .
f~ 6~~
Jndire:t cvlind~
arran<;~edfor
\. vert;cally-mcunted
immers:on heater
TableA24 Double feed copper indirect cylinders to BS 1566:Part 1 (coil type)(Drawings ·s· ~n_d ·c·;_·J·
Minimum tbickn- of copper sheet • Coil
before forming primary Heights -of acrewed
i'! . heater connections
Grade2 Grade3 test
British External Storage pressure Designation Designation
r:_o:':. Standard External height capac- Heating
. type diameter (over lty•• surface
Test preuure:
2·20barU
Test pressure:
1·45bu::
7·00bar H: J
Maximum
L M P of
acrewed
of
, primary
I~ reference• dpme) working connections beater
Maximum worlr.ing Maxium working pr...ure connections
bead:15mt ~ .'bead:10mt 3·50bar::
~t;-
'
·· ·
.. 'compression fittings and capillary fittings or by silver
brazing orby suitable methods of welding, designated
Table X.
capillary frttings or non-manipulative compressio>
fittings, designated Table Z. (These tubes are· nc
·recommended for bending). ·
:h . .
(2) Half hard copper tubes in straight lengths and The tubes are supplied in one of the followir.
1.L ·annealed copper tubes in coils suitable for burying conditions:
· j-:. underground and for connection by means of com- H As drawn. . fH Half hard. 0 Anneale
;·;:. Table A25 Dimensions and working pressures for half hard, light gauge copper tubes
'._,. to BS 2871:1971 Table X Part 1 . ·
l ,'_:
'il': .
: ; .· 28 28·055 27·975 . 0·9 . 40.
\t~:.
35 35·07 34·.99 •. . 1·2 42
42 42·07 41·99 '1·2 35
54 54·07 53·99 1·2 27
.67 66·75 66·60 1·2 20'
76·1 . 76·30 . 76·15 . 1·5 24
108 108·25 108·00 1·5 17'
133 133·50 133·25 1·5 14
159 159·50 159·25 2·0 15
•sased on material in tH condition at 65'C
·Table A26 CJimensions and working pressures · .Table A27 Dimensions and working pressures
for half hard and annealed copper tubes · · for hard drawn thin wall copper tubes
to BS 2871 : 1971 Table Y Part 1 to BS 2871 : 1971 Table Z Part 1
Outside dlam•ter Maximum Maximum Size Outsid• diameter Maximum
Size Nominal working wortUng of Nominal working
of thickness preasurH pressures tube maximum minimum thickness· p....aures •
tube iH 0 mm mm mm mm bar
maximum minimum condition• conditiont
·mm mm mm mm bar bar 6 6·045 5·965 0·5 .-113
6 6·045 5·965 0·8 188 144 8 '8·045 7·965 0·5 . 98
.·.a 8·045 7·965 0·8 136 105 10 10·045 9·965 0·5 . 78
0 c 10 10·045 9·965 0·8. 106 •82 12 .. '- :·12·045 ... 11·965 ...... 0·5 .... :~.-64.
.:. ;;12 12·045 11·965 0·8 87 67 15 15·045 14·965 .· 0·5 ° ··.:.:50
15 15·045 14·965 1·0 87 67 18 18·045 ·17·965 0·6 . 50
. ··:18 . 22·055 . 21·975 0·6 41
: ;·
18·045 17·965 1·0 72 55 22
. ;._~:22 22·055 21·975 1·2 69 57 .28 . 28·055 27·975 .. 0·6 ·.<:32 .
28 28·055 27·975 1·2 55 42 35 .. 35·07 . 34·99 0·7 :,; .30
42 .. 42·07 .. 41··99 {0·8 .·.28
Section-~ Hot and Cold '\Vatm· supplies
... Tubes ..
Table A28 Internal diameters, weights and capacities of copper tubes to BS 2871: Part 1 : 1971
Table X Table Y Table Z
0.0. Approx. Approx. Approx. Approx.
size equivalent Internal weight Capacity Internal weight Capacity Internal weight Capacity
dia. perm·· perm dia. perm perm dia. perm perm
mm in. mm kg litres mm kg litres mm kg litres
6 4'80 0·0911 0·0181 4·40 0 ·1171 0·{)152 5·00 0·0774 0·0196
8 .L
4 6·80 0·1246 0·0363 6·40 0·1617 0·0322 7·00 0·1054 0·0385
10 8·80 0·1580 0·0608 8·40 0·2064 0·0554 9·00 0·1334 0·0636
12 .1
• 10·80 0·1914 0·0916 10·40 0·2511 0·0849 11·00 0·1612 . 0·0950
15 t 13·60 0·2796 0·1452 13·00 0·3923 0·1326 14·00 0·2031 0·1539
18 ~
e 16·40 0·3852 0·2112 16·00 0·4760 0·2010 16·80 0·2918 0·2217
22 .1
4 . 20·22 0·5308 0·3211 19·62 0·6974 0·3024 20·82 0·3589 0·3405
28 1 26·22 0·6814 0·5399 .25·62 0·8985 0·5153 26·82 0·4594 0·5648
35 H 32·63. 1 ·1334 0·8362 32·03 1·4065 0·8056 33·63 0·6701 0·8882
42 1t 39·63 1·3675 1·233 39·03.. 1·6996 1·196 40·43 0·9216 1·283
!
j 54 2 51·63 1·7691 2·093 50•03 2·9052 1·966 52·23 1·3343 2·142
:1 67 2t 64·27 3·244 63·07 "3·124 64·67 3·285
': ~ 76·1 3 73·22 3·1287 4·210 72·22 4·1437 4·096 . 73·82 2·5131 4·281
) i
108 4 105·12 4·4666 8·67~ 103·12 7·3745 8·328 105·72 3·5834 8·772
i
II : 133
1 5 130·38 5·5151 13·411 130·38 5·5151 13·411
I
i
159 6 155·38 8·n95 18·962 ·.
- 156·38 6·6056 19·206
' I
1\c:<. 11 shouid t= ;-;c.:ec ;;-.:· :--; ·.·.~';:"'.:s ~:\·e~ c•~· •:::·
tl-" , .. :: \VC:C!' a~ this tE:n~:£:rf.L.:re v.. i:! be thE s:..--'"':"_ o: th& secc:-:d ar.ci t~.:,:
~ i on!y and not the\\ o::if:r::~ \':~-'= .. • ;: \". :~. -..·:ater. A':- i :.:~~ ~~ \·. :::~: · c.::J:-:-:ns (i.f:. vvt-:-2ht per rn - cap.=.:·:·: ~:-:r m) lis!€d fo: ec-:·
a! 4 · C v.·ti g hs i ~ s- 1~.::. v.·::: ~ ~·: :_ =
• ~ =-~· r:-:e:re- c~ ~ ~~~~ f1 1 ,~ v. -.. - c!as~ oi tub.;:.
l.
j i
~
.
·,
. Light gauge stainless steel tubes
Light gauge stainless ste,el tubes to BS 4127: Part 2:
1972 are suitable for use in systems where the working
( pressures do not exceed 13 bar.
I Size of ~ube
maximum
Outside diameter
minimum
Nominal•
thickness
~
f 28
35
28·055
35·07
27·950
34·965
0·8
1·0
,' ~- 42 42·07 41·965 1·1
:-. ;. 1!: . ~ •
;, ,,,c- .. . . .
~
-~~~f?jecna-
. :;,-o%
. tole: a-nee.----- - - - - · - - - - - ... - - - - . --
:
Ste~l Tubes.· .
Steel tubes to BS 1387: 1967 Steel tubes and tubulars Tubes are available either black or galvanized. Tubes
suitable for screwing to BS 21 pipe threads, are made i in. (6 mm) nominal bore are not galvanized intema
in two thicknesses which are designated Medium and They are normally supplied in random lengths of fn
Heavy. These are distinguished by the following colour 4 m to 7 m (13ft. to 23ft.).
bands- on the pipes:
Medium tubes blue
•Heavy tubes red
Table A30 Internal diameters and capacities of medium and heavy black steel tubes to BS 1387:19£;;
and weights when filled with water at 4?C
Medium Heavy
· Nominal Internal Capacity Weight perm Internal Capacity Weight per in
bore diameter per metre when filled diameter per metre · when filled
with water with water
. mm in mm litres kg mm litres kg
6 i 6·1 0·0293 0·4393 4·8 0·0181 0·5141
. - .8
. 10
-··'-·*· ··- 8·9
:.12·4
- 0:.0622
: 0·1208
.0·7162
. . 0-9788 .·
7·8
11'·3 ..
0:0418 ....
. ·. "0·1 003 . ·. -~- .. '·1 ~-1303.
•
0~8208
i
15 t 16·1 0·2035 1-4335 .... '14·9 -• o:1744 ; :..·.~-1·6344'·
20. .. l . 21·6 0·3665 1·9565 '2Q·4. :2·2368
··- 0·3268
···-- 25 .. ... 0·5187 . 3·5087
1 27·3 . 0·5855 3·0455 .25·7
32 1l 36·0 ·1·018 . 4·188 . 34·4 . 0·9296 . ;·;.·.4·7996.
40 1-! 41·9 1·379 5·029 40·3 .. 1.·276 5~746
. •50 2 53,0 2·225 ·.. 7·395 51·3 . 2,066 ·; 8~306 ...
65 2-! 68·7 . 3•708 10·338 . 67·0 3·526 11·546
'"
._ ... :- 75 3 80·7 5·116 13·756 79·1 . 4·915 15·215
100 4 105·1 8·676 21-076 103·3 8·381 23·081
-~~H.- 125 5 129·95 13·263 29·963 128·85 13·039 31·339·
·~1
150 6 155·4 18·~67 38-767 154·3 18·699 . 40·499
·Note: In calculating the weight per metre of filled tubes. the
weight of screwed and socketed tubes has been used.
-~: .
. ~
:;
......:.
!-,·~
.•·
-. ~-:
\:~~,,--· ·-
..~-:~-~
><·'·•
-_ ...
.. .. ~· . ··-~, . ~;~~:"'•
.. - : ~ ::~:''~;::~.:~i~;~f~~i -
1- • ·•
:[. -~~:-;;;.:
;::-,-.:.:.:/; - ·:-·-- ··..
' :?·_:•;-!
lt~i}{:.' . .::·.
· ....
. . . r ..
0 ~·. • •. i
TableA31 Polythene Pipe (Type 50) for cold water services toSS 3284 :'"1967
Wall thickness
Class C Class D
Nominal OutsJde 0·89 MN/m 2 1·20 MN/m 2
size diameter 130 lbf/in 2 173 lbf/in 2
300ft. head 400ft. head
min. max. min. max. min. max.
1 mm in. mm mm mm mm mm mm
I
I
Unplasticized PVC Pipes
The dimensions and maximum working pressures of
uPVC pipe for cold water services are laid down in the
following table.
l The dimensions for uPVC pipe for other purposes are
set out in BS 3506: 1969 Unplasticized PVC pipe for
industrial purposes. ·.
Table A33 Unplasticized PVC pipe for cold water services to BS 3505: 1968
Nominal Mean Wall thickness
size outside Class B Class C Class 7
Class D Class E
diameter Averaged Individual Averaged Individual Averaged Individual Maximum Averaged Individual
l: sustained
working
min. max. max. min. max. max. min. mu. max. min. max. max. min. mu. min. max. pressure
1
in mm mm mm mm mm mm mm mm mm.. mm mm mm mm mm mm mm liar
I
i 17·0 17-3 • 1-9 1-5 1-9 3-2 3-5 44
J 7\ l 21-2 21·5:--~----------....,--------~---....--::"2·~1--:1-:;·7:---::2:-::·1:---::3:-::·7=---4-=-·-=-1-...,._..,.40::---
::.J
i ~~:: ~~...,:~---- - - - - -......----..,.------------::}.-:-~--=-!:-=-~--:-~:-=~-!-=-~=-9--:-::-=~---,--=:=--
~-:-:12,..-----4·2 -142....,.·4--------....--------=-2""'·7---=-2·"""2-...,2:-::·7=""·-3""'·2=--'""'"2""'·7=---'-=-3·.,..2-4.,....·8~--=-5.-::-3--2=-=a--
--1=-i-..,-_48--1-·- 48-·4. --- 3·0 2-5 3·0 3-7 3·1 3-7 5·1 5·6 25
--7 2~~6=-o-~2----=6o=--=-5-----------=-3--=o---..,-2~-5=--~3-=-·o-~3-~7-~3~.1~-e-~~-7......~4...,.·5--3~-9=---4-=--5=---::5:-::·8=---6=""·1=--....-n~-
-~2i-.~~~~--------------=-3·75--~3~-&~~3-=-5--4·~.=-5-..,-3=-·9=----=4-=·5--:;5-=~--::4-::·8....,....-=5"·~5---------
3 88'7 8!H 3·4 2·9 3·4 4-1 3-5 4-1 5·3 4-6 5·3 6·5 5-7 6·6
_ _,_4--:-1-:'-14;..,-1,..---:-11.4 ·5 4·0 3·4 4-o=---...,5--=-2---:-4.-=-5,-...,5,....,·2---=-&~-8-~6-~o-....:6;...:·9;._...,8'"'·3:---...,7'"'·3:!---8:-·4~---------
5* 140·0 140·4 4-4 3·8 4-4 6·3 . 5-5 6·4 8·3 7-3. 8-4 10·1 9·0 .. 10·4
6 ""'1:-::6-=-8--=-o-1:-::&8·5·--=-5-=--2--4""'·5=----=-5--=-2......-:7"'"·5...;._-...,..6·~6:--=7~-6=----:-9..;·9---=-8·-=-8-1,..,D""·2--:..:12,...,·1,----:-:1o~-8,.----:-:12'""'·5=----------
J ---=-7·--1...,.9-:-3.-=-5 194 -o 6·O 5·2 6·0 ·--::8:-::·1:----=1.-=,.,...·....-a=--s=--..,-1~1-=·4......-:1:-=o-=-·1~.-:-:11:-:-:;7=---=-13=-·s=---=-12;:-·4-=---=14-=-·=-3- - - - - - . . , . -
--···a--2-18·8:---=-2=-=19:-:·4:---=-s-,..1 5·3 6·1 8·8 H s-o tt-& 10·3 11-a 14·1 12-6 tH
-9--244:; 244·8 6·7 5·9 6·8 -:-9.-:-8--B,_,·J~-1..:0..:·0-..:1.;...2·.:.9.-~11:...·5~--1;.:.3~-3-1:,.;:5...,:·8-1,..:4-:·1--""16,..:·3:--------
---l0---2j2:-s-27J:4-T5--6-S---7-B~--=-9--:9~~7:-- 11-2 14-3 1z.a 14-B tH'--=-=15:-::-7::--:-:18:-::·1....,....-------
12 323·4 324·3 8·8 7-8 9·0 1~2..;·9---=n"'"'·=-5-~13,....:-3;._.,..,1-=7~-o--:1-:-5·-=-2-1~7,..:·5=--7o2o,...,·8=---:-:18:-:·7=---:-:21,...,·6=---------
14 355·0 356·0 9·6 8·5 9·8 ' 14-1 12-6 14-5 18·8 16-7 19·2 22·8 20·5 23·6
16 405·9 40&·9--1o-:9-9-"f". ---o-:11,...,·2:-'-:1:-:-6-=-·2--=1-:-4--=-s-~1&:-:-7=--'""'2..:1..:·1-....,1-:9-·-=-o-7o21,...,·9:---.:,.2s'"'-o--:-:23:--4,.---=:27=-·o=---------
1B 456·7 457·7 12·3 11·0 12·7 18·2 · 16'3 18·5 23-8 21-4 24-6 -'
-2il____ 5.o7:s- 5o8:s-13"·7--tf.214-12ii"·-:-2-~18:-·1=----2..:o--=-9-,.;;..:...~~___;;.;._____;:.___ _ _ _ _ _ _ _ _ _ _ __
22 55s~3s5·a-:-3-tS.013-4--t5T--iZ:1 19·9 2z.a
1 ~) -24-- 609-i 610·1 16·3 14·& 1-=-6·7
8--=-24,..·1=---2~1...,.·7,---....,25:-:--:,·o----------.,..---------------
I ..o..:..•
I
J
.
I - -·- ~------------·-"·--------
·'
-.
·.. · ·.:
Section A Hot and Cold water supplies
Tubes
~
.. .
Asbestos-cement pressure pipes ..
Asbestos-cement pressure pipes to ss" 486: 1973 are
<» ••. . .·;;;
available in the following •engths. Other lengths are ·
supplied on request.
-... ~-.
,p .
Table A34 Lentiths of pipes •fS··
....
lI·'
l" -:·.~
"I .• 50 and 75 3
i: 100 to 250 3 or4 } +5
-20
I.
,J! · 300 to 900 4 or 5
.} The classification. test pressure and dimensions of asbestos
· ···cement-pressure pipes are given in- the following table. . ··-- .,._ ~
mm mm mm mm mm
50 69 ·o-6
75
100
96
122
0·6
0·6 .
150 177 177 0·6
200 232 232 240 0·6-
225 259' ._259 268 ·o-6
250 286 286 295 0·6
300 334 345 356 :0·6.
350 392 405 419 ..0·8
400 448 463 478 ··o·8 •.
..
.··: .·....
- .: ·~·
,:- -~ :; .· ,,,iicN;t~~~!;f}~i;J~
o.
-
·······--:·
:.-··:~::~~~;5~~::}_::~·.:. '
Lead pipes
Lead pipes and lead-silver-copper ailey pipes are now The following tables set out the recommended sizes
designated by Code Numbers ranging from Code 1 to and working pressures for lead pipes for hot and cold
Code 29, full details of which are contained in BS 602 & water services.
1085: 1970 Lead and alloy pipes for other than chemical
purposes.
11
Tubes
.;
Table A40 Centrifugally cast (spun) iron pressure pipes for water, gas and sewage
to BS 121.1 : 1958 standard thicknesses, external diameter and weight per metre of barrel
Class 8 Class C Class 0
... Nominal Works test pressure 3447 kN/m 2 Works test pressure 3447 kN/m 2 Works test pressure 3447 kN/m 2
internal Field test pressure 122m head Field test pressure 183 m head Field test pressure 244 m head
diameter External Weight External Weight External Weight
of pipe Thickness die. perm Thickness dia. perm Thickness dia. perm
I • of barrel of barrel of barrel
I
0
mm mm mm k!l rnm mm kg " mm mm kg
75 7·4 9·5 14·45 7·4 95·5 14·45 7·6 95·5 14·91
~ ' . 100 7·6 121 ·9 19·39 7·9 121·9 19·99 8·9 121 ·9 22·37
125 7·9 149·9 24·88 8·6 149·9 27·14 9·9 149·9 30·87
150 8·4 177·3 31·52 9·4 177·3 35·12 10·9 177·3 40·45
175 . 8·6 204·7 37·70 10·2 204·7 44·01 11·7 204·7 50·21
200; 9·1 232·2 45·39 10·9 232·2 53·80 12·4 232·2 60·88
225 .-. 9·4 259·1 52·24 ,11 ·4 259~1 ~ 63··01 13·2. 259·1 72·30
250 -) 9·9 286·0 60·88 h1·9 286·0 72·83 14·0 286·0 84·61
-300 '·10·9 333·8 78·49 - 13·2 ·- 345·4 - 97·69 15·2- -- 345·4. 112·04
350 11·7 386·6 97·52 14·2 399·3 121 ·.93 16·5 399·3 140·70
375 11·9 413·0 106·60 14·7 426·2 134·95 17·0 426·2 155·03.
400 12·4 439·4 118·30 15·2 453·1 148·57 17·5 453·1 169·96
450 13·2 492·3 140·86 16·3 507·0 177·59 . 18·8 507·0 204·28
500 14·0 545·1 165·18 17·0 560·3 205·84. 19·6 560·3 235·46
525 14·2 571 ·5 176·48 17·5 587·3 222·30 20·3 587·3 256·47
600 15·2 650·2 215·44 18·8 667·0 271·25 21 ·6 667·0 310·23
675 17·3 729·0 274·43 21;1 746·8 341·55 24·4 746·8 393·20
The above are metric equivalents only, of the dimensions given in BS 1211: 1958 which are the standard dimens•ons.
,.
e DE DE e
ti "l
--· D:N-·· I
5·5 m
Class K9
-
,
J
' - 1-
.I
-c-:--D:N-- :
Class K12
- t --$·
Nominal
internal DE e Approx. mass Mass of pipe DE e Approx. mass Individual flange mass
diameter perm of including perm of
ON pipe barrel socket pipe barrel NP10 NP16 NP25 NP40
mm mm mm kg kg mm mm kg . kg kg kg kg
80 98 6·0 12·2 75 98 7·0 14·1 2·9 2·9 2·9 2·9
100 118 6·1 15·1 92 118 7·2 17·7 3·3 3·3 3·8 3 8
150 170 6·3 22·8 137 170 7·8 28·0 4·9 4·9 5·9 7·9
200 222 6·4 30·6 184 222 8·4 39·7 6·8 6·6 8·7 13·4
250 274 6·8 40·2 240 .. 274 9·0 52·.8 - 9·6 9·2 ..13·.1 .21·7
300 326 7·2 50·8 306 326 9·6 67·3 12·8 12·4 18·0 31 ·3
350 378 7·7 63·2 381 37810·2 83·1 14·1 17·2 25·5 -
400 429 8·1 75·5 454 429 10·8 100·0 16·3 21·9 33·2 -
450
500
480
532
8·6
9·0
89·8
104·3
543
634
480
532
11·4 118·3
12·0 138·2
18·1 26·7 42·2
21·8 37·0 48·7 -
-
600
700
635
738
9·9
10·8
137·1
173·9
835
1060
635
-738
13·2 181 ·8
230·8 40·5
30·8 57·3 71 ·5
'55·6 - - ·-
-
800 ,842 11·7 215·2 1312 842 15·6 .. 285·5 -. 54·8 74·0 - --.
1000
900 -945
1048
12--6
13·5
260-·2 --
309·3
1'590'
1894
945' l6·8' '345·4
1048 18·0 410·6
64·3 88·2
81 ·4 122·9
-- --
1100
1200
1152
1255
14·4
15·3
362·8
420·1
2220
2573
1152 19·2 481 ·7 . 98·7 1-41 ·4 -
1255. 20·4 557·8 .. 120·7 185·1 - - -
Note: Standard pipes with east-on flanges are normally supplied only m ·
· . short lengths; lengths available can vary dependent on source of supply;· :-~·.
-. ••_...
:
.
.. <.
·-~·:· ~"":..·.:_.:-~,-:.~.-.·.·.-.· ~·. ... :..
,• • ' . . ·,
'••,•.
~~~:,;.' ;·:: .
~··,. .. ~'
~.
·: •• l
· '. :_ :, -.. :':;: : .-: ';:· .<,~~~::f-iE~~~:}'~i_;J~:}~:~i~}l·· ,._.'· '(·;~;%:~e_~::
"'Table A41a · Standard flanges
Nominal Pitch
internal c:irc:le Bolt holes
diameter diameter
ON D c g a b c Number d s Radius Mass
mm mm mm mm mm mm mm mm mm mm kg
Type: r~ P.1 0
80 200 160 133 19·0 16·0 3 8 19 15·0 6 2·9
100 220 180 153 19·0 16·0 3 8 19 15·0 6 3·3
150 285 240 209 19·0 16·0 3 8 23 15·0 6 4·9
200 340 295 264 20·0 17·0 3 8 23 16·0 8 6·8
250 400 350 319 22·0 19·0 3 12 23 17·5 8 9·6
300 455 400 367 24·5 20·5 4 12 23 19·5 8 12·8
350 505 460 427 24·5 20·5 4 16 23 19·5 8 14·1
400 565 515 477 24·5 20·5 4 16 28 19·5 10 16·3
450 615 565 527 ~25·5. 21 ·5 4 20 28 20·5 10 18 ·1
500 670 620 582 26·5 22·5 4 20 28 21·0 10 21·8
D . 600
700
800
780
895
1015
725
840
950
682
797
904
30·0
32·5
35·0
25·0
27·5
30·0
5
5
5
20
24
24
31
31
34
24·0
26·0
28·0
10 30·8
10 40·5
10 54·8
900 1115 1050 1004 37·5 32·5 5 28 34 30·0 10 64·3
1000 1230 1160 1111 40·0 35·0 5 28 37 32·0 10 81 ·4
1100 1340 1270 1221 42·5 37.~ 5 5 32 37 34·0 10 . 98·7
1200 1455 1380 1328 45·0 40'·0 5 32 40 36·0 10 120·7
Type 1~P!6
Type NP25
80 200 160 133 19·0 16·0 3 8 19 17 6 2·9
100 235 190 159 19·0 16·0 3 8 23 17 6 3·8
150 300 250 214 20·0 17·0 3 8 28 18 6 5·9
200 360 310 274 22·0 19·0 3 12 28 20 8 8·7
250 425 370 331 24·5 21 ·5 3 12 31 22 8 13 ·1
300 485 430 389 27·5 23·5 4 16 31 25 8 18·0
350 555 490 446 30·0 26·0 4 16 34 27 8 25·5
400 620 550 503 32·0 28·0 4 16 37 29 10 33·2
450 670 600 553 34·5 30·5 4 20 37 31 10 42·2
500 730 660 613 36·5 32·5 4 20 37 33 10 48·7
600 845 770 718 42·0 37·0 5 20 40 38 10 71·5
Type NP40
80 200 - 160 -133 -19·0 16-·0 3 i . 1~. 17·0 - 6 2·9
100 235 190 159 19·0 16·0 3 8 23 17·0 6 3·8
150 300 250 214 26·0 23·0 3 8 28 19·0 6 7·9
200 375 320 281 30·0 27·0 3 12 31 20·0 8 13·4
200 450 385 343 34·0 31·0 3 12 34 22·5 8 21·7
300 515 450 406 39·5 35·5 4 16 34 25·0 8 31·3
____ _, __ ,.......... _____________
_. ____ .
---------··------------------~------ -------·- ---- ----·--·· --·----
:·'.
Section A Hot and Cold w·ater supplies
Tubes
.:· .
Table A42 Grey iron pipes for wa~er to BS 4622 (1970)
Standard pipe
"
n --+-··.- ;
DE e
---,--~
1
·-. I.
)
5·5m .I
Class 1 Class 2 Class 3
Nominal Approxi- Approxi- Approxi- Approxi-
-· - ·internal
'r(~
·mate mate Mass -~ mate· - · -Mass --mate Mass.
diameter DE mass e.. mass of e mass of e mass of
-v. ON ··.... of socket perm pipe ·perm - pipe_
ltg' ·--· .. k.g' -
·-perm - - pipe
kg'----. -
!! mm -mm kg mm kg ltg mm mm ltg
·r
~ -so 98 5·5 7·2 14·7 86·5 7·9 16·0 93·5 8·6 17·3 100
iPi 100 118 7·1 7·5 18·6 109 8·3 20·5 120 9·0 22·0 -128
. -150 170 11·5 8·3 30·1 177 9·2 - 33·2 194 10·0 . 35·9 209
200 222 16·8 9·2 44·0 259 10·1 ·. 48·1- 281 11·0 52·1 304
250 274 22·9 10·0 59·3 349 11·0 . 65·0 . 380 12·0 70·6 . 411
300 326 29·8 10·8 76·5 450 11·9 84·0 ~. 492 13·0 91·4 533
350 378 37·5 11·7 96·3 567 12·8 105·0 615 14·0 -114·5 667
400 429 46·3 12·5 116·9 690 13·8 128·7 754 15·0 :-·139·5 814
450 480 55·7 13·3 139·4 823 14·7 153·6 901 16·0 166·8 973
. 500 532 66·0 14·2 165·2 974 15·6 181·0 1061 17·0 196·7 1148
600 635 89·3 15·8 219·8 1298 17·4 241·4 1417 19·0 262·9 1535
11 700 738 116·8 17·5 283·2 1675 19·3 311·6 1830 21·0 338·2 1977
Note: Approximate masses of sockets and masses of prpe are applicable only to castings having sockets for lead caulked joints.
iI
'i
Standard pipe with east-on flanges
e
--+---~-£
'
-~
1
'
L
i
"t . -··
,;
.
c· ! - -- --
vc' .. - ·b
·a
f Holes drilled off centres ·
unless otherwise specified
Type NP10
Nominal c
internal Pitch Bolt hOles
diameter 0 circle g a b c ft -st- ·Radius Mass•
ON diameter No. d
~·~ .
'-
\
80
100
mm mm
200
220
mm
160
180
mm
133
153
mm
24·0
25·0
mm
21·0
22·0
mm
3
3
8
8
mm
19
19
mm
43
45
mm
13·0
1325
mm
6
6
3·7
4·2
kg
·.~
,I
.
.... . . . . . . ,. ·'' ........... ~...... ·.:oo~:-•
Nominal Mass
size .per .
metre Safe distributed loads in kilogrammes for spans in metres
·· mm kg
A B. 1·00 1;25 1·50 '1·75 .. 2·00 '2'25 -2·50 2·75 3·00 3·25.
": IJ.
203 X 102 25·33 15183 13451 12126 11005 10088 9375
. 178 X 102 21 ·54 11515 10190 9171'' 8356 7642.
152 X 89 -~ 17·09 10394 8865 7744 6929 ..-6216
127 X 76 13·36 8050 6725 5808 4993 ~·
r·
I
Table A44 Loading of timber joists
Dead load. (weight k
Size of
joist Spacing of joists in millimetres
inmm 400 450 600. I 400 450 600 I 400 450 600
Maximum span of joists in metres
38 X 75 1 ·03 0·93 0·71 0·98 0·88 0·68 0·86 0·78 0·43
;:?"\ 38 X 100 1·74 1·57 1·21 1·60 1·45 1·13 1·34 1·23 0·98
!0 38 X 125 2·50 2·31 1·81 2·29 2·09 1·66 1·85 1 ·71 1·38
38 X 150 2·99 2·83 2·46 2·80 2·65 2·23 2·38 2·20 1·80
{
38 X 175 3·48 3·29 2·86 3·26 3·08 .2·68 2·79 2·63 2·24
I·· 38 X 200 3·96 3·75 3·26 3·71 3·51 3·06 3·18 3·00 2·61
I 38 X 225 4·44 4·20 3·66 4·17 3·94 3·43 3·57 3·37 2·93
44x 75 1 ·18 1·06 0·81 1 ·11 1·00 0·78 0·96 0·88 0·69
44 X 100 1·97 1·78 1·38 1·80 1·64 1 ·29 1·49 1·37 1 ;10
!. 44 X 125 2·62 2·52 2·05 2·50 2·34 1·87 2·05 1·89 1·54
I
! 44 X 150 3·13 3·02 2·64 3·00 2·84 2·47 2·57 2·43 2·00
44 X 175 3·65 3·51 3·07 3·49 3·30 2·88 2·99 2·83 2·46
J· 44 X 200 4·16 4·00 3·50 3·98 3·77 3·28 3·41 3·23 2·80
44 X 225 4·66 3·62 3·15
l SOx 75 1·33
4·50
1·19
3·93
0·92
4·47
1-'23
4·22
1·12
3·68
0·87
3·83·
1·06 0·97 0·77
'•
I 50 X 100 2·10 1·99 1·55 1·:99 1·82 1·43 1·64 1·50 1·21
I
j"
50 X 125 2·73 2·63 2·29 2·.61 2·51 2·07 2·24 2·07 1·69
50 X 150 3·26 3·14 2·81 3-~12 3·01 2·63 2·74 2·58 2·18
l
!
I
. 50 X 175
50 X 200
3·80
4·33
3·66
4·17
3·27
3·72
3·64
4·15
3·50
3·99
3·06
.3·49
3·18
3·63
3:01
3·43
2·62
2·98
50 X 225 4·85 4·68 4·18 4·65 4·48 3·92 4·07 ·3·85 3·35
r_ 63 X 150 3·51 .3·38 3·09 3·24. '2•94 .2·~9 ··2·51
... 3·36 -3~93. ·e.. -.-
63 X 175 4~08 3·93 3·59 3·91 3·77 3·42 3·53 3·36 2·93
1
63 X 200 4·65 4·48 4·10 4·46 4·30 3·90 4·03 3·83 3·34
63 X 225 5·21 ·5·03 4·60 5·00 4·82 4·37 4·52 4·30 ·3·75
I
I
75 X 200
75 X 225
4·90
5·49
4·73
5·30
4·33
4·85
4·70
·. 5·27
4·53
5·08
4·15
4·65.
4·25
4·77
4·10
4·60
3·63
4·07 .~
···~:
···,
:: ,."
..
I
. -
The thermal conductivity of insulating materials, with degree Celsius temperature difference (W/m°C}.
the corresponding bulk density, is expressed as a The following tables are taken from BS 1334 :.1969-
"manufacturer's declared value" appropriate to the Specification for the use of thermal insulating materials
conditions of use. This is based upon the results of for central heating and hot and cold water supply
tests by the appropriate method as laid down in BS 874. installations and from .BS CP 99 - Frost precautions
... .;
_,
Thermal conductivity is expressed in teims of watts
Goules per second} for one metre thickness and one
for water services. · · .... ·:-·-~
.-.
• Table A45 Minimum thickness of insulation for hot surfaces
Declared thermal conductivity
I·: W/m°C
0·03 0·04 0·05 0·06 0·07
- --·- ·- ----
Nominal pipe bore or internal diameter
-
----- ··· ·- - -·- ·MilliniUin thicknesS ·mm-- ··-r· --- ··-----.
-~- -~7··-
•·
_, ·:_.: ::i#~?~~iF~?~~"t~I:~~~t~i-~~~:-;_:.;':ti.:.::~~~~lf:lt~lm~l
List of British Standards and Codes of Practice
Codes of Practice
CP3:-Code of basic data for the design o(bl,il,·.a~s 799-0il burning equipment
CP 3:-Chapter VII: 1950 Engineering and 1•t·'·t) services 799: Part 2: 1964 Vaporizing burners and associated equipment
CP 99: 1972 Frost precautions for water sen·i,'t~ 799: Part 3: 1970 Automatic and semi-automatic equipment
CP 131: 1974 Chimneys and flues for domesti.- ~·~·liances burning atomizing burners up to 36litres per hour and associated equipment
solid fuel 799: Part 4: 1972 Atomizing burners over 361itres per hour and
CP 310: 1965 Water supply associated equipment for single and multi-burner installations
CP 312:-Piastics pipework (thermoplastics m#.ttril!ls) BS 843: 1964 Stationary non-instantaneous electric water heaters
CP 312: ~art l: 1973 General principles anc ,-h;.•i~:e of materials (constructional and water requirements)
CP 312: Part 2: 1973 Unplasticized PVC ri~•~twork for the BS 855: 1976 Welded steel boilers for central heating and indirect
conveyance of liquids under pressure hot water supply (rated output 44 kw to 3 MW)
. CP 312: Part 3: Polythene pipe for conveya"•"' of liquids under BS 1250:-Domestic appliances burning town gas
pressure . 1250: Part 3: 1963 Water heating appliances
CP 324: 202: 1951 Provision of domestic elt\tm' water heating BS 1894: 1952 Electrode boilers of riveted seamless welded and
installations cast iron construction for water heating and steam generating
CP 333:-Selection and installation of town \HI~ hot water supplies BS 2883: 1964 Domestic instantaneous and storage water heaters
CP 333: Part 1: 1964 Domestic premises for use with ·liquified petroleum gases
;~ CP 333: Part 2: 1948 Schools BS 3377: 196[} Back boilers for use with .domestic solid fuel
:g CP 337: 1963 Flues for gas appliances up to Ukw l150.000 Btu/h) appliances
rating BS 4433 :-Solid smokeless fuel boilers with rated outputs up to
CP 342:-Centralized hot water supply 45 kw .
CP 342: 1950 Centralized domestic hot wat~r supply BS 4633: Part 1: 1973 Boilers with undergrate ash-removal
CP 342: Part 1: 1970 Individual dwellinas 4633: Part 2: 1969 Gravity feed boilers designed to b\lm small
CP 342: Part 2: 1974 Buildings other than individual dwellings anthracite ·.-
CP 403: 1974 Installation of domestic !luting and cooking Chimneys, Flues, Accessories,
appliances burning solid fuel
CP 403: 101 : 1952 Small boiler systems U$ill\l solid fuel Flue Gases and Fuels
CP 413: 1973 Ducts for Services BS 41: 1973 Cast iron spigot and socket flue or smoke pipes and
CP 3002:-0il Firing (Parts 1. 2 and 3) fittings
BS 526: 1961 Definitions of the calorific values of fuels
British Standards BS 567: 1973 Asbestos cement flue pipes and fittings light quality
Calorifiers, Cylinders, Tanks nnd Cisterns BS 715: 1970 Sheet metal flue pipes and accessories for gas fired
BS 417:-Galvanised mild steel cisterns ami covers tanks and appliances
cylinders BS 835: 1973 Asbestos. cement flue pipes and fittings heavy quality
417: Part 1: 1964 Imperial Units BS 1181: 1971 Clay flue linings and flue terminals
417: Part 2: 1973 Metric Units BS 1294: 1946 Soot doors for domestic buildings
BS 699: 1972 Copper cylinders for domestic pu1poses BS 1756 :-Methods for sampling and analysis of flue gases
BS 853:-Calorifiers for central heating and hL•I water supply 1756: Part 1: 1971 Methods of sampling
853: Part 1 : 1960 Mild steel and cast iron 1756: Part 2: 1971 Analysis by the Orsat apparatus
853: Part 2: 1960 Copper 1756: Part 3: 1971 Analysis by the Haldane apparatus •
BS 1563:1949 Cast iron sectional tanks (rectnngular) 1756: Part 4: 1965 Miscellaneous analysis
BS 1564: 1975 Pressed steel sectional (rectnnuular} tanks 1756: Part 5: Semi-routine analyses .
BS 1565:-Galvanised mild steel indirect cylinders annular or BS 2740: 1960 Simple smoke alarms and alarm metering devices
saddle-back type BS 3142:-Manufactured solid smokeless fuels for household use
1565: Part 1 : 1949 Imperial Units 3142: Part 2: 1965 Cokes for domestic closed appliances
156&: Part 2: 1973 Metric Units 3142: Part 3: 1970 Specially reactive fuels for all types of
BS 1566 :-Copper indirect cylinders for domr~tic purposes domestic open fire
J -
1566: Part 1 : 1972 Double feed indirect cylinders BS 4250: 1975 Commercial burane and propane
1566: Part 2: 1972 Single feed indirect cylinders BS 4543 :-Factory-made insulated chimneys
BS 2594: 1955 Horizontal mild steel welded sloiii!Je tanks 4543: Part 1: 1976 Methods of test
BS 2777: 1974 Asbestos cement cisterns 4543: Part 2: 1976 Chimneys for solid fuel fired appliances
BS 3198: 1960 Combination hot water stornutt units (copper) for 4543: Part 3: 1976 Chimneys for oil fired appliances
domestic purposes · Pipes, Fittings, Flanges and Supports
BS 4213: 1975 Cold water storage cistern:;. polyolefin or olefin BS 10: 196Z Flanges and bolting for pipes. valves and fittings
copolymer and cistern covers
BS 4818: 1976 Expansion vessels using an inllllnal diaphragm. for BS 66 & 69: 1970 Cast copper alloy pipe fittings for use with
sealed hot water heating systems ' screwed copper tubes
BS 4994: 1973 Vessels and tanks in reinforc~d plastics BS 78 :-Cast iron spigot and socket pipes (vertically cast) and
spigot and socket fittings ·
Boilers, Boiler Mountings, 78: Part 1: 1961 Pipes
78: Part 2: 1965 Fittings
OiJ Burners and Stokers ~ as 14l & 1258: 1S68 Malleable cast UM .and wt ~ppp~r iiiiOy_ .
BS 749: 1969 Underfeed stokers screwed pipe fittings for steam. air. water. gas and oil
BS _759.: 1975 Valves, gauges and othor safety fittings for BS 486: 1973 Asbestos-cement pressure pipes
applrcat1on to boilers and to piping installatiuns for and in connec- BS 534: 1966 Steel pipes. fittings cmd specials for water, gas anc
tion with boilers · sewage
~S 179: 1976 Cast iron boilers for central hu11tlng and indirect hot BS 602 & 1085: 1970 Lead and alloy pipes for other than chemical
i ~
' . . . . .
. •.. . ~ter.supply (44 kw rating and above)
.
· purposes
,' - .. ,.. •• t •••
Section .P... ·Hot an<?: 9old water supplies
- .
List of British Standards and .Codes of Practice
.
. .
·.· 1) ••
. .
Pipes, Fittings, Flanges and S.upports
BS 864: 1953 Capillary and compression tube fittings of copper and BS 2580: 1955 Underground plug cocks for cold w:::.1er services
copper alloy (Scottish type)
" 864: Part 2: 1971 Metric units BS 2879: 1957 Drainage taps (screw-down pattern)' ~
864: Part 3: 1975 Compression fittings for polyethylene pipes BS 3454: 1962 Materials for water tap and stopvalve sezt washers.
~.::; BS 1211: 1958 C.ent,rifugally•cast (spun) iron pressyre pipes for BS 5163: 1974 Double flanged ca~t iron wedge gate valves
water. gas and sewage ·· · BS 5412:-The performance of draw-off taps with metal bodies •
BS 1306: 1975 Copper and copper alloy pressure piping systems BS 5413:-The performa!lce of draw-off taps with plastics bodies
BS 1387: 1967 Steel tubes and tubular:. suitable for screwing to 5412 & 5413: Part 1::1976 Dimensional characteris(ics
BS 21 pipe threads 5412 & 5413:. Part 1: 1976 Water tightness and pressure
BS 1494: 1951 Fixing accessories for building purposes resistance characteristics "'
BS 1710: 1975 Identification of pipe lines · 5412 & 5413: Part 3: 1976 Hydraulic characteristics
BS 1740:-Wrought steel pipe fittings (screwed BSP thread) 5412 & 5413: Part4: 1976 Mechanical characteristics.
1740: Part 1: 1971 Metric units 5412 & 5413: Part 5: 1976 Physio-chemical characteristics
1740: Part 2: 1971 Imperial units BS 5433: 1976 Underground stopvalves for water services
BS 1972: 1967 Polythene pipe (Type 32) for cold water services ·~
BS 2035: 1966 Casi iron flanged pipes and flanged fittings Threads, Jointing. Solders and
.J:\
,_ ~· .;)
BS 2871 :-Copper and.copper alloy tubes W
.I~·'
2871: Part 1: 1971-Copper tubes for water, gas an~ sanitation elding Rods .,...-·~..... ..' . . ·.
