Inspection & Test Plan: Document No.

:ITP 001
ARABTEC CONSTRUCTION (L.L.C)
Procedure
Concreting for Sub-Structures & Waterproofing Rev. No. :0
Saadiyat Beach Villa Resort For Boundary Wall Date

Type of Testing Requirement/ Acceptance Inspection Points Verifying / Control


Item No. Inspection Description Reference Document
Inspection Criteria ARABTEC ITA Consultant Data Forms
1.0 Approval of documents

Sh. Drwg.
1.1 Shop drawings Review Gen.Spec, ,Vol.,Sec. Contract Drawings R - R
Submittal Sheet

Approved Shop Drawing & Standard Method statement


1.2 Method Statement Review Gen. Spec., Vol.,Sec. R - R
Specification submittal Sheet

1.3 Mix design Review R Test R ITA Test Report,


Sec.03300,
Gen.. Spec.,
2.0 Materials
Gen.. Spec.,
Materials approvals and conformity of delivered
MARs. Test
certificates,
materials:concrete,water
2.1 Review R Test R Supplier
proofing,form releasing
documents,
agent ,curingcompounds,polyethene sheet and Sec.03300,
Delivery notes
associated materials Sec.03300,
Shop Drawing clause 3.13
3.0 Blinding clause
Gen. Spec., Sec 02335
2.02

Visual
Surface Preparation and leveling of Sub-grade to Sub-grade shall be
3.1 Visual Gen. Spec., Sec 03100 cleaned H - H Checklist & WIR
proceed blinding concrete
Gen.. Spec.,
Lines and levels are as per approved
from
3.2 Lines, levels & formwork Gen.. Spec., P - S Checklist
shop drawings
any loose materials and compacted
properly
Supplier delivery
3.5 Concrete delivery Visual W - W
note
Sec.03300,
Survey Sec.03300,
clause 3.13
clause
3.04 1 of 5 Form # 17028-Rev 1-Feb 04
Inspection & Test Plan: Document No. :ITP 001
ARABTEC CONSTRUCTION (L.L.C)
Procedure
Concreting for Sub-Structures & Waterproofing Rev. No. :0
Saadiyat Beach Villa Resort For Boundary Wall Date

Type of Testing Requirement/ Acceptance Inspection Points Verifying / Control


Item No. Inspection Description Reference Document
Inspection Criteria ARABTEC ITA Consultant Data Forms
Placing of blinding concrete , compaction
3.6 Visual W - W Checklist
and leveling
Sec.03300,

3.7 Curing Visual S - S Checklist


Sec.03390,

4.0 Waterproofing (Above Blinding )

smooth
concrete surface,all
Surface preparation for blinding to proceed
4.1 Visual H - H Checklist & WIR
waterproofing Gen.. Spec., preparatory
Sec.07100, works (blinding) must

clause
Gen.. Spec.,
4.2.2 Application of two coats of bitumen Visual Approved method statement H - H Checklist & WIR

Sec.07100,

4.2.3 Waterproofing to be covered by Visual clause Approved method statement P - S Checklist


3.04
Sec.07100,
LEGEND : H-Hold point, W-Witness Point, R- Review Documents only, ARABTEC - Arabtec Construction (L.L.C)
clause
S-Surveillance Inspection, P-Progressive Inspection 3.04 ITA - Independent Testing Agency
WIR - Work Inspection Request

2 of 5 Form # 17028-Rev 1-Feb 04


Document No.:001
Arabtec Construction (LLC) Rev.:00
Inspection & Test Plan Date:
Concreteing for Sub-Structures &
Waterproofing for Boundary Wall Page:1 of 1

SAADIYAT BEACH RESORT VILLA

P088

INSPECTION AND TEST PLAN

Concreting for Sub-Structures & Waterproofing

ITP / 001
Document No.:001
Arabtec Construction (LLC) Rev.:00
Inspection & Test Plan Date:25 Feb. 2009
Concreteing for Sub-Structures & Waterproofing Page:2 of 3

Revision
revision No. Date Prepared By Reviewed By Approved By
Description

0 For Approval