1. BACKGROUND
1.1.1 This tender is to appoint a CONTRACTOR for the works which consists of
engineering design, procurement and supplies, manufacturing, construction,
testing, commissioning, and services as specified in the scope of works to be
furnished, supplied, or performed by CONTRACTOR.
1.1.2 This tender is to appoint a CONTRACTOR for the WORKS of PIKAP Project for
the period of 24 months (12 Months execution with sectional I.A + 12 Months
Defect Liability Period upon sectional I.A) of work execution.
1.1.3 For this tender, since it’s a combination of 4 different projects, CONTRACTOR
shall commence the Engineering Design at the same timeline for each package
whereas the execution of work and Initial Acceptance will be based on each
timeline for each package. The proposed timeline for each package can be
observed as below.
Open
2.1 PROJECT BRIEF
2.1.1 Initially, there are 2 projects to be executed in FY2023, for projects Auto pH
Correction at 6340 COC Receiving Pit (ETP) and KSV Installation for Acid
Injection at 4820 & 4200 Neut Pit. As part of the cost optimization and project
acceleration, PMT propose to bring forward 2 projects, which are projects Utility
Effluent (UE) Pipe Replacement at U4820 And 4200 and Pipe Replacement at
Neutralization Pit (Neut Pit) At Demin Plant that were planned in FY2024 to be
executed together with the 2 projects mentioned earlier. All 4 projects combined
is called PIKAP Project.
2.1.3 The combination of PIKAP projects is based on FEL readiness which has been
presented and endorsed to PRPC UF during Project Steering Committee (PSC)
on 13 July 2023.
Open
2.1.4 The description for each project as follows:
Six (6) nos of leak have been reported along the UE transfer line from ISBL
U4820 to ETP.
Boundary of change:
a) From U4820-T-004 and U4820-T-005 to ISBL U4820
b) From U4200-T-005A and U4200-T-005B to ISBL U420
Carbon
GR
GR
Open
Picture 2: UE Pipeline Overview at U4200 Pit T-005A/B
Carbon Steel
GRVE
GRVE
Open
Project timeline as below:
Open
SCOPE 2: PIPE REPLACEMENT AT NEUT PIT AT DEMIN PLANT
Incorrect piping material was used, resulting in the delamination of Glass Reinforced Vinyl
Ester (GRVE) pipes and subsequent clogging of the strainer. If the delamination and
clogging are not addressed, it will interfere with the smooth flow of acid and effluent mixture
into the neutralization pit.
The neutralization process will be prolonged, and the level in the neutralization pit will rise if
the neutralized water cannot be transported to the Effluent Treatment Plant.
This disruption will bottleneck the daily capacity of the demineralized water plant
(1380m3/hr) and cause disturbances in the supply to other plants.
The scope of modification is to replace piping inside neut-pit from GRVE to CS with PTFE
lining which involves 2 locations i.e at Pit 4820-T-004 involving replacement of line 250-UE-
4820-70592-1N103DC-N and Pit 4820-T-005 involving replacement of 250-UE-4820-
70597-1N103DC-N. The new pipe size is 10-inch CS with PTFE Lining, and the length is
25m for each pit.
Open
Project timeline as below:
Open
SCOPE 3: KSV INSTALLATION FOR ACID INJECTION AT 4820 AND 4200 NEUT PIT
The existing design check valve does not ensure a completely sealed isolation, thereby
failing to prevent the backflow of regen wastewater into the Sulphuric Acid injection line
during operation. To prevent a recurrence of acid leakage caused by material incompatibility
and corrosion, modifications to the pipe, specifically the installation of a KSV and self-
regulated PCV, are necessary.
Open
4820-T-004 Neutralization pit:
i. Modification of sulphuric acid (SA) injection line 25-SA-4820-70541-1C127DA in
to header 250-UE-4820-70592-1N103DC-N to include new KSV, check valve and
ball valve of.
4200-T-005A:
i. Modification of sulphuric acid (SA) injection line 25-SA-4200-71547-1C127DA in
to header 150-UE-4200-70571-1N103DC-N to include new KSV, check valve and
ball valve of.
4200-T-005B:
i. Modification of sulphuric acid (SA) injection line 25-SA-4200-70542-1C127DA in
to header 150-UE-4200-70574-1N103DC-N to include new KSV, check valve and
ball valve of.
Open
SCOPE 4: AUTO PH CORRECTION AT 6340 COC RECEIVING PIT (ETP)
ETP experienced pH min 6 of incoming COC influent from user cause presence of high level
H2S gas exceeding PEL (10 ppm) at COC receiving pit (6340-T-001). H2S release to the air
through checker plates gap at top COC receiving pit, it will have unpleasant smell and create
toxic condition. Hence automation of caustic injection is required to neutralize the COC
effluent to 9.5 pH.
Injection point
Open
Project timeline as below:
Open