2871: Part 2: 1972 Tubes for general' purposes BS .21: 1973: Pipe threads for tiibes.arid fittings· where press~re~
BS 3284: 1967 Polythene pipe (Type 50) for cold water services· tight joints are inade on the threads .
BS 3505: 1968 Unplasticized PVC pipe for cold water services BS 61: 1959 Threads·for light gauge copper tubes and fittings
BS 3974:-Pipe supports . BS 84: 1956 Parallel screw threads of Whitworth form
3974: Part 1: 1974 Pipe hangers. slider and roller type supports BS 219: 1959 Soft sOlders
BS 4127:--Light gauge stainless steel tubes · BS 441:1954 Rosin-cored solder wire 'activated' and 'non-
4127: Part 2: 1972 Metri.: units activated' (non-corrosive)
BS 4346:-Joints and fittings for use with unplasticized ,PVC_ BS 1453: 1972 Flller materials for gas·welding
pressure pipes BS 1723: 1963 Brazing
4346: Part l: 1969 Injection moulded unplasticized PVC fittings · BS 1724: 1959 Bronze welding by gas
for solvent welding for use with pressure pipes. including portable BS 1806: 1962 Dimensions of toroidal sealing rings (o-seals)
water supply BS 1832: 1972 Oil resistant compressed asbestos fibre jointing
4346: Part 2.: 1970 Mechanical joints and fittings principally nf BS 1845: 1966 Filler metals for brazing ·
unplasticized PVC BS 2494: 1976 Materials for elastomeric joint rings for pipework
I!.,
Jo
4346: Part 3: 1974 Solvent cement
BS 4504:-Fianges and bolting for pipes, valves and fittings Metric
BS .2n9: 1973 Pipe threads
BS 2815: 1973 Compressed asbestos fibre jointing
.
ll! . ··'' ~~~~~:,,1;;~4F~:;~:·rpt::;·;J:::~~~~-'j. bot ·~d ~r-~~ :~ ,524:~ ~75 Rtgtd ur.Wne foam' ·' •Y~fAilfj·~·: ~. ;. ,%
I
Do111estic central l1eati11g
Flow of water in pipes
The installer should agree with the· client the internal Flow of water at 75cc through copper tube to BS 2871 :
temperatures to be provided in the various rooms to be Part 1 Table X•
• heated. Except where there are special requirements. Pressure loss in N/m2 per metre run.
the following table sets out generally acceptable room
temperatures and air changes.
Table 81 Room air temperatures
and rates of air changes Table 82 Small bore systems
::;.;~'·:. '' ..:'·:··;" ··... '_:·._,__ ,...,.._, "~.-Air·_ .., · · ' .... ..;.. _.-:.·
_
0·66 194
0·68 204
0·70 215
0·72 227
0·74 239
G--76-- 250.
0·78 262
0·80 274
Velocity
1 m/s
.· ..,.
...... .
~ .'
··----~-·-.. ··
..- ·:~/';_~ ~:-/·f.f~-:::L:~-.;i:~~~
1
I
Sec-tion B D 0111 e 3 t i c cent l ·a l he Ci tin f:
'
.
" Flow"' of water in pipes Heat emission from pipes
Table 83 Microbore systems Graphs 81 and 82 give the theoretical heat emission per
hour from single horizontal uninsulated steel tubes and
<)
Flow rate*--.. .
•·· 1.>. ( • •• !f?.. -- P:... •'
painted copper tubes when exposed in still air at
temperatures between 1 ooc and 20~c. but allowing for
. g/~ · ... : . 6mm
-~ ... ,,. - . -~.
12mm
natural convection currents.
0·007 810 182 46 '21 The emission will be greater in conditions of draught,
0·008· 975 210 55 28 depending upon the velocity of the air. For example,
0·009 1165 - . 245 68 34 with an air velocity of 1 m/s, there will be an increase of
0·010 1395 285 81 40 up to 100% for pipes up to 25 mm diameter. Where the
0·011 1625 325 94 47 air velocity is 0 · 5 m/s. the increase will be 50% for
pipes up to 50 mm diameter.
0·012 1885 360 107 53 The emissivity by radiation of a surface will also depend
0·013 2165 405 120 60 upon the surface condition. For example, tarnished
0·014 2475 460 133 66 copper tube will emit approximately 75% of the values
0·015 2800 525 145 73 given in Graph 81 for painted copper tubes.
0·016 3155 595 164 79 Vertical pipes
Q
]··: . 0·017
0·018
3535
3930
665
-740
180
195
88
97
Pipes fixed vertically differ in their heat emission from
those fixed horizontally. Whereas small diameter pipes
emit less heat, large diameter pipes emit more heat. The
0·019 4350 815 215 107 following table- gives examples of_ the percentage of
I •
0·020 4800 903 234 113 heat emission from vertical pipes as compared with
0·021 5330 990 253 120 horizontal pipes. ..
0~022 5780 1075 273 126
0·023 6210 1165 293 133 Table 84 Heat emission allowance from hot
0·024 1260 313 139 water storage -
. 0·025 1350 338 146 ·-"'""'· "''··----·' .· .. ,.~'':~:;:·~:•.. ;.~! ··c.
~
omina....,.-
0·031 2010 520 223 cylinder ·Storage Heat emission ,*kW .
.~
.
0·037
0·043
2755
3585
754
1030
313
413 ;c~~-'~,.~}~7per:~~=-~~-i_ns~iate~-~:ln~~l_a,!~~~
0·049 4485 1325 536 60 0·24 0·12
0·055 1670 665. 117
0·061 2030 795
0·067 2410 925
0·073 2830 1080
0·079 3280 1235
0·085 3780 1408
\
i'-:-)
·......:;,
0·090 1547
0·095 1710
0·100 1860
0·105 2030
0·110 2220
0· 115 2365
Table 85 Flow and return temperatures etc.
0·120 2540
0·126 2785 r::·.>:~~;·.:_::·:~=--~- 7~~i~~~~::~
...
k
Velocity
1·5 m/s Accelerated/Gravity max. system design
flow temperature 82
Accelerated system design return
temperature • 70
Gravity system minimum design return
temperature 60
Accelerated system design temperature
drop• 12
Gravity system max. design temperature
drop- --22
Accelerated system mean water
temperature • 76
· Gravity system mean water temperature 71
.. • A temperature drop of up to 16' C ma1>.irnum ma~· be
aaop:ed if advantageous pipe sizes are t'lus ob~ained. ·
~~:·-.:.: ..: •.·
• . • , ' . ;.;~7 ' '' •
~~:·:.
··-·--------- --
..-,: ·. -. :;:-'. ~~u¥' :::·:"::g:-~~ ;:;~~~i{f.
I
l
Heat emission from single horizontal uninsulated copper tubes
.. Graph B1
to BS 2871 when painted
~--~:--~!--------~~----~------~,-----.--~,----~~----~~--~~
\
C \ I
~---'\:~'\~~:----~·--~:----~·----~--~:----~:--~----~!----~~--~~
8 \. ~ I i I j !
~, , I
-~ t : i
'\. I !\. ! I i ; i~ 'i I
~~.~~;---rl~,~i---~,1--~,--~.~--;--~,--~--~i---~i.--~~
0
~ :"\. I '\. I i i I I I
\.i \... ! '\.! 0
~~~--~,~--~~~---+----,~--~--~---4----+---~--~~
l ! . l
'\: .'\. i '\. i I ! !
~ ; "-; .~
~~--~.---~,."·--~~~%~~--~:"~~~.--~j--~!--+---~1--+-~2
; : l ! 0 -...
c
0
:::1
~~-··~~:~_,J___~~·,---~'~
"~,~~--~~·.---4~--~·~--~--+l--~--~
~---~~~~~---~~~~~~~-~~~-~~·~~:r·"~--'~i--~~---r---+---+--~~
"'- ! " -1 : 'X i' ! "-i I
•
.... ' .,., '-~'O ',,, "-' ' "''" ..._,~ ·;, -~{:-:0~;·;~;;:1~
I 6
.·/: .
·~ ..:.;. ... . ~
.. :, ~~·-~}~:
..... .. . . . : ·,
~ ...:·.· ... \ ., .t.
·< ..•:!.,. • ,4· ~- .. (j) :c UJ
.·...• .. .so
. ·.•'·
..• 90· . 130 ' 170
,
210 . '2 50 '-' . ·: 290 ,. . 330 ..-,.':' .. '""' '. '·'" ..... "'. . ' ..~ --- @'· CD CD
v ,...DJ
~-~
'0 (J
1/ ~-
•,
~ ~
.
)
. . ·. i .
'
1/ 1/ ) .ll ..
· .
.. ,."
I)
. \'
~
'· '
'! ' !:
:r
tg
~
c+
I-'·
0
.· 'j ~
I ~ ~
... ~~ .
I I I I
If ;" /
.•
" ~ ~
3
-·
en
l:l
tJ:j
vv
. '- 130)
'/
·I I v J
v /
/
~
v ·. '··,;
''
I/
/
::t
CD
Ql
-·
en
0 tf
r+•
vI y = 0
' .. 120) I
I J
v.
I
v·
II ~
/
/
/
.· ..
1":
/
;
/
/
"'I
~ CD
3
c;;· ..... s
ct>
en
" I,
0
·.
I IfI J ll i·: .. ~ I II" en
-· .....
~
7~
) / ' ~
3
, ~ 'I
I/ If ~
v . I/ I ...
'I
.., ~
~"'
0
::J
.... -·
(J
lj
, ",
"C (J
·f ~~ J ) / .t! ...0 CD
'110
1/ I ~ ; ~
~J
I
~ / v ~
v -ll .I /
~- ~
~
:,;;
·3
"C
CD
en
l:j
~
~
, I ·I ~ ~- ~v 'I ,y
-/
/.
, , ~
:,;; !
,
:,;; "'
~ I
~.
::J
P'
1-J
100
. l I
vI I
1/"' ,_, I~ !.'.I v I /
7
- "? t'- ,. II"
I
-
(0
CD
:r
t::r'
ct>
s;P
.....
v
' ~
7 .. ...N'
, I I , I 1/
-~
~~ ,y ~
, , ~
II"
- 1--··: --
0
t:l
, y'
.I (JQ
90
7 ~ 0
I I 1/ I 1/ .I·- t;:.~ / /
, .. :,., ( ::J
r+
I ,.I I / I l i 7
/
/
/ --
~
II" i
-- i
-
Ql
1:
80) .
~ 7 :,;; - -·
::J
7·
lI J 1/ I ! Jv ~
I / t~ :,;; ·'
') . ::J
en
I I II I 'I / / / ""/ ~ ' -
1:
I i/1 , Ql
i
'.
/ ~ ' r+
I I I I /
l / I v /
~
/
' . '
I
CD
r+
1:
0"
CD
~'JjJ·v~~~){ ~'~/
..
I
. ' ' tu
. I .i·: :
-·- - 1-- en
.. · .· Vll_V ~ ll -_II
\ j1~~-t i v ~. ~ .~ r.. '
. .. ·:
~-- · __ w
.. ;I
. i
'- ' ~ . ' .·r .
ClO
~
100 J2Q 140 160 180 200 220 240 260.. 280 300 320
.
340 360. 380: .400; 420 440 460 480 500 520 540 560 .....
· ... ··
1 ·.
Table 86 Heat emission allowance from tank Heat losses through building fabric
surfaces The following table 89 lists heat transmittance
coefficients in both Sl and imperial units for various
..J" types of building fabrics.
In each case, the average figure given is that which
50 0·22 0·10 applies to most suburban and country dwellings. The
0·15 figures given for exposed conditions should f?e used
60 0·32
when calculating the heat losses for dwellings witn
70 0·43 0·20 N., N.E. or E. exposures on hillsites, at the coast or on
80 0·58 0·29 riversides. . ·. .
+ambient air 16·· C.
For external walls, windowS, roofs and ground floors,
·. the full difference between internal and external
temperatures should be taken. For partition walls and
· Table 87 Percentage of heat emission from intermediate floors, the temperature difference between
vertical pipes as compared with each side ofthe wall or floor should be taken.
horizontal pipes ----"""·-·· .. __. ,____
. .
.,
- .... : --··-·--· ----. __ .:.:, --.-- ;__ - _-::.,:_..,_. -··_
__ -·-. ----· __ .. --'----
---- -- ------------ ----------
§\;~~;
____.. ___ ... -------··· .. -----..:..:-"
·-. -- ----·-
.... · -.. . __, ..... ---· . :~
------
·-·:
20 78 80
. 25 1 80 83
32 83 85
'40 85 87
50 2 87 89
65 2t 89 91
75 3 91 ' 93
. Insulated pipes ·
·. . The heat emission from insulated pipes varies mainly
with the conductivity of the insulating material used
. and its thickness.
It is most important that insulation be kept dry, as damp
insulation can increase heat losses by up to 400 per
cent.
Table B8 below gives the heat emission from pipes
·insulated with materials of various thermal conduc-
tivities and at varying thicknesses.
Table 88 Heat emission from insulated pipes ·
. Heat emission W /m run of pipe per •c (in still air at 20"C)
Thermal conductivity of insulating material rNim"C)
Nominal o·040 1 o-oss 0·070
pipe bore
mm in Thickness of insulation in mm
20
Section B D01nestic central heating
; "
'- Heat losses through building fabric
• Table 89 Hpat transmittance coeff~cients (U values)
- ~:J~~~~~i-
·:: ··.·.--··.·.·· ........
..
l ..
I
)
' .Construction
! :· . .. ·..·...
! :'·:· '-: :.. Roof glazing . .. : _
H'J.?t~t~;,Jnterrnediate floors ·- ·--- -~ - _,., .- '""-::· :"> '_._,, __ :· ·... : -. ··-:::;·,~---"-:•. . · ~ ·-~ - ·.- ·:. ;~/f¥.,
J i:~~~:f:~A(yvooa floor on joists. plaster ceiling --·· -- ~ ·- : .,:: ···-..·' ·>.,.., ...: , o\(:"~·-·:::-...;)~.:.. .. _"< .._.,. :.. : ·.:~~-: ~~;!:~:-~;.·..:£: .,..,-;-: .>> -::·~ .·.: _, ··.~.'~-·- ~.=~_:·_:·_.~_,_·'"_=_~..
l_:·.:. _·~:_~- i~.: -:.
1 :· __ : -:.:<downward transmission . .. . .·,,.,.">:(:-:~~=-.:· : ~--1 ~:so.· _:;.~,.-;·->~·-:<:·:o~2s· _ .. _,. . .
j ,'''-"·,:-:_:upward transmission i: · _·· :] ·70 - - - . '·. ·_. --_0·30 · ·~Y.~:-:.:t·.-;
..· zo·. :
~- .· ;J 50 mm (6..) Concrete with 50 mm (2") screed .· ·":. ~· I :. '. • !
. ·.· __.:
..
I upward transmission. · _:2·70. . :..._, ... -:..: ..
-~
;.,:.
J • ~·· .. ·-oo:·
150 mm (6 .. ) Concrete with wood flooring ::._:·. r·· . : ..- :.:·.: . ;,~·. .-
'[
I ..
Graph 83 Cavity wall insulation
""\
I
) .
'D· ·
:· •. :
•••
.;
..
..
'.
I
Section B Domestic central heating
.4."',•;.; ••
~ : ··- .· .: :' . ,
- ~t~·
~~~
~5~~·~;:
...·. ..,,
., ..
.
'·
~~;-<.
·.·;,
:-n ·'
r
~-~tint u~~· -~ f T~•l
;
"'i:' ·:i . . ._ Room ·:·"". · Dlminslont · -Air Ch _ TeMp · _Toto I · _ _ Totoi ~-
' :!u w
1~
i~~t
···R•••
••·
>L".
' •
Tomp : '~.-,Surfm
•c •.
'.;_ l
"'
w H
Yolumt
113
Aru
112
or
Dt4uct
Rmltlnt COlli WJ"C. Rill
•c
W
Require•
W/113 length
11
Silt htlll
- 1111 Will
' W:
Ftr Plptl II Nt
1 ,.
T"'
tmlu , For
tteh
W
~utlnt
! Unitt
rutan•• ...
~
·-____. - - - -" -- . . __
1
/ . . - , -" ·- ----- . ---- ::.::... ------ ..- ............._ --·- - - - - · -;--- ..-:·-
J; i\, -~ zr:....liist~ == -~~ ·~= -=--= ~:. ____ ·-·----- -------~ =:== ~.-=: ~~~~~-- ~:--=-== -=-.:~ ----~:·:.- -~::·:· '~-~~ +~-:~ ~
g
r..~ . ' --1-wintfow- ·a:-ir -- rz --·--a.& ... ~-~--- ·4-nn:o· -·--zz--· ·a7'5~ir· ---- ··-..----· ·. . . . . -~-- -·-·-··-·11------ w-•·~···~a-·-····- ..
~'. •. 2rr-siiuth- ---- ------r---. ----·- -·---- ----.- ------- ----~--·...................... - ............................. ~.........1. -·-----~-. ··-·.. ---..- ...... ·-·- ~-Jr··-·-· r::Ci'
. . .• ~~~~===~~=~==:~-;~~:~~~-~~~],:; ~:-~~-:~~:~.=,=
o;- ~.
~
::!'
o'
:::.
C;J
:::.-
I...
·;:
,
---~-~_!_~-Waif- 5·5
:-:-:-;.-.- - -
2·5 13·75 3·6 1o-1f 7o6 10·8
j_ _
2f_..._f:fro- ·-·- ----~ ---~_:
_,_.__·. ---- . ;.. ~ -_ ------- ---~-E-
_.., ... --':-.1 .. - ..... ----------. --
. . _,. ] .;. . - - _ _ ;. . . . . : . :. .
:_j""'" __ - - - - ---·
~~' · ;:;outh · ; .! ·: i 1--r-....;....J....
...
.' ., 21
----!--- --~- -- .. --==-- _,___ -- __. ____. --
·· --~ 1 _• .
- - - - - ---'-f--·1
·---~-:.ij ___ "
:.'! ....
~~~ ~--. 21-=-~~~~---~~
:: . Well
., .-.----- ·zr-t-Wasi---
· :,Wall..
3·6 2· 5
·---· ·-·-··.-
== = --:- :~=~~ ~~~~- -~·. :··=~ :~-~~~~ ~'=~:~·---~ ~~=:.~. ~=~- -~:-~: :.~- -~-~.:.::~·- ~::· -~~·::~~--:~
9· 00
3·6
1·08 9· 54 22
---- ·---- ·------
8·64 0·96
210·0
_____.......................... .
· · --·--- ---·-..
8·3
·
~ ··---·
22 183·0 __ , ·
~--~
·_! :
!_
~~
::...::.. ................- · _..:.....
-.-_-- --
· . .
. ........____ ------ ---- ............ ..... - -·-- ----· .........-- -----7- ....... ______ ,_
== --- ----__·:=~:. -=- =-~== :~:~::~= .=..: .:=~-~:~: ~-·~~--- ~~ :~.~ =-~~ :. :=~~-- ===~ -·-- =:~=~=~
-C.::...--~--'----·----------·-- --~- --------~
___ ,_
~. -~---~=- -·~ ==~
t' .. _ 21 Aoor .!i_·5-t-~·6 19·8 ·•. ~.68 13·5 ~Q- -~-~-:.!. .....:. - ..-- .. .:. . .. _-·· 1-~ __ -----·-1-·---·-+-'---H-
J .:.;.____;,_ --~"-:::-· . - ----1-:------- ------=-t-- ~·- --.... .;,..._;,j ~ - - - --;--··---" - - - - ---11----t
:; · ., 21 ROof 5·5 3·6 !.~._8_1----t--- .!I~. L.!L!B.. f-~-- ~1·0 t-· ______ :...:.h J. : ·---·-- ..........
;~ - ·- . 1--- ---- . - - - - r.:--=='--::.= ...-......:. ---- --· .•~. : : -,--1-:-"---1~·
.~;. __ __ . : -'--- _________
.~zn· q . --=-~-~---~ ,,...,_,_-11---1----+---+..:.......~~----
~~ ,·,. ..~--~ .Z.:JL J.~. ;_B.~ kJ.~.!l --
-~
~
': ,\
- - ----t-·- - -
---
~-- ~-·- =~~=~--_
- - ---f---- __,._ ---- --· --·-
. _ _ . ·---~~--~-~ . . ._---~4j0. ........ ·-..
4· 0 20 . 90 : 360
-
,. . . ·--
,
f~,;~
~: ....... ,.. ----I---
c- -=--+--=~~==:::.~~#;=\:=~~+
,
.
·
. .
·· · · '
'
1
8 ·-1--+-----
Fan
--, ·/i·
·'
.,.;·
"
Table 810 Effect of insulating building fabric would reduce the normal recovery time. Thermostatic
control will need to be fitted to maintain the domestic
The approximate reduction of heat flow resulting from hot water service at a design temperature of, say
• insulation of various building fabrics is as follows;..
;~:::: ~-- ::·:-- :.::·-~·:_. ;. :~- .. ·'- .· • · · · --~ · Reduction
60-71 oc
(140-160 °F) bearing in mind that if the
.. T . ··:- ~- ~- ~:- - f D.H.W.S. was to reach the same temperature as the
~~F .. .. .. ype . . . . .. :. o heating flow, scalding would occur.
~~~ric j{:L.,~-~ :;~1 .~.~i.t1;~. ·:4:;~ ;,,:. sT:L; ,+,;;~,;;;i:~·: :.:: · The use of an expansion vessel !n- some caces exempts
the installation from the Model Water Byelaws
Ceilings 75 mm glass fibre 80% requirements and therefore the radiator connecting
Cavity walls foam insulation 75% piping ca·n be embedded in concrete floors.
• The installation should conform to the HVCA 'Guide to
I,
Suspended floors 50 mm polystyrene 80%
Good Practice-smallbore and Microbore domestic
Solid floors 25 mm solid insulation 50% central heating, Part 2, Sealed Systems'. The vessel
Windows double glazing 40% itself should meet the requirements of British Standard
4814 : Part 1 : 1972 (Expansion vessels for Sealed
Hot Water Systems). ·
Space heating elements The size of the system is limited in both cases to 45 kW
.~
4 ;;:lf The effect of painting radiators with ordinary paints (150,000 Btu/h), but the general installation principles
~ may be ignored, as such coatings do not materially described apply equally to much larger systems.
alter the heat emission. Metallic paints such as bronze The essentials of the HVCA Code and British Standard
or aluminium however, reduce the overall emission of are summarised below:
radiators by up to 15% and should not be used.
The emission of heat from radiators is affected when Maximum flow 99 "C 21 0 'F
they are fixed in an enclosure or are provided with temperature
shelves. The effect is as follows: Circuit 8-17 "C 15-30°F
lt!nc(~iur! ,:": ,-:.~'fjit~·\[Efiici};n :e~issio;_;~g,¢jn;:},,:C:;: temperature
drop
Fixed in open A reduction in emission of
fronted recess approximately 10% Maximum 3 · 0 bar 44 lbf/in 2
Encased with A reduction in emission of boiler wor"jng
grille in front 20-300,!{,, depending upon design pressure
Fitted with A reduction in emission Safety valve 0 · 3 bar above 5 lbf/in 2
shelf over of 2-2·5% blow-off max. working above max.
pressure pressure working pressure
Manufacturers' data on the heat emission from radiators
is usually based on a temperature difference of 56°C, Minimum 0 · 1 bar 1 · 5 lbf/in 2
water to .air. pressure at
To calculate the emission ·at other temperature highest point
differences, multiply the emission at 56°C by the of the circuit
~~ following factors: Maximum 1 · 5 m/s 4· 9 ft/s
'J· Table 811 Temperature differenceJn deg. C water velocity
~~7.~."...--.: -,"""'1~·~·~~..... ~~~-~--:!'!!·~""""" in circuit
Lk--- ,~::.-4Q~Ji~5~5_6 .. :_:sp~5.;..:.7o
Factor 0·63 0·75 0·87 1·00 1·13 1·27 1·41 Table 812 Approximate sizes• of diaphragm
expansion vessels (Microbore systems)
Sealed system operation .··-"·.·...
.. :·~--~-=
...
:_ •• : :· ;
. ····;· · N~mi~~l vess;·, size·•..
:~.·_··
The basic difference between a sealed and an open System load litres·
system is that a diaphragm or membrane tank. together
with a safety valve and pressure gauge is substituted for Traditional · ·. · Low water· ·
the normal cold feed and expansion cistern with open :. ·. · ·• ..: · ·:· , ~- . · boiler and .· content type boiler
vent. ~- -kW::. ;:_ Btu/h :: :· · radiators :. with fan convectors
~:_:>. ·:··.:.p··:.:.pt ... -·..-·. · ~:.:. ". .: .~ ~ .,.,~ ·~-·. ~:~ ...... ·e,,;;;.;; -e;::-;;... ;.:;:-\-;;.:;...i.'';;Ji..,:.• .
A sealed system often operates at temperatures higher 10,000 4 4
than 82 oc {180 °F) but in such cases standard radiators 3
are not recommended, due to the possibility of accidents 6 20.000 4 4
as a result of contact with surfaces. It is recommended
that convector radiators, skirting heaters or fan convec- 12 40,000 8 4
tors are used with sealed systems operating at tem-
peratvr~s in excess of 82 °C {180 °..f). .
18 60,000 12 a ..
The actual system is installed as previously described. 24 80,000 18 8
. The expansion cistern and open vent being substituted
by a diaphragm tank and ancillary components which • The correct size should always be calcu!ated from total water
cont~nt of the system.
must be located and installed according to manu-
facturer's instructions.
Advantage can be taken on the domestic circuit by
usi~_g a_ reduced tube size, as the higher temperatures
. '
·io.
'•
. ,o: -..
!- . :.:.
connected to a sink or garage tap at one end, and to a
non-return valve followed by a stop-cock at the other
end. Tank/pump units are also available from some
Gas Central Heating
Gas central heating units or boilers installed in
compartments
!1 manufacturers.
I Experience with sealed systems shows that make-up The compartment. whether modified or specially built,
Jl •
may be needed in the first few months of operation. ~
shall meet the following requirements :
In commissioning a sealed system, it is generally {a) Have a half hour fire resistance from internal fire,
"
,j advisable to maintain a low pressure and high tem-
perature for a period of a few hours to assist in venting.
and the inside lining or finishing should be
noncombustible or a class 1 finish.
When the system cools down the pressure should be The door must have at le.ast the fire resistance of
adjusted to a value equal to the static head plus a the compartment walls.
margin of 0 · 5 bar (7 lbf/in 2). The final pressure at full (b) For good acoustic insulation. should preferably be
temperature and with all the circuits and heat emitters built of brick or clinker block plastered on at least
~orking should be less than 3 · 0 bar (44 lbf/~ 2). one side and supplied with a well-fitting door.
i -
(c) Be of sufficient size to permit access for inspection
Safety devices and servicing of the heater and compartments. It
Safety valve Non-metallic disc and metal seat: fixed should not be made larger than necessary in order
setting. (To conform t() BS 759). Discharge pipe to to avoid the use of the compartment as a storage
rear of boiler. cupboard. The makers' recommendations regarding
High temperature (manual reset) limit statTo operate an minimum requirements should always be obtained
independent valve (oil or gas-firing), or switching off and observed.
electric supply (oil-firing). (d) Be fitted with a door of sufficient size to permit the
Maximum setting 110 °C {230 °F). heater to be withdrawn from the compartment.
For solid fuel an additional link to the circulating pump (e) Be fitted with permanent openings for air for
is required to keep the pump running when. the flow combustion and compartment ventilation as
temperature exceeds the design limit by 8 oc (15 °F). shown ill the table below:
Instruments
Pressure gauge To be fixed on the boiler or connecting Ventilation of rooms in which are fitted
pipe. conventionally flued central heating appliances
Thermometer To be fixed on the boiler or connecting or boilers either freestanding or in
pipe. compartments (not including combined
appliances in living rooms) .
Radiators and convectors . A purpose-designed ventilation opening must be
Maximpm surface temperature on any exposed part, · provided in an outside wall of the building; this
82 oc(180 °F). opening may be either:
(a) directly into the room or space containing the
Diaphragm expansion vessel heater, or
Size Acceptance volume must be equal to the total (b)- (for appliances not excee-ding 2500 W) into an
'! • volume of expansion of the water from 10 oc
(50 eF) to adjacent room or space which has an internal
11 0 oC (230 °F). lrrespe~ive o.f thi nsrmal workiAg purpose= provided sp.ening to the robm~ntaining
temperature. See Table B12. the appliance.
Connections The vessel can be connected directly to The minimum effective areas of all purpose-designed
the system or piped to it, in which case the minimum ventilation openings must be 560 mm 2 per 1 000 W of
connection sizes should be: maximum output of the appliance. If a water heater is
.. Up to 24 kW (80,000 Btu/h) 15mm installed in the same casing as an air heater, then the
Over 24 kW (80,000 Btu/h) . . •. •. 22mm area of ventilation openings must be based on the
~~.- _____ ~~~ ~aJ~~_should be fitted 011 the connection pipe. combined output of the air heater and water heater.
r
'
.
·~
D
. Gas central heating units or boilers
installed in compartments
a Table 813 Minimum free areas of openings to be provided into .the compartment
Up to 18 kw .·1250': 275 ·.
Any flued central Up to 60,000 Btu
·Kitchen heating - 560 mm 2 per
ventilation 18-26 kW 1360 300
appliance or 1000 W output
boiler 60,000-90,000 Btu/h
·f.·.
waste pipe conveys the discharges from ablutionary and
culinary appliances to the drain through a trapped
....
-~' Fig. C2
gully. Deep seal traps are not required on the two-pipe . Fully
system. ventilated·
.
' Fig. C1
li~""' •
Two pipe system
=' _.,•w~' ;'";';·_~>\YPy'p· a
one-pipe
system
Fig. C2(a) ~
Alternative
• ~nk [_a~ cWac. method of
connecting
ventilating
.,T~pfloor>> · pipe
.. ,.
~ ..... Fig. C3 The modified-one-pipe system
~
~ ..
:..· ·:··:
·'· ....
·Sink' ; .
i, Bath .· ..
···.
·~-_··:,-:Bath.
__ .......- ....................__......
_.. ;
J
I
j ),~ ..... ~.._,;..,. .-~-... - - -...--~~...--- -·'~ -- -·----4_.....,.__ ..... ~ .............. 4-- .... _________ ..._._ _ _ _......_-"-'--.....:.:....:....~.:..---~.-·----~
Bath
Fig. C5(a) t-
Modified
single stack
system
-·;,·
~ Fig. C5
I.
The
' ~ \ - single stack
system
Sink
' ..
_....
. ..
~- - ~
.
'
r
J
J.
...
diameter to be half of stack diameter. (4) No offset Vacuum System
venting required in lightly loaded systems of up to 3 A vacuum sanitary pipework system is based on the
storeys in height (e.g. low rise houses). (5) Offsets principle of using air, instead of water, to convey foul
aove highest branch connections do not require water away from specially designed water closets. The
venting. water from water closets is termed 'black water' and
JrllJTI.~aste applial'!ces as 'grey water'. Vacuum flushing
The Sqvent System of WC contents r~uires only one litre of water and
'Sovent' sanitary pipework system is a relatively new pipelines need not ·be laid to the gradients necessary
· system tested and deveiO'ped in order to overcome the for gravity waterborne installations. The vacuumW.C.
negative and positive pressure problems associated suite, although similar: in appearance, differs in
with trad·itional systems. Wrth the use of a mixing fining construction from conventional types. The bowl
and a. bottom aerator (Fig. CB) it is possible to install contains no trap but has special accommodation for an
normal size stacks and load them above present limits airtight outlet valve and flushing apparatus. Branches
without vent pipes. from W.C.'s, stacks and main sanitarY discharge
pipework need only be 40-50 mm dia.
Fig. CB ·. 'Sovent' Pipework Fittings The main stac" however, would generally be enlarged
to the next diameter UHU\Sl1r8 velocity of flow does not
.!'f exceed the suggested limit of 10 m/s during peak
' '
..
I
j.~-.
+ + we.
···!··.• ~-
:.... ::·_
-:. ., ::•.
·~· ... . ·. : .. ~·/3':.·~·(:···an~· ~:~/:·;~i/:·
:.::__;;.:··· ..
. ·. ~ '2 .~:,;sl'l~ii.iRterat.tflelawer.'incf:·;; - ·
~===LJ_~·_::·,-::_·•..:_··-·;_··z::otihe finin~· deflects·water;!iJ
.• • • • 6
3
. ;.~ · smootbly.·.mto :the stack..'\'!"
-~~.~ •..:and prevents impingem'ent·..)
: .. .~.'~!~bY., ·Water:;:flc?Wjng' do:t~n. ~:j.
:: •• . from· above· on the internal·(;,
of the
.. ···
-:'~Stack
.;:dia;mm Centre line of
7~150 branch not to
. ....
~-~
be below this
point
: ~ Connection
· not permined ·
: . in this area -~ .
i
~···Y
.
0 •,~~........~~~-...-·.:............,. ......A,..;,!'>'"'Ooo"""-'"·i ...............,._,......... _....._ .. ____ ........... ...,._
appliances. It is necessary to limit the pressure fluctua- (b) The length, slope and diameter of the discharge_
tions to ± 375 N/m 2• (a negative pressure correspond- pipe.
. ing to about 25 mm loss of water seal from a wash- Seal losses _produced by effluent flow down the
down W.C.). Where venting is recommended, the vent discharge stack depend on :-
pipe may be run separately or connected to a vent
stack. Vent connection should be above the spill-over (a) The flow load which in turn depends on the number
level aniflnstaffed. with a continuous fall back to the of appliances connected and frequency of use.
appliance. Branch discharge pipes serving ranges of (b) The diametar-of the discharge stack.
W.C.'s do not usually run full. therefore branch venting· Excessive seal losses can be prevented by the proper
may only be necessary where bends are introduced. and correct use of the design procedure provided.
The occurrence of full bore flow depends upon factors
such as the length and slope of branch discharge pipes
and the form of connections.
Foaming
The increasing use of detergents produces problems in
sanitary pipework installation. A small amount of
· Inspection and testing of discharge pipes detergent can- cause a large amount of foam· when
. Work should be inspected and tested during installation, dropping through a discharge stack. It may be necessary
care being taken that all work which is to be concealed to connect certain lower floors to a separate discharge
is tested before it is finally enclosed. Final tests should stack. Commercial applications, such as laundries,
be applied on completion of the installation both fc:>r , should have an independent system of discharge pipes
soundness and performance. Normally, the air test IS connected direct to the drain. Bends at the faot of
used for soundness. but if the water test is applied. it detergent foam carrying stacks, should be as gradual as
should be used only up to the level of the lowest possible, ideally 2 No 135 ° large radius bends. The
sanitary appliance connected to the system, and then following recommended procedure will reduce the
only in new systems. When testing old existing systems, effect of foaming:- · .
it will be necessary to limit the pressure applied because (a) The discharge stack diameter must be determined
of shallow trap seals: the water test should not be used. on the maximum discharge loadings required for
Any defects revealed by the test should be made good each condition and building type.
and the tests repeated until a satisfactory .result is
\ . obtained. -
(b) Discharge stack to be a minimum of 76 mm
diameter one type of sanitary appliance .
Reference should be made to Local Authority and other (c) Maximum loading of discharge stack not to exceed
enforcing authority requirements, particularly where ! cross section for peak discharges.
pipework passes througl:l areas where blockages and (d) Avoid offsets in wet part of discharge stack and
,.I leaks cannot be detected. In general. sufficient access horizontal runs otherwise additional venting is
should be provided to enable complete systems to be required. ·
tested. Access points should be carefully sited to allow (e) Separate-er combined dischargestacks:-
the entry of cleaning or testing equipment and con- (1) Up to and including 4 storeys - as current
sideration also be given to adjacent services. Traps and requirements.
joints that are easily disconnected can be an advantage
so additional a.ccess is required only..under exceptional
circumstances:The discharge from urinals can give rise
to heavy disposits, especially in hard water areas. Fig. C74 Length and fall of basin waste. Design
Regular maintenance is therefore required and access curve for 32 mm wastes and 75 mm seal P traps
should be provided so that all parts of the stack, connected to single wash basins to BS 1188 ot
branch, discharge pipe and trap can be readily cleaned. similar.·
Where the vertical discharge pipe has a long connection
to a manhole· access should be provided at ground . ~- --~- .y;.;:--·-:- -~;·~_ .... rJ:::e . ;.··.-~\ . . . 9._:~:--~: ~~""!'i!*'-~~~-=:::~;.'?'F,.,~
floor near the foot of the stack. In multi-storey domestic ... > ~~--,r--r--r--r-r-r-:-:-r-r-r-r-1
buildings, access shoul~ be provided ~t 3 .st?rey
• intervals or less. In public and commercial buJidmgs
and more complex drainage systems, access should be
provided at each floor level.
The discharge from appliances prod~ces pressu~e
fluctuations and the system must be des1gned to retam
adequate water seal in all traps under normal working
conditions. The pressure effects that may occur are due
to self-siphonage, induced siphonage and back
pressure. tt mav In! necessary 10 use a vtmtilating p1pe ·
to limit the pressure fluctuations in the system within
the acceptable limits. The effect of the flow of water
from the appliance into the branch discharge pipe must
be considered taking account of:-
(a) The design of the appliance (funnel shaped
,. appliances increase the. possibility of self-
--~-~s.lpnonage)-.-··--·- ·· ··
---------.. . . . ;......;.--.:.·•. . .....· . . . . . _, . . . . .
~.·· ·~··_ ~ "-"'o.t----.----·-------·-~ . _,_ __._ . . . ·~--·-·-·-· _--...,;... ___
·l Foaming contim.ied
'• .'
(2) 5 storeys up to and including 9 storeys - Where adequate ventilation is provided to the system,
connect ground floor appliances to separate some small increase in the stack loading above one:
,• discharge stack or individual connections to quarter full can be considered. Such an increase should
drainage system. not. however, cause the pipe to carry a flow load in
(3) 10 storeys up to and including 15 storeys- excess of one_ third full. Guidance as to the probable
ground and first floors to separate discharge stack loading to be expected under any giyen_ conditions
stack. or flow rate can be obtained from the Graph No. C3.
(4) 16 storeys up to and including 25 storeys - '
ground, first and second floors to separate From the hydraulic conditions given previously and
discharge stack. from experimental deductions. formulae have been
(5) Over 25 storeys - relevant practical results derived to enable the flow rates in tall stacks to be
should be consulted. . computed. Work carried out at the Building Research
Station and the USA National Bureau of Standards has
confirmed that a formula of the type
Air test
An air test should apply a pressure equal to 2. 4 mbar q=Kdt or K~
(38 mm) water gauge and should remain constant for agrees closely with the observed flows in tall cast iron
a period of not less than three minutes. The water seals · stacks. When the pipe is loaded at one quarter full,
' of all sanitary appliances which are installed should be
fully charged and test plug inserted into the open ends
. of the pipework to be tested, each plug being sealed
K = 3 · 2 10 -s. For other flow loads the value of K is
as follows:
with a small quantity of water. One testing plug should 1/3 full K = 5 · 2 1 0- 5
be fitted with a tee-piec~. with a cock on each branch, 1/5 full K = 2 ·1 10 -5
one branch being connected by a flexible tube to a
manometer. To apply the test, air or smoke is introduced 1/6 full K = 1 ·3 10-5
into the system through the other branch of the tee-
piece until the desired pressure is shown on the where q == discharge capacity in litres per second
manometer scale. Alternatively, the pressure may be
applied by passing a flexible tube from a tee-piece
d = diameter of stack in mm -
attached to a manometer through the water seal ~f the When K .:... 3 · 2 1o-s (i full) the calculated values are
trap of a sanitary appliance, the t~ then being carried as follows:
out as previously described. Table C2 Maximum capacities
Defects revealed by an air test may be located by the of stacks flowing quarter full
following:- • ·· · ~
(a} A smoke producing machine may be used which
will introduce smoke under pressure into the :·~~::~~~:!IJ~!i~:~~:;t:~~~~,~c1~;~:t:.:~z::
defective pipework. Leakage can be observed as 50 ::c 1 . 10 :.: . :' 70
the smoke escapes. ·
(b) Soap solution can be applied to the pipes and
65 :..- 2·00 -....·. - 175
/.- a
· joints, under test, leakage can be detected by the 75 ' 3·25 -,. 375•
formation of bubbles. 90 .. 5·00 ~~~.'. ~ 700
Capacities of stacks
100 u 7·10 "::.,-.
- 1200
Owing to the terminal velocities which are attained in 125 r 12·30 ..~ : . ~./ 2800
vertical pipes, there is a practical limit to the capacity of 150 20·60 .- - -~ 6000
any given stack. In order to reduce hydraulic and
pneumatic disturbances to a minimum, most authorities •not rr.cre than 1. \V.C.
recommend as an upper limit a stack loading of about a
quarter full. This degree of loading provides room for an Estimating stack loading
air core to flow freely down the stack during fluctuating Most methods of estimating the probable usage of
• _discharges. appliances and the flow loads on discharge pipes and
systems of underground drainage are, in principle,
The maximum flow possible at any given stack loading methods of applying the Binomial Probability Distribu-
depends also upon the frictional resistance of the inner tion Law to practical conditions.
surface of the stack. Smooth pipes of copper and
plastics allow slightly higher terminal velocities to be The probability graph, No. Cl, page 72. shows the
reached than in rougher pipes such as cast iron. This probable usage, baseq on a mathematical certainty of
cfifference in the final velocities reached is not, however, 99% success, of various numbers of sanitary apRiiances
substantial_ enoi,Jgt) l9 effect materially .the discharging tor the given conditions m value of 'p'.. . " --
capacity of the stacks.
. Terminal velocity is generally in the range of 3 to 5 m/s
per second depending upon the size of stack. quantity of
where p = -
t
T
flow and discharges from branches. Terminal length is t = time in seconds appliance is discharging.
the distance that a discharge must fall to reach the
: .• constant terminal velocity and is generally achieved T = time in seconds between successive usage of
within approximately two floors.· appliance. · ·-- -- · -, ----------c--
.,
I
~-~
..
. -... -................... . -.. ................ -.--....- "'-··~-- --·-~~- ...... ___:_·
-~~---·_·.·~;_: ·::···.
•
.
. .
