Professional Documents
Culture Documents
Final Payment
Final Payment
\
)
FINAL PAYMENT
1
Final Payment Ahamad Abdullah
I
FINAL PAYMENT \
CONTENTS
1.0 INTRODUCTION 3
5.0 CERTIFICATIONS 6
ti
1.\
APPENDICES
Examples
Tutorials
KPKR's circulars
l-
2
Final Payment Ahamad Abdullah
1.0 INTRODUCTION
This is the last payment to be made by the employer to the contractor (or by the
contractor to the employer) after the completion of the works.
Final account shows the final contract sum or the total cost of the completed job to the
employer.
Final contract sum incorporates the original contract sum and adjustments for variation
works, provisional quantities and other adjustments allowed under the contract.
There is not much money due to the contractor in the Final certificate since most have
been paid in the interim payments.
The final payment provides final opportunity to the S.O. to make correction and
adjustment to payments made through previous interim certificates, if necessary.
The relevant contractual provisions regarding Final payment are as shown in Table 1
The above clauses explain the procedure to be adhered to in the payment process
which include:
a) The'timing of payments to the contractor.
b) The amount to be paid to the contractor.
c) The right of set-off by the employer.
d) The enforcement of payment.
e) The procedure and conditions precedent.
3
Final Payment Ahamad Abdullah
CLAIM prepared by
contractor (Clause 31 .1)
1,
FINAL CERTIFICATE
prepared by S.O.
(Clause 31.3)
fi
< 30 Days
PAYMENT made by
employer (Clause 31.5)
The contractor is responsible to submit claims to the S.O. for the purpose of preparing
final account.
The contractor is only required to submit claim for loss and expense and account for
nom inated sub-contractors.
The contractor is not required to make claim for other works as it is the responsibility of
the S.O. to determine the value of the works to be paid to the contractor.
4
Final Payment Ahamad Abdullah
The claims should be submitted as soon as possible to the S.O. and not necessarily
after the issuance of the Cerlificate of practical completion.
It is unreasonable for the contractor to expect the certificate to be ready on time if the
contractor releases the information in a mass at the end of 3 month after the issuance
of the Ceilificate of practical completion.
The contractor should include all claims in his claim document since no more claims
will be entertained after the expiry of the 3 month period.
The S.O. should only consider substantiated claims that are submitted within the
stipulated time for final account.
'... reason of delays as sfafed under clause 43.1 (c), (d), {e), (f) and (h), and
... direct loss and/or expense ... the Contractor would not be reimbursed by
a payment made under any other provision... then the Contractor shall within
thirty (30) days ... give notice in writing fo fhe S.O. of his intention to claim
...'(Clause 44.1)
The contractor is responsible to submit all supporting documents regarding claim for
loss and expense and account of nominated sub-contractors for preparing the final
account within the 3 month period.
The employer will prepare the final account on the available information furnished by
the contractor within the specified time.
5
Final Payment Ahamad Abdullah
The S.O. does not have to consider the supporting evidence given after the 3 month
period.
4.0 CERTIFICATIONS
The final payment process only start after the works has been approved, that-is after
the issuance of the Cerlificate of Practical Completion.
An inspection of the work will be conducted by the S.O. on expiry of Defects liability
period.
The Final certificate must be issued within 3 month after the expiry of Defects liability
q)
period if there is no further defect as in Figure 2.
3m
12 months IS 3 montl€ I
l<-----------?l
lf the inspection reveals outstanding defects, the S.O. will prepare Schedule of
defects that can be issued to the contractor within 14 days after the end of Defects
liability period.
3m
12 months s1 3mo F 3 montl'lsl
<- --------71
The contractor has to make good the defects within 3 months after receipt of the
Schedule of defects.
6
Final Payment Ahamad Abdullah
The Final certificate must be issued within 3 month after the issuance of the
Certificate of Completion of Making good Defects as in Figure 3.
The certificate must be issued within the stipulated time and it is considered a breach
of contract if the employer cannot do it on time.
The contractor should be paid for all work done by him as well as for loss and expense
incurred.
a) Final contract sum or the total cost of the completed job to the employer which
include:
t. Originalcontract sum.
ii. Fees and charges for supply of water, etc.
iii. Variation works.
iv. Remeasurement of provisional quantities.
