Risk Assessment - Radiography - Onshore
Risk Assessment - Radiography - Onshore
Low May be acceptable; however, review the task to see if risk can be reduced
(1 to 6)
Medium Where possible, the task should be redefined to take account of the hazards involved or the risk should be reduced further, prior to task
(8to12) commencement. Appropriate management authorization after consultation with special personnel and an assessment
High Unacceptable. The task should be redefined or further control measures put in place to reduce the risk. The controls should be re assessed
(15to25) for adequacy, prior to task commencement.
SPECIFIC SAFETY HAZARD / HAZARD EFFECT PEOPLE AT RISK RISK CONTROL MEASURES RESIDUAL
ACTIVITY ENVIRONMENTA Type of VALUE Existing and proposed RISK
L ASPECT injury/damage
1. Transportation of Traffic Accident Fatality /body injury RT worker 20 1. Vehicle driven by personnel with 6
workers, necessary valid license & appropriate driving
materials, and authority issued by company only.
equipment to the site 2. Adherence to life saving rules and
company safe driving policy
3. Periodic maintenance of the
vehicles.
4. Strict Supervision to ensure
compliance
Workers fall from Fatality/body injury RT worker 20 1. Do not exceed number of 6
the vehicle passenger.
2. Proper adequate and safe space
for worker to sit.
3. Periodic maintenance of the
vehicles.
4. Strict Supervision to ensure
compliance
Equipment fall off Injury to other motorist RT worker 20 1. Ensure equipment secure safely. 5
vehicle Damage to equipment 2. No overloading.
2. Manual Materials Fall of material Knicks and cuts RT worker 9 1. Competent and trained 5
Handling. while handling Pinch points personnel
Ergonomics Injuries to worker 2. Tandem lifting – ask for
Excessively heavy Damage to materials assistance
materials Damage to equipment 3. MSDS ready and understood
Unsafe materials Struck by or caught between
4. Adhere to stacking and storing
Damage to vehicles
Unsafe stacking and requirements of the site
packing 5. Good communication with all
Unstable load relevant parties
Incorrect material 6. Discuss risk assessment at
identification Toolbox Talk with all workers
7. Strapping to be secured and
checked prior to movement
3. Walking in, out, and Slip due to wet Bodily injury RT worker 12 1. Wear Slip resistant safety shoes 4
around the workplace surface 2. Barricade any spillage/ slippery
floor immediately and inform to
relevant discipline immediately
Poor Items not stored correctly can fall RT worker 12 1. All items and tools used must 4
housekeeping and cause injury to workers be stored in their correct place. All
Fire due to items must have a storage place
combustible/flammable materials and all items must be stored in
their correct place
2. Working area should be
cleaned before commencing the
job.
Hit against object Head injury RT worker 5 1. Safety helmet to be worn 4
2. Survey of protruding surface
shall be carry out and adequate
barricataion to be done
Falling object Head injury/fatality RT worker 20 1. Safety helmet to be worn 6
2. Do not walk under the line of
fire
3. Working area shall be
barricaded and enforce strict
supervision.
4. Tool box talk before
commencing the job.
4.Radiography of Exposure to III health to workers and RT worker 16 1. Ensure safety regulation before 4
permanent weld Ionizing radiation surrounding personnel due to commencement of work
jumpers radiation 2. Cordon off the area and install
radiation warning symbols
2. Use of barriers/collimator
1. 2. Use of dose rate alarming
2. 3. Use of pocket dosimeter
3. 4. Use of thermo luminescent
dosimeter
4. 5. Use of survey meter
5. 6. Ensure the recommender
distance is used while barricading
for radiation workers and non-
radiation workers
6. 7. Ensure that radiation safety
devices are pre-tested and used
accordingly
7. 8. Restrict the entry of
unauthorized person. Wear
appropriate PPE and Film badges
8. 9. Protective equipment –
coveralls, safety shoes, ear plugs,
safety spectacles, hard hats,
gloves, respirators
9. 10. Radiography source in/Out
Register should be maintained at
source pit and at site
10. 11. Deployment of competent RT
technician
11. 12. Good communication with all
relevant parties
12. 13. Discuss risk assessment at
Toolbox Talk with all workers
involved
13. 14. Obtain and maintain the
necessary work permit
Dropped objects Head, shoulder injury. RT worker 12 1. Pre task dropped object survey 6
Fatality 2. Personnel not to operate below
3. Area below to be demarcated (Danger
Zone)
4. Use of complete PPE i.e. hard hat, coverall,
goggles, gloves, earplugs, safety shoes,
disposable filters if operation is in
ventilated area.
Slips and Trips Bodily injury RT worker 12 1. Work areas cleared of boxes 4
2. Ensure good housekeeping to keep
walkways free of slips and trips
3. Use of complete PPE i.e. hard hat, coverall,
goggles, gloves, earplugs, safety shoes,
disposable filters if operation is in
ventilated area.
High Wind speed Possible increased cooling or RT worker 15 1. Stop work if conditions become dangerous 4
hypothermia risk, increased 2. Wear proper footwear and clothing,
dehydration risk in dry humidity including gloves and head protection.
Decrease in efficiency, hindrance to 3. Secure loose materials at work site
communications between team 4. Be wary of wind blowing rope in to
members Danger of unsecured areas making retrieval difficult.
equipment or material being blown 5. Tie of ropes when not in use.
into the access zone 6. Ensure ropes cannot be catch by moving
Difficulty communicating objects
RISK MATRIX
Low May be acceptable; however, review the task to see if risk can be reduced
(1 to 6)
Medium Where possible, the task should be redefined to take account of the hazards involved or the risk should be reduced further, prior to task
(8to12) commencement. Appropriate management authorization after consultation with special personnel and an assessment
High Unacceptable. The task should be redefined or further control measures put in place to reduce the risk. The controls should be re assessed
(15to25) for adequacy, prior to task commencement.