As an example of the application of the probability ratings to be assigned to the same appliance to take
graph to a practical case. if 100 applianc~ each of this difference in usage into account (see Table C3).
which takes 10 seconds to discharge their contents are
used at 500 second intervals. the value of
Discharge unit-flow rate graph
Graph C2 has been prepared to enable the flow load
p =-r - t
~ = 0·02 of various kinds of. sanitary appliances to be estimated
500 either when in grbups of the same appliance or when
used in conjunction with mixed groups of sanitary
Reading from Graph No. C1. six appliances. only out applianceS; The axes of the graph have been given in
of the 1 00 installed can be expected to be found discharge units and the probable flow rate in both
discharging simultaneously. If, in addition to the above, Imperial and sr metric units. To enable a rapid assess-
we know that the maximum flow rate of each appliance ment to be made of the diameter of a suitable vertical
is 2 litres/sec.. then the probable flow load to be discharge pipe for any given loading, the right hand
designed far is 6 x 2 = 12 litres/sec. scale, marked in both sets of units, can be used. It should
be noted that the actual flow rate in litres/sec. (or gal./
Discharge units min.) is the real capacity of the stack. Any discharge
(·
• In practice most systems incorporate many different unit system which may be adopted in design is merely a
kinds of. sanitary appliances which may, nevertheless, convenient method of determining the flow load and
finally be connected to the same discharge pipe or drain. thus a suitable pipe diameter.
Under these conditions it is more convenient, and
indeed essential. to use a system of related unit values Drains receiving discharges
which have been determined mathematically to make from vertical stacks
it easier to design for these mixed systems. These unit Permissible load on drains
values, which are assigned to each appliance, are Where a vertical discharge pipe is directly connected to
usually called discharge units. a drain, it is recommended that the horizontal drain
Any system of discharge units must of course, be taking the stack load should be not less than. 1 00 mm
related to an 'index appliance' which is usually given a diameter and designed to flow nat more than about
discharge unit rating of unity (1 ). In the system of units two-thirds full at peak conditions. This limit on the load
adopted in this publication.. a domestic wash basin, to be placed on the drain is to prevent surcharges
·having the lowest flow rate and having a small probable causing high suction in the system.
usage has been adopted as the unit appliance. All ather
sanitary appliances therefore have discharge unit values Connections to drains
which are numerically higher than unity. Depending Any direct connection between a vertical discharge pipe
upon the precise usage of a particular appliance it is and a drain should be made by means of a long radius
possible for a number of different discharge unit bend or, if adequate vertical distance is available, two
Table C3 Probability data and discharge units for sanitary appliances connected to sanitary
pipework above ground
t- T · probability flow rate discharge
Appliance sees. mins. 'p' litres/sec. gal./min. u.nits
W.C. (high level cistern) 5 20 0·004 2·27 30 6
W.C. (high level cistern) 5 10 0·008 2·27 30 12
W.C. (low level cistern) 7 10 0·01 1·82 24 12-
W.C. factory (male) 7 3 0·04 1·82 24 45
W.C. factory (female) 7 1 ·5 0·08 1·82 24 90
W.C. office (male)
W.C. office (female) ' 7
7
10
3
0·01
0·04.
1·82
1·82
24
24
12
45.
Wa?h basin (domestic) 10 15 0·01: 0·34 4·5 1
Wash basin (factory) 10 1 0·15 0·34 4·5 10
Wash basin (office) 10 2 0·08 0·34 4·5 5
Sink (domestic) 20 25 0·015 0·75 10 3
Sink (canteen} 38 mm waste 80 20 0·06 0·75 10 12
Sink (canteen) 50 mm waste 50 20 0·04 1 ·12 15 15
Sink (small laboratory) 30 8·0 0·06 0·08 1 ,. 1
Seth -{domestic) 75 75 ''0·015 -·, ·"06 14 6
Bath (hotf!l) . 75 30 0·04 1·06 14 18
Bath (hospital) 50 mm waste 60 30 0·03 2·27 30 35
' Urinal (per stall or bowl)
Shower (domestic)
10
120
20
10
0·008
0·20
1·00
0·08
13
1
1
1
Shower (public) 180 12 0·25 0·12 1 ·5 4'
t :'.:.;..c,~:.....N;()!!'.:.~P.I:)!ia.nc.es having a continuous flow from their o:.:tle:s should have the computed flow rate added or. to that predicted by using
~~~~~~~~-q_~._u.~~ts, for the other fitments. ··
;~ ~->·$§1:~-~
..
~- :.:.: ....
.. .....
- .... .: ~ ~-
The amount of air required to limit the pressure loss Guidance as to suitable ventilating pipe sizes for various
.. varies between about two and five times any given
water flow rate•
stack loadings may be obtained from Table C6, which·
is based on .. the previously stated pneumatic and_ .
hyd~ulic considerations.· ·::_;,
.•.
. .
.Table C6 Diameters and lengths ofventilati!Jg pipes··
Diameter of Proportional Discharge : . Length of ventilating pipe in metres ...
·' ·..
discharge pipe
mm in.·
load on
Stack.
units l
40 mm .. 50 mm 75 mm · 90 mm 100 mm 125 mm · 150 mm
~ .. 50 2 0·25* 85 70 300
l. . . '75 3
0·15
0·25*
100
450
45
30
300
200
l . ~ -.. :::.. _-.-....-..--..-.·._____.:..0·...::3.:..3_ _ _ _~;.:::;.;__..;,.__ ___:_~=::....·--·~.:.:~:.:.0...:,__3_0_0_____:_______..-.. ---------------
\!:. . .. _;·.'.;
.•-(
·.:.
-- --- • .-90
. --- . ----
'-
_,;,;;;.;;;_,___ ~_.....;.....~..;:.._--.:..:3..::..00:,....__ __;___1:..:0_
..... 800 -----·-.···· - - . --15 .: - 11 o... --.200
. 1550
,-·10 - ---·90 .. 150 - .._...._.,... ~---.-
_...::~__:.~----;.._.;......;..- ....---:-,
.......
-~----·-···· .·-···--·-
75 . '160 300
'-1···_·=.. - .·. 100 -~. .50 .- .:100
k2gg
90
200 ......-:.::"·~:-.
'·
_._·. --~--·:.-~-·
..
40 160 :!·-
Table C7 Minimum sizes of discharge stacks and ventilating pipes required for various
loadings; Dwellings ·· · .. · · · ·
Stack . . .. •... :·-·
··, . . . ,_·· -_,~
. diameter
Type mm Requirements
( Houses· ..
:-·. '.:·'
-·: _.,.
•• <··
Single family dwellings
up to 3 storeys 90 . Single stack
...
.
~ ·:--·:.·.· connection on alternate floors connection on each floor
. Up to 12 storeys 125 Single stack · Single stack ··' - .. .
12 to 15 125 Single stack-c ····- 50 mm vent stack with one - •. · .: : ·
· connection on alternate floors . ·
Up to 25 storeys 150 Single stack Single stack
i
Section C Sanitary Plun1bing and Drainage
t'"
I. of appliances connected to a common branch in a The flow rate for 615 discharge units is approximately
building where very congested periods of use may be 4 · 6 litres/second.
_ _ _!~~~c;t._-~!...s..c;;hool_s, ~he ~gures given in co_lumns 2 As a 100 mm discharge pipe at one-quarter loading can
· ·and 3 of Table C9 should be doubled. carry 7 litres/seconcj! thi_s size wilt be satisfactory.·
I-
l. .•
I ..
I The separation of foul water and rain water (c) Incineration of domestic refuse can be achieved by
The separation of foul water and rainwater within a open fires but where this is not possible, the use of
0 building is recommended and recognised as good small or larger units should be considered.
practice. Where rainwater is allowed to enter a discharge (d) Sanitary towel disposal can be carried out quite
stack. in the case of a blockage, it can cauSE the
i
·~
building to be flooded with sewage. The practice of
combining foul and surface water within a building is
cheaply and quickly by incineration, maceration or
in sealed units (collecting bins) for either storing
for bulk disposal or utilising a chemical solution to
therefore extremely inadvisable or contravening the destroy the used towels.
Building Regulations and Local Authority requirements. (e) Owing to its varied nature, hospital refuse should
Grease traps are used for the treatment and/or disposal be di!;posed of by maceration (near as possible to
of grease laden water. Types available enables either . the disposal source) or by incineration.
the retention of grease which has to be removed at (f) Compression systems are available which reduce
regular intervals or with the addition of special powders, the volume from !rd to 1/12th.
the grease can be chemically broken down (actimatic (g) Composting refuse in agricultural areas is consider-
type). . . ed the most economic method of disposal. Refuse
Floor drainage should be provided where drainage of collectiqn and disposal methods used should be
water is necessary from adjacent or su~rounding floor determined in consultation with the Local
areas and direct to the sanitary pipework system. This Authority.
provision should be adequate to cope with the
operations and functions to be carried out in that Sanitary Accommodation:- .
particular area. Flushing gullies should be provideq to •(a) Reference should be made to CP 305. The
· overcome problems associated with cleansing of sterile planning in most instances is performed by the
locations or locations where cross infection may occur Architect, who should be advised of special
once the floor is washed down. The contents of the requirements and where an alteration to the
gully can be flushed away and replaced by clean water. layout, within structural limitations, can affect
Potato-peeler machines should be independently con- economies and performance.
nected by their own discharge pipe, to nearest stack or (b) Hand drying facilities can either be (1) disposable
drain (!nd. should only be flushed with cold water paper (2) roller towel . (3) warm air electric
because of the high Starch content. machines.
Vegetable paring machines should be drained in (c) Soap solution dispensers, fed from local or central
consultation with the Local Authority depending upon reservoirs provides a ready alternative to the
whether water sprays or sludge interceptors are provision of bar soap. .
I' required and where positioned in relation to ~nnec- (d) The use of the spray mixer tap has produced
~~ . ' .
savings in water consumption, economies in
..
} .. •
-------------- --------- _____. ··-· --- ..... ····- ----~----- -- --- .. ·- .... .:. ..,. _____ ·- ----
.
Section C Sanitary Plumbing and Drainage
...... ~-
i\[\.
. I ~1
. ..~'\ . . ~ ~~~~~
. . j
\\
~<l~t-.;,.
. '
\ .~ · .. 1\ \~ .
. db
A
0.·~
.. 1'
.· r\ ' .....
.. ..
.
..
_-
. -·
. ·.
....
.
-·.-
-~-
·_..
...
.
.,
·- ·-
~
.
i\ \ .· \ 0
0
g·
..
"0'' \.
!X.l~
I
~
0
0
CD
.\
'\
'\ \ ·.'\. ·>K\
_,
\. )~ •\[\
.·'\!~ .. \..,
~
x·
~
\ .J\1 .
'~
i\ '
1\
"'r\. .\1. ,.f\ .\ \
\.. \
.
..
--- ~
. -
·"
[\
'~1-l~\
I .
\.
... -.·.·
..
..
----------- ..
...
g'0 ... -··-··-- -
. < -.·
~- \ l\1 ~ ' .,
~ '\ '~I'!\ ~ \I\ \'
·C.
' ~
. l'\1 :'\ "
. ·. ..r- ~-
.\
r\. . ~ \.
--. .
'
.. ~
~
I
~ '
\
\ 1\t ' \
-·.
\'\1 \
f'd ·. 1\. ~- '\1~'\ ~' \' ~·\ \ \ 1\ 1\ 1\•\ --
-c'
r .. .
...
":
' . ,. . i\
- --
_Q -- -· -
.-··
1\ \ ~ ~- i\ ~
.":-( '1\·~
..
\ 1\~ \\1.\
1\ ' ' ·"
" ,. '
'
,.
·. :1
! : ;
..
i\ ~ i\ ·.
"'
-
"\. '\.
~
~--
~
'\..
\..
"\.
I"· -,.,:
' \.' ·i\·.:\ .\·;·\
·l\.
'
\ \
\.
'\.
\
\.
:1\. f'- '"-
~
'..
.
.
\ . ·..
'\
.\ \ ' \
.I\ '
'I
1"\.' '" ~\
.i\.
~.
· ..
\
~
\ \ l\' \'~\\ "'' 0
'"'~ ..
~ I~
\-';_\ ~\\ g- -·:~-{:~.~---.~· .
. ·.,.
.
~
.. .
. ~-
..
i\ 'f\1\[\ '\ ~
- ... ··-
-~
- \'··'
\ 1\ i\l\
..
1\ 1\ ~\ '\\
---·-. . .. -· ... ·--· ..... ....
···_---~~~-~-~:::~---~
"
\. .
,··\ ~- \ \
~ .
!, ~ ,'?; :~ ~· _.,_ ·:..· .. - -· ..
I -\ ,K\
1\ 1\\ ~
...
\ >: \
..
.· ..
~· ~\!'
..
.
"": ..
,• •,
<~~:;. .
fl\K'
',, .
.
.. ·- ~-... -~. ~ >:~. ~
.·
..
: .· ". . .··
.. . ·.
. ' 0 0 0· ·0 . 0 0
I ···-$2·· CD"'- '0 111 "''
.. ----·-------- ---. ---'---· ... ~ .
··:· ..
\ .. .. ::.~~~~..
I
···· ..
Graph C2 Discharge units and flow rates
•(IIJll Ja+aenb) S)[:>elS J~!lJSA lO JSlSWe!Q
~·~ ~ V) g 0 ~ ~
.5···~----------~~------------~~~.
~ J.. ~ -------i-----------i------------~+---------------~V)
_,,._ ~ _{N ...
M N
·---· --·--··~·
.. .
a1nu!w -!ad suoneB U! a1e.r MOJ:I
:.
~"-
'---------+-------t--1---t--"-t.-'
r
~.: ..
"'
1-----+--~'-..-+-.+-...-_+-__- __ +---+-~---...- - + - - - - + - -.__.,--__+-----,.---1\ ·:;:~~
r-------~-----~-~r~~~-;-~r--+----+-~~'---·--+------r---~r----~--it
... o·.
•:--+-------t-.,----+---------1 S2
""-.~;......;.--+----+-~
r-------~---------+--~~~~~.~~~~i~--~--~--~--------r-------~------~
0 .· :c :·:·"·:
. ,_ •
...
\. <:
. '>".!.
•:-·· ..
' ... ..:. .
~- ·:. .~· ··
·.. ..r: . ~ .
._..··
.'... ·.:·:".: ...
______ ._.....,_..,_...__......... .........., ____ ~ -; --............... , _____________ ---·-
. ·_ ~ .... ~-· - ...
.:.~ .-
Section C Sanitary Plumbing and Drainage
: . 2· 3 4 5
7
6 . ·7
.,,
7
..
~
.. :···,
l--------+------+-o.....'----+-I--I---+-/-+--/+--+-~II-+--L4ooo
I I ·I II
15 l--_..:...----+--------+--,-+--+-7-+--+--:.7,___.,-l-7-+-~~
l - - - - - - - - - - + - - - - - - + - r - - - 4 - - - - v - -II
--HIL---i-----4-3000. I 7 -7 ....
. / .· ·, ... 1__;_...;;.:._,_
•
1--:---·--··----..;.···.:..--·----__;;_-+-·.;;;···;.__;;,;;;;_~~-++-"'-'-'--J·~...;...__;_;_,I+
if_ ···'.
_;-4·;.;.·_;·~ -- -=~:·:.~ .,..
1/ . ___ /_ .. 7 I _ .. _-_.:.._· ·-·.--.::.
,_-
-
JO
.
9.0
~ 8.0 _,....
I II 11. )1 -I :,-.---,_~
.. · .· .. t __
1500 .. · ._·::·.: .. -
. . . .,--
~
·:__ ·_'(
. .5
I.
1,.
1(,
,..
.. _
. •;-·.··
Sanitary Accommodation
. ' -:.· . . . . . . .
._,_,
Reference sho.uld also be made to CP 305: Part 1: 1974 or latest edition.· - . '• ~~---
;.~ ~:it;};~~~~
For over 100 additional
,_;: .. _·
.provislon determined by
r>-
L· ~-
J the number of wc·s - .·· ...... - . ·-. -c-C -':
i (see previous item)
•Wash-basins-
·trough or. ·
1 for. 1- 15 persons
· 2 for 16- 30 persons
·r: t -~g =~r?::.(_ -__·: :-_:<,::::,~r;~~
1
· 3for 31~ 50 per-Sons·, · · ·· · ·· ·
washing fountain · 3 for 31- 50 persons
4 for 51- 75 persons 4 for 51....:,.'75 per-Sons_--_ .. ··. · --
_ 5 for 76-100 persons 5 for 76-1 00 persons" _. ·: ...
For over 100 plus 1 for For over .1 00 plus 1 for. ·· ··
every additional25 . every additional 25 · · .'. . . . ..,
persons or part thereof .. persons or part thereof
I
~ .
:: Cleaners· sink At least 1 per floor, preferably in or adjacent to a sanitary apartment · ·
Bins, Incinerators 1 in every sanitary
'. or Maccerator units accommodation regularly
r... . for sanitary used by femal~ __ ...•.._:..-
• ··---··· --·- __ dressjngs_ disposal
__=...;._.;.... _ _.__;,_ _ _ _ _ _ _ _.;.__ _ _ _ __;__ _ _ _;___;,__;;;..,;;;;,;~
. ;·:~::·· -;:.:... ~. - -
~.: .. .,. . . ·~ ~
. ·...
... ~·•·.~. Sanitary accommodation . . , .. _: -~ _:..:~::_.~ : ;:. .~~~
.. ·.•· ....... . ~ . .:•.·.:-· --:-·
.d ,•'t.
·.:_..
_.. :.Table C11 Dwellings . . . . . .t
.. .
No. of persons '. _·. :·,· ····.-:-·::..-._~: . ' .
_ _ _ _ _ _...;._ _ _ _ _ _ _d_w_e_n_in..;g_s_s_u_ita-:-·-b-le_f_o_r_ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _···~··~·~-·-·_...;.;·..·-.·.,;.·~'·...;.·· .. ,...
·· Type of dwelling Appliance 2' 3 4 5 · &and above Alltypesandsizesofdwellins(:', :---~· · ·
' w.c..
!i-·.
~
-·.Dwelling on
>:-.<;one level, e.g. Bath .. _
:. ::' 1"'
1
1•
1
1t
1
1t
1
2t
·1 . .•.•. . ..- ' ·-."'~ · . ... ·' ·. ::~< ~~:._ ~.>~£0·:~~) :; ;;;~:~ I .._. ··. :.
bungalows and Washbasin 1 1 1 1 1 and in addition 1 in every separate w.c>.
flats ··compartment which does not adjoin •'.: ( ··
·;'
". Sink and
a bathroom ., ·
_I i drainer 1 1 1 1 1
Dwellings on W.C. 1• 1• 1f ·. 2: 2! ,, . '
two or more Bath 1 1 1 1 1 .... ·:, ·. . .. ·. " . :· :.
- .. ---------levels,-e.g.:~.--- .. --. -Washbasin- 1----1 --1---- -.1 · · 1~-- ----- and in addition-1 in every separate W.C:":-"'--::-";~
: ,--. hduses or
.. ____ .......... f~~.:':,"-!.'Nhich do~~-~-~()~".~:... :o:· -c~
-~( ~- · :~":~~ison~tteS. -~ ~---sdin~ and dr<ti~er . , ..... -- ·1 1 · · _:-- :_,.__ -· .. · · ·: ·· ·:=:~- ·,:::::::::~~r:z~-::;.0:::.-=·::~~
. · : · .. · : . . , . ramer. . 1 -1
-.--;·.
'
i
,l ··. ~!~~~~~~:.~:~.:.::::::::::~:• <"""'' """" •~ both
_Note 2: In Scotland ...a washbasin is required in every W.C. co,mpanment (Regulation 07 (6});.~ .
1961. soa;on 33)
-<; ...:•.~7_'.!t':•:::.s_..,__-,_~.-- -~:-:;·
Note 3: In Scotland, a shower may be provided instead of a bath in a!! dwe!iings both private and. public (Regulation'07): · ··; · .· ..
. ·~. ~ :·~~~~-,;~ :~
•. .··
. This table is based on 'Homes for today and tomorrow' (the Parker Morris Report) and of the: Cir~ula~ J~/37 Ml;liitry:~f:~-~-J~i~g ~~d >: •-
.. Local Government. and the new Scottish Housing Handbook.Btilletin No. t, Metric· space standards. Attention is direCiea:fo_tfie Builcling -~-~7
·. Standards (Scotland) (Consolidation) Regulations, 1971 where these apply. · · · · · c ,.'"!.~<<;3'>/ ·: · '>-
. •• ·.-:·.~. ·::._ ··-:~·.•.:·{'(.:: ·.:·.:·l.; :·.
:~b:~·:::·::.::::~~;~~ ;or 7
elderly p80Ple
--...;.;.------~-----------------....,..-----....,.._.,.~---~~-.-·
__ Type o~ dwelling Fitment
~ ;~::~t~~i~~
··•·
.. · -~ ,:;::);'::;r;:~~,::.;L:'·'~.<;~~f~:
Communal facilities Where communal facilities are provided the following additional provisions
must be made:- · . · ... · · : .
Common room for self contained · · W.C.-- at least 1 .. '· •···;:;.:.· ,._ "···, ,. · ..
·I or grouped flatlet dwellings Wash-basin 1 in or adjoining the W.C. comp~~~~~i;~;-~:.L~~--~:-- ~' _._.
'_J. .. _Tea pantry._or kitchen Sink and drainer_.-: J :. _ . adjace~t to common room:}i..~-~-~ :~~0iZ.~.:::~~~~~~;::~-~
. i. :
.
l
I Laundry room-grouped flatlet Sink. 1
. I .. schemes Washing machine 1 _; ......
!. Spin drier 1
'.l
·•
..... ·.•.
...
. '~.. ·. . . .
'-~·' ' . ~. .. ., '.' .. ~ . ' .•.. ··.·
\ \
'1"
"-r .._,. .
•
,. J.···
·I
.. .• •
.. -\'·
I I ! ....
...
·l· •.
J :;
. .. ~
Table C13 Residential Homes
:::.
~--.-.
Basic bed-sitting accommodation with other communal
; .· ~-:: · : rooms including dining-rooms. ···
. L:. ··- . ;.._;• ..
,.:-~. Baths .·. . ·1 to 15 . __ . ,. · -·-· .. ! .
-~ .--~'
l .- Hair-washing cubicle 1 per floor.
-'!'
-~ _..,. __ .._. -· Cleaners·· room - ~ ;;..;..;:... -'--· ·_:::'; ::~: .\~.:__:::... ...-.·...:-=!::
Wash -basin · 1 to each bed-sitting rOom '
·-.. -------. :···~::·-~-....;.. _.;,-~----~~--:-----~----:7
-,-,::·:~ Sep·arate--cwas!ting arid: ... W.C~fac,lities tor visitors: .shou1c!- -bi. -~ --~----- -.-~ -- ··_.-_·-~:~-~\: ~~~{7-~~~~~~ ~:~-~:j;~T~~~-f.~t:~--
_·· ·:· __ 'COnSidered. -+~ .. -5.-:~.:. . ·· - . ···- ·___ - ..... .; : :· ..· _:: .. ~; .
.·~as:d on_Mir:!suy Of Health { Lcce! Authori;:y) Building Note Nc. 2.
."Homes ior·elderly people.· · .·· · ,... : :.- .:, ~_:- \_·_: .
. . •·:.:.·-~- ·--i-J
(-. See also 2.24 of CP30,5~ ~ait: 1974,
l ~. .•..
_.,.
I !•'
1--.---·
) .~ .
Table CT4 Factories .·.... ·:·,,
Auention is calle_d_ to the Factories Act 1 963.The S~niii!,.Y Accommoda~ion Rt>guhit 11 ·t~• ~
· n. Er 0·1 ~38 No. 61.~ ~~:~d. ~t~~r Reg~l~ti~~~
applymg to speclflc·trades or occupations which may·requ;r~ more extensive pro~i~;,,._l~ .· ·. · .- · ::_ !" ,.. ···.. ·'· •
Note: Attention -is drawn to the necessity to
provide. facilit~ for the disposal of SP.t'M•'I- ~,.,:.sr_llgs. - · . -, .: ·_.:. ::' ,., .._;. · .. :F.
See also 2.2.5 of CP305: Part 1 : 1974. 1 · · · ., · .' ' ' '
....
. .. ~ :
.··~: .
....
. .····
..... ·.
~-c'~·§J:::~~§:·~--~;,·,·."-'~~i:":''""~;f)::.-:'.
::·>;~~?~,:>::<~;~>-
' ·.·. ....... ... . ...··
:.. , _: _: .;~[.: ;s;_. /L-0·:_::. ~~:~~;~~:;-;;~( ;.:;~~·);~~,_;:x.~~::-..~ -~- ~: ·x :~ ,:,;.,;;gd~i;:;;:~¥;;~:~~~~~~
..... ... _,_
., .......
\ ... .
I ,
\
Section 0 Sanitary Plumbing and Drainage \
I •
.
•
.···:.··
.~-·-,:·:Sanitary accommodation
. ·.·: ...
~ ·.;" ..
Table C15 Schools
~-:·:
• ', ·'fitments
.
·
..-
Special Schools Primary Schools Secondary Schools
<All. ~fittings'· ·. 1 per 10 pupils less than 50 pupils - - Less than 1.000 pupils .
. _, ·:.te~ ,: _.:.-. · -·
1' ••
1 per 10 children . .. · · ·
'
'· · 1 per 5 children, where more than 50% stay for a mid-day meal or
',_ 1 per 10 children
l
Bath sinks· 1 per 40 children
·.. Boarding Schools
. W.C.s ; 1 per 5 pupils
J • Wash basins :: 1 per 3 pupils for first 60 pupils
i\ 1 per 4 pupils for next 40 pupils
·s;f~~ihi- ·-·- -· --~; -~- ~=~ ~d~~~fJtor every additional
,:-·
- Shower baths
·-..-~----,_;_ · :1 __
May __________________________ s_ pupils:t _
be provided as alternative to not more than half the number of baths
......;_...;..
. :.. ~~here sanitary a'ccommodation for day pupils is accessible to. and suitable for the n~ds of boarders: these ·requirements may be reduced
:.~;-:to such extent.as may be approved in each case. . . :- __ · · ·· : · · ...
?:;;N~te_: A_ttention is.dl-awn to the necess.ity to provide facilities for the disposal of sanitary dr9Ssi~gS. ·"
· the Standards for School Premises Regulations, 1959 (S.I. No. 890) as amended by the Standards for School Premises (Middle
. Regulati.ona- ~ (S.~ N&-. 463}. -- .·' ; : .. · · · ,.joi":,,.:":, ;;_,_ ':;;-,.' . · c .. ~,,_:,:./:::~-~:.,.~;:;o::.>:,;::~~ . ·.!:;::
blishm1~nts not mentioned above reference should be made to·the Department of Education and Science•-"'·''· · -: ·-·::7 .. ,._.._. ·: ·
·in .Scotland are based upon the School Premises (G;;neral Requirements) (Scotland) Regulations 1967 5.1;1 967 {1_199: . - . ·-- -
-_ of..CP.305 :Part I: 19.74. . _ ,· . . ~- . . ' - - ·.· . .;. . ,::·. ·.;
••• '1:
',::: ,·,.
; .-; .,T, ,c·'-:_-~·'=-"· +':,.:-•~-".c- .,;-c;-" . -'~· ~ ·-·;~_:·~·'., :i~~,:.l;~i~*~;~i;{,i~ii~~i; ;:;·. . :i:I~~~£j\i5i
••;
. ·~ ....... ·..~ .. -~·- ~ --. ·. "" .
\·
\. ' .. ·:.\ .. · - ·~'
~. I.
i-·
\
.....
·:··
-..... -;. Table ci 6 :Cinemas, Concert Halls, Theatres and similar buildings used for public entertainment·
Fitments For male public• · · · For female public• .' .
,,~!;::.·'···::- ·. Water~closets -· .. In theatres, concert halls and similar.- .· :Jn' theatres,; concert halls and similar .
.. . . ··~· premises: .· premises-~,-., : .::·· : . · · -· · · · · · ·· · ·..:.~. ·
·' ..
~~.: • ....:~ ·: \·: ..:~: ·~~ .. -~ ..:
: .
. .. ~~ :
Minimum 1 up to 250 males plus 1 for every · ';:'. Minimutt;.2 to 7S fernc~les plus 1 :or · up
;i·
additional 500 males or part thereof. · · ·- every adQ.itional 50 females or part ·
· thereof. · · ~ "_ · . · ·
In cinemas-: · -. · '
.. ·.. · =·
In cinemas:
Minimum 1 up to 250 males plus 1 for Minimum 2 up to 1 00 females plus 1 for
every additional 1 00 females or part ·
every additional 500 males or part
thereof ·thereof.
See also t . See also t .
··.·Urinals In theatres, concert halls and similar
.. :.-...• ~-:=--· ...::..::•. :...:.- -·- .. - -· _ -__ premi~es:_ . ____ ---·· _____ :.:;.. . ·-=-~ ...:.::.:-.:.._.::..·_-::·.:..==.:.·-~ .- •..:.: .. :·----=---··:: ___________________ _
Minimum 2 up to 100 males plus 1 for . -------:----·:--·----_;____ :... ..__________ ...; ______________...,..: __ _
-.·!: _· = ~--·7 ~~~G~~~:~~~--~~<.-; _-._r;~%;~a~~les or part thereof.==,~:-~= __ .-.-• --.,~·-= ~-- . . . _..,..,..,. -~ ....._...:_~"":"'--~- ..... ···•.. ~;, ·--:-·· .:: ··.- .:. :~.:~;·.·.---~~~~:;.
...
. ~:.-~···:-~i;·.",~:-···' -. ·-:- ..
.. , ·..... . Minimum 2 up to 200 males plus 1• for ·-·-- ·"' _-··· ...
every additional 100 males or ,
. :.:-·:.•..._.·.:·: ..
.
...
i··:wash basins 1 in respeCt of each water-closet and; In .. _ 1 i'n respect of each.water-closet:,
·~
>: ' :: .· ~
~_.
· addition; 1 .in respect of each 5 urinals
.--- • ·:. : •• p •• ••• •. . .
___________-..,;.,;--.;.----------------------------------------
'.
. .i.iCieaners' sinks ·_
.~.:< !J;:':;;.\.:•~<· · :'
Adequate provision sh~uld be made for cleaning facilities including at le~~ one:·:··.·:·~::·· '·-~:
· .· · · cleaner"s sink ··- .. . ~ :. - :·-: .- ..- . . · · · • · _..,_~:'' ~'~ ·c :::.:: ::· ,-.~-:
····:.:-;_.,
;' .· *:.t(may. be assumed that the total audience will consist of equal numbers of males and femaiEis. .. . ..•.. , • · · ._,':. ·'·
,·!
.. '}rn;~:ases of buildings or places (includ:ng churches. places of histone interest etc.) where·a· numb~r of people cong~ega:el:~a~it?rY
.. ·accor:nmodation should be provided -having regard to the anticipated maximum n)Jmber of people congregating there.:·::' .. ~~·,:·:;:":~~.;·_:6~;;;· :-,.-<· .
<
·.·Note: Attention is drawn to the necessity to provide facilities for the 'Ciisposal of sanitary dressir)gs~< · · . · ·.·. ·. · ;iX-< :'·);\::.·~··: __ . :·
·;, -.~e~~-a_ts~.2.2.7 of CP305: Pan 1:1974. · · :.. :-'.:i:··< ··-··:~. . .:::,::~ ..~:j:;::;·~~~$;:~:';1\
·'. .--. ·' ·' · ·. ' ·· · ·" Staff . \ . · : :'" :::;.- ·:< · ·:· •. ~;-:' :. _- - ·-> ·!_..;;:: :.~~ {'\,:~·· i:,:·~,,.::}:;{
·.:;>' :~ .· Some members may be subject ici the Regulations made ·urider the· Offices, Shops a'rid ~2? :~ <.:~. ~'
.. ·... '- Railway·Premises Act:; for~mbers, the Regulations should be used as a guide.~"~;~· T·.; •.
Performers . . ~-:~ ~- _ . . ._. · · ··: . . ~-. -~~~--~ . . .-··~.:··:~ ·. :: · .... ·
··:.· The sanitary accommodation provided will depend upon··individual circumstances bUt - : , ·
.. ..: guidance may be obtained from the Regulations made under the _Offices, Sh~_ps.and ,
Railway Premises- Act. · ·. · · ·
,,.
I_..' .
.. ·...... ~ .. -:'·.: ..
•
- ...
. .. .·
.
. . .. . .
.. ··- .
·. ~- .:·::·•, Sanitary accommodation
...... ., -·~. '
·.-.-.
... : ~ . ..,., .
-
~--· ..... _ . . .,.,_---~------l'-· occupants~
. · · . baths en suite
rooms with . . .-.- ---- ..... ---. -- -~- _,;____,._;;,;
"!" ....
__::._:_.:..,__·
:·--~-.. -;-.
_ ___ _,
: ( ·:,.:.:··'
:_.,;_· ____ ------~- -·-.· __ ._ ---.-:.. ..:-. ..:.;,~--
. Wash basins 1 in respect of each W.C. 1. in respect--of each·2 W.C~ ·_ ·.. :: ·•·
. ;:-· and; in addition 1 in respect of :·<·.:-.;;~~·::-~·.:·~. -~~. . . - :• -:::---·~-
x·" =,~ each 5 urinals -~/· T--=-~ ';.·.-~----.~; :_; _.. _·; .- .,
Nofe 1 : Attention.is drawn to the necessity to provide facilities for the disposal of sanrtary dressings: • ·.··-' :·..,. -- · ·, • •· :: ...:· · · ·
.;· Note 2: Attention is drawn to the requirements of the Food Hygiene {General) Regulations:1970; thti' Food Hygiene (Scotland)
·Regulations .1950. ·· · · · - · · · ··
-~!'ie also 2.2.9 of CP305; Part I: 1974. .. . - >
. ·I • • -~ • •. J • .-' ·._·. •/ •
...
~~~~$.:~·,·,~~,,••·.'•·
·: ;~-- . • • .• 1 •• , -< ••
.·::jJNf~:~:{~<~1·?i-~.&~¥}J~T_;~-~~~~~;
_;_ ..:;_·.---:·-... -~ . . :·~--,:..:).~.~•. :.. :.:..-. ---..:::;·/:·.!
~·::·:~-~; .:"''" •; ~t~ :.:·.-:~·:.:~--- .;. •-;. . •
•• ·.; •
~: :, .. :· _:·:., '· ... _. :· . ;. -:. :- ......... ./: ... - ... , '~ .·
.. __ .4_....... _ ..
.~ .. •
;.,,
•
.
~-.. ~ .. ,--;:Wash basins 1. per 60 persons 1 per 60 persons .. '1 for each 60 1 .for each 60
, ___ ..~..:.,·: .::.. __ -~( ·-··-·. _..... _____ . _ -:-· ----::-·......: pe~ons._ .... c........ ..c...: .•• •. persons. _____ ....
_ :~~-Showers,, . / . ... ... . . .. 1 for each 40 ·------ _·_ .. 1 for each 40 .. ·- -'-· .. -
•.•. -"'=.-;;::::_·,... , ,·.·:·• .: - ·:··· .. ......__. __ .. ~ -··--- - ----.· .----:-- ., .... ,-~·-•":persons.-- .--.---.-:- . ·. -·,, persons-.:·-:---- ..•-...;,:~-- ·
<~'(·~-· Number:of. persons based on pool capacity calculated ir: ;;:cord<.mce with. M:J:-LLG.,D~ Bulletin No. 45 Swimming Pools. 1962: ·.
·
~ . ·.:.·.·:-:;·._·.:;Note: Attention is drawr> to tt1e l'ecessity to provide faciiitie£ tor the d1s~sal of sanitary dressings; . ·
· .... -- ~~Seeaiso2.2.10cfCP305:Partl:1974. ·· ,_ · · ·
., .
- '')
. <\Wash basins 1 in each bedroom, plus at 1 in each bedroom, plus at 1 in each bedroom, plus at :.;.·: ..
·· ·':(•'·~-~ ' · · · least one with each group least one with each group· ··least one with each group.:'. __ ;
. -- "> .•·/ :·:.- · of W.C.s . . ., -of W.C.s ·. · .: ·of w;C.$ •· <--:<: .·.
.·. :;;. _:...::·~~-~~-:-----------:----'--:-------.......;._.......;.:-"--=----~-:---:-.......;.-:--:-~~~~-:-· ·.
··~;(J4jB<fthS'' ; · ··.1 per 4 persons · 1 per4 persons · ---·.. · ·per 6 i)e..Sons.·-',;:··:~~:-1:';,~.~';t'.i:.:' :t
• f.~t~~i::~rnpoo 1 per 18 persor1s .. · -'??.per__tr..~~~s_::-/_:-~,J?-.:_::{~;¥.?~-·
~-: ..•- _.- ··.-···.
<Cleaners' sinks At least_one per floor
For administrative buildings ;'.- ..;.·.· :·.,;:: .
.. · ~-.
Staff may be subject to the Regulations under the Offices, Shops . ,, ·.
and Railway Premises Act, but for all members the Regulations
should be used as a guide- see Table C1 0. .. - .
··------------------------~------------------------------------------------
.Sanitary provision for wards must also be considered; the tyJi€ and number required will vary with the type· of hospital. .
Sanitary accommodation should be provided for both male ar.d female \'isitors. preferably associated with a waiting room •.
Note: Attention is drawn to the necessity io provide facilities for the disposal of sanitary dressings.· . . . .. ·
·. ·:·.. ..:~.· S~e. alSo 2~2.1 1 of. CP305: Pan I: 1976. ~~ · · ·· ·
. . ~·
(
,, ;_:~-:..~ ..·_:Table C21 Places of public assembly-Art galleries, Li~raries and Museums.
·~· Fitments For male public• .' For female public• For male staff . · For female staff
W.C.s 1 per 100 up to 400 2 per 100 up to 200 1 for 1-15 persons · 1 for 1-12 persons
For over 400, add at For over 200, add at · 2 for 16-35 persons 2 for 1~25 persons
the rate of 1 per : the rate of 1 per 1 .. ;
250 or part thereof 100 or part thereof ,;, :
tfi''r~;~~~FE~~·~\t:ii;:#A~~~,!~~~r
1 per !?0 persons
... ·· · · ,, c; · ···''· · ,
. 1 to each W.C. or range of W.C.s ·. ·· '1 for 1-15 persons · ~ : ·;. 1 for 1
2 for 1 6-35 persons :< .: 2 forJ
Section C Sanitary Plumbing and Drainage
.• Individual systems
Examples of systems of natural ventilation for individual Plan Plan
dwellings employing one or two separate horizontal or Ia) lbl
vertical ducts, or a combination of horizontal ·with
Fig 2 (Sections above, plans below) (a) individual horizontal
vertical ducts, are shown in Figs. 1·a, b, c. Because there ducts (b) common-duct with vertical shunts
is a risk of these systems operating in reverse, replace-
ment air should be drawn from the outside by an inlet
duct (Fig. 1a) rather than from an adjoining room or Mechanical ventilation
lobby (Fig. 1b). The risks of variable or reverse air flow associated with
:::-']here is no connection between dweilings but in natural ventilation systems, and their unsuitability for
\_: .:.luildings of more than four floors, the space require- tall buildings, have led to the general use of mechanical
ments for individual vertical ducting become~xcessive ventilation in the UK. Basic types of mechanical extract
and wind speeds are often too high for trouble-free system are illustrated in Fig. 2.
operation, especially of horizontal systems.
Individual systems
Common-duct systems Individual mechanical systems require a single duct,
Common-duct systems for natural ventilation could either vertical or horizontal, connecting the internal
effect a saving in the space needed for ducting but are room to the outside air; an extract fan installed in the
not recommended because of the risk of air flow duct operates continuously or intermittently. There is no
between rooms in different dwellings.
....
connection between dwellings. Such systems are
nM '/
•
.. --=---~.t
,. ------ .
~ /
P.l
.. .. ------
'
~,, /
~
~
I*'I IIJllI
1111
""
II.
,,
------
--
"
.
.. ,. we
/
'
II
II
" ~==·--
,. --- /
------t>; "
•~
'
~
Fig 1a (Section) Horizontal Fig 1 b (Section) Horizontal Fig 1 c (Section) System with
system with inlet and outlet system with outlet duct but no combination of vertical outlet
ducts · inlet duct (replacement air enters ducts and horizontal inlet ducts
from adjoining lobby)
... ------------ ------------.... ----~ _____ _____......,___
.,..,. .;......---~-
•
specially suited to converted buildings and to owner- through a vertical shunt at least 1 m long; this should
occupied dwellings in which the responsibility for terminate at its lower end with an inlet piece inserted
• running and maintaining the system lies with the through the servi~e duct wall from the internal room.
occupier. Most local authorities and landlords prefer The air speed in a shunt duct with smooth sides should
one or two large fans external to the dwellings, as in a t~ot exceed 3 · 5 m/s. or in a main duct 7 · 5 m/s; higher
common-duct system, whereas individual systems in a velocities may lead to noise and cause a nuisance.
large building need numerous small fans and outle~ A shunt duct syStem in wnich air extracted from an
points, often on external facades. internal room is paSsed vertically upwards (Fig. 2b) is
I nterminent operation may be allowed and the following preferred to a system with horizontal branches because
I. notes are a guide to reasonable design. The fan should
operate while the compartment is occupied and for at
it is more compact in layout offers better sound
attenuation between dwellings and is less likely to
least 20 minutes thereafter. It should extract during any allow carry-over of smoke between dwellings in the
single operation at least 20m 3 of airfrom a W.C. orfrom event of a fire. Because of noise transmission. flow
L a bathroom with no W.C., or 40 m 3 from a bathroom
with W.C. The air speed in the duct should not exceed
3 · 5 m/s. Adequate provision must be made for the entry
variation and fire risk, shunt ducts from dwellings on the
same floor level should not be connected to the· same
vertical main duct.
of replacement air. A spare fan or motor, to take over in
the event of breakdown, is not necessary. (c) Extract grilles, balancing devices and
Individual systems should also conform to the dampers. An extract grille should be fitted to each
recommendations given under the following ductwork inlet piece; it should be sub-divided into no
I •
headings:- more than six equal parts. The pressure loss through a
I: Ventilation requirements Section 1 (b) grille should be at least 25 N/m 2 at the minimum
Noise · Section 2(f) allowable air flow rate, so as to limit the flow variation
Flow measurement and testing Section 2(g) due to external pressure changes. As an adjustable
Entrance lobby and replacement air Section 4 grille is closed. the pressure drop increases, air speed
increases, and at some point noise will occur. The
• Common-duct systems designer should ensure that the system can be balanced
Most buildings with internal bathrooms have common- . and will operate satisfactorily before this point is
duct mechanical extract systems operating continuously , reached. ·Balancing' means adjusting the various
Horizontal branches or vertical shunts link the internal resistances to air flow in the system so as to obtain the
rooms of each dwelling with Jhe common duct. Air is required flow conditions throughout. A system may be
extracted through a grille from each room and replace- prebalanced, when resistances are set by the contractor
ment air flows into the rooms through any .gaps rdund before the ductwork is installed, or site-balanced after
the doors or through grille~ in corridor walls. . installation.