V. Expenditure of Prime cost sums.
vi. Expenditure of Provisional sums.
vii Testing of materials and works covered, up
vii Fluctuation of prices.
ix. Cost of disposal of fossils, elc.
x. Loss and expenses.
'and after setting out or allowing for all paymenfs'- to safeguard the contractor's rights
to any money previously cerlified that the employer may not have paid.
7
Final Payment Ahamad Abdullah
The S.O. is allowed to deduct any money owing from the contractor to the employer
This includes:
a) Cost of making good defects (Clause 48.2).
b) Diminution in value of work due to defects (Clause 48.3).
c) Liquidated and Ascertained Damages (Clause 40.2), etc.
The contractor's agreement to the account in the Final certificate is not required. The
contractor can bring the matter to arbitration if he is not satisfied with the Final
certificate.
ANE ADDBESS.OFCONTRACTO R:
SYARIKAT RAHMAT SDN. BHD.
NO. 20, JALAN 2/3A,4OOOO SHAH ALAM ?'
t.
CONTRACT NO. : UITM/PB02/2003
DEDUCTION:
RETENTION MONEY:
1, Contractor
2. Subcontractor
PREVIOUS PAYIUENTS'PAID (No. 1 - 22) RM 3,286,370.00
ADVANCE PAYMENT: tstu1_32!09.4=q9.
AMOUNT DUE TO CONTRACTOR: RM 270,321.51
'No certificate of fhe S.O. ... as conclusive evidence as fo fhe sufficiency of any
work, . . nor shall it relieve the Contractor from his liability to amend and make
good alt defects ... shall be final and binding in any dispute ...' (Clause 32.0)
8
Final Payment Ahamad Abdullah
a) The Final certificate is an evident that the works have been properly carried out and
completed.
- The continuing responsibility is transferred to the S.O. since he has expressed
his reasonable satisfaction with the work. The S.O. is also responsible for the
supervision of the work.
- However, the final payment certificate is not a conclusive evident that the
works are perfect i.e. strictly in accordance to contract. The contractor
remains liable to employer for any breach in complying with what has been
specified,
- Limitation Act - 12 years for contract under seal and 6 years for others
b) The Final certificate is an evident that all necessary adjustment to the contract sum
has been done accordingly.
- allvariations, claims have been considered.
c) The Final payment certificate is not final and conclusive if the dispute is brought to
arbitrator or court. The certificate ean be disputed in such circumstances as:
i. Fraud in the preparation of the certificate
! - by contractor in presenting information to the S.O.
- by Q.S. in financialelement in ceftificate
- by the S.O. in drawing up the account.
ii. Defects which would not have been disclosed by reasonable inspection before
issuance of certificate.
iii. Accidentalinclusion/exclusionofworks.
iv. Arithmetical errors in the computation of account - including quantities and
pricing errors.
The Final Certificate shall state any finat balance due from the
Government to the contractor or from the contractor to the Government, as the
case may be, which shall thereupon become the debt payable...,(Clause
31.4)
Final payment certificate is the last certificate issued under the contract. lt is a
precedent to final payment.
lf the final contract sum exceeds the total amount paid to the contractor, the excess
shall be paid to the contractor by the Omployer.
The S.O. is responsible to certify to the Employer the amount of payment payable to
the contractor.
The certificate is binding on the employer and he must make the payment within the
period for honouring payment ce(ificate as stated in the Appendix i.e. if none stated,
the period is within 30 days after the issuance of the certificate.
On the other hand, if the total amount paid to the contractor exceeds the final contract
sum, the excess shall be paid by the contractor to the employer.
'... no final payment due to the contractor ... shall be made unless and untit the
contractor shall have safr'sfi'ed fhe s.o. by means of a statutory Declaration ...
the workmen ... have received all wages due to them ...and that att dues and
contributions ... have been paid.'(Clause 31.5).
I
Final Payment Ahamad Abdullah
Before releasing the final payment, the S.O. has to make sure that the contractor has:
a) paid the workers'wages, and
b) made all necessary contributions to the authorities.
This is to safeguard the interest of the workers as the workers might not be employed
by the contractor after the completion of the work.
