Plants & Equipments Startup Instructions
Plants & Equipments Startup Instructions
Plants & Equipments Startup Instructions
Approved By Director
Change Record
Date Doc. # Rev. # Reason of Change Approved By
00 Initial Release
Page 1 of 16
Doc # SPP – WI – 01
PLANT STARTUP SEQUENCE (LINE 1 & 2) Rev # 00
Rev Date:12/08/2021
If the raw material include (Tissue & Wash and clean the Chest # 1, Turbo, Vibrating
2 Extra Bright) then pas it into chest # 1 2 Screen washer # 2 and their Connected lines.
otherwise pas it into chest # 4.
Now Tissue and Extra Bright Pulp will
Wash and clean the Chest # 4, and the Refiners
take in chest # 4 after screening and
3 3 with their connected pipe line.
washing via Turbo , HDC, Johnson Screen
and washer # 2
Wash/ Clean the Chest # 13 and its Connected
Now Refine this pulp via Refiner and store it
4 4 lines.
in Chest # 13
Line # 2
Startup Sequence Shutdown Sequence
Prepare the required amount of pulp by Shut off the pulper and wash/clean it with
1 taking the available raw material in the 1 water. Flush the lines and clean the pulper
pulpers (Star &Worm) Area.
Pass This Pulp into Chest # 9 Through Wash and Clean Chest # 9 and 10 their lines
2 2
HDC, it is Reservoir Chest. also
Page 2 of 16
Doc # SPP – WI – 02
PLANT STARTUP SEQUENCE (LINE 1) Rev # 00
Rev Date:12/08/2021
2
Open Chest # 10 Pump With pulp stock Shut off the Circulation pumps & Vacant Flotation
flowing in level box then tank with pulp
3
Open Pumps # ( 02,03,04,05 Circulation Flush out all pipelines and Chests connected with
Pump) flotation tank
4
Finally Processed Pulp is in Chest # 11
Page 3 of 16
Doc # SPP – WI – 03
PLANT STARTUP SEQUENCE (LINE 1) Rev # 00
Rev Date:12/08/2021
4 Start discharge screw, heating tube, Shut off Disperser, all screws and Twin wire press
shredder screw, plug screw
5 Start the feed pump # 14 of Twin Wire
Press
6 When pulps starts coming in Disperser,
open steam & its control loop
7 Finally processed pulp is in Ch # 17, Open
Dilution & use Pulp for further Process
Page 4 of 16
Doc # SPP – WI – 04
PLANT STARTUP SEQUENCE (LINE 2) Rev # 00
Rev Date:12/08/2021
01
Open high Pressure pump Shut off Chest # 10 pump
02 Open Chest # 10 Pump With pulp stock Shut off the Circulation pumps & Vacant Flotation
flowing in level box then tank with pulp
03
Open Pumps # ( 02,03,04,05 Circulation Flush out all pipelines and Chests connected with
Pump) flotation tank
04
Finally Processed Pulp in Chest # 11
Page 5 of 16
Doc # SPP – WI – 05
PLANT STARTUP SEQUENCE (LINE 2) Rev # 00
Rev Date:12/08/2021
01 Open H.P.P ( For wire Cleaning and Washing) Shut off Chest # 11 pump & fine Screen # 2 pump
02 Start high speed washer from PLC Open Flushing water in fine screens & flush for 5
minutes
03 Start fine screen # 1 from DIP panel from PLC (
Shut off Fine screen # 1 & # 2
Never Forget sealing water)
04 Start Fine screen # 2 from DIP panel (Never Shut off the main motor of high speed washer &
forget sealing water) discharge screw
05 Start Fine screen # 2 Pump from DIP penal Shut off high pressure pump
06 Start fine Screen # 1 pump from PLC. Flush out all pipelines and Chests connected with
high speed washer
07 Finally processed pulp is in Ch # 14
08 Start Agitation of Ch # 14
01 Open high Pressure pump(For sealing water & Shut off chest # 14 pump
heat exchanger)
02 Start Disperser with new load from
PLC(Before startup check it’s all inter locking Unload Twin wire press rolls
lubrication, sealing, feeding screw, steam
Loop
03 Start flushing of disc heat disperser system &
Start Twin press & open its shower
continue it for 30 minutes
04 Start discharge screw, heating tube, shredder Shut off Disperser, all screws and Twin wire press
screw, plug screw
05 Start the feed pump # 14 of Twin Wire Press
06 When pulps starts coming in Disperser, open
steam & its loop
07 Finally process pulp is in Ch # 17
08 Open Dilution & use Pulp for further Process
Page 6 of 16
Doc # SPP – WI – 06
SPP EQUIPMENTS WORKING INSTRUCTION Rev # 00
Rev Date:12/08/2021
STAR PULPER
01
After passing the pulper, shut off pulp auto valve and now
Start feeding the recycle raw material in the pulper
wash and clean the pulper with fresh water.