The notes that follow conform generally, though not in
every detail, with : ·
The air-flows into a system from various floor levels
The Building Regulations-1-972
should all be approximately equaf. The ·baJancmg of
The Building Standards (Scotland) (Consolidation)
air-flows into a common main duct, if necessary, is best
Regulations 1971
done by using an extract grille adjustable at the face, or a
Greater London Council Byelaws
fixed circular orifice plate within the shunt duct. The
BS CP 352 ~1958 Mechanical ventilation and air-
conditioning in buildings · ~
area of the orifice should be at least one quarter that of
the shunt. Main duct flows can be balanced by dampers
BSl CP 3: Code of basic data for the design of
at the hea'ds of the vertical main ducts.
buildings: Chapter IV Precautions against fire
B.S. CP 413:1973 Ducts for building services
1 Ventilation requirements There is no statutory upper limit to the air extract rate
(a) The minimum air extract rate from a W.C. or from a but it is suggested that the recommended design rate
bathroom with no W.C. is 20 m 3/h; from a bathroom should not be exceeded by more than 20 per cent; too
with W.C., it is 40 m 3 /h. high a rate can waste heat during the heating season.
(b) Extracted air should discharge to the outside air and Air extract rates should, therefore, be within the
the system should be separate from any other ventilating following limits:
plant. w.c.. or bathroom with no w.c. 20-28 3 /h m
The ventilation requirement is expressed in terms of Bathroom with W.C. 40-56 m· 3 /h
• volume of air to be extracted rather than air changes per In the past. blockage of balancing devices within shunt
hour, because this can deal with rooms of different ducts by accumulated dust and dirt has been a major
sizes. Consideration of flow in these terms simplifies cause of deteriorating performance. There should be no
testing and the specification of standard duct sizes; it adjustable damper, balancing device or other adjustable
flow restrictor within the vertical duct-worki nor should
meets st9t!.ll91'YJt!QUirements for all practical P!JTilOses.
any such device be fined immediately behind a fixed
2 The system extract grille. If blockage occurs at the grille face, it can
(a) Design air extract rates should exceed the be seen and easily cleared away. Access points should
minimum rates stated in 1 (a) by about 20 per cent, to be provided to allow ducts to be swept .Dampers at the
allow for variation after balancing. tops of main ducts are a potential source of noise
because of the high air velocities through them. They
~'"f.. . (b). Shunt and common main ducts. Inlets from are. best positioned away from the uppermost dwelling,
~~i.:.fC?P~~s-~oiJid be_ connested-to-the-common-main duct eg at pointski:n-Fig.-3-;·------ ·-, · ·-
~~~~iliitiiiRBa~~j!J::tC:~::~:.:.~~: . . .
. •' . . . • .,.. , ~ •'• ~"·' • r
I
~i.·· c:
_ ~ ..···L·.:_._r•..:',·.' _ C: ··r
.... ''· ... l ..; •. ~,··-
l ...:-=. .. ,'!' 't:-~-·--·
.; .1. 1.. t
J,.. 1 •- )1.1'"•
1
l t ,..·"Cl
c-._ J J Til'"
..L.. ct.1·,-a(r'
• .1 l t" ~:-:
;.
.,
-,
'
S ,.,_ Satisfactory
u Unsatisfactory Piping Material
l Limited attack High
or absorption Silicon Poly- Rigid Poly-
Iron Glass ethylene PVC propylene ABS
•"\
''c~heroicaa__;··:z:·::·~~- :-~~~::~~-);~~c~~~-.:~:~~--~.:::?.'~';t~20 _ 6~~--~;=~·:·:··,.~o ~~i:::f~7)_~_-6Q·:~ii~:~~~f.:.€gf}~9i9l
Acetaldehyde 100% s s s s L u u u s
40% s s s s s u
Acetic acid 50% s s s
10% s s s s
Acetone s s s s u u u u L L u u
., Alcohol, ethyl s s s s L u s L s s s
J:.
Alum s s s s s s s s s
Aluminium chloride s s s s s s s s s
Aluminium sulphate s s s s s s s s s
I Amines s s s s
Ammonium carbonate s s s s s s s s s
Ammonium chloride s s s s ' s s s s s s
Ammonium fluoride u u u u s s L
Ammonium hydroxide s s s s s s s s
Ammonium nitrate s s s s s s s s s s
Ammonium phosphate s s s s s s s
Ammonium sulphate s s s s s s s s s
Ammonium· sulphide s s
Anilene dyes s s s s u u u u L L
An ilene hydrochloride s s s s u u u u
Anodizing solutions s s s s
Antimony trichloride s s s s s s s s L
Arsenic acid 80% •. s s" s s s s L
Barium carbonate s s
~
.~
Barium chloride. s s s s s s s s
Barium hydroxide s s
~ Barium nitrate. s s. s s
Barium sulphat~ s s s s s s s s
Benzene ~s s s s u u u u L u
Benzoic acid s s s s s L u s
Boric acid s s s s s s s s s s
Brine s s s s s s
,l
Bromine L L s s u u u u L L
Butadiene s s
Butyl alcohol s s s L s
Butyric acid s s s s s s s s
Calcium chlorate s s s s s s s s
Calcium chloride s s s s s s s s s ·s
Calcium hypochlorite s s s s s s s s s L
Calcium nitrate s s
Calcium phosphate s s s s
Calcium sulphate s s .•
Carbonic acid s s s s s s s _s--
·- CarbeFt monoxide s s
Carbon tetrachloride s s s s u u L u u u L u
Chloracetic acid s s s s L s L
Chloric acid 20% aq. sol. s L
Chlorine dry gas
Chlorine moist gas 10%
J . . Chlorine water sat. sol.
,;.;;:·::~
~
i'
., . ., ----
~!.;.~!T·~~:···l"'·· ·.
L
s_
L
s
s
s
s
s
s
s
u lJ.
u.---u . -
s L
L u
-L·-lJ.
L L
•.:"
~-:~
~. ........... :.·...; ·... I
Section C Sanitary Plumbing and Drainage
Chloroform u u u u
Chlorosulphonic acid s s s s u u L
Chromic acid s s s s s s s s L
Citric acid s s s s s s s s L
Copper nitrate s s s s s s s
Copper sulphate 10% s s s s s s s s s s
Cupric chloride u u s s
I
Cuprous chloride s s s s: s s
; -~·
Ethyl acetate u u L u u u
Ethyl chloride s s s s u u u u
. Ethylene glycol s s s s s s s
Fatty acids s s s s s s s
Ferric acetate s s s s
Ferric chloride u u ;S s s s s
Ferric nitrate s s s s s s s
-. Ferric sulphate s s s s s s s s s
i
I~ _.Ferrous chloride s s s s s s s S· s
Ferrous sulphate s s s s s s s s s
: l Fluosilicic acid s s
!i Formaldehyde s s s s s s s s L
Formic acid s s s s s s u s L
Fruit juices s s s s
Gallic acid s s s s u u s s
Gelatine s s s s
i
I Galaciatacetic acid s s s s L L u u
I
l Glycerine s s s s s s s s s
l
i \
~ .. :... Hydrobromic acid s s
0
... ·~
.
S= Satisfactory Piping Material·
U= Unsatisfactory
L = Limited attack
• or absorption
High
Silicon Poly- Rigid Poly-
Iron Glass ethylene PVC propylene ASS
. .. fi1em ica.Lf.j~~~- ::,·:;:;.::·':;~:;~~{··:~¢ ~;1\::-'2C, .· so t:;~~'t:;~;~ ,:_·&o ?}~ :~::~r2o ;6Q .:;:~~~~:-:::~2.o>~· ~2? ·.:~':~~::20.:.~ 1-:;~~·~o ~oo:·:
Magnesium carbonate s s
Magnesium chloride s s s s s s s s s
Magnesium hydroxide s s
Magnesium nitrate s s
Magnesium sulphate s s s s s s s s s
Maleic acid s s s s s s L
Malic acid s s s s s s L L
Manganese chloride s s s s s s
J,. Mercuric chloride u u s s s s u u s s
Mercuric cyanide s s
Mercuric nitrate s s s s s s
Mercuric sulphate s s s s
Mercury s s
Nickel chloride s s s s s s s s s
Nickel nitrate s s
Nickel sulphate s s s s s s s s s
., • Nicotene s s s s s s '
Nitric acid 50% s s s s s L L u u .u
95% u u u u
~ Nitrobenzene s s s s u u u u L L
Nitrous acid s s s s L
Oleic acid s s· . s s L u s s s L
Oleum u u s s .U u
Oxalic acid s s s s s s s s s s
Paraffin s s s .S s s L u
Perchloric acid 1 ()0,6 s s s s s L s
Petrol s s s s s s L u u u
( ..• ;o.•
-- Phenol s s .S s s s L s s u u
Phosphoric acid '-5 s s s s s s s s s s s
Phthalic acid s s s s
Picric acid s s s s s u u s
Potassium bisulphate l L s s
Potassium chlorate s s s s s
Potassium chloride s s s s s s s s s s
Potassium hydroxide L L L L s s s s s s s s
Potassium nitrate s s s s s s s s s
• Potassium sulphate s s s s s s s s s s
Pyrogallic acid s s s s
•
.) \
·----¥-·--- -----------.. p ---....'-"-~·"~'-~ - . . . . . . . . . . . . . . . . _ _ _ _ _ .... _ . .. . _ _ , , ,_ _ . . . _ _ _ . . . _ _ _ _. . . . -~-- -·· _ _ _ _ _ . . . . . . - :_ _ _ _ _
--· .. -------~-.
S =- Satisfactory
U""' Unsatisfactory Piping Material
L '""' Limited attack High
or absorption Silicon Poly- Rigid Poly-
j Iron Glass ethylene PVC propylene ABS
f
i •
~6~~~~::.~~:~~i~~~d~~28~~~~~~~~~
(
ir, •
Salicylic acid s s s s
Sea water s s s s s s s s
Silver nitrate s s
Sodium bicarbonate s s s s s s s s s s
Sodium bisulphate s s s s s s s s s s
Sodium bisulphite u u s s s s s s s s
Sodium chlorate s s s s s s s s s s
Sodium chloride s s s s s s s s S·S s
Sodium ferrocyanide s s s s s s s s
Sodium hydroxide L L L L s s s s s s s
Sodium hypochlorate s s s s s s s s s L
,•"
:,.;
Sodium nitrate s s s s ' s s s s s s
i Sodium phosphate s s s s s s
i
';1:
I Sodium sulphate s s s s s s s s s s
Sodium sulphide s s s s s s s s s s
Sodium sulphite u u s s s s s s s
Stannic chloride L L s s s s s
Stannous chloride s s s s s s s
~ ... Stearic acid s s s s s s s s
Sulphur chloride L L s s L L
Sulphur dioxide (moist) u u s s s s L s u u
Sulphuric acid 50% s s s s
75% s s S L
95% s L L u u u
Sulphurous acid u u s s s s s s s
Tannic acid s s s s s s s s s
Tanning eXtracts s s s s s s s
Tartaric acid s s s s s s s s s
Toluene s s s s u u u u u u u.u
Trichlorethylene s s s s u u u u u u u u
Urine s s s s s s s
Vinegar s s s s s s s s s s
Zinc chloride s s s s s s s s s
Zinc sulphate s s s s s s s s s
Nott-: The tablE: is only intended to ser.,.e; as c guide; and pore;.:;a: us;;rs should sa:rsiy themselves th<H th.o cr:os::n material will provr·
satisfactory under their particular working conditions. In c.ases rndica:ed as l!mnec! anac~ or absorp:ior.. the material may prov~
serviceat-,le with good dilution and flushing or may be us:>c wher;; a!:t:~na::ve> r"!a:,;rials are unsatisfactor\' <nd where a limited life •s
·permissible.
,.
::.~~::~;~~-~:.:··-~-..\.: . ~<- ·... · .... - .
·:.:~~:~~--;-~. ~;Th.e :de,sig~ of rainwater outlets, pipes and gutters
:.=~~~~t~/~2~7·;~~;,i~~;if.;_ ,,. :~~-~-: .· ...• _-,' ~- ... -~
c:~ ..~~-:-'0··~~-or~bb'i-c'vidlbris'(f~~dirl this sectic.n
. ·... :-
....
RA = Roof arE:;a ir. r·:
t.J. ;.
A =-._:
!):c;r.·i~:t;! c~ rc.::."-.t::·.r~= =:.;..~ .-. n. ·:t
Cross sec1icn c: \"~a!er·=: c.~:=~~ c1f CH.!~:e!" in n1=
. ......:.; h~ ·'= 0(-pth of w·a!er ai-ouli.::~ i- :-:-.rn •· .
.·.. ...
.. ·.
-;·.·
r
E ·=-
= Rainfall a!lowc~ce in r:-;,- ;:~r hour
Mean ;..-.:id:h :Jf :c..:::er ;~. ~ ·,. '
:.-. -:.·. c· ::-:: ·V\'id\h c.f \·;crf· ;:..!·. .::~:E- :.. :7 ..:::~! ;:-, :r·· . i Trat:·-szc:=(;~
b. =- \\'!C~J~ cf ~~~~~r : ..:-qc ir. ~· ·· gi.!nen:
-~~;:.:.j;·~~t~T~:\1aw~li~~~}h~~f~)~:·
:>:>.-'
~--·
,·. •.••·· ~l~~~~~ri%"b::'lS3S.:S~\ -
_If a;r()of;:J~~bB~~-~~c!·J>(y.:~nJca_l .~all~·-:n_sing ·above the. . then RA, _ ._1 000 . _... ._ ,. ~. :':_!_._',;'
' ·· roo~ ~ome ~.llow~nc~_shq~Jd· be made for the additional · ·-
~~~~r.~~~~~J~i~;-·:.~;_::.;~-~~J~i.~~-L:. ~.·-!;~~--~_,, ~ ,_ .- . .
Section C Sanitary Plumbing and Drainage
;
where RA = the roof area to be drained in m2 diameter of the outlet is permissible. It is recommended, .
D = Diameter of outlet in mm however, that for industrial . buildings a minimum
h 0 = depth of water in mm diameter rainwater pipe of 75 mm be specified. For very
small roofs a diameter of 65 mm could be considered.
Formula (ii) may be usedto determine the dimensions
of a rainwater outlet to a flat roof where a cesspool or It can be shown by basic hydraulic principles that the
_ par~jlel glitter i~ r10t provided. The limiting head in this diameter of a vertical rainwater pipe for any given roof
case is h 0 = !D. By substitution we get area can be determinl(d by applying the formula ·
5
D i RA='= 3·2DY
R A = - - - . . . . . . . . . . . . . . . . . . . . . • (iii) 1000
1000
In the case of an outlet to a large gutter, a-depth of flow This rainwater pipe formula has been plotted on Graph
at the outlet of up to h 0 = !D is permissible. By· C4 from which the diameter of .rainwater pipes for
substitution we get given roof areas can be determined.
1·60 i Horizontal pipes _
....
.;-· RA = . 1 000 . • • . • . . • . . . . . • . • • . • . . . . (iv) If the near horizontal portion of a rainwater pipe runs
-{...
for a considerable distance an investigation of the
Formula (iv) may be used to determine the dimensions hydraulic conditions existing should be made. Under
of outlets to large gutters. · these conditions there is a danger that a backing-up of
Graph C4 has been drawn to include formulas (ii) (iii) water at the foot of a .bend. i.e.- at the change of
and (iv). Problems requiring the application of these direction from the vertical to the horizontal pipe can
basic hydraulic formulas can thus be solved at glance a occur at peak flow due to the reduced discharge
and with minimum calculation. capacity of a horizontal rainwater pipe compared with
one of the same diameter fixed vertically.
Outlets wi1:h.slotted gr~tings
Standard offsets offer only slight resistance to the flow.
An outlet from a flat roof or a paved area which receives
rainfall is sometimes provided with a grating of the Use of Graph C4
types shown in Fig. C19 and this can cause consider- The Outlet Sizing Graph C4 has been plotted to
able restriction to the flow of water. The flow capacity determine suitable diameters for outlets for flat roofs
of such gratings when submerged by water can be not provided with gutters or cesspools and also for
obtained by using this formula. - outlets to gutters. In cases where it is required to limit
Q ==!Cd A V2gH the depth of water at the outlet to a flat roof the
where Q ==quantity in m3/s~ necessary data has been incorporated.
Cd = discharge coeffiCient of the slots Flat roof without gutter
cd = 0. 6 fo·r bars with sharp edges For determing thao.utle.t.di<imeter to a flat roof without .·
· Cd = 0 · 8 for bars with rounded edges gutters, line A on Graph ·c4 should be used. If a limit
A = total area of slots in m2 is placed on the depth of water at the outlet to the roof,
\ ·~·. g = 9 · 81 m/s2 (gravitational acceleration) follow line A until the limiting depth is reached and then
. -- follow the appropriate line with the limiting depth
H = head'over grating in metres_
marked thereon.
The equivalent horizontal roof area which can be
drained into such outlets can be determined by using Example 1 A flat roof 240 m2 in area and not provided
the following simplified version of the above formula. with gutters is to be drained by two roof outlets.
Determine the diameter of the outlets.
RA=·cd~ Area to be drained by each outlet is 240 + 2 = 120m2 •
3r Referring to the graph and following line A. the roof
outlets will be seen to be 1 00 mm diameter.
where RA= roof area in m2
If the outlets are suitably shaped (see Fig. C17) then
• a = total area of slots in mm2 reading from line C rainwater pipes of 65 mm nominal
h = head over grating in mm diameter may be used.
Cd = 0 · 6 or 0 · 8 as circumstances warrant Example 2 If the depth of water at the outlet on the
r = rainfall allowance in mm/hour same roof is required to be limited to 20 mm determine
The type of roof outlet used and its actual free area at the the outlet diameters necessary.
inlet should be determined from the manufacturer's Referring to Graph C4 and following line A and then
information and checked against the inlet size (free the line which limits the depth of water at the outlet to
area) on graph C4. 20 mm, a roof area of 120 m2 requires a 150 mm dia-
-meter outlet... The roof then requires two ., 50 mm
'
'
.. Sizing rainwater pipes
Vertical pipes
diameter outlets. The roof discharge into the rainwater
pipe remains as for Example 1 so the 65 mm diameter
Where a standard outlet nozzle is used it is normal to will suffice for each outlet.
use a rainwater pipe of the same diameter as the nozzle. Example 3 A flat roof 60 m by 24 m is to be drained
... Where the rainwater outlet takes the form of a properly into cutters each having two outlets (see Fig. C20)-.
. shaped transition piece (Fig. C17) some reduction in the Determine the diameter of gutter outlets to be provided.
· __ ~c-diameteL-oL..tha.r-ainwater pipe compared__with.the Area of roof = 60 x 24 = 1440 m:~. ··
......... -.
Flat roof without gutter Example 3 continued
Area to be drained by each outlet 1
20 Xi X 10 X
cos60°
=~=360m
. 4
2
= 20 Xi X 10 X 1._ =100m2
In this case as gutters are provided reference should be . 1 .
made to line 8 on Graph C4. This shows that outlets
of not less than 150 mm in diameter should be used. As this area will on!Y reql!ire z -standard eaves gutter.
If the gutter outlets are suitably shaped reference to line Graph C5 can be used. Reading from this graph the
C shows that 100 mm diameter rainwater pipes are eaves gutter outlet should be not Jess than so· mm in
permissible. · . diameter. ·
Example 4 A North light roof to a single-storey factory Roof areas 8
(Fig. C16) 40 m by 20 m is to be provided with valley The plan area may be considered in this case as wind-
and eaves and drop pipes to a horizontal trunk rain- borne rain is likely in one direction only. The plan area
water pipe. Determine suitable sizes for the gutter
outlets. rainwater drop pipes and the horizontal trunk = 20 x 1 0 = 200 m2
rainwater pipe. The reading on Graph C4 shows that the gutter outlet
should be no~ ~ess t~an 1 ~5 mm diameter. lf a-.suitably
Roof area A shaped trans1tron prece 1s used, the rainwater pipe
The true roof area of area A when the roof pitch is so= is should be 90 mm nominal in diameter•
·.· -~~h::\1,~:~~
.8 :·3 ·. ·C :~· -~ ·
·':"·.· .. ·· Fig~:·c1s .·
· .. ::.:;
'Wind direction
.· D -· ... ~
. ·..=··
. . . . ., ' . ,.,.-,_-;_ .-~- -~. ··i "---~ "'·-·
. _ _ ,~1--~ . . .- w~~~~~~;.~
. -=·
-.
,. .·_.,
·... ·· :
."C - -.- . . _- . . . - Fig:C18...~ £·,_., ~ ·:.:\·--.
t
... -· .., .. ____ '"_,. __ ......... ~_-... ' . 1-..· ........... _.,., ______., _____ ... - •. .._ ..... _. __ ~--------··-·· - ..
·-·-------- ·--·--------·-
Roof area C and other causes, eaves gutters do not always maintain
The true roof area of area C when the roof pitch is 30° is the fall given them when first fixed and it is recommend-
20 X f X 10 X 1·15= 172m2 ed that the flow capacity of a level gutter should be used
Working from Graph C4 the gutter nozzle should be as the design capacity. Additional flow rate due to any
1 00 mm diameter and if a suitably shaped transition fall that is provided will thus provide a design rnargin.
\ piece is used the rainwater pipe may be 75 mm diameter. Building Research Establishment Digests 188 and 189
dealing with roof d(ainage gives a table of flow
capacities of level, half-round and ogee gutters up to
Horizontal trunk rainwater pipe 1 50 mm size. These are expressed in litres per minute ·
This pipe will be. required at its extreme end to carry the and in order to relate them to roof area in m 2 the flow
whole of the maximum flow. The metric Box can be rates were firSt converted to m 3 per hour and then, by
used to determine its diameter. using the recommended rainfall rate of 75 mm per hour,
to m 2 of equivalent roof area.
q = ~!¥ This final conversion has enabled a direct plotting to be
made on Graph C5 on which suitable gutter outlet
sizes are also indicated. ·
where: q =. litres/sec
d = diameter of pipe in em This graph is based on flow capacities for level gutters
with an outlet at one end. The position of the outlet has
H = head in metres a big effect on the flow capacity of the gutter but
L = length of pipe in metres considerations such as appearance or ease of con-
If the fall is limited to 1 m in 100 m this formula can be nection to the underground drainage system often
further simplified to: determine the outlet position.
If an outlet is situated centrally in _a length of gutter, the
q = .!_
50 vids u
gutter capacity required will only be one half of that
needed for an end outlet. If the ·outlet is not at the
or litres/s = 5~ ~ end, . l_
. the gutter capacity required will be a fraction L
Converting to m3/hour (1m 3 =1000 Jitres). of the total flow load_as shown in Fig. C21.
m3/hour = 60 x 60
50 X 1000 V
lds Effect of gutter angles
u If a square gutter angle is situated within 4 m of an
outlet, it will reduce the effective capacity of the gutter.
A= 20 X B_
3
202
A=-- • • • . • • . . •.• • • • • . • • • . • . . • • . • (ix)
3
In the case of a trapezoidal gutter (Fig. C22), the area
Dimensions of gutters is given by:
(a~ b)
The basic expression for the flow in any gutter or
channel at the point of free discharge is: A= h0
Q = mean velocity x cross section of water at outlet
Taking the rainfall rate of 75 mm per hour into account
and completing all conversions, it can be_ shown that
and B = a + b where B is the mean width
- 't· 2
V X B X h0 '
RA = 20 •••••.•.•..•••••• .-...... (v)
Width of gutter
where RA =roof area in m 2 lt is- recommecnded that where access to a gutter is
B = breadth of gutter in mm required, the minimum width .of the gutter sole be
250 mm to enable a man to walk along it.
h 0 = head over outlet in mm
·~· V = mean velocity of flow
The mean velocity of flow reached for any given depth Depth of gutter
is given by the well known formula : For large industrial gutters, it is suggested that the
freeboard or height above the water level to the top
v =~~ of the gutter edge when the gutter is flowing at its
maximum rated depth should be 50 to 60 mm.
Converting to mm head Example 5 Determine suitable dimensions for an
industrial gutter which receives the rainfall from a roof
V= Vflo (vi) 450 m2 in area.
11 . From the outlet sizing graph C4 the diameter of outlet
By combining these two basic expressions, we get the :necessary is 150 mm. From formula (viii)
basic flow formula for level gutters and channels: B.= 20
so a suitable width of gutter would be 2 x 150 =
RA = A jh"; 300mm
220
. . 0 150
But area at outlet= B x h0 Depth of water at outlet (h 0 ) i s - = - = SO·mm
3 3 3..
·soRA
S =- Bxh.l
220 . .
•....•...•...•... • .. • .... (VIIii) . . . Design depth of water at still end- .. 2Ft o
= 2 x 50 = 1 00 mm
Relationship between rainwater outlet and to which must be added the freeboard of 60 mm. A
gutter dimensions suitable depth of gutter would therefore be
The following mathematical relationship between the 100+ 60 = 160 mm
_ rain_water outlet and gutter will be found useful to Giving the size of gutter required as 300 X 160 mm
•:·~.--, :-c . ... de~•gners. . .. ·---------- . ·-rectaAgular.-~c-··.-...
. ~ ~/: .. :.;,.
-- t
~·~......~··,:
-- - - - - - - - - - . . - ............... _
... ______ -·- ... _________________ --~------·· ---------·-...................,.....
....·.
,· • ..::1 ___
• •••
. . . . . ·.
',····
The design of rainwater outlets, pipes and gutters
.· ..... :·_~-. · ..... ... ~· .:
·o .\ \ ..·: ;·
.··.: '~ .
......
"·N [\. :\ .
.· .. ,··
\.· -~ -·: :.. ·
·_ ··~·
·.
.·•· :.
·\ \
.. -" ... ,.
_. ·.. ·. -:··,..,
·- - -·-··-·-:::.l:.:--.----:7--~~...:--
. .."C
--
.. . ·C::
__ ·,:·:-··-~·g
..... . en
...
. Cl)
... ·.·. -~
.
·::l
·o
·,
N
. ; ..
··:-
..---.
-----'
: \,':
.......
! '·: I
'------ -~
~· ..
-:.-,..
. • i .·. ~
--~ '
.
' ' .
,
.., ::''
.. ._
--;--.-----..._)
.... .. ,.
j•, .! 'i
~. ;__ ·..!: t. i:,·;l
~-~.
C)
D1
'C
., 20 m•
";j
.·:.' n·
. ~-:t..' . .
! (() · 42 1/s) U1
... '4 · odl c.l• -1
4! og c.l: . ' I . :J''I' 12so
. · 0
.' , '' 8: .
l - I - , ··-·
.•,'
i !
:I
cc
,.,,~~·; 10()
,,. .
h ·. .-. ,.
.,
-~ •.
4
~
J
nolm. h.r. ~ ·= 30
(0 · 63 1/s)
....0
(!)
Q)
<
CD
~~, ~~~~~~i;~
~l~iHJ::.
---~--, --- --~- -111
.
.(II
cc
.~·.'100
. ~
4 400 c
.: 116.
:.126
4!
=
(!)
1-~-------:-""7"-~+~:-:--~------:-·r--~ .
6 nom. h.r. ·' _.___ 500 ell
.r·.:::~
Q)
.·
;;
:I
:t· og '-'· . c.
,'; 126 6 nom. h.r. 0
4!
-~ cr+
..J16 tr~ h.r. I
" ~
I
: 600 IJ
. ,), ' \ -!
""
-~ ~ -~·.:
·\_~ .··.~.I
I.
... ·
...
~ '< :,. !
t.:'
\.?·.~-~ -~·_2 .
~:t<::.._::
-•- · ... '· y' I ,, _.:. ·,, 'I· . Tj i . l•oo l
.. '•: :.'·
,.
':4~tH;
- - · -+. ·---·· •• -~··- ··---·-.~.~-..... ~~..,.., ......r.....-.... ,..:~-~~--------~-.~..................... ..; ...... _, _ _ _.;.___ _ _ _ _ _ __
= 2 X 125
3
+ 60
= 83+ 60
Depth = 143 mm
A suitable gutter would be 250 X 145 mm rectangular.
I
~; .
\
~ .. \
\
.~~ "
1:: ·:· .
t~~~~!~<~o~~~~~p:,)•st•
:.Shower (publiq)
1 ~g
180
~g
12
g:~a
0· 25
: -I~ 0·12 .
"~~- ~:~1f: 3},
,, _1 ·.5 . , ·.:.. : · 4
~0~:~.--,:?.;::~;._";.~ote :_.App.!ia,nces having a continuous !low_ from_ their _o_!rtl.e!s_ sho~ld have _th~. c~-~. P.. ut.ed fL~ r~t~. ~~~~~.on t?}h~_t i>reqict~:ect,bY._.~~!n?.:.
~~~,;;.,.. · ,;.;:~-:--<;d•scharge~umts, for the other fitments.. ·. · . · ···: · ·. · '>.. : .., "- · ·: · · ·.,.~.".~~:••if,-:.-,?-,:.~....,,,. ,;:•·'1f'.'-'•?.':Jt!:'1'l5~ ~s:;;.;-v.
~Drfo.;;.~;;:~&t.-t;,~:,;t..~~-\·.~{..::;.:.,··.:.··.;._,·.;.::,_.<···:· ·...:·..... '-~:·~·.:.: ... ~ .• ~ ..... ~-..-:.. : .: .: •. /·. •·.. -.:;.~;-~: .... -·. ·.:_: ': ~- :~t'::~,.,>.:~~~'f'~.~)l!'.·--:-:,~~~·..:::..,:~;!~iY}~..f~~~·:W~ ·~r;t,;!~~!_!:..t.
j
Section C Sanitary Plu1nbing and Drainage
;
t
(
L
r
li~u'frac.!:t;;t;;::I®~ztrz:;:t~:factor'r?
Roofs.. 0·95
V = -._1__ m i ii
. 0·01 d
I
Roads 0·57-0·90 V= 100mlii
"j
f: Paths. 0·50-0·75 and the Chezy coefficient for these three materials is
I
•i ~~~ .
j Parks and gardens 0·10
J V=100mdt
i .·I ,. ~.
!\..·.~.
~
Chezy formula
The Chezy formula is usually written in the form:
identical to those used in the Manning""formota, the
essential difference between the two formulae being
that K in the Crimp and Bruges' formula is a constant
V = Cv md xi for all materials. The Sl constant "K" = 84 can.
where V = velocity m/s however, be readily derived from the Manning formula
· md = hydraulic mean depth in m by giving n a numerical value of 0 · 0119.
By substitution. and after completing the necessary
sectional area of flow A arithmetic, we obtain :
- ----:----:----
wetted perimeter
= -P
K = 1·00
• . • head or fall 0·0119
= me1mat1on or 1ength
. K= 84
. Crimp and Bruges' formula can, therefore, be written in
C = Chezy coefficient = V{2Qfg f ·its Sl form as: ·
V = 84mi ii
where f = coefficient of friction The equivalent Chezy coefficient is given by:
g = gravitional acceleration = 9 · 81
m/s2 c = 84Tndi
By choosing a suitable value of C. the Chezy formula Design graph C1 0 has been plotted from charts for the
j• can be used to determine the flow in pipes or channels hydraulic design of channels and pipes. (P. Ackers,
f::'_,_: ::". . undermost conditions. Hydraulics Research Station.) ,.
~ Exponential formulae · Graphical comparison of the Manning and
·1! By rewriting the basic Chezy formula in the exponential
form V = K md" iy. it can be made to fit a much wider
Crimp and Bruge's formulae
with Chezy coefficient C
range of conditions. Two exponential formulae which Graph CS has been prepared in order to provide a ready
have been widely used by Civil and Public Health means of selecting a suitable value for C (Chezy} as
~~E. ngip~-~.rs . are_. Manning's formula and Crimp and given by either formula for any given pipe ~iameter or
•
~~-~!}l!J~~ }!Jr:mula. . value of.md. . ,._ '~"),(.
~••-;!;;;,·~~~~~-·:~ . : .•,,
1.
---------------~-......,,,..,.~----,._~'Ok-"""'~WO...- ·~~---· .. -·"- -.. .- . . ~~-----··--·"''"
f
....
!:_
i
t
3/5
0· 82
0·72
0·68
1 ·21
1 ·15
1 ·10
so Q varies as 0 · 77
or say, three-quarters of that of a pipe flowing full:
(d) When a pipe is flowing at three-fifths of the depth,
from Table C25:
t 0·50 1·00
md = 1 · 1 and c.s.a. = 0 · 68
fxgmp/e 2 A l 00 mm .diameter pipe is flowing. three ... 9r Q veri€!~ !.!~ v'"fl' x 0 · 96 = 1 · 05 x 0 · 68-· .
quarters full. Calculate (a) the actual cross-sectional so Q varies as 0·714
area of the water. and (b) the hydraulic mean depth at or say, seven-tenths of that of a pipe flowing full.
this flow. ·
(e) When a pipe is flowing half-full, the discharge is
(a) Cross sectional area (full) exactly half that at full bore because the proportional
hydraulic mean depth is unity at this depth, but the
A=?f·d2 = ~ X 10Q2 proportional cross sectional area is exactly half that for
7X4 10• a full pipe. . · . 7' :.- . ·~ :-:;·::«~..?.-.tio.r4. ·.:~
. ..·.. ' ·. ~ ~·, ...... ':~~. _.!,·,
, . . . ._ _.._. ..___·--.---------- • .. ,. ._.
_,~ ·-M·'"'-·------~ . .-
' .
', ~
,- The flow in pipes not running full continued
Example 4 A smooth channel 2 m wide conveys water head h
but i -
at an average depth of 500 mm. The channel is laid to length L
a fall of 1 in 600. Calculate. using Manning's formula
(a) the mean velocity of flow in m/s and (b) the h \J2
di.scharge in litres/s. or--
L md C2
By using the Ch~zy formula in this form, a suitable fall
can be determined.
f '-
Drainage pipe sizing calculations (7) Deduct Col. 9 hom the high point invert level
•f-
l •
In calculating pipe sizes for drainage installations, it is
essential to record in a clear and concise manner all
recorded in Col. 1 OA and insert the resultant in
Col. 1OB to give the low point invert level.
factors which determine the selected pipe size for the (8) Where back drops occur the depth is recorded in
(• section of the drainage installation under consideration.
The calculations should be recorded in an orderly
manner,· so that arithmetical checks can be easily made
Col. 11 and the revised low. point . invert level
inserted in Col. 12. .
(9) The pipe mat~rial should be recorded in Col.-13, ·
at the completion of the pipe sizing exercise, to enable and any notes made in Col. 14. ·
the implications of ·subsequent site variations to be (1 0) After carrying out arithmetical checks, the
assessed, and the necessary modifications to the calculation sheet headings should be completed,
drainage design made where necessary; and finally to including a list of the design drawings and the
provide a source of design information for the designer relevant data transferred to the production
or the building user, which can be filed for future drawings before filing the sheet.
i·· reference.
,.,·.'.·. Design information which it is necessary to record, Above ground drainage sheet Figs. C27 and C28
includes gradients, maximum and minimum flow rates, (1) Accord to each pipe section a reference number,
velocities and depths of flow together with the invert and define the function of the pipe section,· i.e.
levels at predetermined points, in the case of under- waste pipe, main branch, stack etc. to complete
ground systems. Col. 1~ ·
The worked examples have been produced to assist in (2) Insert the appliance ty'pe under Col. 2.
design and for recording calculations for above and , (3) Insert the appliance discharge unit rating under
below ground installations. Each calculation sheet has Col. 3A; or in the case of a common branch or
an accompanying schematic illustration to assist in stack insert the total discharge unit load on the
understanding the worked example. pipe section in Col. 3B. ·
I (4) Under Col. 4 insert the appliance discharge rate,
Underground drainage sheet Figs. C25 and C26 or the pipe section discharge rate in the case of a
(1 ) Accord to each pipe section a reference number, common pipe or stack carrying several discharges.
using manholes and junctions as section change . (5) From the appropriate graph select the pipe size
poi11ts and insert in Col. 1. and insert in Col. 5. For vertical pipes· or stacks
(2) Establish the flow rates upon which the design is insert the proportional flow ratio, for horizontal
based, using the accepted methods described pipes insert the gradient, velocity and depth of
elsewhere and insert in Col. 2. flow parameters in Cols. 6, 7, 8 and 9. (This
(3) Select from the pipe sizing graph or·hydraulic activity only applies to common branch pipes and
tables, a suitable pipe diameter and gradients, stacks, in the case of an appliance waste pipe the
which meets the acceptable velocity and depth of size only needs recording.
flo.w .criteria and insert in Cols. 3, 4, 7 and 8 (6) From the appropriate table or calculation record
respectivefy. the vent pipe size and length in Cols. tCf and 11.
(4) Express the gradient as the tangent of the angle of
slope, and insert in Col. 5. Note:
(5) Measure ~he length between the pipe section The above calculations, and the use of the calculation
recorded in Col. 1 and insert in Col. 6. sheet, should only be necessary in above ground
(6) Multiply Col. 5 x Col. 6, the product of which is drainage installations other than single stack systems.
the vertical fall which should be recorded in
Col. 9.
•."".""'-""·""...""
. ....,.._.,.._~-~--'"'""'-~·''·"'...,..,....,.·'-'""·"";·'-~''*.,.·.,.... ....,.,,_:•,.mr....___..,<""*·"'.s..,,_..~.,..-f~*""'S_,:.--~*'"""":':'~
. .4':-,..·.~-#""/'!"'_~--,:"".{"";*··'"' ..""·':..."'!:,"".~.-o:o.c""';"!"._ft<:w""'•."'!!!?liP!I;!
..';.,.: . ~--?!f~,!"' ... sa:::::e>.o;;o~::,"'!!·¥""''.'""'·':..,C!!"".""'~-:"";:~"";-_:'P:".:''"":'~~~.(f'l""'"··""'·w~-!'""»-•
•.S~It'!T""·""··""
::.Fig. C25 ·: · .·· ·c.·•·· , .. c, ··_·:··- . : •.
-~ Underground . :· ;-, .
..
·.
- ------- ---------
.,. ,··
L
M K .. ·
·- ·.-
·.:: .. ·
N- .·
•·:.·· ....
~ .
"' !·
.... ··c'· . . II .,.>.··.,;.+ . . .·,; ~.:-.._.:;, . :&,:\, ·- -.
Fig. C28 Drainage calculations (above ground)
Project Drainage calculations above ground
1 2 3 B. 7 8 4 9 10 11I 5 12
Pipe Appliance Flow 1/a j Size!
Prop. Gradient Velocitym/ai Depth of flo\11 Vent Vent
Discharge Units No tea
mm Size Length
Ref. Section I Type Appliance Total! max. min. i mm Flow I:L max. min .. i max. min. min. mm !
A-B Main Branch w.c. I 12 1·82 I I 100 ! - 1 :24 1·05 I I 30 50 20 -
C-B Waste Pipe w.c. I 5 ·34 1 32 - - - - - - -
B-0 Main Branch - 2·161 -
I 100 ' , :24 )1 ·05 )30 - - -
' E-D W.P. Sink .12 ·75 1 42 - - - - - -
_.-
- -- 0-F Main Bran~<.!) - :u.o 2·91 ·1-t.OO 1~ 1·W - - -as ,. "--
- -
F-M Stack 310 "'-2·91 ! 100 <115 100 10 - - -
G-H Main Branch Dish Washer --250 2·50· 175 I 1 :24 1·14 31 75 40 -
J-N Waste Branch
H-K Main Branch
Sink 12
I 262
·75
2·60
I
42
i 75
I
1:24 <1·20 <40
- - - - --
'
L K Waste Pipe Sink 12 ·75 I 42
K-M Main Branch 274 2·62 I 1s 1:24 1·20 <40
·. ~"£~~·~;:. M~N Stack·
-- ...
584 4·10 1100 <114 ~00 20
- ·.. •.. .. ..
~~i~~~~ J~ ·: :~·: -.
,•
.
----------------- ~--- ---""""'- . ,....... ._.. ___ ··--~-···-·
Sewage lifting
The main type of pumping methods for sewage lifting considered using a high level float connected to a
are (a) The 'dry-well' arrangement, (b) the 'wet well suitable audible and visual alarm.
! • submersible' arrangement, (c) Self contained or Natural ventilation is often sufficient to remove smell
'packaged unit~' (d) pneumatic ejectors (air operated). and minimise any danger from gas collection.
Pumps used for sewage lifting require to be reliable and FC?r pumJ) terminology ref to Section F.
unchokeable, accessible for easy maintenance, robust
'\ . and wear resisting. The type of arrangement should be
decided in relation to rate of pumping, total head, the '
chemical and physical composition of the sewage and
location etc.
The 'dry-well' arrangement is generally favoured in that
the pumping equipment is located in a dry sump. A
variety of self-contained or packaged units are available,
generally each unit incorporates its own suction well Inspection and testing of drains
and connections for incoming and outgoing drains.
The rising main size is. subject to various consideration All lengths of drain and all manholes and inspection
during flow conditions. The most economical velocity chambers should be capable of withstanding the
fa lis between 0 · 84 m (2 · 75 ft) and 1 · 2 m ( 4 ft) per appropriate test.
second. The economical design for the rising main A water test should be applied after laying and before
depends on the velocity at the normal rate of pumping. backfilling or placing concrete surround. Any leakage _
The total pumping head must include static head, will be visible and defects should be rectified. After
friction head. pump friction loss and velocity head. All backfilling, a further test should be made.
junctions and bends should be securely supported and Wherever possible. testing should be carried out from
fixed to withstand the internal hydraulic thrust. manhole to manhole. Short branch drains connected to
Washout valves should be provided to facilitate a main drawin between manholes should be tested as
draining down and maintenance. Air-release valves'
\ . should be provided at unavoidably high points. Non-'
return valves should be provided at the outlet of each
one system with the main drain.' Long branches and
manholes should be tested separately.
pump as well as isolating valves. · Water test
Sewage pumps should as a minimum provision be The test should be carried out by inserting suitably
duplicated, duty and automatic standby. Each pump strutted plugs in the low end of the drains and, if
should cope with the design flow and where three necessary, in connections and by filling the system with
pumps are installed, two should be capable of._dealing water. Small diameter rubber tubes can be used where
with the total flow, with automatic standby as the third necessary to release entrapped air. ·.• ·
pump. The basis suggested where combined flows are For small pipes, a knuckle bend may be temporarily
encountered be that using a 3 pump installation, either jointed-in at the top and a sufficient length of vertical
of two-duty pumps be capable of handling the D.W.F., pipe jointed to-it scrartcrprovrde th~requirecttesfheact. ··
both the duty pumps to be capable of handling the Alternatively, the required test head may be applied by
I c......·: ~
combined flow with the thl!d pump as a suitable
automatic standby.
means of a small bore pipe leading from a suitable
container and connected to a plug.