The relevant contractual provisions regarding Final Payment are as shown in Table 2:
Clause27.7
progress of the Works
Final payment to Nominated Sub-Contractors
fl)
Clause 28.6 Payment to Nominated Suppliers
Clause 30.10 Finalaccount
Clause 30.1 1 Items in Finalaccount
Clause 30.12 Conclusiveness of the Final account
Clause 30.14 lssue of Final certificate
Clause 30.'15 Final certificate
Clause 30.15 Final certificate not conclusive
Similar provisions as P.W.D. Form 2034 (Rev. 1/2010). Some differences are as
discussed below.
The contractor is responsible to make all claims required for the preparation of the final
account.
The claims should be submitted within 6 months after the issuance of the Certificate of
practical completion.
The Final account must be completed within 6 months after the Architect had received
the necessary documents from the contractor as shown in Figure 5.
10
Final Payment Ahamad Abdullah
lf there is delay on the part of the contractor in submitting the necessary documents to
the Architect, the period for completing the Final account will be adjusted accordingly.
E.g. if the contractor takes I months to submit all the necessary documents then the
Period to complete the Final account will become 14 months instead of 12.
'... the Contractor fails to submit all documents necessa4l/ for preparing the Final
Account, the Architect ... complete and lssue the same based on the information
available within the Period to complete the Final Accounf ...' (Clause 30.10)
lf the contractor does not provide all the necessary information, the Final account must
still be completed and issued by the Architect within the Period to complete the Final
account stated in the Appendix as in Figure 6.
ln this case, the Final account is prepared based solely on the available information
furnished by the contractor.
6.2 Finalaccount
'The foltowing shallnot be included...'(Clause 30.11)
Items not considered in the Final account are the deduction for:
a) Liquidated damages
b) Set-off by the employer
c) lnterest payable by either pady
These matters are to be resolved separately by the employer and the contractor. The
employer may recoverthe payment for those items
a) as a debt.
b) from any monies due or to become due to the contractor.
c) from Performance bond.
11
Final Payment Ahamad Abdullah
The contractor's agreement to the Final account is not required. The contractor can
bring the matter to arbitration later if he is not satisfied with the Final account.
'lf nothing in the said Final Accounf is disputed ... within three (3) Months from the
date of receipt of the Final Account ... conclusive and agreed by the pafties.'
(Clause 30.10(a))
Both parties are given the opportunity to contest the Final account prepared by the
Architect.
lf the Final account is not disputed by either party within 3 months after its issuance,
the Final account is considered conclusive and agreed by the employer and the
contractor.
< 3 months
'... the party disputing the Final Account ... wriften notice to the other pafty ... within
three (3) Months of the date of receipt of the Final Account ... The Architect or
Quanfiy Surveyor within three (3) Months from the date of receipt of the grounds of
dispute shall either amend or not amend the Final Account. Any party disagreeing
... shall refer the dispute to arbitration ... within three (3) Months from the date of
receipt of the amended Final Account ... Failure to refer the dispute to arbitration ...
deem to be conclusive and agreed...' (Clause 30.10(b))
The provision sets out the procedure in case of disagreement by either party to the
Finalaccount:
a) Within 3 months after receiving,the Final account - either.par[ycan send notice
statihg the grounds of disputes to the other party with copies to the Architect and
the Q.S.
b) Within 3 months afterreceiving the notice - the ArchitecUQ.S. will decide to
amend' or notlo'amend the'Final account.
c) Within 3 months after receiving the amended Final account or decision not to do
any amendment:
i. the disagr6eing party refers the dispute to arbitration.
ii. if not - the original Final account or the amended Final account as decided
by the ArchitecUQ.S. is considered conclusive and agreed by both parties.
12
Final Payment Ahamad Abdullah
Contractor/employer Decision by
received Final account Notice ArchitecUQ.S Arbitration
Disputes
6.2 Finalcertificate
'The Final Ceftificate sh all be r.ssued.'
30.14(a) within twenty one (21) Days after the Period of Honouring Certificate for
the payment of the Penultimate Certificate; or
1
30.14(b) within twenty eight (28) Days after the Ceftificate of Making Good Defects
has been rssued, in the event no Penultimate Certificate has been rssued.'
(Clause 30.10)
Penultimate certificate can be issued within 14 days after the issuance of the
Certificate of making good defects.
ln this case, Final certificate is issued 21 days after the Period of honouring certificate
as in Figure 9. Period of honouring certificate is 21 day from the date of the certificate,
if none stated in the Appendix.
lf there is no Penultimate ce(ificate, Final certificate is issued within 28 days after the
issuance of Certificate of making good defects as shown in Figure 10.
