DOCUMENT COVERSHEET
Document Information
Project No: PM210012 Project Name: NEOM Green Hydrogen Project
Project Doc No: PM210012-LTG520-OI3-00012 Rev 04
Document Title: ITP & Checklist for WTG Foundation – Excavation, Conduit Pipe, Lean Concrete
Review Status
Specifier (Email)
Status Code:
Date(DD-MMM-YYYY)
Revison History
AP.
Date Vendor / 3rd Party Doc. Release Purpose Prepared By Checked By Approved By
Rev
00 13-Feb-23 ISSUED FOR APPROVAL AJ AC KM
01 17-May-23 ISSUED FOR APPROVAL AJ AC KM
02 30-May-23 ISSUED FOR APPROVAL AJ AC KM
03 4-Jun-23 ISSUED FOR APPROVAL AJ AC KM
04 6-Jun-23 ISSUED FOR APPROVAL AJ AC KM
Page 1 of 2
TAG Nos
Fill in list of Multiple Tags if not able to accommodate on cover sheet.
Page 2 of 2
DOCUMENT / DRAWING
COMMENTS RESOLUTION SHEET (CRS)
Project Name: NEOM Green Hydrogen Project AP Project No.: PM210012 Review Code:
3rd Party/Vendor Transmittal Ref.: LTGEN-TRANSMIT-001952 Actual Date Received: 06-Jun-2023 Code 2 - Comments as Noted
3rd Party/Vendor Name: LARSEN & TOUBRO SAUDI ARABIA Co Unit Code: 520 - Wind General
ITP & Checklist for WTG Foundation – Excavation, Conduit Pipe, Lean Concrete PM210012-LTG520-OI3-00012 04
COMMENTS RESPONSE
11 01 02.6 SRB Please correct the serial No's. 2.6 id belongs with 2 points. Noted & Updated Yes Closed Closed
12 01 2.1-3.7 MK (NGHC) Items from 2.1 to 3.7: NGHC inspection level shall be ''S". Noted & Incorporated Yes Closed Closed
13 01 03.1 MK (NGHC) Items from 3.1: NGHC inspection level shall be 'W/R Noted & Incorporated Yes Closed Closed
14 01 02.6 MK (NGHC) Item 2.6: is duplicated and the sequence of activities shall be revised. Noted & Incorporated Yes Closed Closed
15 01 General MK (NGHC) Signatory of the ITP: Others shall be replaced by "NGHC". Noted & Incorporated Yes Closed Closed
Concrete Sampling and curing shall be incorporated as inspection Noted & Incorporated in ITP "520-ITP-CIV-GEN-WTG-004" Section 2.8,
16 01 General MK (NGHC) Yes Closed Open
interventions. & Checklist "520-CHL-CIV-GENE-WTG-014" Section 9,10
17 01 General MK (NGHC) Signatory box for NGHC shall be incorporated at Inspection Checklists Noted & Incorporated in all Inspection Checklists Yes Closed Open
S/C column is made void, as it is not applicable for the scope of this
The ITP shall be revised by removing "S/C" column and assign all "S/C"
18 02 General MK (NGHC) ITP. Further the participation levels of other stakeholders are revised as Yes Closed Open
inspection level to "L&T" and "L&T" inspection level to "APEPC".
per the comment
Page 1 of 1
TAG Nos
Fill in list of Multiple Tags if not able to accommodate on cover sheet.
Page 2 of 2
LARSEN & TOUBRO
INSPECTION AND TEST PLAN (ITP)
520-ITP-CIV-GEN-
ITP No. ITP Description ITP for WTG Foundation- Excavation, Conduit Pipe, Lean Concrete Project NEOM Green Hydrogen Project
WTG-004
ITP Rev. No. 04 Client Air Products Contractor Larsen & Toubro Package ☐ Grid ☒ Generation: Wind BOP
Discipline Civil Sub-Contractor Vendor Contract No. PM210012 Date 06-06-2023
Sub-Contractor
L&T Site QAQC ☐ Records Verified Client / ☐ Documents Reviewed Client / ☐ Documents Reviewed
Engineer ☐ Work Verified Representative ☐ Approved Representative ☐ Accepted
Sub-Contractor
L&T Site QAQC ☐ Records Verified Client / ☐ Documents Reviewed Client / ☐ Documents Reviewed
Engineer ☐ Work Verified Representative ☐ Approved Representative ☐ Accepted
7, 28 Days Result to
11 Compressive Strength 16 Mpa achieved Test Result ☐ ☐ ☐ be attached
L&T Site QAQC ☐ Records Verified Client / ☐ Documents Reviewed Client / ☐ Documents Reviewed
Engineer ☐ Work Verified Representative ☐ Approved Representative ☐ Accepted
Sub-Contractor
L&T Site QAQC ☐ Records Verified Client / ☐ Documents Reviewed Client / ☐ Documents Reviewed
Engineer ☐ Work Verified Representative ☐ Approved Representative ☐ Accepted
Sub-Contractor
L&T Site QAQC ☐ Records Verified Client / ☐ Documents Reviewed Client / ☐ Documents Reviewed
Engineer ☐ Work Verified Representative ☐ Approved Representative ☐ Accepted