'_.· The size of the suction well must not be too large or Precautions should be taken by strutting or otherwise
septicity may occur during periods of low D.W.F. .Pump to prevent any movement of the drain during testing.
motors should not be required to ·start operation more
than 15 times per hour. The suction well must not be too After allowing a suitable time for absorption of water by
small in relation to the pump capacity. In practice, the joints or pipes. the water should be topped up to the
compromise generally used is to provide a minimum required level before the test is commenced.
storage of two minutes running time for ·the pump, the _ The test before backfilling should be commenced as
.. pump being sized at twice the design inflow rate, the soon as practicable after laying, but the drain should
suction well, therefore has to contain 4 minutes inflow have been filled for approximately one hour before test
.. capacity requiring 15 starts per hour, or less, of the
pumps. The storage capacity is measured between the
readings are taken.
A t~st pressure of 1 · 2 m ( 4 ft.) head of water above the
cut-in and cut-out levels of the individual pumps. It is soffit of the drain should be applied at the high end but ·
recommended that the well depth should contain, not more than 2 · 4 m (8 ft.) at the low end. Steeply
about the highest cut-out level and overflow level, a graded drains should be tested in stages where the
suitable depth be allowed for peak flows. above maximum head would be exceeded if the whole
section were tested at once.
" . Guidance should be sought from the pump manufac-
turers as to the setting of electrodes or float control
The loss of water over a period of 30. minutes should be
measured by adding water from a measuring.vessel at
- . levels tG take into aooount the I'Uffll' eharaete1 is tics and regular fmervats Of ten minutes and noting the quantity
·'
.. starting times. The sewage pump on the separate
system should generally be capable of dealing with rates
of flow up to 6 times the twenty four hour average.
of water required to maintain the original water level in
the standpipe. The average quantity of water added for
drains up to 300 mm nominal bore should not exceed
Where overflowing is not possible or flooding cannot be 0 · 06 litre per hour per 1 00 linear metres per mm of
tolerated, standby plant using some other form of nominal bore of the drain (up .to 12 in nominat bore,
• power should be provided to overcome electric power 0 ·1 gall. per hour per 100 linear ft. per inch of nominal
_f~j!yr~.. Means of notificatlon..olpump failure should be bore}.. ""_______ -·---··--~··-·--~----~-------·
. •' .. -
_:· .. ,' ,·
. f '· ...... "'- ~·~·· ..... .,... ... • ..
_·_-.· . .-. . ·.·_ .... ~; . ~ :..... .
. .--.. ...... - ',·
~ .
.. ·. -~..
.•:-:_~~_i.:._-~-~~-':;_-·:.·. . ..~ . :
~-- . :' ~ ~-·
. _.•:. _
·Trade effluents
; ,.:-.· ..
Refer to Section 2 of the Public Health (Drainage ·of Table C26 Petrol interception
Trade Premises) Act 1937. Trade wastes have been -.--.. . . . . ~.~~-~·-··R~~~
..
• • •• • • • • • • ....
.. ·o ...
..
:-
,.,
!.
!
,·
1:
I,
.I'· •
\
r
J:
.
'"{ ~
I
l I -.
0
0
N
en
CD
I u
c
1
·l
.~
-ac.
I
·r -... ca·
0
CD
0
.c
2 E
·I z
::::1.
~ 0
! c:c
1 I 0
-.o
tJ. . .
··-· .
• ·.· ·.·
.. ··.
. . .·. ;
..
-o
I
l
i
!
I ""'
.,. I
t
~---. -
-------·-·-···--
...
.....
_
~-:-;-- .
~~:;F~~=;;:;~"·'"'..0::~~;~ .
::=::::;;:::::z:::;::::;::=::::::::::;-= I
. . !1 ..
(',.
. .. ..t'),
., .
I ..
·· .
()
mfiA'f' r~:f~l
"0 CD ct
:.1
=r 1-'·
>'·
,....:. ___..i (') 0. 0
········:·' I !· co CD
,;,,.·•"!' .,,....,
....f".,,1
.; : . i
! ~/ !:
/
'
j
.I
I
0
0
-·::s
en
CQ
::::J
0
r:n
fi:\ ;·~:
:l!i!.;:'!'tf ·:... ' 0
of:·~~': ...J ()
·::;y:·i /.. .
, ' •' ' ." I1---lI I I I 4I 'I I I 'I 1/ :
- -
CD
.....
~
~ ... ...
0
C"
P'
t:l
.......
-c::s-·c-·.
... CD c+
:::J ~
.~r,
.,·,'
~ ~ ' r+ "i
·'i' •.'.',· ", 'I
0 ~
"!:·., .....
,• I ~
.,"T1 CQ ~
<. .
70 .
( !:!'. s
-.s .·~.)
0
:::J
n.
-·
Cl)
::s
Cl)
o'
.......
~
;}.i, 60
~~• :crlni1& Br~~
::T
Q)
~
cc
CD
!'JQ
~
t:l
p..
,;;.\:8 <~·:, 50 1-~'""---;+--+-'---f r -r .,
i~~lU1
tj
~-~~:(!~~ :. 40
. ;: I
_; ___- .
i
-h-----1--'-+~· 1-7---
1-1
p5
.....
tj
IF
P'
.[.·;~ ~~:~n;1;
crq
ct>
...
<: . · ·I 1 \ .;
....... ,· ·~
.·:.,
. ":·.··
~~
..
....... , • ·~!
.•
30 '•·
,...... ....
r. ..··.'1 .. < ·· ,.. 1~/: ·
.· ...
! . . .
I I
·'I .Ji·· ''.
'··
.r .. . I
/.'
~-·· . I
~\~iF 2 ~oo3 , . :,:.
'I I I'!l Ill ~o25
II JI
.~o4
. ·;f! r
.I
...~.~,.,, •
~i~~r~ .
.
Friction
\ ·"''
c~efficient f
·005 i·007
!
!
· ·OJ ·03, •.
.
.
. .. t
'' '
·I
,, .
. , :
:, ·:; . '
,
, ·15 ·2 ·25 ·3 ·4
~.;
;
..•
~
,jo • ~
i :.":
.Graph C9 Comparative flows from houses and flats
i""'
~· -··-
I I I III
:--::=···
,:._..:;....
.8
~
g
-~
0
0
0
<1. .
0
0
0
0
0
0
....
0
0
2
0
0
IZI
·C
·o
'<l
0
....
0
0
..,........
0
0
0
N-· .
o.· o-
.. !:2 co
~-:.~:··.~·
:.~;_-:
... r-~--~~---r------~~~--------~~--r--r----r---~----,-----~~-------r------~~--~--------,------------, g.
..,
'1 ~ - ....
~------~~-------+~~~----~~~~--~--~--~~--~~------+----------+-------4--_-_-------~g . 0
'·· 0
0
N
r .--
,:·
' .·
.:·..:•
:._,--:··
··._....::: ·"!·
\&f~:~~--;
ip._:_ •.., .... t---::!'~--+-..:..~--+---:rr-~'--+-+-f-+--+--'~""=-+----:.,..--:--+----'---t--"'""'"""::-+---:--""'7--t
Section C Sanitary Plumbing and Drainage
J
... · .. . ....... .:-•
~ .
I
..... "
'. Types of pools ·· Pig. 01 Pool cai/acity . ·,._.,
Swimming pools are used for several activities which
are listed as follows : all water Jess than 1·5m. remainder
• Teaching Pools Children's Pools : deep ..
Competitive Swimming Pools Recreational Pools ........·.·..·.·.•.•.•.·.·······.·:·:-:-:-:-:-:-:·:·:·:·:·:·:·:·:·:·:··:::
Diving Pools Domestic Pools non-swimmers
Teaching pools
The dimensions required are in accordance with Table
D1 and the width of swimming lanes for instruction
purposes are about 1 · 8 m. The width ofthe pool may be
built up in multiples of 1 · 8 m. The use of the width of
the pool for the teaching of swimming strokes should be
considered. Four lanes would give a minimum width of
7 · 2 m. This width gives. a reasonable distance across Calculation of capacity -
l__ the pool for swimming practice. A depth of 0 · 90 m is · •· Diving pit 3 divers in water
{ .c ~necessary for the teaching of swimming therefore a · 9 waiting at pool side ;
':' ., ·sufficient area of shallow water should be. provided in · _Zone two Swimmers 3 • 3li sq m per person in water
the design of the pool. Pool sizes are shown bela~: · + 1 /3 above for no. at pool side
Zone !hree Non-swimmers 1 sq m per person in water .'
+ 1/3 above for no. at pool side
• Table D1 Teaching pool sizes
Depth for swimming as .previously stated is not
~""'L~ri9tii ····· ·-~ Wldt~ !·:·::'.Depth--~ ..- important providing there is a minimum of 0 · 90 m. For
·. Metres
the majority of pools this would be a reasonable depth
Metres Metres .
for the shallow end increasing towards the deep end.
Approx. :.: .. : Table 02 refers to recommended sizes.
~n~~ D"p~d
. ·. " · nie-tric · Shallow max. .· Diving
' . ·, ..
-
pools
.'':Actuai -!dimension · ·:End : ··. Depth.
ti.-..:.. .... -. .: .•. · ·. •.. ·~···'· .... ~'""-~~··"-.p-.._...,
12 · 5730 12 · 5 7 · 2 or 9 · 0 0 · 90 1·750 8
16 · 7640 16 · 66 7 · 2 or 9 · 0 0 · 90 1·750
20 · 1168
25 . 1460
20
25
7 · 2 or 9 · 0
9. 0
0 · 90
0. 90
3·000
3·~50
.
~~:; ~;.:f- ~·~·-ry:::~?~~~/': ~ '?~:~': ..
Table D2 Competitive· Swimming pools
·'·"' -·
,.
.
·•.
.. - . .. . 45°max slope
~~· Minimum·
.. depth
(at shallow
ngth Width end}
. Metres Metres Metre11 I
Approx. I
· ·'I 8
.. standard -I . . . .
metric -L~·.;.;;.~.:.;,-
- . E
i.:._,..Actual
________ ;
25·1460
-~·
dimension
~-~-----··---·--;..
25
.. --· ----·
12
·_ . ·- ... •• -~·:.
0·90
ro i;• .' ·.,___
. . r---- -"'__
-~----=--r-·
33·5280 33t 12 0·90
0;90 '· •. Fig. D2 ··Di~ing pool c!imsi1sions
50·2920 50 16
Where the diving pool is incorporated in the main pool
Competitive swimming pools the dep~h;of water at the diving end should be:-·
For international championship events the length of the - ·· ~
.. pool should be not less than 50 m but the alternative For a 1 msp~ingboard a depth of 3 m is required.
, . 25m pool, plus a separate diving pool, may be preferred Fo; a 3 ~ -~~rlngboard a depth of 3 ·50 m is required and
:_.'_o·andisinfactrecommendedbytheAmateurSwimming an·area~of.-6·2 min front, and 2·7 m each side,
,~ AssociatiOFI. The 25m pool is suitaBle fen 'GeuFtty and, • measureqlrom a vertical line dropped from the centre of
··• District Championships but not for National Champion- the front:end of tha board. .
ships. The width is governed by the number of swim-
ming lanes; these should be 2 m wide. The 50 m pool for a 5 m firm platform, depth of wate·r 3 · 80 m and an
.. should be 16m or 81anes wide with a possible increase area 7-m:inJront and 3m on each side again measure
-::.to a width of 20 m 10 lanes to comply with'full inter- . from a vertical line dropped from the centre of the front
-n:o.~rnn"'• . conditions for swimming and water polo. ·: . end ofthe bOard. · · · . · . · · · : · .:: · · . . ' . : ·:: ,
~~.:f:t~-~2:~--~i;.;. ~- ~--
·: ;·, : •.
fl!ll,f;s.\0-o"l';":"... ;• .. _,... _.,., .. ,
· •- •·-
''-•
,:::':.;::~~~-~;- ~i,~{;~--~~:#.i..< ~~s k~-~~>:: ~::~i<~·k::·f(~;;?,~~!;if~1.;F,'TS.;;;~~~~~~~~i~f<;:,
-
\'••\o •• '•. -.,-..., .• , • '• • <, .-.C-.~oo..>-:t.:-0 ,.;;J.:.'..t'!:.~l'-- 4":.'1-~.~~1><:
• •. - •-• --·· • ·• (,
Pollution and purification
m
F Clla<aKeoc•llorhaiwl 4·S m 4·6 .. 3·801 3·& II 5
G Depth of water 3·0 Ill 3·5 Dl 3·8 II 5·0.
H Depth maintained forward 5·3 Ill 5·2 II 7·0 II 10·5.
I Depth maintained at si~ts 2·2 Ill 2·7 Ill 3·0 Ill 3·Q II
J Board length 4·0 Ill 4·0 Ill 5·0 Ill 5·0 Ill &·D m 9
K Board width 0·5 Ill 0·5 Ill 2·0 Ill 2·0 Ill 2·0 ..
N~t~ ·\:\:at{-:- d~Si.-..:rb~r:c:c !~.-,~ :~;-. · .... ;:
~:~i~'~;~~,~~~F;,~,~~-~::~t;~_:::;:}::.~~::;~·.ec€-~,~!;-~~~Hs~~l::;:~~~~~:I:
Qli tht- S:~.,;rfjC~' 0~ tht: p-~:(;!. i··,,s 5l~Co~L~ Cp-c-r~H.' frc-rr, U'idt-·· :f,~
6
l
10
. ..
•
Method 1 .
The inlets are arranged along one long wall an(f'the
outlets are in the opposite wall. Both. inlets and'
outlets are spaced more closely at the shallow end to
• .provide a quicker turnover. As the water flows across
the pool it has a shorter distance to travel and results
in a more rapid circulation. It is recommendt:~d that
one outlet should be located in the floor at the deep
end and be fitted. with an anti-vortex device. This
outlet can. also be used for draining down the pool.
Method 2
Four to six inlets, are ·set in the short wall at the
shallow end of the pool. The outlet should take the
form of a scum channel running around the whole
perimeter of the pool except the short wall at the A-Standard scum channel.
shallow end. At least one floor outlet should be '
provided which must be located at the deep end close B-ASA Type scum chamel.
to the short wall, where with a suitable modification C-Scum channel and concealed
to the pipework, it can also be used for draining the .channel. for draining
pool.. Access to pipework around and below the
pool should be seriously considered for maintenance bath surround.
purposes. ·
Method 3
In this method the outlets consist of a perimeter scum
· channel and three or more outlets along the centre
;·-~·:.~- :~line_· of the· floor. The inlets are arranged at pre-
\
. de1ermined spaeing -«<und- -the- who~· perimeter ~f
I"'
the pool, a little below top water level ; a practical
I
dimension would be approximately 0 · 30 m. Again
with reference to method 2, duct access should be
considered for outlets in the centre of the floor of the
pool. This method is considered to be one of the most
systems.
,.. •.
. . ·: ·?. ·.•
' .. \ ~ ~·
Fig. D5 .Scum trough design
The purified water enters the pool through inlets
located on the centre line of the floor at regular spacing.
The water leaves the pool via a channel set into the pool
surround deck around the entire perimeter of the pool.
A balancing tank is included in line from the scum
channel to accommodate water displacement from
bathers to ensure,an even flow to the treatmeot plant.
This channel alsci provides drainage from the pool
surround deck. ·.
ffi?
...
77
5':1F:e Q.VAzwx¢)• vq I Sterilisation
Sterilisation of swimming pools may be carried outby
tne use of ozone, bromine, iodine, chlorine dioxide,
. . .
Chlorination
There are three basic methods of chlorinating water:
1. The injection of gas by means of a gas chlorinator.
2 The addition of sodium hypochlorite or chloride of
lime (bleaching powder}, from solution fed
apparatus.
Skimmer outlet. 3. The addition of other compounds which liberate
chlorine or chlorine containing compounds when
- l
dissolved in water.
The use of chlorine gas has previously been considered
the most efficient method of chlorination because the
dosage can be accurately controlled ; this method is
used in large and medium sized pools.
Under chlorination is potentially a hazard in control of
Circulation channel bacteria namely coliform bacteria '8 Coli' which is .an
iAhaei1ant of the ifltestines ena its pre5ensec in -large
numbers is considered a possible danger to·. bathers;
Frequent testing of public pool water by the Public
Health Department is already mandatory and should
·therefore cover this hazard~ ·
Over chlorination can give rise to complaint~ from
bathers due to irritation of the
~ ·~. :-~·
--\ ~ ._
Pollution and purification
, Chlorination (continued)
Some of the adverse features of chlorine as a sterilising After filtration the water is passed through a battery of
agent are:- silver plates which are similar to the copper plates for
Floc formation. The electric current passing through the
· 1. ltis highly poisonous in concentration. silver plates liberates silver ions which have a streng .
sterilizing effect. It is claimed that these silver ions not
2. It is aggressively corrosive to certain metals. only effectively kill off bacteria but also remain in the
In spite of these apparent serious drawbacks, chlorin- water after it has returned to the pool and continue to
, ation nevertheless has been used for 50 years as the sterilize the wate:- as fresh contamination occurs from
premier sterilising agent for swimming pool water in all the bathers.
countries of the world. However, current trends would
indicate a movement towards the greater use of sodium
hyporchlorite.
Sterilization by chlorine dioxide
The required concentration of chlorine can be detected Chlorine Dioxide which has been used fairly extensively
by suitable test methods. Further information is on the continent is generated by the action between
available from the · manufacturers . of chlorination Chlorine anQ Sodium Chloride in solution. It does not
· equipment. · react with ammonia and so cannot produce Nitrogen
i Chlorine gas dissolves in water to form hypochlorous Trichloride. In the range of pH values which occur in
acid and hydrochloric acid + CL 2 = H 2 0 HOCL = + swimming pool water. Chlorine Dioxide is stable and is
an effective bactericide. .·
, HCL The hydrochloric acid will be neutralised by
' alkalis present in the water, while hypochlorous acid Chlorite residuals may form in the pool water and the
(which is a strong bactericide) will react with organic effect of these on the bathers is not completely known.
and nitrogenous compounds.
The student or engineer wishing to pursue the chemistry Aeration
of this process should refer to 1, 2 and 3 of the Biblio- There is divergence of views on the use of aerators. The
, graphy. object of aeration is to improve the· appearance of the
water and to give it a bright, fresh -and sparkling
Because ammonia is usually present in some form or appearance. · ·
other, the hypochlorous acid will also react with it and
forms complex compounds known as chloramines. If The disadvantages are stated to be:-
chlorine is continued to be fed to the water, it will cause
the chloramines to break down into nitrogen and (a) It reduces the amount of free Chlorine in the water.· · <>•- •
hydrochloric acid and the surplus chlorine will.f.Qrm (b) It may cause corrosion in the heating unit. ·· · . ·0 .
hypochlorus acid. The chlorine concentration at which Many public swimming pools have discontinued the
the chloramines are broken down and hypochlorous use of aerators because of the problems arising. out of
acid starts to form is called the 'Breakpoint' and the maintenance of equipment associated with aeration. In
technique in achieving this is known as 'Breakpoint the case of open air pools, the aerator often co~ists of
chlorination'. - fountains-or-water-tans which have an aesthetic appeal
to the bathers. · ·
The fundamental objective of B"reakpoint Chlorination
; is to produce a free chlorine residual without at the same
, time causing discom'fort to the bathers. Ozone
After chlorination this is the second QlOst popular
' General practice is to maintain a free chlorine residual of method of sterilization of water. It has been found that
1 mg/litre (1 p.p.m.) at the deep end of the pool when capital expenditure and running costs exceed that of
· the fresh water inlets are concentrated at the shallow chlorination systems. This system is used largely on the
end. · sterilization of drinking water supplies. Ozone is a pale
The pH range in which swimming pools operate is 7 · 4 blue gas with a smell similar to chlorine but far less
· to 8 · 0. Lower pH values than this will form dichloramine pungent.
and nitrogen trichloride, causing eye irritation to
; swimmers. ·
Equipment required for ozonation
The pH will also influence the rate at which the (a) Electrodes
' breakpoint reaction takes place and it is important that (b) Insulators or Oialectrics
: this should be as rapid as possible to avoid a build up of (c) Air drying between the Dialectrics
ammonia. (d) Cooling equipment to reduce the temperature.
Ozone is orily slightly soluble in water. In normal
Flocculation and sterilization by metallic ions swimming pool water Ozone will be quickly dissipated
Flocculation and Sterilization of water can be achieved from the solution. It is essential that any germicide used
by means of Metallic Ions,· principally those of the in the treatment of swimming pcol water should remain
-~.
:cele111ems of Copper, Atu_mintum and·Stlvet. in the water- un-til it has mairculated so that bactefia are
killed quickly to prevent cross infection between
The Katadyne Silver -process of water sterilization, bathers. It is therefore desirable to add another
· consisting of introducing silver ions into water through sterilization chemical such as Chlorine to provide a
specially prepared and treated candles. The principle is residual in the recirculated water. The disadvantage of
. very attractive as the objectionable smell of chlorine is sterilization by Ozone alone is that it does not fulfil this
eliminated. · · requirement. ·
..
··tti'~~\ii:·:C:::-~ ..·
'
. -
- 1~
J
• •, • '
·,.:.. ' ..
. l
._..,.
~ •• ...:.J:. (......._. ·•···
:: .. •.·.. ·.·t ..: ••
. ·..
~ .. , .....: .· ... .; ::_,~i-1::·:..; :.'~;:~.:~j~.t;;~
..
Bromine Fig. DB Vertical raked pressure sand filter
Bromine is in the same group of elements as Chlorine
which it resembles closely in chemical properties.
,•
Saharan North
Town Methane natural Sea
gas gas gas
Calorific value (Btu/cu. ft.) 500 995 1126 1016
Specific gravity 0·48 0·56 0·64 0·58
Wobbe number 727 1134 1400 1330
Air required (cu.. ft/cu. ft.) 4·46 9·57 10·84 9·77
..
Air required (cu;.ft/1 000 Btu) 8·92 9·62 9·-62 9·62
, Flame speed factor 35·0 14·0 14·6 14·1
: - · --- - _-~---:----'--T----'-:-·~;-:--:;~,:
r-::-.:J....~'Ifoii;···;:_:.:.
:.::...~·..:~__:..;-
__ __---.~...;...
:.-_-_:-..:.:-_- __-_-:-.-.-.- - _ --_-_--_-_-_-:_-:_-:_-:_-:_-:_:::_-:_~-:_-:_""':'+'---_-_-_:-.. -;_
__ . ~.:-.:-..:...-..;...:~I;~~~:I.r~~..,ooot
~~-~
~-· -~:~-
=~. J! : .. ' ; i.:
;-i--i--+-+--1!,
;-!-'-;
f
00~
:; ; ' ;. ' j .
:--·
0
N
..,
6
B.llaw Jed 1 W/N sso1 eJnssaJd . .· . . .·
····:
......... ·. ....... :.': · ..·.··.= :-.: ~ a-~.-~·?: ·. ~·-~;i,;~::~·~~~,~~if~----,
Section E Piped Gas Services
Table E3 : BS Case reference numbers and dimensions for meters if plate consrrLtCl~Jo,n
:up to 1000 cu ft/h (28.3 m~/h} rating · .. · · · ·
· Dimensions of meter cases . .. . ..~--·... ~. ~-... . .
Width Height Depth Offset. . .. ·'. ... Width-. . ··' ' '·'"
.. . . ..... . .. : .
_-P~e~aym~nt mota~·only · -\)...~~-:-i:··.
Back to front ... ·..· -·: .. ·-·:·-~:?:~~: ...
·including ::.1r11~t .bOsS: . . . . _";_;- ·:·~~~ca-nt~a nile _.. -'~~-;:!.:;;_: ·
·. c=et;:/~~~::~~..:,:.::~~::'t~e~ess.
. Centre Including . panels but
·as case Nominal to feet from not bezel nor ::.)i:·'··•
·reference sizes of cantre ground to attached .. ::centre line ·.-·· · ··:left side of ' '' ·:· ·
·:·number • connections of bosses boss face fittings .·.·._.of boss ·
;
..
-
Table £5 Typical equipment gas consumption figures
:: ..~.·-.. '·.
............
. . '..- .... ..·
·~~~ ~
Sectior.:. E Piped Ga::: Servic:e:::
Compressed air
Table E7 Formula for converting volume of compressed air to volume of free air
Air tools are usually rated in c.f.m. offree air. Where ratings of other air ~uipment are not
given in terms
P, -7- 14·7 Q __ Q, (P ~ 101325)
offreeaircon- Q = Q, q =q, P..;... 1·033
· sumption, the 14 · 7 1 · 033 101325
following for- Q = Cubic ft. of free air q = Litres free air Q = Cubic metres free air
mulae may be Q, = Cubic ft compressed air q 1 = Litres compressed air Q 1 = Cubic metres compressed air
• used to con- P 1 =Compressed air pressure P = Compressed air pressure in P =Compressed air pressure in
vert. p.s.1.g. kg/cm 2 Newtons/metre2
Weight and Volume of Pure Air Pure air at 32~F (CCC) and 14 · 7 p.s.i. (1 01 · 325 kN/m 2 } absolute {atmospheric
pressure) Weight: 0·08073 lb/cu. ft. (1 ·29 g/litre). Volume: 12·387 cu. ft/lb. (772 litres/k~}.
/,Compressed air
\,;Table
..
,_ _.
E10 Receivers
. for compressed .air systems
!!H"m ,~::: ~!JE ltE ~E ,J::E :~:E l!:E ~:::~! -~t:! -;i:E t~t~·~!:::,l
f~iTh~ above chart shows the amount of water which will accumulate-·· For example. at 5·4 bar. with a temperature of 3Z~2oc.
(90°F), a, ::;~~u;.'
:;~::.every 8 hours in a compressed air system using 471itres/sec. of , compressed air system would. contain ·_419 Jitres· 'of. water in ·\·.:;~:;•~-
. ~\;:~~~fr:-~ed air at di~~nint ai~ temperatures, and air pressures. .-· ;vapour form every 8 hour~; · . .;·:";: }(::-~ ~--:){'(~;:( ~('. :':.~\;\z~if~
1
'!"·:·;~ C~ ,,ow 'w.~·-· -~-·:~·~·:~'·.
•• - . . . . . . . ,• ",·-'·~:: ... }'{~·5..~
,i..· :;- ~ -,.. ·_~: ···~·-· ;:~-" .._:;.~~-
.· i]able E12. Equivalent volume of compressed air at common pressures
·.:~Volume of Equivalent volume (litres) when Volume of Equivalent Volume (litres)when ... ·.. -~
{•' :·: free air compared to gauge pressures of . free air • compared to gauge pressures of
::-:·_..:, ··litres · 4 bar : 5 bar 7 bar litres 4 bar · · 5 bar · ··7 bar ·
- - - - - - - - - . . , . - - - - - - - - - - - · : .. ·<.;·,-;.;
' 1 ·01 i' 0·84 0·63 175 . 35·3 .. 29~5 .
2·02 ;: 1·68 1·26 200 -40·4 . · .. :··33·7
··"-3·03. --~ 2·52 1·90 .'2.25 :45,4 :.=--[fl37·9
. • 4·04 ;;3-37 2·53 .- 250 . ·.50·5 . •. ::: 7~t42 ·1
·. 5·05 •t4·21. 3·16 .275 .'. 55·5
. 6·06 !5·05 3·79 .300 ;60·6 .
'7·07 t5·89 4·42 350 . •·70·7
·8·08 16·73 5:06 , 40o · i<8o·8 .
- Table £13 Volume of compressed air carried by medium grade stee/pipes, . :...- ·" --<. ~!~.:~;:~
. ofminimum bore. to BS 1387, at given velocities · "; .. - . ··.~. •,
.. -: ...-
~::._..
Velocity Flow of air (litres/sec.) through medium grade steel pipe to BS 1387,minimum bore .. :-:.~.
···... m/s 15mm 20mm 25mm 32mm 40mm 50mm ·65mm ·75mm ·100mm 125mm 150mm 200mm '·
'.-. -~----3-0 0·6 1·1 .·1·7 ·3·0 4·1_·:,6·5::-10:9.~p5·1 25·7 .. 39·2 .:··56·2.·.,98·5("'
.t:?~~ts·K;_;:~ ~: ~ ·-~ :; ·~:~ ;:~ ·!~~ ?:~-:~~; --~~~:~-r;:;:~~~·~ :~·~~~ :·~~:r:~:::~~!:~ ;:j~~~~~g :.h:::
·· ·---·. -4·5. o-9 1·6 2·6· 4·5 6J.: 9·8 --.16·4_,•-_-:22·6 ::38·5. -· 58·8 ·.\84:2 147.-o--~~·
-:
,>. 5·0 1-o 1·8 _2·8 5·0 6·8 . 10·8 ';18-2 \i-25:1--:i-'42·8· .65·4 _(};93·-e --164·0 .
. -.. -5·5 1·1 ·2-0 3·1 5·5 7·4 11·9 20·0<~27·6 ·-A7·1 .. ·71·9 ·-103·0 -: 181·0 -
··.,··: .... 6·0 1·2 2·1 . 3·4 6·0 .8-1 •13-0 _;;21·8 ::~30·1 :';:}51·3 '78-5 .· 112·0 .''.197·0 -:::
·;·_; ·. __ •; ·6·5 1 ·3 2·3 3·7 6-5 8·8 14·1 23·7 :-;32·6 ;-.; 55:6 ·... 85·.0. '122;0 ···213·0 ->
: ~:·-~:_.·7·0 1·4 2·5 4·0 7·0 '9·5 15·1'· '25·5· ~--35·1 :-'59·9 .'91·5 ... 131·0 ... 230·0
~:.·- .. :-:4.:···- 7-· 5---- -1·5 - ..:-'2·7 -:--4··3--- -7-· 5- ---10 ·1----1.6,2:...:~27 :.3 ,__..:37.:.6 .... -~64:.2_ ~::..98. 0 .. 140·0 :.'''·246. 0 .
-~~-·---- 8·o . 1·6 2·8 4·5 8-o · ·1o·8 --:17--3 '29·1 -·~40:1-~~:68·5 • 1o5:o~:-~-::,-5o:.o~2sa:a·:~
'·:-~·.- ~_- .~_.- :.f ~.:_i t,=-.~ ~:.·\-• ·:._: : ~ ~ ~;~ ~-·~ :~ --~ :f :~:~ .· :;~~~ :~-=s::::~:~~f-~{:£w.4J
',
•. .
•o • --
.. __-. c
- '-'---. ... • • f:~~;,:;'';_::-~0:;;';.~'. .. ·~--:~_-~3~,,i._.:~-i>~~~;;:•:::::7~ ·
''·- : -:c - , - _ ;:":-
·~~~~ ~~~~~~~:g!] : ; '•\ -,~;.> ~:'-
.--/ c::·, ;;_ J . .;-·,_ __
~-·
;~:::i~~rab~e
'·· .-;__,,_,/<· T_ypica/equip;;,~t con_;~:,;;:.;~:..-~.:~uni~·-·.g.~:;,P~.·-_'~~.···:/1._1_:_~. _.- ;.?_.·:.~'".s _:-._~.- :.i~.· ':-,:_ -. ~_: _: -.1~- ·~.t ·~.' -_:.~ _:.~ -;._~ ' ~:·,-~ -·.-~., _t._' ~-;·_~:.,_·~. ·- .~·'-:_·t.:? _r -,_~: -· ~_: .- ~ :.·_ .·~:.~;·:_i~.:,~.:_~-'~- .-·
Ei 4 _ .'::· >_:....._ ..
_ •.
._ _ ..
__ .. ..
_ _..-'·:.:
..-:_:_:·;.:__ :._•.
_
,. ..
~~~?-·······~
:~: S''f§k~ir:motors per kW
•. .. '"/c'"; •. e;l ,
:. ~-~·----' ..- ··;:·~-~,~~t- · :,,f~"2~."t<}~.-~:t6 ~ 22 ·:··G·; \:;~·:··)2::1:~{~:~~::~};:,:;-~;.,:z· :)!:;i
1
: ::i~:z~::icontractor's tools, breakers, diggers etc.. - ·'.,, .. · "-· · ·. ·- --:-~_:;_~----~:. _::~:~:~~-~-~;:~{ L~~~~~2 ~-_.35 ·.-· ~- -: .'.: ·.:·.. _·. ~~~.:~~,;~~~~-~-~(-~;.:t~;~(5 ·_.0 ~..-;~~~~~~,
·:' .':\~}1~lWorkshop
-..· ... ,....-_ __:._
~--
tools, blast clearers, small
_ _ __;__ _ _
' ... · ··____;~
. ·,: ~ -/ . • ,;~-:<•,;.;:-, -(~;.;:~:\1 0 ~ 13 •·. :.:. ;; ~{;, :· :' :-t~Y:f'~~;;i.';;i~'iif9 · 5- :~;:i.
__;;___;,_~......-..:.;-;-,;;..__..;...~~~_..,..,......;.;,..;....__~~--'-:~~~~~7
:·:r ;~--- · ;_' · , · btast clearers, large · -~ · ' · /:.:-?, :> :·-~-~;~:,-()o :..·ttO · ·<.;;~:[:': >"-t~;W~i::t~~·Wf~::.S::s-:~ _:_:tf
~>~ ...:..__ _ ___:.:.:.::.::..:.:..::..:.:...::..~::.:.::.::---.....,.---=-..;...;...-~~..;...;........,.-._..,..,.---:-..;...;...+~~:-:-':"'~---'-'""'"?.+:
- ; ~;<:Percussive, light ·· · 2.:.. 8 <):: ·-<: '-; ,:·: ·:'_.
· • ··~:: .::··,:~\;:;'_:o~:';-l'j;t; 5 ;·5 ":t~i:.
•t/~~j;Percussive, heavy · " -- · . . . :; :\?----- 3:.: ''t~-~:;i'h 0 ~ 15 ~;:,:>~_-'·:': ~~;::.;;,:z.;_;;-..5'; 5 -·'"~Y.
:·.-_·::··-~-Rotary (eg drills etc.) . ··_ . _.. : ~- -_~:::-( ~-2~15 · .'·.-;'::··';· :·,~:r~:~;·3·5~'-5·b
. ···Spray guns . 0·5-10
·, Medical CA reqts refer to HMSO Publication HTM 22.
.· :'"·:· :-:· . :.
:·'. :. . _--~ -~. ;. .
,:'
.....
· ~~- -·-- -.. --- -- -··
., ...
.
Compressed air
.. · ' .. ....._.·-·_
_ _
. ~ ..
:
.-.,.
. -C-
-Jl
8·
70
·V ,_
-.
._-.
.
·._
i-=~:~--~~-1~,~-"- ~-~t~~~~·~~:,·--·~
· ·" ,~_-c~ 1~; E~8: .1t~~~~ {~:: -::,~ ~·~ ·~1~
.• ·. --I
' .
~--~ : - · · - . · /
• ._,_ ,...
.- ., ····"---~~-:- - :·_:,;··~- ··- - ----;_ • :-•
.;\·.,;.-,.
•• : , .;;;:_:.•:u_
• ~---·:~
. ·-·-·
./
-C),'~:f~ ;.:~+:·~E~Sds~;~--
Pe
_ _ - _ : _:.,
j~:;:-:~~~
··:S · _ -;;';> · . _•: ., ·- 2.·_ 8 litres/~ laboratdry , . _ _:· :.\~~
___ ,_:_: _ -~24 ----. :,c-:; --·'-. " -- ->_-;:_-;,: - - - :~~;~)!:;;;-: __ .,
".: --~ <''_ . • "- ' "-.- . -~- .. _\; .-. .~:~ ;\&,;·:.-~;:: ' --~~~
·~:.
. "':_ _-,__._-
:· ~
: - -:c.- " : ·:.··. ---- ..
.. -:-···: _-
' . . . .
.j. ' . ·:·.--.:·
· · • j,·;e ~~i~f~i;
;. -:~7: ~'--Technical Memorandum No~ 22) · "' · ,- <· :,;. :.: · ·,
.: .--:~~ -~-~~-=-.' :~2.'(18'
..... ·:·ward Suction · · \ 250 TORR · .-:-·-:·.
.... : :- .
·,Theatre Suction <250 TORR .::??::·so
X-Ray Bolus · .150 TORR 686' .. ·.:·: 27
·Dental {a) high suction low flow '· 30 TORR ;,>.:)~660 .·. .:··.-26 -100
{b) low suction high flow 700 TORR . ·.·-·.···
'·:-635 25
· Pathology and Pharmacy laboratories -15- 1 0 TORR .. -· _:. .. ~ ...-:- --..
; !_:·--:·_:.:.:::::.,':~Acceptable speed· of evacuation at laboratory vacuum .:.·;;;_:c:.: .::..-.::.~.,::::..... ~:~--_;'·:~_~'1:::::~·~.::-~..c:.::::....i:. . --::-:-:-=:: . . -~ :.0 -'-~ ... -·-:•..,.:.:~..:::::.::.=..:_.~ .
>··:- · ·.·
_:; :=::.··.·..:.:.~::.. : =.-..~J": -~ :-:;':i¥2J'[~?Jti~¥f
> · :-··.:bench outlet is usually 6 litres/mm of iree air at ··. · · ·· · : • ,::~.!, "•: '"I
·g;.;!~B·~ ::::
4 bench outlets
16 bench outlets·
. _ .:, , ·'·.·sos ~, ;,;..F~:2o ·
.460 'j;;c18·1~; \\1_-.!f~~~~~.
.. ·For more detail sizing see Graph E6. '· .
.· -~ ..
. :·~? '
:·:\-.:.. :;~:-. :_~f-~=~
c~Cilc:~~~
. . . ~"< .· have a direct affect on the capacity of vapour created at - .
. .. :".any particular pressure. It would be necessary therefore . :· ·
:·. .to have these various vapours analysed, howevenhe .- :: · . ,.·. ·. ., -.- · ·, ·
. : :.~;:following will serve as a rough guide:- '' · • · ·· '\,-:"~?- _ ---: ····._:~ ·~~.:~_~_-;ifj_ .·. ~ -~· .
.,..·.:. · ~ .;; . :;~:~~~~h outlet is passing 6 litres of free air at atm~~~~-'~ ,;'; ·f~;
· ·· · . phere into the system continuously and it was required
to maintain a vacuum of 100 mm Hg at the outlet point:··
the calculation is as follows:- · · ...· · ·
£t~_:_f~,!~~;~ •.. :··.~-:~~:~(··-·~~---·
Vacuum
..
Pump sizing for individual chamber work
T = pump-down time {evacuation time) Graph ES enables pump-down time or pump size to be
F = pump-down factor from graph for given evaluated for any clean leak-tight rotary pumped system
pressure down to 0 · 1 torr.
S = pump speed (free air displacement) Due allowance made for change of pump volumetric
V = system volume efficiency with reduction in pressure but impedance of
.. (N.B. V and S must be consistent units i.e. litres
and litres/min) .
connecting pipelines neglected.
. To calculate time taken to reach certain pressure in given For recommended plant layouts consult specialised
system with given pump:- manufacturers and for medical vacuum consult Hospital
FxV Technical Memorandum No. 22.
T=--
S Reference should always be made to specialist vacuum
To calculate pump speed required to reach given pump manufacturers.
pressure in given time:-
FxV
S= Medical gases
T
The term medical gases covers the following:-
a) Medical compressed air (oil and moisture free)
• Example b) Vacuum or suction
Pump size required to evacuate a chamber of 60 litres to c) Oxygen
1 torr in 3 minutes.
FxV d) Nitrous oxide
Pump speed S = - - e) Nitrous oxide/oxygen mixture N 20/0 2
T Oxygen and Vacu~,~m are used extensively throughout
From graph E5 F = 7 most hospitals and are usually required in the following
7 X 60 areas:-
hence S = = 140 litres/min 1) In-patient departments
3
Therefore pump with displacement of 140 litres/min
2) Operating suites
and ultimate vacuum better than 1 torr required. 3) Maternity departments
4) Accident and Emergency areas including out-
patients
Graph E5 Pump sizing Vacuum and compressed air are required in dental
1000 suites, and operating-suites-for-patient ventilate~ and
operating surgical tools.
1\ Nitrous oxide is required in operating suites, maternity
\ .
,.
'' I
f
'
I
'
i '
'
!
:
'
I
I
units and accident and emergency areas. In addition
N 2 0/0 2 is usually required in maternity delive,.Y rooms.
! l 1I !I
L\ I
! For c; fl!Ore co~prehens,ve departn1ental b"e~~.CO\\'i1 and scale of
100 ' !
pro·~·isior. c~·:--:s~:~ Hosp;tat Technic::! ~·./e~..:i:~:"'.~:.:'i"'1 No. 22.
~
'
I ,. I I
'
'
\ ; ! i I '
... 10 ~ I ! I I
I
!
! I i'
0
1-
'
' .~ i I
...
Q)
' I
I
:I ! I 1
...
U) I
I I \!
U) I
'' i I
I
I
Q)
ct 1·0 I
I
' !
r.
i I
i
' I
!
....1\.' "'
!
;
'
I i !
1.
Single stage 0 ·I
pym.J1 -
i \"-! I I
2.
Two stage
pump or
l
'
:
!
;'
i X
.,/' :
combination !
T T1
'
I I
0·01
0 2 4 6
'
8 10 !2 14 16 18
~
2v
Time
- - - - - - ···- - ·-- ···--·------·-·----~..o.;._:.~.:._
' .
I.
1
I·
\ ·:,. :\: \ \ !o·:'- i j • ~- I\ :'•i:•:·
~~
'1-
i
I·.
;
.•
I
:
I' :
"
I
.g
., . . .
:
...
!i:
'i .
,
I! !,1.
,.,,
I I
:
o!
i
:_
I I
I 1
i 1,
I '
'
l ' :!,i
"d•
,! • 1 I
I I
•
I
•
I
! '
''
'
i
t ,-
I '
, '
''
'
.~,
!. :.·
:'\. ~ ;
l
; I
I
'
,,
.
!\.
·"
i'
I
-
I-~--~---+~"H'~-~~:+~~~~~-+--~--~\~-,~-·~'+'HH~~'~-~+-r-~---~'\-iT'·~·r,''i''~~t~tt~~~~-;
J• • ! . ; I I ! ' I \· ! ; I I I ;' I \. ! ' : . I !\' I 1\. !
6
;. I!
:! I III i i I
I iII iII
I '
l
'i!
I:
i !
!' '
J ! ., ,.
'
\ I'~~ 1I
!ii\·!