13
Final Payment Ahamad Abdullah
,!1
TUTORIAL
Based on the information given in Appendices 1 to 4, prepare a draft final account for the
project.
'|.4
Frnal Payment Ahamad Abdullah
Appendix 1
PARTICULARS OF CONTRACT
1 Preliminaries RM 136,000.00
2 Main building works RM 5,535,800.00
3 Nursery / kindergarten RM 105,550.00
I 4 Security complex RM 35,500.00
) 5 Externalworks RM 230,800.00
6 P.C. and Provisional sums RM 1,461,200.00
TOTAL
l@
PRELIMINARIES
15
Final Payment Ahamad Abdullah
Appendix 2
PROVISIONAL SUMS
1. Landscaping RM 190,000.00
2. Computer room Rtvl 85,000.00
16
Final Payment Ahamad Abdullah
Appendix 3
SUMMARY OF VARIATIONS
1. Building works
c) Wallfinishes
Omission RM 45,650.00
Addition RIM 35,500.00
.! d) Floor finishes
: Ornission RM 35,220.00
Addition RM 25,550.00
2- Externalworks
The following items for external works have been re-measured and prices agreed
upon.
3. P.C. sums
a ) Air-conditioning
i. Accepted tender figure: RM 21"0,500.00
ii. Variations: Omission Addition
V. O. No. 1 10,300.00 16,200.00
b Electrical installation
Accepted tender figure: RM 75,500.00
Variations: Omission Addition
1
V. O. No. 5,300.00 9,200.00
2
V. O. No. 5,550.00
17
Final Payment Ahamad Abdullah
Appendix 3A
c) Curtain walling
i. Accepted tender figure: RM 236,500.00
ii. Variations: Omission Addition
V. O. No. 1 15,500.00 35,500.00
d) Lift installation
i. Accepted tender figure: RM 390,800.00
ii. Variations: No variation
e) P. A. System
?] r -!.4, :i i -, Aecepted-tender fi gure .RM 58;500:00
ii Variations: Omission Addition
V. O. No.1 8,500.00
V. O. No.2 5,530.00
4. Provisionalsums
a) TNB Sub-station
i. Value: RM 53,500.00
b) Computer room
i. Value: RM 88,500.00
d) Landscaping
Value: RtM 158,500.00
e) Piling works
i. Value: R[/1248,000.00
1B
I
CONTENTS
SECI'ON DESCRPT'ON
I 'i,:
] :iiililiil:,,:liJ$iii;:,,,,,,,,,i'
.l: ,;
1 i -i
,:,.:,.
.1:,::::';,,_,:1
::1
C Voriotion Certificote
E- . Stotutory Declqrotion
I
eADANGAN ITENGUBAIiSUAIDAr$l{Ali 8in&mrrutild, 4gm{&E Kq[DAr STEETBDA Dr ],tO. 16; JArAN ss 24113
fAUAlt MEGAH. PETALING iIAYA' SEL&IIIEO*. Oe,nrur, ngrSrnuu (flIO{JK TETUATN S]MEBB$.I ESAJ,Ty SDN.E{ilD.
j
t. ORIGINA1 coNr\cr sux RM 39s, 590 - oo
1
I
rd*i ti,ooGlo @nd.sedqn (RM0
v.o. I\ro. ,
Adjustrnent to PC and Provisional Sum 221,160.OA
V.O. No. 2
Omission tlor.ks 60,580.0'0
ill
V,O- No. 3
Additional l{orks 82,L72.0O
V.O. No. 4
Profit & Attetrdance.
(Rlnggit XaJ'afllair : On Euodred Niactl' Flvo lgoc*erd four EuDdred Twentl' Tro Only)
PREPARED BY :
CERTTFIED BY :
DATE A!F.CI{ITECT
APPROVED BY :
I{AIAYSINI f,INGGIT : ONE HT'IIDRED }II}W[Y EIW frSOUSAOID EOUM, HI'}IDRED T[{EI[IY TTdO OTfJY
(RU 195,122.00)
t
as the FINAL/TOTAL VALIIB Of IO*X DO0IE zu{D I/fte. trr,ave nci f.ulrt.tteli
claim of
whatsbever nature under thir.Co.ntraet
i-
STGNATURE bE COUrnactoR. j,......