Page 7 of 16
Doc # SPP – WI – 07
SPP EQUIPMENTS WORKING INSTRUCTION Rev # 00
Rev Date:12/08/2021
WORM PULPER
03 Raw material weight is 1500 kg for virgin and 2250kg During this pulper impeller should be in the running
for recycle. condition
04 For Virgin raw material fill the pulper with water and
raw material to 15m3 volume and start the pulper
After that open the drain auto valve and drain the pulper
give 15 minutes for slushing and passing. Open the
and close the drain valve and shut off the pulper.
auto pulp valve of worm pulper and auto dilution
valve, auto pulp valve of secondary pulper.
05 Now start the pulp and pass the pulper properly and
close the all valves except the dilution valve of
secondary pulper.
If there is any contaminants retain on the secondary
pulper screen, open its auto drain valve and dispose
of these contaminants in trammel screen for further
screen the pulp and final reject.
Page 8 of 16
Doc # SPP – WI – 08
SPP EQUIPMENTS WORKING INSTRUCTION Rev # 00
Rev Date:12/08/2021
03
Due to centrifugal force vortex will create and
cause the high density particles to flow down
to the lower part of HDC, Here these particles
are drained via automatic drain
Page 9 of 16
Doc # SPP – WI – 09
SPP EQUIPMENTS WORKING INSTRUCTION Rev # 00
Rev Date:12/08/2021
Turbo Separator
Page 10 of 16
Doc # SPP – WI – 10
SPP EQUIPMENTS WORKING INSTRUCTION Rev # 00
Rev Date:12/08/2021
Page 11 of 16
Doc # SPP – WI – 11
SPP EQUIPMENTS WORKING INSTRUCTION Rev # 00
Rev Date:12/08/2021
01
Open sealing water. Stop feed pump
02
Fill the high pressure screen with water Open the fresh water in the screen for 5 minutes.
03
Close exhaust valve on screen cover. Stop fine screen motor.
04
Start Screen motor. Disconnect the power supply to the equipment
05
Put the accept valve opening to 65% open, the
Close the sealing water.
Reject valve open to 20%
06
Pressure difference of feed and accept should
For long duration shut, Empty the equipment
be 1.5 Bar
Page 12 of 16
Doc # SPP – WI – 12
SPP EQUIPMENTS WORKING INSTRUCTION Rev # 00
Rev Date:12/08/2021
Washer (Filter)
01
Open the fresh water and back water. Shut off the feed pump.
02
Wet the washer screen with water. Flush the filter with fresh water.
03
Start the main Drum roll motor and turn over
Close the main motor.
roll
Page 13 of 16
Doc # SPP – WI – 13
SPP EQUIPMENTS WORKING INSTRUCTION Rev # 00
Rev Date:12/08/2021
Refiner (TDR)
04 Put the disc on load according to the SR Shut off the main motor and close the sealing water.
requirement.
Refiner (DDR)
Startup procedure Shutdown procedure
01 Open the sealing water. Unload the disk.
02 Starts the refiner at unload condition from PLC
Close the feed pump
room.
03 Open the feed pump and start the pulp flow
Open the fresh water to wash the Refiner and its
according to the capacity of the Refiner at 1.5
connected pipelines
Bar.
04 Put the disk on load according to the SR Shut off the main motor and close the sealing water
requirement (It will be done automatically from valve.
PLC when the pulp pressure existence between
the disks will appear
Page 14 of 16
Doc # SPP – WI – 14
SPP EQUIPMENTS WORKING INSTRUCTION Rev # 00
Rev Date:12/08/2021
Vibrating Screen
02
Open the shower water. Stop the Shower water.
03
Start the pulp flow. Shut off the vibrating screen.
04
Store the reject and discard.
Page 15 of 16
Doc # SPP – WI – 15
SPP EQUIPMENTS WORKING INSTRUCTION Rev # 00
Rev Date:12/08/2021
De Flaker
Startup procedure Shutdown procedure
Page 16 of 16