I '
.. ~
:
r.
J
.... ~· .. ~ '""'':-~... ·. ·~
--. --. ~------ ---·-··--. .. . ·--··~__;....___
...
I
::
''
~- --- -~--- ·----------
Definitions
Capacity is the volumetric flowrate delivered by a Total head on the pump is the static delivery heac
pump, normally expressed in cubic metres per hour plus the velocity and friction head in the entire pipr
(m 3 /h), or litres per second (1/s). system, plus the static suction lift, or minus the positivt
static suction head, as the case may be.
Static head is the pressure exerted by a liquid at rest. Note: for diagrams illustrating the various heac
to the surface, expressed in terms of vertical head of conditions on a pump, see fig. 1.
liquid. Net positive suction head (NPSH) is a method Ol
Velocity head is the pressure needed to set a liquid specifying suction performance under critical suctior
in motion and is generally of practical importance only conditions including altitude, high temperature and higt
in the case of pumps of large capacity at low heads or vapour pressure and the limitations of the pump itself
where the suction lift is near the limit. NPSH available is the absolute pressure of the liquic
Velocity head = 0 · 5 x M x V 2 where M = 1 kg. at the pump entry less its vapour pressure at thf
V = Velocity in m/second. pumping temperature. It is an expression of thE
installation conditions.
Friction head is the head necessary to overcome NPSH required is the minimum absolute pressure
resistance to motion rn pipes and fittings and is of great necessary at the pump entry to maintain the required
importance as it may exceed the static head. flow without cavitation.
The NPSH required must always be less than the
Suction lift (negative) exists if the source of liquid is NPSH available.
below the pump and is the vertical distance from the
centre-line of the pump down to the free surface of the , Atmospheric pressure varies with the altitude above
· sea-level and with the state of the weather. Normai
liquid.
atmospheric pressure at sea-level is 1 · 00 bar =
Suction head (positive} exists if the source 'Of liquid 10·20 m head.
is above the pump, a condition generally known as Gauge pressure shows by how much the intensity of
"flooded suction": It is the vertical distance from the pressure in the gauge exceeds the surrounding
centre-line of the pump up to the free surface of the atmospheric pressure.
liquid. Absolute pressure is the gauge pressure plus the
pressure of the atmosphere. When a pressure is referred
Static delivery head is the vertical distance between to, without "gauge" or "absolute" being stated, it is
the centre-line of the pump and the free surface of the understood to be gauge pressure.
discharged liquid.
Vapour pressure is the minimum pressure necessary
Total suction lift (negative} is the static suction lift to prevent evaporation of a liquid at a given temperature.
plus the velocity head and friction head in the suction All liquid evaporate spontaneously unless prevented by
pipe system. external pressure, the vapour pressure increasing rapidly
with rise- in temperature. The vapour pressure of water,
Total suction head (positive) is the static suction for example, is zero at freezing point but reaches normal
head minus the velocity head and friction head in the atmospheric pressure, 1 · 00 bar at 100°C, which is the
inlet pipe system. boiling point of water at sea-level.
Vacuum is normally measured in millimetres head of
Total delivery head is the stati.c· delivery head plus mercury, indicating the degree of partial vacuum in a
the velocity head and friction heaa in the delivery pipe pipe or vessel as a complete or perfect vacuum is
system. impossible to attain.
Fig. F1 Pumping Definitions
c:
0
-:;:'0
/
u "'
..
;
I
:J "'
"'..c:
"gc:~
I '0 0.-
0 ·.:: :::
' 0 0
u:~il
"'
..
I
/
(;.
-.i ~-~~l~:?~·:t~::~~;:=:t:;r:: :~
, ', - . .. '~
. ·. ·
·- ...
•. .: . ~ :.,~:c. ~: . . . .
\ '; ~;i;~--Defiriitions •':'
/
.·,.· ·~:_"'..·:_ ~·-..-~..:-~..~·_-...;."'_s'muc.~tio'
..
.......... ~i.~.;~ -:?il~ .<:·_._:_~:'li '_.: -'_·~-~n'"·li.ft
.. .•· -: ·.~-~-·.:m_~- ·. · -·i_.-~_-., _·, .~:_. ~- · ~·- ..'.·_· .::··:.-~.~·_,f_r.·~-~---·~·1t;.~.:7,1:_:.•~--'-(:
..··.·... - -· ·· · ·
. ... ·· ~- ..>
,,....~',, ,.
. Cavitation ····o~.r:-t::~ ~&.---
·:~;,;;:.]{~~~~~~:~::
, •< ·. When afluid (liquid or air) is ~··sucked" into a pump, it is. Cavitation is a rather complex and undesirable· con~·
,;';···.<rn fact pushed in by the pressure of the atmosphere as a · dition that may occur in a pump installation and .can ..·
>, ·; •;_• .:::result of. the pressure of the .fluid iri the pump being usually be recognized by a metallic knocking whic.h may .
.:_,: ?·-~.:reduced. The pressure of'the atmosphere, and hence vary from very mild to very severe. - .,, '· :_ ·'
·>· . · :the deptl] from which a pump will "suck", varies with In general terms and -referring to centrifugal pu.mps, ·
.:·. : . the altitude above sea-level and with the state of the when liquid flows through the suction line and enters
· ·-'!:'.\,_\weather (see definition of Atmospheric Pressure). . . the eye of the impelter an increase in velocity occurs .
, :. · ·.·: ·.rhe·:suction lift for which a· pump is listed is, unless .. which is accompanied by reduction in pressure. If the
' ·: ;.-... ·otherwise stated, the total .suction lift of which the ·. · pressure falls below the vapour pressure corresponding
· - ·pump is capable at the listed speed, assuming normal to the temperature of the liquid, the liquid will vaporize .
·. · temperature at normal atmospheric pressure, deductions and then consist of liquid plus pockets of vapour. The
being made for high altitude and for high temperature liquid then reaches regions of higher pressure through
.~: and vapourpressure. The suction lift of a pump is also the impeller and the cavities of vapour collapse, giving
. · -~ · affected by the viscosity of the liquid, but this should be rise to the noise described above.
· .·. ·<-..:.covered by the makers' ratings at stated viscosities. . Although cavitation is "popularly" associated with
. ·.:;:~,:"The effect· of vapour pressure· on· permissible suction centrifugal pumps. it is a condition that can arise with
· :. ~:: :-'>lift is <important, particularly with volatile liquids such .any pump installation unless care is taken with pump
::c·.;_:~-~as._gasoline,· aromatic solyen_ts.. and inost _liquids at . selection and planning the installation. In general terms; · ·
\( - ··. elevated temperatures andwhere suction lift is necess;. the following conditions should be avoided ·as far as
·. ·.,-~ ~ary, full details ofthe installation should preferably be possible. ·
]);t7,E~>Te.tetred to the:--stq)plier. for, consideration. Where the
··>;:-:_;~-;'~suction conditions are liable' to be criticat,:it will be.·
1 ·Suction lift higher or suction head lower
·. r_ecommended by manufacturer. . · ··. . .
than
jc~JJ~~.~;:.t:o":.'culate N~~H wlues to ensure correct . .·~ ~~~ '!'!'~~~.::flyh~~f~n~~." that for which the
, . ;;_,:,;.>>fower and efficiency 3 ·speeds higher than manufacturer's recommendation.
. For centrifugal pumps, care should also be taken that
islJ.(f~.'~~:;er. of a pump .= ti;o(~e~;~~s) they are not operated with heads much lower than
the head for peak efficiency or with capacities much
·,,:. -~ · ·,·,. = .· newton x metres
' _~~:~Sh••d
· higher than ~e capacity for peak~ efficiei}CY~- It is
~,~(~_,,, ·advisable to operate as near the·peak~·effi~iency as
possible, particularly if there are . othe('adverse
conditions present which may tend to . promote
r·\i<·\... ,. kg X g·:a1· X head - cavitation. · · ; ·:.
· ·· : seconds
Self-p.riming
- 9·81'x litres x head When a pump is operating under suction lift (negatiye). ·
{j'. ::. ::.:-. ... -'. .·.. . . . · . . _. : . ,:< seconds conditions, self-priming._ is the characteriStic;:.v.rhich ·
::::;,;:Pump power= 9~81 x'·l/s_;< m .. ·· enables the pump to evacuate airfrom the~sui::tion tine;·-~ ,
~t~"_rattS N:' . ., .thus creath1g' a· vacuum Which allows' the at.iTiosph~ric. ~- ..
pressure to push the liquid through the ·sui::tfoti'~pipe'~J
into .the pUmp.·· .· .. .· ~ . -. :-- _:··;--·~·.S.;~- _- _ ~_,_-~- ·
• N-ote: 1 kg!s =-- 1 1/s This is a normal characteristic of positive-displacement:· -
1 newton = 1 kg ;~ m;s• = force pumps but simple centrifugal pumps are not setf.:
newtons= kg :x.S·81 priming (see notes on .. Puinp Types"). · · · ·.:· _.
The total pump head must inCludP: the measured pcinp heed ..: ~
·::·,:~. _~. pluS- ~J( pipe and fitting resistances p!us the velocitY head .. .-_ Water hammer (Refer .to Section A-Hot and. Cold.· ·
')', .. >}·~ ·,:·J.H. = L-;.. Lf+t mV 2 : . . . . ·. . .· Water 5ervices). · ·
::.::,_:....:·.f "The efficiency of a pump is the ratio of the input power to the
·, "'. · ·• .. ~brake power. The brake power is the power absorbed by the purnp.
. · ··:·..:·:··.'."· . · ·:-- ·. · · ·· output .. · . · · ....: --- ;- · .
· • .. .'·efficiency %
· . · · mput ·
= -.--.·:·
.'< 100 ·_. , · ·· -_::.
. :.• Input or power to be provided.· -_l,.
. ' . ' .
output in kW l, :?.;:;{;t~~
•.
=''·"'""""''-'''"''" .. ·:.
,,;i~~~
efficiency:. % .
'to the combined effectiveness :of thr: pump and motor
efficieneces of about 50% are quite normal for coupled sets.
' -,~:~:··.:·
:_;-"--
.. : . :. '.
.•. .
.. ·-. . .... ';
The two main pump classifications are centrifugal At the point where the curve intersects the head·
and positive displacement. there being many different ordii'late, the generated head is at a ma-Ximum and
types· -within each . c~tegory. However, the main .corresponds to a np-flow condition:: this is often .
characteristics referred to below can be. regarded as · referred to as the "closed valve pressure" and a.
generally applicable. · centrifugal" pump should not be left operating in· this
A centrifugal ·pump in its simplest form consists of an condition for any length of time as it will rapidly over-
impeller and a volute casing which has to be fitted heat due to the horse pc)wer at this point being turned
completely with liquid when the pump is in operation, effectively into heat ~nergy.
the impeller "throwing'' the pump liquid to the outside The -main characteristics of centrifugal pumps can
of the volute thus imparting kinetic energy. In this way broadly be summarized as follows:
a centrifugal pump is capable of generating a certain
head which varies according to the pump speed and Capacity varies with hea_d (see 0/H curve}
the accepted method of expressing the relationship
between capacity and head is by means of a "character- Capacity proportional to pump speed
istic curve", often referred to as the 0/H curve where
Q is the quantity. (flow rate} and H is the head. Head proportional to the square of the pump speed
Typical characteristic curves for a simple centrifugal Non self-priming. · ··
.
- pump including power and efficiency are illustrated in
Graph F1. Suitable for low-viscosity liquids.
J
!'
•
Graph F1 Typical Characteristic curves ·-=·
•
Maximum generated
head closed
valve position
l(---- -~--
I•
15+--------r-------+------~------~~~-~~~------r-----~
Peak efficiency. Pump
- should oP!arate as near
j --~this point las possible
...
I _....
12 I
,)
I
\ ... -.
.:;-.·
Cll
CD
I
!;:=.:
CD
EI
s·
"C
.c
Ill
CD !
-----+------~------~~----~--~----r-----~60
,,; Efficiency-
. ·.
!I
j
iii ...
0 II I
1-
!!!
-~
iD"
61 50 :J
n 4
<
;ft.
i 45 3
J
I :;
I 3:
0
31 40 Q.
2
I
i ··~ .
JO
1·-
-~
•
•
1
r. - .·· ...
2
.
4 e 8 · f-t'-10
Capacity litres/sec:
. . . . .· ~- .j ••• ,~ •.
.... ~·-~·:;j,., . • ... }.f;
Section F Pun1p5 and P1.uuping
Pump installation
It is most important that pumps are correctly installed Relief valve
and the following notes are intended as a general guide. Positive-displacement pumps will develop excessive!
high pressures if run with the discharge shut-off c
Locat:ion throttled and a spring-loaded relief valve should b-
"The pump should be in an accessible location and fitted to the pump. A relief valve is designed to giv
there must be room for dismantling and maintenance. temporary protection against an abnormal conditio:
· It is normally advisable to raise the pump above floor and, should the valve operate, the cause should b-
level so that it is more accessible and can be easily ascertained and rectified.
drained.
Electric motors
Piping Squirrel-cage· AC motors are the normal choic
The size of suction and delivery pipes should be care- wherever possible and can usually be started direct
fully calculated and should in any case not be smaller on-line. ~nder these cond!tions, the average mote
than the pump connections. For long runs of piping or takes four to six times full load current on starting an
when handling viscous liquid they should generally be where local regulations or conditions prohibit direct
larger than the pump connection. For other than very on-line starting, the use of slip-ring motors or othe
simple runs, the actual pipe losses should be calculated reduced-current starting methods should be considerec
so as to check the total head on the pump. It is quite The type of enclosure, e.g. drip-proof or totally
common for the friction head to exceed the static head. enclosed, should be considered with reference · t
Piping should be accurately cut and fitted so that it can conditions under which the pump will be working.
be bolted up to the pump branches withoutl)utting any
strain on the pump or pipe joints. Easy bends should Switch gear
be used and sharp elbows and tees avoided. Particular It is not possible to protect a motor adequately b
care must be taken that the joints in the suction line are means of fuses only as a fuse that will carry the norrnc
absolutely tight to avoid loss of capacity or difficutty in starting current is too heavy to give protection again~
priming due to airleaks. In the case of non-self-priming ordinary overloads and pumps should be controlled b
centrifugal pumps the suction pipe should slope up starters with suitable overload releases, set in accord
towards the pump suction to avoid the possibility of ance with the manufacturer's recommendations.
trapping air ih the top of the suction piping.
Suction strainer
For most industrial applications or where solids may
be present a suction strainer should be fitted to protect
the pump. The total area of the holes in the strainer
should be never less than twice the cross-sectional area
of the suction pipe, preferably three times as a general
rule and four times or more if there is likelihood of
frequent clogging.
........~. '""''
-~.:.~-:~~~:_t_"?~~-"-~' =-~-~--
,,,, ~·~·;·... ~,~~~~~· -. ~.
-
. . ~riying_ th~ pump in reverse after stopping. CP 310:1965: Water Supply
Fire protectio11 ser·vices
Princip~l causes of fires
in buildings All equipment has to be submitted to the FOC for
testing and approval and lists are published giving the
The three basic essentials required before any fire can names of approved suppliers and the equipment which
start are:- they manufacture and install. The majority of sprinkler
(a) ·Fuel, i.e. something to burn. installations in the U.K. are designed in accordance
(b) Air, i.e. oxygen to sustain combustion. · with the current edition of the FOC Rules and these
(c) Heat. rules are also applied throughout the world in countries
The process of combustion or burning can be likened to where the insurance'is carried by British companies.
a triangle as shown below. They also form the basis of the rules recently adopted ·
by the European Insurance Organisation.
The address of the FOC is : -
Fire Offices Committee,
Aldermary House,
Queen Street,
London, E.C.4.
The FCC's Testing. Station is at Bareham Wood in ·
Hertfordshire.
In addition to the FOC the Insurance Companies have
also formed the Fire Protection Association (FPA); to
provide information, assistance and publicity material
to industry on all aspects of Fire Prevention and Fire
Fire triangle Protection. The FPA operates from the same offices as
Removal of any one of the sides of the triangle will ilieFO~ .
result in extinguishment of the fire and this is the In the U.S.A. ~the principal org~nisations responsible
principle on which all forms of fire extinguishment are for producing rules and standards are:-
based. National Fire Protection Association {NFPA)
60 Batterymarch Street,
Classification of Fire Risks Boston,
Fires are divided into three classes, A. B and C, as shown Mass. 02110
in the table below, together with the methods of U.S.A.
extinguishment and the extinguishing agent. Factory Mutual Engineering Division {FM)
Method
1151 Boston- Providence Turnpike,
Risk of Extinguishing Norwood,
Class involved extinguishment agent Mass.,
U.S.A.
A Wood National Board of Fire Underwriters (NBFU)
Textiles Cooling Water 85 John Street,
Paper New York 38,
All goocfs N.Y.,
manufactured U.S.A.
from above The NFPA publishes a series of standards in the form of
a 10 Volume National Fire Code covering all types of
B Inflammable Smothering Dry Powder .
Fire Protection but it does not approve equipment or
Liquids C02 Gas installations. Equipment approval in th"e U.S.A. is carried
Foam
out by the Testing Laboratories of FM & NBFU and
c Electrical Smothering Dry Powder they also publish rules and standards. Approval of
Equipment with a CO 2 Gas individual installations is carried out by the Insurance
Non-Conducive Company concerned as in the U.K.
Agent In view of the large number of U.S. owned firms in both
this country and on the continent, FM have recently
opened a branch office in London at the following .
Insurance companies, their role and influence address:-
Insurance companies play a major role in the provision FM Insurance Co. Ltd.,
of fire protection equipment especially automatic Palmerston House,
sprinkler installations by virtue of the reductions in Bishopsgate,
·. premiums offered when approved equipment is installed. London, E.C.2.
To control the approval of equipment and to produce · ~ ·
recognised standards of what is considered to be good
fire protection engineering practice (or rules) the tariff
Insurance Companies, i.e. those Companies applying
common premium rates, have joined together to
,....., .. , · organise. and finance what is called the Fire Offices
~:~~~n~~. (FOC). ·
~i~l#;4·~~;>· ~· -~··
Sprinkler installations
• • ' f" ·:
• :ll•·
Section G Fire protection services
Sprinkler installations
·"' Spacing of. sprinkler heads
• <>
Flows through sprinkler heads
Area coverage per sprinkler at various pressures
The maximum floor area covered by a single sprinkler Running·pressure
is laid down in the rules and varies with the Hazard p.s.i.g_::. bars
class as shown below :
10 0·70
Extra Light Hazard generally= 21m 2
20 1°40
Ordinary Hazard (All G-roups) = 12m 2
30 2°10
Extra High Hazard generally = 9m 2
40 2·80
Extra High Hazard wit~ in storage racks = 7 ·5m 2 3·50
• 50
Spacing requirements 60 ·4·20
The detailed spacing requirements can be found in 70 4°90
Sections 3100, 3200, 3300 and 3400 of the FOC Rule 80 5°60
Book.
The maximum distance between sprinklers is as follows : Graph Gt
Extra light Hazard = 4 · 6m 0 2
ftti~fffi~:~'2~ .· ' ·,
Hose reel installations
A hose tee I consists basically of a- steel drum or reel non-kink rubber hose but hose reels fitted with 25 mm
on which is rolled a length of suitable rubber hose with dia. are available if required. The usual lengths of hose
a shut off nozzle at the end the whole unit being are 23 m, 30 m, 36 m and 45 m. Each reel is also fitted
connected to a suitable water supply. They are installed with a 5 mm lever operated shut-off nozzle at the end
to provide the occupants of a building with a first aid of the hose. ·
means of fighting a fire whilst awaiting. the arrival of In determing the length of hose to be used the critical
the local Fire Brigade but they are not normally used factor is the requirement that all areas of the bu-ilding
by the Fire Service personnel unless the fire happens to must be covered·-and no part must be more than 6 m
be a small localised one as the amount of water from the hose reel nozzle when the hose is uncoiled.
discharged by each reel approximately 23 litres/min. is Manually operated hose reels are fitted with a wheel-
not sufficient to extinguish a large fire. head type isolating valve on the inlet to the reel which ·
is closed when the reel is not in use to prevent the hose
Statutory regulations from being continuously subject to water pressure.
Before running out the hose it is necessary to turn on
Hose reel installations are normally provided in accorel- the isolating valve and a warning notice to this effect
ance with the requirements of the following statutory
must be positioned adjacent to the reel. Automatic hose
regulations : reels are fitted with a valve which is opened or closed
1. The Factories Act 1961. · by the revolving action of the reel when the hose is
2. The Shops, Offices and Railway Premises Act 1963. pulled out or- rewound and with this type it is only
3. The Building Regulations 1976. necessary to pull out the hose and open the shut off
nozzle atthe end to allow water to be discharged. It is
4. The London Building Act 1939 (Section 20}. however normal practice to fit a lockshield type
5. The London Building (Construction) Bye-Laws isolating valvepn the feed pipe so that individual reels
1972-74. can be shut down for maintenance purposes without
In addition to the above, Para 1600 of the 29th Edition isolating the whole system.
of the FOC Rules requires that hand extinguishing
appliances be provided in all sprinklered buildings arid Fire protection Discharge from Jets
this includes hose reels. The FOC's detailed require- Table Gt was derived from this formula.
ments for hose reel installations are contained in Quantity · Velocity x area
Appendix D to the Rules for Automatic Fire Alarms. q=Cd X Vx A X 1000
putting Cd=O · 96- coefficient of discharge
Positioning of hose reels H inm
As hose reels are intended for use by-·th"e building din mm ··
occupants it is of vital importance that they are placed V in m/s= J2gH
in readily accessible positions so that they can be used q in litres/sec
without exposing the personnel to danger. This means 7t d2
that they must as a general rule be fixed along escape q=0·96 xJ2gH X - • - X 1()3
routes or adjacent to fire exits so that personnel 4 106
escaping from an outbreak of fire will pass them on
their way ta_. safety and can thus use them without This reduces to the following formula:-
having their means of escape cut off. q=3. 35 d2 ..j'H
In office blocks especially the multi-storey type, t_he 1000
hose reels must be fitted inside the actual office Example when d . = 8 mm
accommodation which as a general rule means that H = 9m
they are fitted adjacent to the fire exit doors into the
lift or stair lobbies. This enables the hose reel to be q _ 3- 35 X 8 2 x'l/9 _ 3 · 35 X 64 X 3 1 0 · 05 X 64
- 1000 - 1000 1000
used without opening the smoke stop doors of the q= 0·641/s
lobby and thus, prevents the lobby from becoming
filled with smoke. In industrial premises it is not always
possible to site hose reels adjacent to the fire exits Table G1 Height of jet (max) in metres
owing to the fact that the width of the building WOI,Jid
prevent the hose from reaching a fire in the centre.: In
these circumstances it is necessary to position the
hose reels in the centre of the building usually on the 3.0 2.67 2.86 2.93 2.96 2.97. 2.99 3.00
columns or stanchions but care must be taken· to 5.85 5.91
ensure that they can be used safely in the event of fire. 6.0 4.57 5.33 5.59 5.72 5.79
9.0 5.79 7.44 8.00 8.29 8.46 8.63 8.72
·,. Types of hose reel 12.0 6.10 9.14 10.15 10.67 10.97 11.28 11.4:
There are-two basit:types-of hose reel, fixed or-swinging. 15 z 10.49 12.07 12.86 13.41 13.72
15.83
14.0E
16.5C
The fixed ,type of reel should normally have their centre 18.3 11.43 13.72 14.84 15.54
line at least 1 · 5 m above the floor. A swinging type 21.3 11.89 15.24 16.76 17.68 18.29 19.02
hose reel can be swung through 180° and be mounted 24.4 12.19 16.15 18.29 19.51 2fl.42 21.3<!
at any convenient height the average being 900mm to 27.4 17.07 19.81 21.34 22.25 23.47
1 · 05 m above the floor. 22.86 24.08 25.6C
reels are normally fitted with 20 mm dia. reinforced 30.4 17.68 21.03
,1'· • • •
.. ... .. . ·· .
. j. ·~ . ~ ; .; AiEii:~;:!i:.
Section G Fire protection services
...... ·
~~ -·:::·.
Dry risers ••• Wet risers •.•• Foam systems
Dry risers
A dry riser consists basically of an empty or dry pipe Inlets
rising vertically up a building with hydrant valve outlets A 100 mm riser should be fitted with twin inlets and
on each floor and at roof level. An inlet (Breaching 150 mm riser should have four inlets. Each inlet consis-
Piece) is provided at ground level in an external wall of a 65 mm dia. male instantaneous coupling to BS 33
to enable the Fire Brigade to pump W'!ter into the riser with a non-return valve and a blank cap secured with
from the nea.rest suitable hydrant. short length of chain. The inlets are normally groupec
Dry risers are provided solely for use by Fire Service together in a sin_gle castingcalleda "breaching piece'
personnel anci they are not intended as-first aid fire or "inlet breaching" which has a single flanged c
fighting equipment for use by the building occupants screwed outlet. The "inlet breeching" must be mounte
in the same- way as a hose reel system. Use of a dry in an external wall with its centre line not more the:
riser in the event of fire avoids the necessity of running 762 mm above pavement level. When positioning inle
long lengths of canvas hose up the staircase of a due regard must be paid to accessibility, the positions l
building and thus enables the Fire Brigade to tackle the adjacent street hydrants and danger from falling glas
blaze much more effectively and in the case of very tall etc.• in the event of a fire.
buildings much more quickly. See Fig. G3 below. Inlet breechings are normally contained in sheet met~
inlet boxes with wired glass doors in accordance wit
Statutory Regulations
"
:.! Dry risers are normally installed only when required by
the Local Authority and therefore there are no insurance
BS 3980. The doors are secured with spring locks s
that they can be opened from the inside by smashin
the glass and releasing the catch on the lock.
requirements relating to them. Most local Fire Brigades
publish a standard for dry risers installed in their area. Outlets
They are normally only installed in buildings up to 61 m Dry riser outlets are 65 mm dia. gunmetal gate patte>
' ..
high; wet risers being required in buildings exceeding landing valves with flanged inlets and female instar.
this height. an eo us outlets fitted with plugs secured by short chair:
They should be mounted with their centre lines betwe~
Size and positioning of risers 91 0 mm and 1 · 06 m above finished floor level.
Risers should be 100 mm dia. where only one hydrant Outlets should be provided for every 929 m 2. of flo
valve outlet is provided on each flobr. When two outlets '- area on every floor from first floor level to the roof. t
are provided on a floor fed from the same riser then the exception to this requirement is made in the case c
diameter should be 150 mm. blocks of flats where outlets are normally only require
Dry risers should normally be positioned in the on every other floor from first floor to roof.
ventilated lobby approach staircase or within a stair- Some Water Authorities require that all inlet breechin£
case enclosure. This enables Fire Service personnel to and landing valves are tested and stamped befo
couple up their hose to the riser outlet in a smoke-free installation.
area and it is not necessary to open lhe smoke stop Automatic Air Relief Vents are sometimes required t
doors until the last moment when the water is turned on. the Local Fire Authority to be fitted at the top of tr
riser.
Owing to the fact that dry risers project above the ro
level of buildings it is necessary for them to be efficient
earthed to prevent damage from lightning.
Fig. G2 Typical arrangement of hose reel system Fig. G3 Typical arrangement of dry riser
Dry riser
Twin inlet
breeching piece
in sheet metal box
at ground level
I
,,'--;:
,
,
.
.J~
Ground
. ,,
DQ.C!f ___ _ :.--~'
Installation
Dry risers should be installed progressively as a building by means of a nut on the outside of the landing valve
is constructed in order to provide protection during body and by use of a special· test pipe and gauge can be
building operations. In buildings over 30 · 48 min height altered to give the correct running pressure when the
the riser must be installed when the building exceeds landing valve is fitted in position.
18 · 28 m in height. It is also necessary to limit the static pressure in the
canvas hose to a maximum of 6 · 6 bars if water is shut
Testing and approval
off by closing the bra.nch pipe nozzle at the end of the
Completed installations are normally required to be hose. This is achieved by means of a spring loaded
tested in the presence, and to the satisfaction, of the pressure relief valve incorporated in the outlet from the
Local Fire Authority and be approved by both the landing valve. The discharge from the relief valve is
Local Fire and Water authorities. piped via a 50 mm dia. connection into a 100 mm dia.
·drain pipe running vertically down the building along-
Wet risers side the main riser and discharging over the suction
A wet riser is a dry riser with a permanent water supply tank. In early wet riser installations a lot of trouble was
system {usually pumped) added on. See Fig. G4. experienced through inadequate drainage facilities and
. it is important to ensure that the drain pipework is short
Statutory regulations and direct with the minimum number of bends. ..
As is the. case with dry risers there are no insurance Pumping equipment
requirements relating to wet risers. Also, as they are
only installed in buildings exceeding 61 m in height The arrangement of the duplicate electric and diesel
fire pumps, starters and suction tank is identical to that
and as there are very few standard requirements it is
advisable to obtain the Local Authority requirements in used for sprinkler installations with the exception of
each instance. the method of control. In a similar way to hose reel
systems the electric pump can be either "Auto On" and
"Manual Off" or "Auto On" and "Auto Off" but in both
Size and positioning of risers
cases the diesef pump (which is the standby) is "Auto
I' . . Again as with a dry riser a wet rising main should be
positioned either in the ventilated lobby approach
On" and "Manual Off". Th~ "Auto Off" facility is
p~ovided by incorporating a flow switch in the electric
staircase or within the staircase enclosure itself. pump delivery line.
; •.. The riser should be 100 mm dia. normally with outlets
on all flqors. Normally only one outlet per floor will be Installation
required but where two are necessary a second riser The requirements for installation during construction of
should be provided at the opposite end of the·building. a building are the same as from a dry riser. If when the
riser is initially installed it is impossible to commission
Water supplies the pumping equipment, then it must be fitted out as a
Generally a wet riser water supply system should be temporary dry riser with a temporary breaching inlet in
capable of maintaining a minimum running pressure a suitable position at ground lev.el
at the top outlet at roof level of 4 bars at a flow rate of As with a dr'y riser it is necessary to efficiently earth wet
22 · 7 1/s. The maximum running pressure permitted risers to prevent damage from lightning.
with only one ou!let in operation is 5 bars.
To maintain the -above pressure and flow rates it is Testing and approval
necessary to employ pumping equi:pinent, usually Completed installations are normally required to be
duplicate electric and diesel fire pumps. In view of the tested in the presence, and to the satisfaction, of the
very high pressures involved (up to 16 · 5 bars at the Local Fire Authority and be approved by both the Local
. pump delivery) direct boosting of the town's mains is
not permitted and therefore it is necessary for the
Fire and Water Authorities.
t
i
I
pumps to be supplied from a suction break tank which
must have a minimum actual capacity of 45 ·45m 3 •
An automatic inflow from a town's main having a
Foam systems
Foam
flow rate of at least 7 · 6 1/s must be provided to refill Foam is a frothy product, similar in appearance to soap
the tank. suds and it is_ so light that it will float on the surface of
liquid. .
Outlets The properties desired in foam are that it should be
Wet riser outlets are 65 mm dia. high pressure landing tough, tenacious long lasting and flow freely. It should
valves with flanged inlets and female instantaneous also resist heat, wind and rain. and retain its water
outlets fitted with plugs secured by short chains. They content for a long time.
should be mounted with their centre lines between Foam has three constituents: foam compound, water
~· 910 mm and 1 · 06 m above finished floor level and one and air; and its production takes place in two stages.
_·oullet should be provided for ever:y .929m 2 of floor •raa. Firsnl'urtiquid foam compound is induced into the water
· In order to reduce the running pressure in the canvas stream and then aeration takes place. The two stages
hose line high pr.essure landing valves are fitted with (induction and aeration) are sometimes carried out in
an adjustable butterfly valve in the inlet which acts in one apparatus but often separate units are employed, in
a similar manner to an orifice plate and reduces the which case the mixture of foam compound and water
under flow conditions when the valve is open is pumped through a pipe or hose to the foam maker
~~·wPI~n. . ba~ and 5 bars. The butterfly can be adjusted (sometimes known.as an aerator box or aspira~o~.. b~x.>:~ .
~· ~ . .::+~{~~·:t~§iiF.:::
Application Foam inlets
Foam may be used for extinguishing fires of oils, spirits, Rooms which contain oil-fired boilers, oil storage tanks
paints, molten fats and similar liquids. Foam may also oil filled electrical equipment or other materials o
be used for items of plant or complete buildings. apparatus for which foam is a suitable extinguishinf
To appreciate the value of foam when used to fight fires medium may be fitted with pourers so placed that .:
involving liquids, it must be remembered that the liquid foam blanket can be formed over the equipment .and
itself does not burn; it is the mixture of air and the floor of the room, Pipework from the pourers would be
vapour given off from the liquid. which burns. Com- connected bac~ to a convenient point in the oper
bustion does not occur actually at the surface of the (generally in an outside wall), tne -firid)rigade can ther
liquid because the proportion of vapour to air is too connect a foam making branch pipe by means of ar
great .to form a combustible mixture. The fire occurs adaptor and pump foam·into the room or basement are;;
slightly above the surface of the liquid. to deal with the fire.
Liquid stored in open or closed tanks is dealt with by Design data
applying foam to the surface of the liquid, in such
quantities as to cover the entire surface of the burning Minimum recommendations for foam systems have
liquid. This blanket of foam exclude.s air and prevents been established by the National Fire Protectior
the formation and possible reignitio" of further vapeur. Association (NFPA) and are contained in their
standard No. 11. Application rates higher than these
Foam should not be used on live electrical equipment . · will be beneficial and reduce extinguishing time but as
because it is a conductor of electricity. a general rule the NFPA standard is accepted as a good
basis for design purposes.
Types of systems
Portable extinguishers High expan!iion foam
Extinguishers generally have a nominal capacity of up Foam has an expansion ratio of between 6 and 8 to 1 .
to approximately 17 kg and should be capable of High Expansion Foam has an expansion rate o"
expelling a continuous discharge of foam in the form of between 600 and 1,000 to 1..
a jet until the whole of the contents have been The method of generating high expansion foam differr
discha_rged. from the method employed with· ordinary foam system~
in that a fan is incorporated to provide the large quantity
Mobile foam units of air necessary for making high expansion foam.
The situations where the quantity of foam likely to be High expansion foam units may be installed as a
required greater th.an could be provided by portable permanent system with manual operation, automatic
extinguishers, foam trailers. tenders or engines may be operation or both. They may also be carried as part of a
used. These unit~ have the advantage iri.ttlat they are Fire Brigade's equipment.
always ready for immediate use, but as they cannot
. quickly be refilled, their use is limited to 'the time taken
to discharge the original contents.
:
,·~
a flexible pipe to the branch pipe. The flow of water
!hrough the branch pipe induces the foam compound
mto the water stream, aeration takes place within the
branch pipe and a jet of foam capable of a range of 9 m
from water pressure of 3 · 3 bars up to 30 m from water
pressure of 8 • 3 bars. · · ·.
Duplicate
electric or
diesel pumps ·
. ...
I
• ;~ ·~;:~:.~:;;-~-&~. ~ ·. : .. ··. .: ~. . :~ ~-~-··· _· •, ~
• v . ·~·~~
.. ... -
,.,, ... .
'\,/1> .... · - ..... ~-··~
"'• ... ~ '•#·
.....
Section G . Fire protection services
Carbon djoxide .
Carbon dioxide {CO 2 ) is a readily available commercial water spray protection to CO 2 storage areas, although
product and it is most familiar, perhaps as the gas which CO 2 is in itself an extinguishing agent.
aerates soda water.
Another way· which CO 2 can be stored is to employ a
At normal pressures and temperatures carbon dioxide single low pressur.e container for the required quantity
·is an odourless and colourless inert gas with a density and since the pressure exerted by CO 2 varies over a
of approximately 50 per cent. greater than air. ·. wide range vyith changes in normal atmospheric
As a medium for extinguishing fires carbon dioxide has temperature, it is desir~):)lf! JQ !=OI'l~()l_tf:le temperature
certain features which should be considered. -- of the contained CO 2 within relatively narrow limits so
that the storage vessel can be a reasonable thickness.
Application ·and more economic proposition. A fully insulated low
pressure vessel .would be equipped with ·a small
CO 2 extinguishes fires by reducing the oxygen content refrigeration plant to control the temperature and
and/or disrupts the fuel to air ratio to a point where therefore the pressure of the liquid CO 2 • •
further combustion is prevented. The normal proportion
of oxygen in air is 20 per cent. and ordinarily a reduction This method of storage for CO 2 has been in operation
to 15 per ·cent. would extinguish inflammable liquids. for many years in industry for purposes other than fire
extinguishing but the system is more widely used now
for fire protection purposes.
Clean anr,t pem)trating •
It is a non-corrosive inert gas with virtually no adverse Types of systems
effects on most materials and it does not contaminate
foodstuffs. It will penetrate into· otherwise inaccessible Portable extinguishers
areas and will disperse leaving no trace whatsoever. Extinguishers are"generally made in sizes ranging from
The gas is not poisonous, but if breathed in quantity it those containing 1 ·14 kg of liquid. CO 2, whose gross
can cause suffocation simply by excluding oxygen from weight is. about 4 °8 kg, to thqse containing 6 . 8 kg of
the lungs. · CO 2, whose gross weight is about 23 kg. The exting-
uisher consists of a steel cylinder containing the
Non-conductivity liquified gas, fitted with a ·sealing disc and piercing ·
It has good dialectric strength and can be applied mechanism or valve.
safely to live electrical equipment.
Mobile supply
Uses and limitations
Wheeled units contain one of two large cylinders which
It is effective on small isolated fires of inflammable are connected to a length of hose and a discharge
liquids, greases and fats, paint dips, enamelling ovens, "horn.. or discharge similar to a portable extinguisher.
paint spray booths, varnish kettles, etc. · ''
It -is well suited for use in electrlcal switchrooms,
substations and electrical apparatus generally, it is also Hand·hose systems
used in situations where the use of water would cause These systems comprise one or more large cylinders
severe damage, e.g. museums, libraries and computer mounted side by side in a rack and connected together
rooms, etc. •. - by a pipe manifold. Each cylinder is provided with a
Carbon dioxide should not be used to· extinguish fires lever operated piercing mechanism. The pipe manifold
involving : 1 · · · · .. is connected direct to one end of the hose reel and a
distributor with control valve is attached to the other
(a) Reactive metals such as sodium, potassium, end of the reel. ·
magnesium, titanium zirconium.
(b) Chemicals containing their own oxygen supply
such as cellulose nitrate.
(c) Metal hydrides.
Halogenated Extinguishing Agent systems
Total flooding
A total flooding system consists of a fixed installation agents in a similar way to carbon dioxide. The systems
of permanently connected CO 2 cylinders with piping incorporate the use of Bromlchlorodifluoromethane
and discharge nozzles similar to that described above. (BCF} or Bromotrifluoromethane (BTM}. Extinguishing
This type of system m~y be used where there is a systems using these gases are becoming popular and
permanent enclosure. The enclosure around the hazard further information can be obtained from the National
must be adequate to enable the required concentration Fire Protection Association, 470, Atlantic Avenue,
. of C0 2 to be built up and maintained for aperiod of Boston MA.022l 0 .
time required to ensure complete and -permanent
extinguishment. A reasonably well enclosed space is
required to minimise the loss or CO 2• Openings should
be closed or be capable of being closed to prevent the
continuing loss of the extinguishing medium. Where.
openings must be closed at the time of a fire, this can
be arranged by providing suitable steel shutters or fire
resisting curtains, which are automatically tripped shut
by CO 2 or electrically. In some cases it is possible to
provide .a CO 2 gas screen across an opening and a
quantity· of CO 2 must be reckoned in the calculation
for this purpose.
Safety precautions
Carbon dioxide can kill by smothering. It is not a poison
and has no damaging effect on body tissue. It can be
likened to drowning. In most cases the actual danger to
personnel is where the protected area is such that CO 2
may enter unsuspected, such as basement, pits,
electrical apparatus rooms, etc. ·
Warning notices, emergency lighting sign, etc., may. be
displayed and the provision of adequate passageways,
exit routes and keeping them clear are all desirable
features. But apart from these basic precautions, certain
safeguards must· be incorporated in the CO 2 system.
Where CO 2 can be triggered off aut~matically by
detectors some means muSt be incorporated so that the
detector~ are isolated from the CO 2 release mechanism
when personnel wish to enter the protected area.
The means of "locking-off"' the automatic part of the
system can be mechanical or electricalisolation of the
trigger circuit. The exaCt design of the "lock-off" List of British Standards
depends on the route taken by the personnel but the and Codes of Practice
object is to provide a safety arrangement which will
ensure that the system is rendered safe before personnel British Standards
enter the protected space. It is also important to provide
visual indication at entrances to protected areas so that BS 336: 1965 Fire hose couplings and ancillary equipment
it may be seen to be safe or not safe to enter. Should a BS 1635: 1970 Graphical symbols and abbreviations for fire
fire occur in a protected space while the automatic protection drawings
system is "locked-off" it is often essential that a BS 1641 : 1BSO Cast iron pipe fittings for sprinklers and other
warning alarm is sounded. Good house-keeping is fire protection installations
essential if these sorts of systems are provided with BS 2599: 1955 Flax canvas unlines hose for fire-fighting and
means of "locking off" automatic parts of the system. . fire protection
The issue and return of keys or locking pins, etc., must · BS 3169: 1970 Rubber reel hose for fire fighting purposes
be adequately controlled. BS 3251 : 1976 Indicator plates for fire hydrants and emergency
water supplies
Test and maintenance BS 5041 : Fire hydrant systems equipment.
BS 5041: Part 1: 1975 Landing valves for wet risers
In keeping with all fire protection installations the CO 2 BS 5041 : Part 2: 1976 Landing valves. for dry risers
system must be tested and maintained regularly. BS 5041: Part 3: 1975 Inlet breechings for dry riser inlets
Because CO 2 does not harm the protected areas it is BS 5041: Part 4: 1975 Boxes for landing valves fer dry risers
vary. easy te-eeff'(~ simulated fife conditions to test BS 5M1 : P.art 5: 1m Boxes for foam inlets and dry risers
the operational side of the installation. Inspection and
maintenance should be carried out regularly by a Codes of Practice
competent qualified inspector.
BS 5306: Part 1: 1976 Hydrant systems. hose reels and foam inlets
CP 402: 201: 1952 Sprinkler Systems
b . Halogenated Extinguishing Agent systems CP 4D2: Part 3: 1964 Portable fire extinguishers for buildings and
¥.:11.;,:.,.: · These systems use a gas and act as extinguishing plant_.
~:~~::~::~:~· ~-~· . ... - --;·-------~-~ .. -··- .......