NAIIE :.....
tl
ADDRESS:.-...
;
v
5
, SI€NATURE OF WIINESS
LL
E
NAUE
I
DATE
-.t3.
o
24 rUS{ rftrf t/t, s}s $t{A$r tIJ}t,sEl,ad{Gofi. DAR{dL
N BER D B +6e$5(m{O4l fAX: +d}&561, }6?6'
E}d6rA$1.
. ! I (J.lu; l,.riiL.\:,l aJ
Ceryryt{c ffiIlAA '
f,
CERIIFICAIE OF FlMt PAU,lEhlt
cADnNqAN MENGUBAIISTAI DAT,AMAN BAtrGqEaX R{X{efl Kf,,Der SEETADA Dr NO. 16, JATAN SS 24/L3
TAMAN MEGAII, PETALING,IAYA, SEIAII€O*. DIRtJ:L S&ISAI{ UbIII{UK TETITASI SX}IEEAI{ REATTY SDN.BflD.
E.INAI, \TATUATION
Fringgit i{alayeia : Four Thouaand Eiglt Hundred Biqhty Five ivtud Sem Fifty Eive On,1y
PREPARED BY:
Date :
Qlarrtity S,urveyor
DmECTORS
I Yoti oro hereby in*nrAed tobrecub *ro fulorhg ulork involvf;q o vo{h*rn to yorrr Corntroct, in occordonce wilh the
ter,rns
i,llnreof, noneh::
O,r.t,SSrON
,
Adiw-lmenr|o PC ond Provisiong! qr*, (reerfppen& f)
li:
iiili'1r. i .
,RM221,760.@
t'
Dote
Dote
-t'
We the undersigned, horefy oacrror*eag€ reoe{* of rho obove vqrbrion deloils ond ogree to lhe vohrlion *reroof oo *oted
.
obove.
.l i
j:. -t
Cordioctol Dote
Tho conkoctor sholl'sign oll copies of lhe vorirrion order ond litrtenrenr reloi&g. cop{ for re,cot*
_:,....,,,J,.
@rl€ fie
Prepored
Quontity Erqte :
a $ppemdix i.
E IADD
I
1t 180. O0
r laOo'for Attendanae L. S,um 'L8,0. O0
I
v|/1
Certffic* d
PracticC Compbfer*
a
Jab trlle and no. : CADANGAI{ METIGUBAlltil'il D"AI'^NT Sqid no. $Uef,/'{r@:
t BANGUNAN RUMAH KEDAT uiib. rc.
tEDltDa
JAtAil ss 24l1r. TAmAr raacAH. pgirr
JAYA, SE.AT{GoR U]{TuK grtESAlI REfi,rr 9a
qHD.
a the uorks were completed to our satisfaciisn ryud taten inropossession on: y3!t..!ru {pgz
xr}
6 a*rd that the said dlfeds tiabilily period will end oo: ffi, iltrV ,!ffi:
:''and
that in said pat or sectirn of the works.
tle sairl defects liability period nil end om
llwe declare that one moiety of the reten{irn t*ooeys deducted under prorix,as
6prrtifioatres irrr nespect of tfie said wonks
or sections thereof is to.be released
SignaturB
alt
/
u0EIl{uIrugunB, architect SUFIAN ARCI{ITFCT Oate: gltst- ilft 1'tU,
I
I
I
i wM )
* **,*.ffiff
t..
dengan sesungsuhol.
:
I
,\
Saya tclah mcnyqryEnakm sgatl kcrir-kcrir :
,
€i*bqi*)
KontrakNo. Bil fl
a. Semua kerja-kerja telah dijala*an @a gap*m dm tel& dry"
b. Semua gaji pek€riaaekerja tehh d[i*e+
c. Sonua carunanKrryr{aa Wang Sinpme; H€riatelah dijel*eo'
d. Danjugatidak da$ryq haa-ngberkaiBn fuSilIkontrak id.