-----·· ·------- ---- · - - - -
...
' . 11/64
3/16
·171875
·1B75/
4·366
4·763
27/64
7/16
·421875 10·716
·4375 11·112
43/64
11/16
·671875
·6875
17·066
17·462
59/64
15/16
·921875
·9375
23·416
23·809
13/64 ·203125 5·159 29/64 ·453125 11 ·509 45/64 ·703125 17·859 61/64 ·953125 24·209
7/32 ·21875 5·557 15/32 ·46875 11·906 23/32 ·71875 18·256 31 /32. . 96875 24·602
15/64 ·234375 5·953 31/64 ·484375 12·303 47/64 ·734375 18·653 63/64 . 984375 25. 003 .
':1/4 ·25 6·350 1/2 ·5 12·6998 3/4 ·75 19·049 1 1 ·0 25·3997
··: .. . -.
' ~.,.
·-,···
Identification of pipelines
•
For more detailed information see BS 171 0- Identifica- appliances, bulkheads, wall penetrations and at an·.
tion of Pipelines. other place where identification is necessary.
According to the complexity of ;3n installation and to the Application of safety colours and code indicatior
variety of fluids conveyed, pipes should be identified by colours.
either: .
1 basic identification colours only for installations
where the determination of merely the basic nature
of the contents is sufficient or
2 basic identification colours and code indications for
installations where the precise determination of the
contents is of importance.
Basic identification colours Safety colour 'references
The basic identification colour may be applied :
BS colour referencE
a) over the whole length or
Safety colour BS 4800
·b) as a band over a length of about 150 mm, depending
on the diameter of the pipe. Red ·04E53
Where banding is adopted, any decorative or protective Yellow 08E51
_co_lour of the pipe shall not be .any of the other basic Auxiliary blue 18E53
identification colours.
The basic identification colour shall be placed at all Code indication colours
junctions, ·at both sides of valves, bulkheads, wall (if other than safety colours)
. penetrations and at any other place where identification Colour BS 4800
is necessary. Valves may be painted with the identifica-
tion colour except where the pipeline has been coded Crimson- 04045
with the safety colour for fire fighting, when the valves Emerald green 14E53
should be painted red. Salmon pink 04C33
Basic identification colours
Yellow 10E53
Basic BS colour
identification references Colour code indications for medical gas service;o
Pipe con-tents colour BS 4800
Water Green ~ 12 045
Steam Silver-grey 10A03 OXYGEN
Mineral, animal
and vegetable
oils; combustible French Blue ·
Brown 06C39
liquids NITROUS
OXIDE
Gases in gaseous
or liquified ,. Yellow ochre 08C35
condition White] ~Blue
(except air)
Acids and
4
alkalis Violet 22C37 L Yellow Ochre
Air Light blue 20E51 ~enchGrey
Other fluids Black Black CARBON
Electrical DIOXIDE·
services Orange 06E51 Yellow Ochre
Code indications
Code indications are: MED.ICAL
AIR
1) the safety colours, viz:
a. red for fire fighting;
b. yellow, with black diagonal stripes, for warning Primrose .
of danger; MEDICAL
VACUUM
c. yellow, with black trefoil symbol for ionizing
maiatiefl ~
_ .. . Light .6IY!Lc . .
d. auxiliary blue in conjunction with green basic SPARE
colour, to denote-pipes carrying fresh water, either MEDICAL
potable or non-potable. GAS
2) information regarding the nature of the contents. Yellow Ochre
Where code indications are used, they should be All pathological services identified by additional 02_ C 37
at, all junctions, at both .sides of valves, service deep rose pink band. ·. . -.__ ,;.. J,:::::. _;.•.. :.. ·
~~- . . .
. -. ' ·:.- - ~\~·~.~~~~.~~~·~t-~;;.~\~:.--
-·· -··.
Section H ConYersion factors and n1iscellaneous data
" .
Optional colour code indications for general building services
Basic Colour code Basic
colour indication colour
(approx. 150 mm) (approx. 100 mm) (approx. 150 mm)
D
.. Central htg ~ ~.ooac Green Blue Crimson Blue Green - ·
Central htg > 1Oo°C · Green Crimson 1 Blue Crimson Green
Cold down service Green White Blue I
White Green
Hot water supply Green White Crimson White Green
· Hydraulic power Green Salmon Pink Green
Sea, river, untreated
'
Green -
Fire extinguishing Green Safety Red -Green
Drainage Black
Electrical conduits
and ducts Orange
Town Gas
Manufactured gas Yellow Ochre Emerald Green Yellow Ochre
Natural gas Yellow Ochre Yellow Yellow Ochre
Oils
Diesel fuel Brown White Brown
Furnace fuel Brown
Lubricating Brown Emerald Green Brown
Hydraulic power Brown Salmon Pink Brown
Transformer· Brown Crimson Brown
Planes of sections should be indicated by thick broken Approximate approx Invert level IL-
lines with pointers to show the direction of yiew, thus:
Diameter dia C/> Kilometre km
RWO
Cooker boiler
Dc
D
CB
Humidifier
Supply fan
• H
38
39
40
41
·0060
·0052
·0048
·0044
0·152
0·132
0·122
0·112
Electric unit 42 ·0040 0·102
heater 43 ·0036 0·091
'
Unit heater 44 ·0032 0·081
45 ·0028 0·071
46 ·0024' 0·061
47 ·0020 0·051
48 ·0016 0·041
49 ·0012 0·030
50 ·0010 0·025
Section H Conversion factors and miscellaneous data·
Spacing of pipes
The accompanying table gives the allowable minimum of insulated pipe, because furring is constructed after
distances between (a) two pipes, (b) pipe and wall and pipes have been installed.
(c) pipe and furring for two pipes with standard It should be noted that, for pipes smaller than 25 mr'n, the
malleable or cast iron screwed fittings. distance for insulation is larger than that required· for
The table has been developed on the; basis of the turning fittings. Therefore, on such small pipes, only the
following analysis: Between two pipes of differing allowance for insulation has been considered in the
diameter there will be two values for the minimum table. -,:.
distance which will allow free turning of an elbow or Example Find the minimum space required for 32 mm
tee. The value used will depend upon which pipe is and 100 mm pipes if the smaller pipe is located near the
installed first. - wall. .
In order that there will be no confusion as to which Solution The table shows. under 32 mm and opposite
pipe should be installed first, the condition giving the 100 mm pipes. that 152 mm is the minimum distance
greater distance between pipes will be considered. It is between 100 mm and 32 mm pipes.
fairly obvious that turning the fitting on the larger pipe To the left of 32 mm in the second column of the table.
will require the larger space between pipes for clearance, find~54 mm as the minimum distance from the wall of
therefore less sjJace will be required if the larger pipe is · the smaller pipe. · .
installed first. The distance from the furring of the larger pi_pe is found
lt is evident that the minimum distance from the· wall ·(above 100 mm) to be 95 mm.
will bethat distance which will allow turning of afrtting The total space is thus 152 + 54+ 95 = 301 mm.
on the pipe. This will be the distance K shown in the In the same manner it can be shown that the total space
first column of the table. if the pipes were reversed would be 1 52 + 124 + 51
The minimum distance from furring (dimension Fin the = 327 mm. so it would be advisable to locate the
table) will not be less than 6 mm larger than the radius smaller pipe near the wall or column.
Minimum distance allowable between centre 1lines of screwed steel and copper pipes
Minimum distance between furri11g (F) .mm
~ .
Minimum 38 41 48 51 '
54 64 70 79 95 114 127 152
distance
from Nom. Nominal pipe size mm
wall pipe 15 20 25 32 40 50 65 80 100 125 150 200
(K) size
mm mm '
Distance between .p1pes, mm
216 200 323 238 '241 248 251 257 267 276 289 305 321 356
' 168 150 187 191 194 200 203 210 219 229 241 260 273
• 'II 146 1.25:- ·t65 168 171 178- 181 187 197 206 219 235·
:; 124 100 140 143 146 152 156 165 171 181 197
98 90 117 120 124 130 133 140 149 159
~
JJ 86 65 101 108 111 117 120 127 133
;i 73 50 92 . 95 98 101 108 114
n
..,.
; .~
60
54
40
32
79
76
83
79
86
83
92
89
95
48 25 73 76 79
41 20 70 73
38 15 67
24 x o.d. of pipe
24 x o.d. of pipe
·1·2
1·5
1·8
2·4
1 ·8
2·1
2·4
3·0.
o~g
1 ·8
2·4
3·0
3·0
3·6
4·2
2:4
3·0
3·0
3·6
4·5
4·5
5·4
1·8
2·7
3·6
3·0
1·2
3·0t
3·0t
3·0t.
1·2
1·2
1·8
1·8
0·9
1·2
1 ·5
1·8
1·8
2·4
3·0
3·7
·.... ,.. ..;. • For pipes conveying ho_t water where it is essential to avoid air locks (e.g. primary circulation pipes).
continuous suppon is recommended. · ":·. : ...... · .,..
·. . ...
~
·.·. 7 .· ···t-:~:~a;::~:~~=.i~~~~o~~ ~~c:;~~d~!~~:~:,~~~!~gtlk --- : .~-- --·-:: · ---~- 7-:-:7]~:;: . . :;. :(~-..;~,,:;.
;.
...H~ad and pressure of water
mblrlbar mrtru
Head
Ill
metres
-~ssare
liN/m' or kPa mbar I bar
Pressure
IIH/nrorkf'a mbarl bar lllelr!
..
Head
1 9·81 98 mbar 10 100 mbar 1·02 19 186·33 1-86 bar 190 1-90 bar 19·
2 19·61 196 mbar 20 200 mbar 2·04 20 196·13 1·96 bar 200 2·00 bar 20·
3 29·42 294 mbar 30 300 mbar 3·06 25 245·17 2-45 bar 250 2·50 bar 25·
4 39·23 392 mbar 411 400 mbar "4·08 30 294-20 2·94 bar 300 3·00 bar 30·
5 49·03 490 mbar 50 500 mbar 5·10 35 343·23 3·43 bar 350 3·50 bar 35·
6 58·84 588 mbar 60 600 mbar 6·12 411 392-27 3·92 bar 400 4·00 bar 411·
7 68·65 686 mbar 70 700 bmar 7·14 45 441·30 4·41 bar 450 4-50 bar · 45·.
8 78·45 785 mbar 80 BOD mbar 8·16 50 490·33 4-90 bar 500 5·00 bar 50·
) 9
10
88·26
98·07
883
981
mbar
mbar
90
tOO
900 mbar 9·18
1·00 bar 1D-20
ill.
·70
588·40
686-47-
5·88
6·86
bar
bar
600
. 700
6·00 bar 61··
7-00 .bar .71·:
. "11 107-87 1·08 bar 110 1-10 bar 11-22 8f) 784·53 7-85 bar BOO 8·00 bar .. 81-::
12 117·68 1·18 bar 120 l-20 bar 12-24 90 882-60 8·83 bar 900 9·00 bar 91-7
13 127-49 1-27 bar 130 1·30 bar 13·26 100 980·66 9·81 bar 1 MN/m• 10'00 bar 10H
14 137-29 1-37 bar 1411 1·40 bar 1H8 200 1-96 MN/m•19·61 bar 2 NM/m• 20·00 bar. 203·
15 147·10 1-47 bar 150 1·50 bar 15·30 300 2·94 MN/m• 29·42 bar 3 MN/m• 30·00 bar 3115-
16 156·91 1-57 bar 160 1-60 bar 16·32 4110 3·92 MN/m• 39·23 bar 4 NM/m• 411·00 bar 4117·
17 166·71 1-67 bar 170 1-70 bar 17-34 SOD 4·90 MNJm• 49·03 bar 5 NM/m• 50·00 bar 509·
18 176·52 1-77 bar 180 1-80 bar 18·36
,
1 millibar (mbar) = 100 N/m2 = 100 Pa
Atmospheric-Pressure at sea level
Atmospheric pressure = 101 kN/m 2 = 101 kPa Atmospheric pressure = 14 · 7 lbf/in7
= 10·33 m head of water = 34 ft. head of water
= 762 mm mercury = 30 in mercury.
The following tables give the approximate weight of Cast iron soil pipes to BS 416
molten lead required for caulked lead .joints. Exact
amounts will d&pend upon the operator and depth of Dia. of pipe mm 50 65 75 90 1 00 150
gaskin introduced. Joints made with spun lead or lead
rope would r~quire much greater weights. Weightof ·_lb. 1·5 2·0 2·5 3·0 ·3-5 5·0
··-~-- Lead kg 0·7 0·9 1·1 1·4 . 1·6 2·3
. ·,;
Cast iron ·pipes for water. gas and sewage to BS 78 and spun pipes to BS 1211
Oia. of pi!)E! in. 3 4 5 6 7; 8 9 ·10.
•mm 75 100 125 150. 175 '. 200 225. 250
Weight of lead lb. 4·0 5·0 6·0 7·0 8·0 10·5 11·5 13·0
kg. 1·8 2·3 2·7 3·2 3·6 4·8 . 5·2 5·9
Oia, of pipe in. 12 14 15 16 18 20 21 24
mm. 300 350 . 375 . . . 400 450 500 525. 600
~ Class A-.B , lb•. 15·0 ·I 1'94 . 20·5 22·0 30·5 34·() 36·0 . 45·0
~ --Weight of lead kg. '6·8. 8·6 . 9·.3 10·0 13=8 15·4 . 16·3 .20·.4
·class e-o lb. 15·5 19·5 . 21·0· '22·5 . 31:·5 35·0.. 37·0 46·0
Weight of lead kg 7·0 8·8 9·5- 10·2 -14·3. 15·9. 16·8. 20,9
:*Sizes of pipes given in lTim are nominal until British Standards are metricated. Figures in l!alic type are no_t preferred diame~ers.
'4i"i1f\j:~fl~i~1:~1~1~~
"Noble" or Cathodic, i.e. protected end
Aluminium cast 25·56 X 10-6 655
Gold Au + ,-~-42 sheet 23·00 655
Platinum Pt + 1:20 Brass cast 18·77 926 ..
Silver Ag +0·80 sheet 19·35 1010. •.
Air vessel A closed chamber which utilizes the Hardness (of water) That property of water, caused
.. ;:· compressibility of contained air, either by certain mineral matter dissolved in it.
(i) to promote a more uniform flow of which .resists the lathering of soap. Hard-
water when connected to the delivery pipe ness is assessed by expressing the particular
or suction pipe of a reciprocating pump, or mineral content concerned as pans per
to the delivery pipe of a hydraulic ram, or million (by weight) or by milliequivalents
(ii) to minimize shock due to water per litre. Formerly it was expressed as
.- hammer when connected to a high -:.degrees-Clark' which was the mineral
pressure water system. content in grains per gallon•.
Air-water storage A tank or cylinder in which water is stored Temporary That part of the hardness of water which
vessel · ·under the pressure of air compressed in its hardness can be removed by boiling, when pan of
upper pan and forming pan of a pumped the mineral content is precipitated as solid
water supply system. Variations in the matter.
amount of water stored are accompanied That part of the hardness of water which
Permanent
by variations in the pressure of the air and remains after the water has been boiled.
hardness
water and can be used to control the
starting and stopping of the pumps•. Head ' The vertical height of a column of water
Pressure which would produce at its base, by
Backflow Flow in a direction contrary to the natural virtue of its own weight. a pressure equal
or intended direction of flow. - to· that to which the water is actually
Backnut 1. A locking nut provided on the screwed subjected. ·
shank of a tap. valve or pipe fitting for The pressure head when the water is at
Static
securing it to some other object.
rest.
2. A thin threaded nut. dished on one face Total • The sum of · the position, pressure and
to retain a grommet. used to form a water-
. velocity heads.
tight joint on a long-threaded pipe.
··.Capacity 1. The volume contained in a vessel. Working head The head of water at which a pipe, vessel
or pump is designed to work. . .
Actual capacity 2. Of a storage cistern. The capacity of the
cistern measured up to the water line. Joint A welded joint in which two pans made of
Cavitation A phenomenon in the flow of water con- Autogenous the same metal are welded together with
sisting in the formation and· collapse of ,__welded or without the use of afillerrod ofthe·same ,
cavities in the water bringing about metal.
pitting on ballvalve outlets and seatings Brazed A joint in which the pans are united with
of valves•. molten brass. {Silver solder) (Many
CiStern A fixed container for water in which the proprietary brands of rod on market) •. : ·.
water is at atmospheric pressure. The water Bronze welded A welded joint · in- which the parts are
is usually supplied through a ballvalve. united with molten bronze. The process is
Storage cistern A cistern for storing water.' distinguished from brazing by 'the ·local
Water Byelaw Any cistern, other than a flushing cistern. building up of the welding material.
definition : having a free water surface under atmos-
Capillary A iine"clearance.:.spigot and socket joint
pheric pressure but does not include a into which molten solder is caused to flow
drinking trough or drinking bowl for by capillary action.
animals including poultry.
Stopcock Manipulative A compression joint which requires the end
A cock fitted in a pipeline for regulating the
type compression of the pipe to be shaped outwards before
flow of water.
assembly to enable the pipe fitting to grip
Cross connection 1. A connection between two normally the pipe.
independent pipelines which permits flow
from either pipeline into the other. Non-manipulative A compression joint which does not require
Note: Such a connection may be a ~pe compression the end of the pipe to be shaped before
possible source of contamination of a assembly because the pipe fitting is made
water supply. to grip the outside wall of the plain pipe by
2. An irregular connection between a foul means of a compression ring.
drainage system and a surface water Fusion A joint made on certain types of plastics
drainage system. piping, e.g. polythene, in which the
Cupro-solvency The ability of some waters to dissolve surfaces which are to be in contact in a
copper. closely ·fitting spigot and socket are
Disk feed separately heated. While both are still hot,
A method of regulating the rate of flow into
the spigofis inserted in the socket, where-
an automatic flushing cistern by the use of
upon the two become fused together.
a thin disk. with a calibrated orifice,
mounted in a union in the feed pipe. Shrunk rubber An '0' ring joint used on certain types of
Diversity factor A factor used in the design of pipework to joint ring plastics piping, e.g. PVC, in which, by the
Probability of determine the maximum rate of flow to application of heat. the socket is shrunk on
simultaneous allow for in a pipe. When there is a large · to the spigot thereby entrapping the rubber
demand. OOFJ\Der ef~ff points. it ia improbable- ring.
Probability of that all will be in use at the same time. Solvent welded A joint made on certain types of plastics
simultaneous,· Similarly, where a large number of outlets piping, e.g. PVC. in which the surfaces
Solvent cement
discharge. discharge into one outlet pipe or channel which are to pe in contact in a 'c_losely
it is improbable that all will be used at the fitting spigot and socket are separately
same time. The diversity factor is the smeared with a solvent. after which the
probable rate of flow divided by the • spigot is inserted in the socket, whereupon
the two become united. ··· ··;.
Section H . Conversion factors and miscellaneous data
Loading unit A unit so chosen that the relative water Water line A line marked inside a cistern to indicate
requirements of sanitary appliances can be the highest water level at which the ball-
expressed as multiples of that unit. The valve should be adjusted to shut off. ·
loading unit rating of an appliance depends Working pressure The pressure at which a pipe, vessel or
upon the duration and rate of flow required pump is designed to work.
at the appliance and on · the interval
between usage. · ·Hot water supply
Pipes An overflow pipe, corisisting of a vertical
Standing tube, standing in a cistern and passing ; A process for rust-proofing cast iron or mild
Bower-barffing
overflow through its base. steel in which the metal is raised to red
Distributing pipe- Any pipe (other than an overflow pipe or a : heat and treated with live steam.
.Water Byelaw flushing pipe) conveying water from a Tongue tee ·A tee having an internal projection· so
definition storag-e cistern. or from a hot water placed as to divert part of the flow from
apparatus supplied from a feed cistern. the main pipe into the branch pipe. ·
and under pressure from thirt cistern.
Breech fitting .A symmetrical pipe fitting in which two
Overflow pipe A pipe connected to a vessel, sanitary Breeches fitting _parallel pipes unite into one pipe. The flow
appliance, $ewer or chamber to discharge Breaching fitting may be in .either direction according to the
A excess water. purpose for which the fitting is used •.
~-
· ·Service pipe- So much of any pipe, for supplying water . Calorifier · · 'A storage vessel, not open to the atmos-
IJVater Byelaw from a main.to any premises. as is subject phere. in which a supply of water is heated.
definition to water pressure from that main, or would The vessel contains an element. such as a
be so subject but for the closing of some coil of pipe, through which is passe~ a-
stopvalve. . .;·supply of hot water or steam, in such a way
Warning pipe- An overflow pipe so fixed that its outlet. thatthe two supplies do not mix. heat being
whether inside or outside a building, is in a transferred through the walls of the element.
Water Byelaw
definition conspicuous position where the discharg!! - Cathodic A method of protecting metal pipes· or
of any water therefrom can be readily seen. ; protection vessels exposed to corrosion. The corrosive
Pipe ring A ring-shaped clamp. made in halves for action is modified so that the metal to be.
screwing or bolting together, which forms protected becomes ·the cathode instead of
Pipe ring, single the anode, and this is done either
part of an assembly for supporting a pipe.
Split pipe ring One half of the ring incorporates an (i) by attaching a block of other metal.
integral socket screwed internally to higher in the electrochemical series, such
receive the threaded end of the_supporting as magnesium, which then becomes_ the
unit. anode and suffers corrosion, or
(ii) by applying a small electric current
Pipe union A union for connecting together tWo pipes. from an external source. ·
It is made in three parts, two -t>f which are
Primary circuit A circuit in which water circulates between
for fixing to the pipe ends, the third being a
a boiler or other water heater and a hot
coupling nut.
watet:Storage--vessel. · ·
PI umbo-solvency The ability of some waters to dissolve lead. A circuit in which water circulates in
Secondary circuit
Back-siphonage Backflow caused by siphonage of a liquid distributing pipes from and back to a hot
from an appliance or storage vessel into water storage vessel. ·
the pipe feeding it. · ·
Closed circuit A system of pipes and fittings in which the
Elbow action A quarter turn tap with a lever handle which same water is circulated and from which no
Tap can be operated by the forearm. water is drawn off for use, as in a hot water
Wrist action A quarter turn tap with a short lever handle space heating system. ·
Tap which can be operated by the wrist. Water Byelaw Any system of pipes and other water
Delayed action definition: fittings through which water circulates and
A ballvalve with its float riding on the
ball valve from which water is not drawn for use, and
surface of the water in an open-topped
includes any vent pipe fitted thereto but
chamber fitted within a cistern. The open-
not the feed cistern or the cold feed pipe.
ing of the ballvalve is delayed until the
water level in the cistern has fallen through Feed cistern A cistern for supplying cold water to a hot
a fixed distance, when the chamber water system.
empties itself into the cistern through a Water Byelaw Any storage cistern used for supplying cold·
non-return valve. When the water level definition : water to a hot water apparatus, cylinder or
rises again, the chamber is refilled by flow tank.
over its top edge, thus quickly closing the Expansion cistern A cistern forming part of a hot water heating
ballvalve. system, which accommodates the increase
Equilibrium A ball valve, so designed that the hydraulic in volume of the water when hot; it can·
ballvalve forces acting on the closing disk or piston also act as the feed cistern for the system.
are hydraulically balanced. Cradle A support shaped to fit the underside of a
f·:·'. · · -~acti-on A ballwlw, fer use-ln large autcmalis ~ mRe. cylinder or appliance.
A slow plastic deformation or movement of
!, ,.-
ballvalve flushing cisterns, which is open when the Creep
float is at top water level and closed when a material under stress.
the float is at bottom water level. A pet cock Cylinder. hot water A cylindrical closed vessel for storing hot
on the supply side of the ballvalve initiates Water Byelaw water under pressure greater than atmos-
the operation. definition pheric pressure. •
· Water hammer A hammering sound caused by violent Indirect cylinder A cylindrical calorifier with- a heating.
surges of pressure in water · element ofannular shape, inside. : · · ''\:, · '•'·\.~ ....
;,,,·\ ~·;· .-,,~:·:·~:~::~:,:~--~-~·~~i_tJ.t...-:
~ Hot water supply
.·Dead leg A length of hot water pipe leading to a Discharge unit A unit so chosen that the relative load-
draw-off point and not forming part of a producing effect of sanitary appliances can
circuit. be expressed as multiples of that unit. The
EXpansion loop A loop in a pipeline which. by flexing. can discharge unit rating of an appliance
. accommodate expansion and contraction depends on its rate and duration of
movement. · discharge and on the interval between
· "' _. · · Expansion joint A joint which permits relative movement of discharges.
'the jointed parts caused by expansion and Flushing trough " A flushing apparatus which combines
contraction due to temperature change.. Trough cistern several discharging units in one long
cistern body to allow the more ·frequent
One-pipe The circulatory flow of a stream of hot flushing of the W.C. pans in a range than is
circulation water in one direction and a stream of possible with individual flushing cisterns.
cooler water in the opposite direction at
the same time and in the same pipe. Garchey system A system for the conveyance by water
carriage, and for the disposal at a central
Parasitic In a domestic hot water system, the plant. of domestic refuse from multi-
circulation unwanted circulation of hot water in a _storey buildings.
pipe circuit. intended to be temporarily Group connector A cast iron double .or triple branch fitting,
inactive. or in a vent pipe.. on a drain. with socketed branches to
· ·. · ·"1:old feed pipe -A distributing pipe conveying cold water receive waste pipes and a spigoted outlet
·". ;_ ·Feed pipe ·from a cistem to a hot water apparatus. for connecting to the socketed inlet of a
', .~Vent pipe A pipe, in a hot water appliance, for the gully or grease trap~ · ·
: Exhaust pipe escape of air and for the safe discharge of loop vent A branch ventilating pipe which; aher
·.Expansion pipe any steam generated. being carried above the spillover level of
. · Plumbing unit A pre-fabricated plumbing assembly of the sanitarY appliance it serves, is .con-
pipes and fittings with a supporting frame- nected at a lower level to a soil or waste
work. pipe, which is not freely ventila.ted to
Direct system A hot water supply system in which the atmosphere. or to the .drain serving .ttie
water supplied to the draw-off points is sanitary appliance. .
heated by a primary source of heat such as Note: In the United States the term is used
solid fuel. gas, electricity or oil. with the following meaning: 'A branch
ventilating pipe which serves.the topmost
Indirect system A hot water supply system in which the range of not more than 8 sanitary· appli-
water supplied to the draw-off points is ances. The upper end is connected to a
heated by means of a calorifier. stack vent and the lower end to the
Spray mixing tap A tap. supplied with hot and cold water and horizontal branch soil or waste' pipe
incorporating a mixing device..pperated by between the two appliances· most remote
the user. The mixed water is delivered at a from the discharge stack_'
restricted rate of flow in the form· of a spray. A pipe which conveys. to a drain the
,
Soil pipe
Spray tap A tap supplied with water at a predetermin- Soil conductor discharge from a water closet. urinal or
ed temperature which it delivers at a slop hopper. In the 'one pipe' and 'single
restricted rate of flow in the forin of a spray. stack' systems the soil pipe also conveys to
•'
a drain the discharges from baths. wash
Sanitation basins. sinks and similar appliances.
Inverted branch,. A branch fitting. for a soil or waste ventila- Soil-waste A pipe for conveying both soil· ani:! waste
ing pipe, on which the branch, which may discharge pipe water.
terminate in either a socket or spigot. is Ventilating pipe A pipe in a soil and/or waste pipe system
either inclined below the horizontal or is Soil ventilating pipe which facilitates the circulation of air
parallel to the main pipe and facing down- within the system and protects trap seals
wards. (The branch is intended for the from excessive pressure fluctuation.
connection of a branch ventilation pipe}.
Waste pipe A pipe which conveys to a drain or soil
Chair A metal frame for building . into a thin pipe the discharge from a sanitary appliance
Waste conductor
partition wall and the floor so as to provide Waste, deprecated used for ablutionary, drinking or culinary
means of supporting a wash basin, W.C. purposes.
pan or other sanitary appliance clear of the A ventilating pipe in a waste pipe system.
Waste ventilating
floor.
pipe
Flushing cistern A cistern provided with a device for rapidly
discharging the contained water and used Receiver. diluting
in connection with a sanitary appliance for
the purpose of cleansing the appliance and
carrying away its contents into a drain.
Note: The nominal size of a cistern is the
quantity of water discharged per flush.
Dual flush cistern A W.C. flushing cistern which gives flushes
'of two different volumes. either of wbich
. g,n be~ b¥ th&-YHf.o
Relief vent An additional ventilating pipe connected
Crossvent -" A short relief vent between the main soil or to a soil or waste pipe at any point where
Yoke vent waste pipe and a main veittilating pipe. excessive pre~ure fluctuation is likely to
·crown 1. The highest point of the internal surface oc ur.
of a pipe or culvert at any cross section. Induced- The extraction of water from a trap by
2. Of a trap. The topmost point of the outlet siphonage siphonage set up by reduction of pressure
ofa at the outlet of the trap. · · • · ·· ·. ·· · ·
.' ~ ...
.. ·.. ' ...."'. ..... , ..
~
Self- The extraction of water from a trap by Back-drop A vertical or steeply sloping connection to
siphonage siphonage set up by the momentum of the connection or near the invert level of a manhole from
discharge from ~he s~mitary appliance to a sewer or drain at a higher level.
which the trap is attached. Balcony A fitting intended to be interposed in a
Stack vent The extension of a soil or waste stack. outlet vertical rainwater pipe passing through a
above the highest branch soil or waste pipe balcony, and providing · an inlet for the
connection, terminating in an end open to drainage of rainwater· from the balcony.
atmosphere; Benching Sloping surfaces so constructed on either · ·
Two-pipe A soil and waste system comprising two side of channels at the base of a manhole ·
system independent pipes, namely, a soil pipe as to discourage the accumulation of ·
conveying soil directly to the drain and a deposits. ·
waste pipe conveying waste water to the Barron's bend A short three-quarter section branch bend.
drain through a trapped gully. The system Slipper bend
may also require ventilating pipes.
Knuckle bend A short radius bend.
One-pipe A soil and waste system in which a single
system soil;.waste pipe conveys soil. and waste Trapping bend An unsocketed 90' cast iron bimd, with
· water directly to the drain. The system may one long arm for use as a dip pjpe in, for
) . also require ventilating pipes.
Catch pit
example, a petrol intercepting tra"p.
_A pit excavated or a chamber_c~nstructed.
. ..
Single-stack A one-pipe system from which, subject to
system the observance of certain stringent niles. in and below the normal level of a ditch,
all or most of the trap ventilating pipes are drain or sewer to trap silt and solid matter
omitted.· and facilitate its removal.
Spray tap basin A wash basin designed to receive the Cesspool ·1·· An underground chamber for the recep-
discharge · from a spray tap without tion and storage of foul water, the contents
splashing. It normally has one taphole and .of which are periodically removed for
no overflow and is fitted with a grated disposal. .·
waste. - 2. A box-shaped receiver constructed in a
roof or gutter for collecting rainwater which
Performance test A test for the stability of trap seals in soil then passes into a rainwater pipe connect-
·and/or waste pipe systems. ed thereto: ' ·
Catch pot trap A bottle trap with a removable lower part Foul water drain A drain intended to convey foul water.
large enough to retain waste for examina-
tion or recovery. Process drain A drain intended to convey process or
trade wastes only. ·
Deep seal A trap having a water seal 3 in. or more
trap deep. Subsoil drain 1. A drain intended to collect and carry
away subsoil water.
Resealing trap A trap designed to retain an effective water Subsoil water drain 2. A. drain intended to disperse into the
seal after relieving excessive pressure subsoil the effluent from a septic tank or an ·
fluctuations either at the inlet or outlet of overflowing cesspool.
the trap..
Surface water. A· drain intended to convey surface water
Running trap A tubular trap having the inlet and outlet drain only. ·
in horizontal alignment.
Drain chute A tapered drain fitting fmed to the inlet or
Vent stack A main ventilating pipe. outlet of a manhole to facilitate rodding.
Wastibasin ,. A sanitary appliance primarily intended for
washing the upper parts of the body. It has Drop connection A length of drain laid vertically immediately
a waste connection and a piped water before its connection to a sewer or to
supply and is generally of ceramic ware another drain.
but can also be of metal or of plastics. Dry weather 1. The foul water, together with infiltration,
Grated waste A waste fitting with an integral grating flow if any, flowing in a sewer or drain in dry
flush with its inlet end and hence incapable weather.
of accepting a waste plug. 2. The rate of flow of foul water, together
with infiltration, if any, in a sewer or drain
Depth of water The depth of water which would have to be in dry weather.
seal removed from a fully charged trap before
air could pass through the trap. Puddle flange A flange on a pipe, at the point at which it
Puddling flange will pass through a water retaining
Wet venting The use of the lower portion of the structure, to increase the resistance to
ventilating pipe, in a waste pipe system or leakage along the exterior of the pipe.
a soil/waste pipe system, as a waste pipe.
Hydraulic The loss of head in liquid flowing in a pipe
gradient .. or channel expressed per unit length of the .
Drainage pipe or channel. In a channel the hydraulic
gradient is equal to the slope of t!le free
Aerobic Pertaining to the action of micro-organisms surface of the flowing liquid.
in the presence of oxygen. A factor used in calculating the rate of flow
Hydraulic
::: · Anerobic Pertainin9 to the action of micrO·I)T£l!ll'li$m.3 mean-Eiepfn ef eliEtuiEf iftit"~ t'1f elmmel•. ft is otmrined ~ ~
in the absence of oxygen. by dividing the cross-sectional area of the
Anti-splash shoe.' A rainwater fitting fixed at the lower end of liquid by the length of the wetted perimeter . ·
a rain water pipe and so shaped as to of the pipe or channel. •
reduce splashing when rainwater is dis- Invert 1. The lowest point of the internal surface
charging into the open air. of a pipe or channel at any cross section.
The vertical fall _in a back-drop connection. 2. The lower poition of the Inter!'~~~ ,. ~- .
surface of a drain, $ewer or channel•. _ ,_.,...-i;,;l\,, ·
.. '·:··.-~~ ...
·· ·:--::. -· :::.:-"'.··.-::·.~ ... :. ·.~.. ,..~'-.ift''" # • ~,·j
. ..
) ,·
. .. ·.•
.. ...
~. .. . ' :· ~. .. : ~~;?,b:.'
f)'r. ..·;;t~ ... . '
f..JZ'tlr. .,.t·
~
·., . . . . . ••••• • . lo· :J
11t.~:f ~
.... -=<"=h
r
I
i
I' .
I
!
Useful addresses
• Drainag,e
Addresses as classified as follows:
1 Contractors' Trade Associations
Joinder junction A junction pipe in which the branch is
manufactured with a closed end designed 2 Manufacturers· and other Trade Associations
to be cut off when the branch is required 3 Professional Bodies
for use. 4 Research and Advisory Bodies
Flushing manhole . A manhole at which water for flushing is 5 Regional Water Aulllorities and Water Companies in
introduced into a drainage system. England and Wales. · ·
Rainwater shoe 1. A rainwater fitting at the foot of a rain- , I Fuel Interests
water pipe to discharge rainwater into the 7 Government DePartments
open air clear of the building surface to
I Training O~isations
which the pipe is fixed.
2. A drain fitting. fixed horizontally at the · 9 Trade Unions
foot of a ninwater pipe, having a vertical 10 Safety Organisations
or horizontal inlet and an inspection open- 11 Overseas
ing with either a grating or a sealed cover.
Raising piece A fitting for extending the height of a gully
Gully riser or of a rainwater shoe. A gully raising piece
Rising piece may have branch inlets. 1 Contractors' Trade Associations
Ramp A short length of a pipeline or channel laid Association If Boller Setters, Clllmney aad Fv1111e1
at a considerably steeper gradient than the Constructol1,
adjoining portions. 64 Queen Street, London EC4 01-248 1755 .
·Rest bend A cast iron or stoneware bend, having a Brltlsll Coaslnlclloal Sleelwort Assoclatioa,
Duck foot bend foot formed integrally in its base, used to . Hancock House. 87 Vincent Squm, London SW1
receive a vertical pipe or line of pipes. 01-834 1713 .
. Self-cleansing The.velocity of a flowing liquid in a pipe .; Committee of Associations of Speclalld Eaginlll'lq
·velocity Coatl1ctDI1 (CASfC) .. . .
or channel necessary to prevent the
deposition of solids in suspension. · ESCA House, 32-34 Palace CoUrt; Landon W2 4JG
01·229 2488 - .
Soffit The highest point of the internal surface of Bectrical Conlriclllrs' Association (ECA),
Crown a pipe or culvert at any cross section. 1 ESCA House, 32-34 Palace Court. London W2 4HY
· Combined system A drainage system-in which foui)Nater and 01-229 1266 . - :: •.:•.• ..:;:-, . . ' . ,_:.
surface water are conveyed by the same Bectricai ContractDis• AssiiCiaifoa of ScoUilld, ·. ·
pipes. 23 Heriot Row. Edinburgh EH3 ~. 031-225 722112
Separate system A drainage system in which foul water and Fed~m~tion ol As:soclatloas ol Speclalldl and Sab-
Contrlcto11 (FASS), .. .· ·
surface water are conveyed in separate 376 Grays Inn Road. London WC1X 888 . OH78 9604
pipes.
Federation ol CIYII Envineerlag Contrlcto11, · ·
Concentric taper A taper for connecting together pipes Romney House, Tuflon Street. .London SW1 ··
Concentric taper having their axes in the same straight line. 01-222 2544 . . . . ..
pipe ' HeaUng and YllllllaUng Contractora' AssociaUon
Level invert taper A taper for connecting together pipes (HYCA), . • · •. . .·
Level invert having their inverts ·in the same straight ESCA House. 32-34 Palace Court, London W2 4JG
taper pipe line. 01·229 2488 .
Buchan trap (Sconish) An intercepting trap with a House BuJJde11 FHersUon,
horizontal inlet having also a vertical socket · 82 New Cavendish Street, London W1 M BAD
01-580 4041 .
on the inlet side of the trap for the con-
nection of an access pipe. It is also obtain- Insulation Glazing Association,
6 Mount Row, London W1Y SOY. 01-629 ~
able with means of access on the outlet
side of the trap. Metal Roofing Co111racto11' Association,
r;Jo Drake & ScuD. Hamlyn House, Highgate Hill.
High invert trap A trap with a vertical inlet in which the London N19 01·272 0233
trap level of the outlet invert is high in relation National Association ol Plumbing,· Heating ami
Low back trap to the inlet . Mechanical Sml:es Contrlcto11 (NAPHMSC),
(Sconish) 6 Gate Street, London WC2A 3HX 01-405 2678
Intercepting trap An intercepting trap designed to be fixed Natiolllll Federation ol Building Trades. Employe!'$
with reverse · on the inlet side of an interceptor chamber. (HFBTE), .
clearing arm 82 New CavenlfiSh Street, London )¥1 M BAD
01-580 4041
Reverse action An intercepting trap which is used when
intercepting trap National Federation ol Roofing Contracto11,
the water from a subsoil drainage system 15 Soho Square, London W1V 5FB 01-439 1753
needs to be brought into the main drainage
Scottish I Nortllern Ireland Plumbing Employe!'$'
system of a building. A ventilating pipe is Federation (SHiPEF),
joined to the trap at the end of the subsoil 2 Walker Street, Edinburgh EH3 7lB 031·225 6842
drain.
Low invert trap A trap with a vertical inlet in which the level
of the outlet invert is low in relation to the
inlet.
Anti-flooaing valve A non-return valve, for use on a drain,
/ usually consisting of a floating ball and
seating, preventing the backing up of
flood water.
Wened perimeter The line of contact between a pipe or
channel, and the liquid flowing therein, at
a cross section. · .. . ·.. •. - -·
... ~-
'' ·; \'
Useful addresses
·~~i'ii~r~Ag~~r:: . :.:fi~~:B~~,~~'tJ:~ut:ri~tr,:,~
.
~-··.~-=:"~--=-~~~~--
~··.. : ·'":"
.......-.............
~--'----· -·-· . ··--·--._.....-;,;.,....;:..·-..:.... :...... .,. · ... .. !·, . . . . · : · . . ~·,..\ ••{;~~:.'~~ _.. ••.•..
·~r
J ·.
Jllllltllla
Dl ftlllllltlag, 11rt11111 Coal UUIIatin .Reseasa AlloclaUoa, Building Materials &,cirt llnllp,
. ·' Scottish Mutual House, 29 North Street, Homchurdl Randalls Road. Leatheltlead, Surny 503 4411 26 Store Street. London WC1E 1BT 01-636 6920
•, . . RM111RU: 49-51236 .· llrltllll Campnaod Air SDCitty, Building Rnamll &tabiiUJIIIIt,
' ·llltltlltl ol Ollllltlty Sumyora, Leicester House. 8 Leicester S!r!et. LDndon WC2 7BN 6ars1on, Watford. Hens. 09273 74040 .
'l.• 98 .Gloucester. Place, London Wt4 AT 01-437 0678 lllldlq Rnaasa Aftlsory Senlca,
(.: 01-935 1859/4048 ' . Building Researr:b Station, Garston, Watford WD2 7JR
llrlllsillral led Stall RIIIII'CII AaoclaUan,
~~-- ·. . : ~-:lliutale·DI ~IIH, : 24 Buckingham Gall, London SW1 01-828 7931 6ars1on (Herts.) 76612 (STD 09273) · . ,
. . . • _, . 272 'London Road, Wallington, Surrey 01-647 7033 Fire Research Station, Borehamwood, Heftis. WD62BL
biJIIItl: *Water-PolhttiDD CDI!IrDI, Jlrtllsll lon-Ftrrlla .Metals flderatloa. '· 01-953 6177 .
· ledson . House, 53 London Road, Maidstone, Kent Crest House, 7 Highfield Road. Ellgbaston, Birmingham
B15 3ED 021-454 n66 Princa Ris/Joroug/1 Labotatoty, Ptjnces Rlsbonwgh,
ME16 &IH. 0622-'62034 Aylesbuty, Buck!. HP11 9PX · Ptint:es RisboiDugh
: lllllltate. of Registered ARbHIICII, lrilllll Standards IIIStlbltln, 3101 (STD 084 44} ·:
· 68 Gloucester Place, London W1 01....S6 1945 2 Park Street. London W1 01-629 9000
BRE Scottish Uboratory, KeMn Road, East Kilbride,
.llllllbllllll olllrlllsJI Eltgllllll'l, Technical Help to: Glasgow G15 ORZ &sf KHbride 33941 (STD 035. 52}
.. Regency House,3 Malborougll Place, Brighton BN11 UB Exporters Department, BSI, Maylands Arenue, Heme/
Hempstead, Hens. HP2 4SO Building SaiYicel Rllllrcll 11111 lldonnaU•
11213-61399 AaoclaUon (BSRIA), .
Heme/ Hempstsr/ 3111
IDsiltalan ai Deailcal &gl11111, Old Brackn111 Lane. Brxknell, Beilcs. R612 WI
' 16llelgtiva Square, London SW1 01·235 3647 lrilllll Stul Carporatioa, Special Slnla Dtrlslan, Bral:kneU 25071 (STD 0344)
~ .. -- · - initlluuoii ol Clwii EDglm,J. .· 1IDy & Stainless Sleels Worlcs Group, P.O. Box 150, Cantraf Ofliee of JalonaaUOD,
~· · - . - :Ureat George Street, London SW1 01-839 3611 TIIISiey Park Wortcs. Sheffield SO 1TQ 0742-40311 11en:uf1s·Rmnt, ·W!stminster Bridge, London SE1 7DU
. lndtallol .. CemiiJDD Ttcllaology, lrilllll 11111-ftrraa Metals, Tldlllolagy Celdrl. 01-982 2;445
. : . 14 ~.Square, London SW1X BPZ 01-245 9189 Gr:'VIl.allomories.. Dencltwortll Road. Wantage, Oxon CaDStrectiDR · l!ldlllry R1111rcll au llfannatl•
~lllllltiiUu lr!lidrlcal &glaeers, IJ).J2 9BJ 02357·2!192 AaoclaiJDII, ' .. . ,
Old Queen Street House, 6 Storey's Gate, London SW1
. Savoy PJace;':!Jindon WC2 01·240 1871 Blildlag Cntra, 1111 Aaoclaa. II
. lllslltlill~ If :Gas. Eaglllllre, London: 01-839 6881 ·• .
.•176rosvenorCiescepl.LDndonSW1X7ES 01·2-45 0911 The Building Centre, 26 Storl Slreet, .london ··~ Collllimers' AaoclatiDII
·IDstltldloll If Heating and VentilaUag Eagl111111, WC1E 781 0Hi37 1022 14 Butlcingham Street. LDndonWC2N6DS 01-8391222
. ·49 cadogan Square, London SW1 01-235 7671 (AIImirrislration): Capper Dni'lcipmut AaoctaU1111 (CDA), .·
01-637 9001 (Information) Orchard HouSe, Mutton Lane, Potters Bar, Herts.
llllllbiiiDII ar Mecaalcal &glnetr~, 01-037 3151 (Bookshop)
.1 Birdcage)Ya!k. .London.SW1 01,.930 7.f76 Potters ~ 50711
Birmingham: :
laltltldloll Df Mlalclpal Engineers, County CoaD~III AlloclaUan,
Engineering and Bul7ding Canlre, Broard Stteet, Euston . House•. 66A Eaton Square, London SW1
~ ~~n·~. London SW1 01-834 5082 Birmingham B1 2DB 021~ 1914 01-235 5173'.· ·.-. . -
JaitHullon Df Plant Eaglnaers, · Corentry:
138 Buckingham Palace Road, london SW1W 9SG District Heating AlloclaUon,
Corentry Building /ntonnation ~ntre, Council Derbyshire House, St. Cllads S1reet, london EC1
01·7300469 .. House. Earl Street, Coventry CV1 5SE
~on Df Produ~on Eagllllllfl, {0203) 25555 Ext. 2512
01·2781964
10 Chestr:rfilild.Stleet, London W1X BDE 01-499 5254 Biistol: Domestic 011 Blmllr ~lpmelll Tilting Alloclltlae. ·
.JDStilliuanllf l'llbllc Heallll Eaglneers, TileBuilding Canlre, BtistDI, Colston Avenue, The 3 Savoy PlaCtJ, london WC2 01-483 3370
32 Eccleston Square, London SW1 01-834 3017 Centre, Bri$lol BS1 4TW Electrical Rnemll AIIDCIIUDD, .
Jasiltuuon If Slnlctural Englnltrl, (0272) 27002 {lntonnation) CleeYa Road, l..ea1llerllead Leathertlead 74151
11 Upper Belgr.Mt Street, London SW1 01·235 4535 (0272) 22953 {Administration) fire Protection AssoclatiDI, .
IDStltutlon of Water Eaglnaars, Cimbridgs: Aldemlary House. Queen S1reet. london EC4N 1TJ
6-8 Sackville Street. London W1 01·734 5422 The Building 'CMIIe, Cimbridge. 15-16 Trumpington 01-248 5222 .
Street, Cambridge CB2 100 {0223) 59625 Fire Ofllcll' Cammlttel, .
IDStltuttan ol General Taclllllclan Eaglnam.
33 Ovington Gardens, London SW3 01·589 9648 StDicHn-Trent Aldermary House, Queen Street, London EC4N 1TJ
The BuDding lntonnation Cent11, College ofBuilding 01·248 5222
Plasllca lastltldl, ~· · illd Cotnmerr:a, Stoke Road, Sllelton. Stokt-on-Trent
· 11 Hobart Place, London SW1 01·245 9555 fire Rnnreii.Statlan.
ST4 2DG (0782) 24651 Melrose Avenue. Borehamwood, Hertfonlshlre
Royal lncarporat11111 Dl ARhltects In ScaUalld, Glasgow:
15 Rutland Square, Edinburgh 1. Scotland 01-953 s1n
031-229 7205/6
The Building Cent11, Scotland, Flat 61111 AaoclaUOD,
6 Newton Temce, Glasgow G3 7PF 041·248 6212 6 Mount Row, london W1Y 6DY 01-629 8334
Rayal lastltula of BriUall An:llllects,
liverpool: HaaUng and Vlntilalian Ruearcll Alloclatlan,
66 Portland Place. london W1 N 4AD 01·580 5533 Building and Design Centre, Hope Street, Liverpool
Royal lnsUtuta of l'llbllc Healtll aad Hyglne. Old Bracknell Lane, Braclcnell, Berlcshire RG12 4AH
L19BR .
28 Portland Place, london W1 01·580 2731 0344 5071
051·709 8484 {Information)
Royal lliltltuUon of Cllartared Sumyors, 051-709 8566 (Administration) Humldlller Advisory and Consultancy IIIYICI,
12 Great George Street, London SW1 01·930 2081 21 Napier Road. Bromley, Kent BR2 2JA 01-4601118
Manchester:
Rayal Society tor tile Promotl1111 Dl Healtll, The Building Cent11, Manchestrr, Hydraulics Rnearcll Station,
13 Grosvenor Place, London SW1 01·235 9961 J13-115 Portland Street, Manchester, M1 6FB Waltingford, Berlcshire 059-13 2381
Royal Town Planning lnatlblta, Dt 061·236 6933 {lntonnation) Illuminating Eaglnetrlng Society,
26 PorUand Place, London W1 N 4BE 01-636 9107 061-236 9802 {Administration) York House, Westminster Bridge Road, London SE1 ~};;
)t'
Nottingham: 01·928 7110 'l..'
.~.~
Midland Design and Building Cent11, Industrial Society,
Mansfield Road, Nottingham NG13FE (0602} 45651 48 Bryanston Square. London W1 01·262. 2401 r~
~
Southampton: Jntematlonal Solar Eaargy Society (UIC sictlan),
4 Research and Advisory Bodies The Building Cent11, Southampton, c/o The Royal Institution, 21 Albemarle Street, london
AcoaUcal Jawes!lgallon aad Raurcll OrgaalaUoa Gromnor Hous., 18·20 Cumberland PlactJ, W1X 485 01-493 6601
Lid· ·• ·· · · Southampton S01 2BD (0703) 27350
~aiont Road; tonaon WC1~ 4Hf '01~20391 - · Janlftnil ~inn lfnlld,
Agrem 1111t laart.· . 17 Lower Baggot Street, Dubin 2
Lord Alexander House, Waterllouse Street. HemeJ lllldlng CDSt lllfDnuUoa Strrlct,
Dublin 762745
· l.eed llwllopmllltAIIeclllllan.>-. ,- -·' ~-> -
34 Berkeley Square, London W1X 6AJ 01-499 8422
. N1U111111 Building Agency,
-
I '
-
-
Hempstead, Herts. Hemel Hempstead 3701 85-87 Clarence Street. Klngsto~~-UpC~D-Thames, Surrey NBA House, Arundtl Street, London WC2 01-&36 4488
Brllbll cast Inn Rasearcll aid DrtiiDPIIIUI KT11RB 01-549 2542 · NaUoaal ECDnomlc Development Caancll,
AaocfaUan, lllldlng Malnlellalcl CDSt lllfDnDaHan St1Yict Ltd., Millbank Tower, Millbank. LDndon SW1 01-834 3811
Bonlelslev Hall, Alvec:hurch, W~re 85-97 Clarence Street, Klngsto~H~pon-Thames, Surrey laUoaal Hoasl-8ulldtrs Caaacll, : .. :·
~Cry 1RB 01·549 010ll3 ·. , . . 58 PorUand W1N 48U 01-387
:. ; ....
--,-'--·"'---'-:::.:;:j;:·?::· '~-:..·,
... ~4-~: .,.:· ;',.
;·.·
Q•, .·
Useful addresses
11{,:.:-~~;-·~·:f:~:r~
WAS 3lW Penlceth (092 572) 4321 Welsll National Water Dftelopmeat Aalllorlty,
~-· ·, ..... .
SouUi West Water AltMrily, . Cambrian Way, Brecon, Powys lD3 7HP
Brec:cm (0874) 3181 · · · ·
! ·Government Departments 3-5 Barnfield Road, &mr. EX11RE
Exeter (0392) 50861 Water ComPanies:
· · 8 Training Organisations Chester Waterworks Company.
Yortsblre Water AIU!ortty,
·· 9 Unions Trade West Riding House. 67 Albion Street. Leeds LS1 5AA 15 Newgate Street, Chester CH7 1DR
1D Saf~ty Organisations leeds (0532) 448201 . Chester (0244) 20501
Water Companies: Wrexham and East Denbighshire Water Company,
11 Overseas 21 Egerton Street, Wrexham LL11 1ND
Yorfr Waterworks Company, Wrexham (0978) 2259
LenrJaJ Tower, Yorks. Y01 2DL YC/It (0904) 22171
Tllama Water AIIHIDrlty,
Snem Treat Water Al!llertty, ~ New River Head, Rosebery Avenue, London EClR 4TP
Abelson House; 2297 Covently Road, Sheldon, 01-2782300
Birmingham, 826 3PS llinnlngllam (021 743) 4222 Water Com'panies:
, A _Research and Advisory Bodies Water Companies: · Colne VaHey Water Company, .
· ··· ;'~uo~J .~dusttbJ Fv~I-EIIicle~ semce. ·East Worcestershire Wi1enrorlrs Com,any,
47 New Road, Bronrsgnwe, B6D 2JT
Blackwell House, Aldenham Road, Watford WD2 2EY
..Abfonl House; -15 Wilton Road, london SWl · WatfonJ (92) 23333
:o1~a 8241 · Bromsgrove (0527} 75151 East Surrey Water Company,
· National laspeclloa Coancll tor Electrical l11slaiiJtioll South Staffordshirr wat!nrorlrs Company, London Road, RedhiH, Surrey RH1 1LJ
50 Slleepcote Street, Birmingham B16 BAR • RedhiH (91) 66333
Contracting (NICEIC), . . Birmingham (021} 643 8131 · La VaHey Water Company,
Alembic House, 93Aibert Embarikment,LondonSElnB
01-sa2 n4& :. . .. · Cheadle Water Works Company Ud., P.O. Box 48, Bishop's Rise, Halfield, Herts A10 9HL
National Society lor Clean Air, 43 Chapel Street, Chsdle, Stalfon1sbire Hatfield (30) 64311 ·
1341137 North Street. Brighton BN1 1RG Brighton Cheadle (05384) 2388 Mid Southem Water Company,
26313 Anglian Water A1r1bori1J, · Frimley Green, Camberley, Surrey GU16 6HZ
· National Water Council, Diploma House. Grammar School Walk. Huntingdon Deepcut (025 16) 503117
1 Queen Anne's Gate, london SW1H 9BT 01-9303100 PE18 6NZ Huntingdoo (0480) 56181 North Surrey Water Company,
NWC · Testing Station, The Causeway, . Staines. Water Companies: The Causeway, Staines, Middlesex TW18 3BX
Middlesex TW18 3DR 0784-54626 Cambridge Water Company, Staines (81) 55464 • • c.:
Rustat Road, Cambridge CB1 30S Ricktnansworth and Uxbridge VaHey Water Company,·
Plastics and Rubber Institute, Cambridge (0223) 47351 Batchworth, Rickmansworth, Herts. WD3 1111
11 Hobart Place, london SW1 01-245 9555 East Anglian Water Company, Rickmansworth (87) 76633
163 High Street, LowestDn Sutton District Water Company, .
Royal Society Df Healtll, Loweston (0502) 2406
90 Buckingham Palace Road, London SW1 41 Carshallon Road. Sutton, Surrey SM1· 4W .
Essd Water Company, 01-643 8050 .
01-730 5134
342 South Street. RomfonJ, Essex RM1 2AL Wessex Water Autllorlly,
-.flllbller and Plastics Research Assoc:tatlon, llomforrr(J0)-46016
Shawbury, Shrewsbul}' 5YR 4NR 093-94 383 Techno House, Redditfe Way, Bristol BSl &NY ..
Tendring Hundrec/ WatetworA:s Company, Bristol (0272) 25491 ·
Science Res11rcb Council, Mill Hill, Manningtree, Essex C017 2AZ Water Companies:
State House, High Holborn, London W1 H 4TA Manningtree (0206_ 39) 2155 Boumemouth ana·District Water Company,
01-242 1262 Northumbrlan Water ~. Aldemey Waterworks, West Howe, Boumemoultl
Society of Brltlsb Gas lnd~strlea (SBGI}, Northumbria House. Regent Centre. Gosforth. BH11.8NB Northbourne (020 16) 2261
56-58 Holly Walk. J.,eamington Spa. Warwickshire Newcastle-Upon-Tyne NE3 3PX Bristol Waterworlrs Company,
0926-34357 Goslorth (0632) 843151 P.O. Box No. 218, BridgwaterRaad, Bristol BS99 tAU
Society of Cbemlcaltndustrles, Water Companies: Bristol (0272) 665881
14 Belgrave Square, London SW1 01·235 3681 Hartlepools Water Company, West Hampshire Water Company,
Solid Smokeless Fuels Federation, 3 uncaster Road. HanJepool, Co. Durham TS24 BLW Knapp Mill, Mill Road, Christchurch, Dorset BH23 2W
York House. Empire Way, Wembley, Middlesex Hartlepool (0429) 440516 Christchurch (020 15) 3361
01-902 5405 Newcastle and Gates/lead Water Company The Weld Estate,
Sleel SheetlnfonnaUon and Development Auoc:laUon, P.O. Box 10, Allendale Road. Newcastle-Upon-Tyne. Lulworth Castle, Dorset
Albany House, Petty France. London SW1 01·7991616 NE6 2SW NewcastJe.Upon-Tyne (0632) 654144 West Lulworth (092941 J 352
Timber Research and Development Association, Sunderland and South Shields Water Company, The Cholderton and District Water Company,
· Hugenden Valley, High Wycombe, Bucl<s. 29 John Street. SunderW!d SR1 1JT Estate Office, Choldenon, Salisbury, Wilts.
Sunderland (0783) 57123 Cholderton (098064J 203
(0204·24 3091) Naphill 3091
Tin Research lnslllute, Soutbem Water. Autborlty,
Guiidbourne House, Worthing, Sussex BN111LD
Fraser Road. Perivale, Greenford, Middlesex
Df-997 4254 . . Worthing (0903) 205252.
·.·.·::·'Town and Coitn11y Planning Assoc:latlon,
water companies: 6 Fuel .lnter~st~ . .
Eastboume Waterw~Coinpany, · Alomlc Energy Authority United Kingdom, ,;_:_ ·'· ·
17 Carlton House Terrace. London SW1Y SAS
01·930 8903/4/5 14 Upperton Road, Eastboume. sussex BN21 1EP 11 Charles II Street, London SW1Y 40P ·-o1:930 6262
Eastboume (0323) 21371 B.P. 011 Ud.,
'f.'":,';. VItreous Enar1111 Development Council Ltd., Folkestone and District Water Company, B.P. House, Victoria Street, London SW1E 5NJ
:· ·~ 2BW~~nW1M7PG 01~2237 Tile GIIM'f -6tlllett, 011etrf 91rr1ett~ Frlilrestane; · 01-821..3000- · - ~ ~ - ·
Kent CT19 908 Folkestonr (0303) 76951 Cenlral Electricity Generating Board,
Water Research Centre,
Mid Kent Water Company, Bankside House, Sumner Street. London SE1
Ferry lane, Medmenham, Martow,Bucl<s. 049-166531
P.O. Box 45, High Street, Snoclland, Kent M£6 4AH 01·928 2011 IJ.
Welding lnsUiute, Snodland (0634) 240313 Electricity Council,
Abington Hall, Abington, Cambridge 0223-891162
Mid Sussex Water Company, 30 Millbank, London SWt 01-834 2333
Zlnc DniloJi,nent Association {ZDA}, 6 Boltro Road, Hqwants Hslh, Sussex RH1 6 1BA Esso Petroleum Lid.,. . . •
London. W1X 6AJ 01-499 6636 Haywards Healtl (O#f} 2662 .. Victoria Str~t. london SW1 01-834 6677' .. ,... ; .·;. ~ .
.....=-·.-c.·:··~;:'\~
·: .. . .
"•:· ...~ .; ..
'
• ' :. .
_...._,_ ";"h ,,.
..
.. :. , • .,..
. " ,_
· ."';.'~ . . ~:.
. -:~-:' -~'- ~.:'!,:.t<;'i:.:';,,;,
.., • ' .,
::;.,.i·~i.t::.,i;;:;.:.:.i:.0f.;
f!T ···~j .. •
1'-;i\,u ·•
~i~.;_::
t·~:r;.··~····· ·~ ·~.,~
.. :.~
.,. .-~;· ;:.:. ·~~ : ~ ~;:, . . :.j:,~~ .'. :<di~f·t.}i~--: t:i·~::¥g~;;!.:; 't~:r.
~,,,·
I #:~• .f'
···-
..... \
Britisll Gu Corporation, Construction lndas1Jy Tralalag Board (CITBI, Amalgamated Uaioll If Ellglnnriog Worters
59 Bryanston Street, London W1A 2AZ 01·723 7030 Radnor House, 1272 London Road, Norbury, London {TICbnlcal aod S.pentsory Section},
Natioul Gu Collsumers' Co•ncll, SW16 4EL 01-764 5060 Onslow Hall, Utile Green. Richmond, Surrey
Fifth Roor - Estate House, 130 Jennyn Street, london 01-940 3341 .
.. ·,. National Training Centres:
SW1Y 4UL 01-930 7431/4 Eleclrleal, Elec1rMic Telecommunlcatloa 111111
;~:>~~-. . BircJ:lam NewtDn, near King's Lynn, Norfolk
:-;· .;:..,;..·, Natioul Coat Board, Plumbing Ualoo, ·
:f::}(::ir ·• East Rudham 291 (STD 048 523) . Hayes Court, Bromley. Kent 01-462 n55
Hobart House. Grosvenor Place, London SW1
~.. -0.: 01-235 2020 . littlers Close, London SW79 2TE 01·542 0096 Eleclrlcal and &giaeeriag Stalf Assoclatlo•,
·..
..'"":'-. .....
\
hlroftna (UIC) Ud., 2 Eddison Street, Hillington. Glasgow G52 4XN ' Hayes cuurt, Brornety. Kent 01-463 ns5 ·
Petrofina House, Yorlt Road, London SEt 7HT 041-882 8338 National Assoclatloa If Fire Olftcers,
01~928 8000 Local Training Centres: 546 Palace Chambers. Bridge Street, London SW1A 2JT
Shell UK 011 Ud., 01-839 5011
St. John's Road. Ipswich, Suffolk 0473-73186
Sheii-Mex House, Strand, london WC2 01-9361234 Hurricane Way, Airport Industrial Estate, Norwich, Natloul Federatioa of Balldlng Trades Operatlns.
Solid Fuel Advisory Service, Norfolk 0603-416029 Federal House, 20A Cedars Road, Clapham, London
. .;;.: · Hobart House, Grosvenor Place, London SW1 SW4 01-622 4451
;: __ :_··. 01·235 2020
Regional Olfices:
Natloul Ualoa of Sllelt Metal Wlllbrs, Coppersmllbs,
:.• Eastern Region, Heating and Domestic Elglneers,
56 Parle· Street, Luton LU1 3JD 75-n West Heath Road, Hampstead, London NW3
· l.llton (Beds.) 27462 (STD 0582) 01-455 0053
l.Dndon and S.E. Region,
·: 7 Government Departments Glen House, Stag .Place, LDndon SW1E SAL
· Dejlartmeni Or Education aad Science, 01-828 7384 .
Elizabeth House, Yorlt Road. London SE1 7PH Midland Region,
9 North Street, Rugby, Warwictshire CV21 2AB
10 Safety .Organisations
01-928 9222 .
Rugby 5546 (SfD.0788) . SrfUsll Red Cross Society,
Department of Employment, 9 Grosvenor Crescent. London SW1X 7EJ 01·235 5454
8 St. James' 5quare. London SW1 01-930 6200 North East Region, "
Jesmond House, Victoria Avenue. Harrogate, N. BriUsh Safety Coancfi,
Department of Energy, 62/64 Chancenors Road, London W6 9RS 01-7-411231
Thames House South, Millbank. London. SW1P 40.1 Yorkshire HG1 50G Harrogal!l 68322 (STD 0423)
01-211 3000 . North West Region, Confederation far.llll ReglslraUon of Gas lastallers
4th Floor Federation House, Hope Street, l.iriipool
(CORGI), • • . ..
Department of tile Environment, Sl Martin's House;140Tottenham Court Road. London
2 Marsbam Street. London SW1P 3EB 01·212 3434 L1 9HL 051-709 8489
I •• ~ •
W1POAS· 01-3879185 .
~;:~-- ~-~ Directorate General Water Engineering, Scotland,
3-4 ClaremontTerrace, Glasgow G3·7XR · .Corgi RegionaJ'Oifices:
2 Marsham Street, London SW1P 3EB 041-332 3323 . .
01·212 4014 Scottish Region, •
West and Wales Region, Granton House, West Granton Road, Edinburgh
Building Regulations, Prot. Division. EH5 1YB 031-552 6960
Becken House, Lambeth Palace Road, London SE1 18-19 Belmont, Bath SA 1 5DZ
01-928 7855 Bath 316695 (STD 0225} Northern Region,
Education Council lor Heating ud Veatllating, Stephenson House, Northumbrian Way, Killingworth,
Property Services Agency: Newcastle-U~Tyne, NE991GB
ESCA Flouse. 34 Palace Court. London W2 4JG
Technical Ubraf)', Room C0011C002, Whitgm Centre, 01-764 5060 Newca.stle-U~yne 683833
Wellesley Road, Croydon CR9 3LY Noith Westem Region,
01-686 8710 + 456014564 Engineering Industry Trilnlng Board,
P.O. Box 148, Clarendon Road, Watford WD1 1HS Victoria Housa, Victoria Road, Hale,· Cheshire
8uJ1ding Information Room, Room 1.6431JmarHouse.. -92·44322 WA15 9AF 061-941 2548
Wellesley Road. Croydon CR9 2El North Eastern Region,
01-686 3499 + 33060161 Heating Ventllallng and Dommie Engineers' National
Joint lndusb'lal Council, Negas, Kent Road, Pudsey, West Yorlcshire LS28 9BW
~ Department of HeaHb end Social Security, ESCA House, 34 Palace Court, London W2 4JG Pudsey 66533
r_l Alexander Reming House, Elephant and Castle, London 01-229 2488 · .Easi Midlands Region,
SE1 01-407 5522 • · P.O. Box 145, De Montfort Street, l.!icester LE1 9DB
Joint lodusby Board for Plamblog and Mecllanlcal
Department of Prices and CoiiSIImer l'rlltectlon, Engineering Senica Ia England and Wales, Leicester 50510
1 Victoria Street. London SW1H OET 01·215 7Bn Brook House. Brook Street, St. Neots, Huntingdon, West Midlands Region,
Fair Trading Division, Cambs. PE19 2BP 5 Wharf Lane, SolihuH, West Midlands 891 2JP
1 Victoria Street, London SW1H OET 01-215 5092 Huntingdon (STD Code 0480) 76925-8 021-704 4101
Standard Weights and Measures DiviSion. National Joint Council for tile Building lndusby, Wales Region,
Abell House, John Islip Street, London SW1P 4lR 11 Weymouth Street, London W1 01-580 1740 Snelling House, Sure Terrace, Cardiff CF1 2UF
01•211 4275 . Polytechnic ol tile South Bank, Cardiff 395398
Department or Trada and lndusby, faculty of Environrnenlal Science and Technology, Eastern Region,
1 Victora Street. london SW1 01·215 78n Borough Road, london SE1 01-928 8989 Star House, Potters Bar, Herts. EN6 2PD
Her Majesty's Stationery Office, Sco!Hsh and ND!tllem Ireland Joint lndusby Burd tor Potters Bar 50793
Atlantic House, Holbom Viaduct. London EC1 Plumbing, Mecllanlcal Englneerlllg Services, North Thames Region, . _ . .
01-248 9876 . 2 Walker Street, Edinburgh 031-225 6842/3 Co/legit House, Wrights Lane, London WB SSN
Home Office, Scottish Technical Edaeation Council (SCOTECI, 01-937 8545 .
Whitehall, london SW1 01-930 8100 38 Queen Street. Glasgow G1 3lY 041-204 2271 South Eastem Region,
Meteorological Office, Technician EducaUoo Council (TEC), 1 Katharine Street, Croydon, Surrey CR9 1JU
284 High Hoibom, London WC1 01-836 4311 76 Portland Place, London W1N 4AA. 01-580· 3050 01-688 7546
Mlnlsby ol Agriculture, Fisheries and Food, Training Services Agency, Southern Region, . . · ..
WhitehaU Place, London, SW1 01-83.9 nt 1 162·168 Regent Street. LondonW1R60E 01·2146000 102-108 Above Bar, Southampton, Hants S09 5AH
Public Recllnls Olftce, Sol/thampton 20100
Chancery Lane, London WC2 01-405 07-41 South Westem Region,
Scotllsll Denlppmp"l Pnlrtml!ll. . . ~ Si Ollill ~ .AYD/1 BA1~ JJJJ!HTSB
-· St. Andrew's House, Edinburgh 1 031·556 8501 · ~ 9 Tratte UntonS - tieaUng and Ventilating Joint Safety Committee,
/ Amalgamated Society of Boilermakers, Sblpwrlghts,
Blacksmiths and Slnlctural Worbrs,
ESCA House, 34 Palace Court, London W2 4JG ·
01·229 2488 •.
i'.,
!.'
Litton House. Eslington Road •. Newcastle-Upon-Tyne 2 Healtband Safely Eleclltl'te,
0632 813205 Baynards House, 1·13 Cllepstow Place, Westboume
8 Training Bodies Amalgamated Uolol If &gloterlng Workers Grove, London W2 01-229 3456
City and Guilds or London lnsUiull, (Constructional Section), lnalltuUon of lndus1rfal Safety Qlllcers, ·.., : ·'
London w1·· 01·580 3050 140 Lower Marsh, London SE1 7AQ • 01-928 5781 .• ·• 23 Queen Sq~. London we,~.~· ~1-27S.H96 .
' :- ....... ~ -....:·:.\.:';"~~ . '
....,~ ~ .~~~~·~;:.;:~:;~~~::·:.:,~.:·:.'.';:·:;~:l:~~~~~:i~~~t~~~:)t~i!!~ ~;
'-r.;;~-,..,;·r,;..:;
...;:~-~~---------.....
_,....,._-;;;,··...-:.;;-~..&...·;..·----~·~:;.·-~·:ti.lll*ll;l"'~·w_-~-~----~--~~--~:.:;':.:_~~~tm=_~--~-~-~--~-:;».;i~c.~.~-~~
.-:·~~.·;..-~= ..
~- ;.·~: : .·.-q·_.~.·~ ~-~.-.~ ~ ;: :'·.~:-.,. . ._._i: _:_-~.: : :_. y,__:!;"fll~·.-_~~-:£r~i:i\=~~-:;:::.·.:J·'
" . :~i·_~-\~·r-_._:_-~<~~-:~::;::.:~~.::~.-o:..~...;.;...:.:...·· .-_ ...
rH~:·: ·::~ ~ . - . . ---·----'-
.~ ~·· ~":. .
Useful addresses
· ...
,Addresses are cl;ssif.ed as follows:
h~ 1 Coirtractors' Trade Associations lllloll latemaUoaale lie Ia Cowerblrt, PIDmllerle, NETHERLANDS
.... _· . ,·_ 2. ,Manufacturers' and other Trade Associations llmllatloa SanltJrlnts, Gaz allll llydraullq~~e Gas Water L11odgleter
lillltralt Plumbers Association.
· .. : · 3 Professional Bodies
lnremational Union for Roofing, Plumbing, Sanitlry Tapijtweg 2, 's-6rarenllage, Holland
·-. ~ Research and Advisory Bodies Installations, Gas and Water,
5 Regional Water Authorities and Water Companies in 10 RJJe Du Debarcadere- 75852 Pvis CedelC 17, France NORWAY
' England and Wales Norste R•rleggerlledrille!S Jalldslorenlng
BELSun.t
I Fuel Interests ·.National Association of Nol'!"'egian Plumbing
federaUo11 ltaUonale des Assoclatlelll de Patnms
. 7 Government Departments Contractors,
lataUatnrs SanltJires II dl Cllall!lage 11 Baz,
Louises ~ate 28, Oslo 7. Norway
I Training Organisations Plomlllers, Slnguetn el Anlolslm Comears de
9 Trade Unions Belglqlll FBIC
SWEDEN
National Federation of Belgian AssDciations of Master
1D Safety Organisations Roriednlngsllrmornas ArlletsgiYarelorllund
Sanitary Engmeers. Gas Heating Engineers, Plumbers,
11 Overseas Zinc Worlcers and Slaters, Federation of Plumbing Employers,
Rue WiHems, 14116, 1040 BnDelles, Belgium. Blasieholmsgatan 4, 111 48 Stockholm. Sweden.
DENJIARK SWfTZERLAND
Dust Varme-, Yllllllatloa-«11 Sa111tets lastallll;r .Scbwelzeriscber Speaglennelster. -. 11d lnstallalftr
Berllalld i
~C~J~. Safety _Organisations
. <· :· "' .
~~:~~~·-~·-:--;i- ~: . . ..
ftrelllag
·Danish Heating, Ventilation and Sanitation Installers
Association, · ·
. .
- -- Swiss Association of Plumbing and Installation
·. · Contractors,
~'(~_;;:,.·,_ l.llndDII CoiiStllctloll Safetr Gl'llllp, H.M. &eM., Hljnaes'lej 75, 2610 Rlldovre Auf der Mauer 1.1, 8023, Zurich, Switzerland· .
t$~'"'' ·.·Training Centre, Bilton W~. Enfield. Middlesex
.
i~~i:::;, _01-804 2756. . .
,.-::\:::C..·.,. lle!StySidt and lor111 West Safetr Cell1re,
FRANCE AMERICA
.. American Society of Plamblag Engineers,
Unl011 llatlonale des Cllambres Syadlcala 111
W(..::<': C/o Government Training Centre, Stopgate Lane.Aintl!e. Cowerbtre et de Plomberie de fraiC8 "15233 Ventura Boulebard. Suite 616. Sherman Oaks,
it~Ji.- ;;:,:,~J~rpool L9 6AW 051-525 0702 California 91403
r'? ;, .
.
~~·· ~> .JioSPA ladtSirlal Safety Training Celltre,
22 Summer Road, Aax:ks Green, Birmingham Z7
National Union of French Roofing and Plumbing Trade
Associations, National Assoclatlilll Plamblng, HeatiDg, Cooling
ContractolS, .
9 Rue La Perouse, 75784 Paris CedelC 16, France. -
:!'f. , . ·. 021-706 4108 1061 20th Street, NW, Washington DC 20036
T~B~}' Place,
~~::~:!e~ 1:"Devonshire Street, Portland
London W1N 2AT 01·580 5678
GERMANY
Zelllralnrlland.Sanltar-lnd Heizlnp· Tecbnlk
AUSTRAliA
Tbe Institute of Plumbing Australia,
Central Association for Plumbing and Heating 188 Batman ·street. West Melbourne, Victoria 3003
· Royal Society for the Pme11Hon of Accidents (RoSPA), Technology,
Terminal House, 52 Grosvenor Gardens. London SW1 5300 Bonn, Meckenheimer Allee 67, Germany Tbe Master Plumbers Association of Western
01·730 2246 Australia,
Sl John's Ambulance Asso;laHon and Brigade, ffALY 37 Havelock Street, West Perth, 6005 Australia
1 Grosvenor Crescent. London SW1 7EF 01·235 5231 Assoetltliin"'Hazlonale lnstallatorf d'lmplalltl Termlcl SOUTH AFRICA
Yortsblre Safety Section for llle Constrlldloa 1 de VenUiazlone, ldrlcl, SaaltJd, Elellricl,
IDduslry, Telefoalcl ed AftinJ. ltaHonal Building Researcb lnsUtllte,
Davidson House, Hales Road. Leeds 12 0532 639227 P.O. Box 395, Pretoria 0001. South Africa. 74-6011
National Association for Installers of Heating, VentiJa.
·lion, Plumbing. Sanitlry, EJectrical and Telephone NEW ZEALAND
~. .
V'a Philippa Turati 38, 20121 Milano, Italy New Zealand Society of Master PlumbelS (Inc),
~ P.O. Box 6606, Wellington, New Zealand.
Tbe Plumbing lllformatloa Bureau,
-~ LUXEMBOURG
Hardware- Federation House, 23 Palmer Street,
· 11 Overseas FederaHoiiS Reanla dn Patroas FerblantielS,
Wellington 1 P.O. Box 27-005
lastallateurs Sanllalrei elllislallatears lit Cbaullage
EUROPEAN INTERNATIONAL ORGANISATIONS da Gra11d11 Ducbe de Lllnmboarg
Common Market Commission, Directorate General lor Association of Tin Plate ManufactJJrers and Sanitlry
Internal Market, and Central Heating Engineers of the Grand Duchy
Rue de Ia loi 200, B-1049 Brussels of LJJXembourg,
7350040n35 80 40 41 Rue Glesener, LJJXembourg
~~·····
~!l;-.
..
·.
'.t~~ :' . "'~'}J;t:, ::J~i;:f4l~·
.···
i., : ...• •
·~ ·: ... •.j ....
~""
f:--:
[
!
·Index
.;·
Page • Page
Sectio'n A Hot and cold water supplies Low density (Type 32) Polythene pipes 3.o.
Polythen11 pipe (Type 50) for cold watet services to BS 3284:
·British Standards and BS Codes of Practice Section A 45/46 1967 Table A31
.Polythena pipe (Type 32) lot cold water services to BS 7972:
Capacities of Cisterns. Tanks and Cylinders 1967 TableA32
Cisterns and tanks · . · Stu/ joists safe loads for Gtade 43 stee/Tab/e A43
· Asbestos cement cistern:s to 852777: 1974 TabJeA18 27 · Unpluticized.PVC pip11 for cold water services to BS 3505:
Galvanised·mild stu/ cisterns aild coven-to BS 417 Part 2: . 1968 Tablt~A33
· 1973 TableA16 26
· TableA19 27
· Loading tables for steel11nd timber joists 42
. Polyolefin or Olefin Copolymer Cister,n:s (Polythene or
Polyptopylene) to BS 4213: 1975 Table A17 27
Cylinders
Coppet cylinders to BS 699 1972 Teble A21 28 ;:
Dimension:s of cylinde11 to BS 417 Part 2: 1973 Table A20 . 28 ::
Double feed copper inditect cylindttt~ to BS 1566: Part 1:
1972 Tebles A22 A22a 29
... ~:~.. coJI.Type TsbleA24 ... 30
·Single feed copper indirect cylinders to BS 1566: Part 2: 1972
........
,
~
<,~::.'~:~z;:,:r.s1.o~ge
30
..
· .BoOSted .cold water innalladon:s 13 2
'· Boosted cold water supply from break tank Fig. AS 15 2
. CapacitY of pneumatic vessel 14
· · : Directly boosted header or enlarged pipe system 13
. Directly boosted system 13
Dtinking watet demand 15
lnditect boosting from breek tanks at low level 13
Ptoviiion of cold water storage to i:ovet 24 houtS interruption
·of supply Table A8 11
I
· '- 32 · Softened watft ····•· •.:; · · •· 1 ·" · •• ·'::- •.. • .. ; ; · 1
,.~ .,.-~"n~",;.":......; .. ·.· i·: f~~~;;:~"-_--.-~~;-'·<. J~~~~~: ·--~~~:;~~·;: :;: '·;: '} ::.~.;r:J.~\~~:f¥:~~: .J-:.ir<· ,.:~,rr ~t-4tr~~~:::
••. . . ,•.
. ·••• .. ~·· • • • •• • ,. .
'
••• c'.• ··.'. . • • •...·,:_..:·~;/.<&·~...;<
. • • .... ~ ...• .•.
~ ~:~i(~)'~ ... lrr;·'):(."'~ ""'· J: ... :•,·-···=~·
.. ........... ~. ........· ·-·.&: ....;..·:.'r:': .-;;.-..
""~-••
.... ' ..,·..4':.~·..•·,s;~
~;-l '"~
.... /1!' ~·. ~·6
•.;. i"f':-. v ,.
,••;.. . .. ·:"·.
Page Page
Section B Domestic central heating Capacities of stacks 66
Chemical Resistance of Laboratory ~nd Industrial Waste
·British Standards and BS Codes of Practice Section B 59 Systems 85-88
. . ·Cavity Wall Insulation ·eonar Boss· System 63
·Ell:n!;><.J~.._,·..·-·. ·:.. Properties Connection of washing appliances .62
· Biological 54 Without venung (to stack or back inlet gu/ley) Fig. C6
Chemical 54 With venting (to stack_ or back inlet gu/Jey).Fig. C7
· Density 54 Connections to drains· ' 67&68
Flammability 54 Design of single branches and·fittings 64
·sirength 54
Temperature stability 54 Discharge Pipe Systems 60
Thermal conductivity 54 Fully venulated one-pipe system Fig. C2
Water resistance 54 Modified one-pipe system Fig. C3
Vapour permeability 54 Modified one-pipe vented stack system Fig. C4
Single stack system Fig. C5
·C:orroslon in Domes1:ic Central Heating Systems 59 Modified single stack system Fig. C5 (a)
·Two-pipe system Fig. Ct ·
· .· ' .. iftow of Water in Pipes _ Discha~e pipes to.sanitary ap_pliances .62
:.--_;.,.,·,Small bore systems Table B2 47 Discharge units 67
;'·~· ~ ¥icrobore_ systems Table 83 48 · .. Discharge unit flow-rate graph
.· Drains ·re;eiving discharges from vertical stacks 67
. :&timatingstack loading·'' · · 66
. :-'~ .:, Gas central heating units or boilers installed in compartments ·57.& 58 foaming . 65&66
.'·:.~:"·Minimum free areas of openings to be provided into the
<:·.,.l:ompartmimt Table B13 ·sa · Inspection and testing~~~ discharge pipes . 65
. · ., :·Minimum free area of ventilauon to rooms provided with a gas Main stack connections · 64
·~~·ll''-""''-::'·-'::;,~;:::appliancB Table B14 .· · 58 . 71.
· Methods of Waste Collection
>),..Ventilation ofrooms in which are fitted conventionally flued
• ·~.·=:central heating appliances or boilers · 57 . Offsets on stack ~ '62
.-··. ·._Ventilation of living rooms in which is fitud a combined gas 1 Performance testing of systems .. . .. 70
· fire and gas fired back boiler 58 · NumbiN of appliances to be discharged.. simu/taneous/y for
- _. ·,:. '· temng stability of trap seals. Dwellings Table CB . ..
·Heat Emission from Pipes ' Number of appliances to be discharged simultaneously for
· Flow arid return temperatures etc. Table B5 48 testing stability of trap seals. Public Buildings Table C9
Heat emission from single horizontal uninsulated copper Permissible load on drains 67'
tubes to.BS 2871 when painted Graph B1 49 Sanitary Accommodation 71
·He11t emission from single horizontal uninsulated steel tubes .Accommo.dation for eldrtrly people Tabltt C12 76
to BS 13B7 -- ~ 50 Cinemas. concert halls. theatres and similar buildings used for
·Heat emission from vertical pipes as compared with horizontal public entertainment Table C76 79
pipes Table B7 51 Dwellings Table C11 · 76
Heat emission allowance from hot water storage Table B4 48 Factories Table C14 77
Heai emission allowance from tank sutfaces T11ble B6 51 80
lnsu/11tttd pipes Table 88 51
Hotels Table C17
Office buildings and shops Table C70
Residential Homes Table.C13
., 75
Heat losses Schools Table C15 78
Air change heat losses 54 Swimming Pools Table C19 81
. Air temperatures and rates of air changes Table B1 47 Separation of foul water and rain water 71
Calculation sheet Fig. B1 55 63
Due to infiltration of air 54 Sovent Syst~tm
Due to transmission through fabric 54 Traps 61
Effect of insulating building fabric Table 810 56 Minimum internal diameter of traps Table C1
Heat transmittance coefficients (U values) T11ble B9 52 & 53 Depth of trap seals
Space heating elements 56 Vacuum Systrtm 63
Ventilating pipes · 68
Sealed System Operation
Diameter and lengths of ventilating pipes Table C6
Approximate sizes of diaphragm expansion vttssels Table B12 56 Minimum sizes of dischatge stacks· and ventilating piptts for
Calculating vessel size 57 various loadings. Dwellings. Table C7
Connections 57 Sizes
- . Diaphragm expansion vessel 57 Termination of ventilating pipes
FHfingandcomm~sionmg 57 The sizing of long ventilaung piptts
Hot water supply cylinders 57 Ventilation of Internal Bathrooms and wc·s in Dwellings 82
Instruments 57
Radiators and convectors 57 Common-duct systems
Safety devices 57 Individual systems
Mechanical ventilation
Expansion cistern sizes Table 81 7 58 N«ural ventilation·
Recommended minimum capacity of oil storage tanks Table 815 58 Waste stack connections 64
Storage for solid fuel Table B1 6 58 Waste disposal units 62