Dm saya meubuat surat akuan ini dmgan kepercayaan bahawa apa-apa yeg tersebut di dalamrya adahh
)
)
:L
(Iandotangan don Mohor YDP Mahkandt @Pelw@!rya,I*@
LAMPIRAN 2
b :':
HARGA MUKTAT,IAD KONTRAK
KURAI.iGKAN +
S \ ,{ *,tl t-9
l. Wang Trhanan fiike berkenaan) yeng relah dilepaskan
(a) s
(b) Subkontraktor-subkonr raktor
Dinanrakan (Jumlah b/h dari
I-ampiraa A l-Jumlah Ruansan 6)............... s
(c) Pembckal-pembckal Dinanrakan
(Jumlah bfr dari Lampirrn A.2-
Fumlah Ruangan 6).. $-
2. Bayaran Inrerinryang rerdahulu.(No I ke 5o. 22) s 3,286;3?0.0oS 31286r3?0.,
214,321.
TOLAK
(a) KontrakrorUtama.......,.......................S
(b) Subkonrraktor-subkonrrakrorDinamakan
(Jumlah b/h dari Lanrpiran A I -lumtah
Ruangan ?)................:.....,..................S
5.
s
5 :.rl- ':- i '6. Kos mcmbaiki kecacaun s
14b
I
Saya/l(ami*, yang nrenandatangani di barvah ini mengaku penerinraan Perakuan Muktamad di atas dan setelah nleneliti
-
buiir-butir rcrkandung di dalamnya. bcrsctuju dengan Bayaran Muktamad Disyorkan Kena Dibayar dan mengaku baharva
Saya,/l(amit tidak ada tuntutal lanjut di barvah Kontrak ini.
Cap Kontraktor
Tarikh: Tarikh:
ETNAIJ SIFI.IARY
1) PPJHK NO. 1
a) Rereasureuent of Provisioral
t, Q:arrtlties t,226,9?i.25
2l PPJHK NO. 2
4I PPJHK $O. 4
33.o n) 23,699.56
5) PPJHK }O. 5
6) PPJIil( NO. 6
7) PPJHK NO. 7
s) PPJHK NO. e
Rercasurernent of Prauisionel
Qusntities as corrtained in
Main Inf rastmcture Rrairraoe
Cqrtract (Additimel) " 96,4O3.90
e) PPJHK !CI. 9
Les€
PERUNTUKAN PEMBANGUNAN :
t. t. ts. at4.
B' liry d"-"grl!i memperakukan bayann mukramad dibawah ini berjumrah Ringgit
MAIAYSiA TIGA RIBU DUA PIJLUH TIGA DAN SEN SEITiBTLAN PULUH SAHAJA (RM
3'023'90) menunjukkan baki muktamad dibarrah Kontrak adalah panit
dan dibayar oleh Kerajaan
seperti berikut:-
l. Kontraktor Utama
(i) Nilai Kerja dan amaun-amaun lain : RM 3,023.90
(ii) Pelepasan Deposit wang.Iaminan
Pelakanaan (J ika belum dilepaskan) : RM 47,885.00
KERAJAAN SELANGOR
No.Kontrak: JKR/PER/SELnt49g
Jenis /Tajuk/Huraian
Pelarasan: Pensuku'ran Semula Kuantiti Cerucuk Basi Keria-Keria Kuantiti S€mentara
Asas (Rujukan Butiran Senarai Kuantiti/Ringkasan Tendpr
|ljukan
S",!3.r! Kurnll-,i No.l , K.!ir-K".ir=gi!l"uk Griir"n n t innn,
11b:I.1),- tr _ ,ur."ru.r,
STtl3) O"n (Buti.rn A hinnn
2. Pelarasan Harga di atas d-inilai mengikut pengiraan yang dikepilkan bersama ini akan
lenjadi tambahanlkuSngkan sebanyak Ringg-it Malaysla:
ENAM RIBU SERATUS
SEMBILAN PULUH SEMBILAN DAIY SEN DUA iULUH
kepada
SAI{AIA (RM 6,199.20)
harga dan bayaran atas Kontrak kepada tuan.
Tarikh:........
A
saya/Kami yang bertanda tangan dibawah ini mengakui perakuan
diatas.
Tandatangan Kontraktor
Nama dan Cop Syarikat:
s.k
Pengarah Cawangan....
Ibu"Pejabat JltR'Kuala Lumpuf .
I
Pengarah JKR Negeri Selangor.
Bank/Syarikat Insuran.
Yang menjamin.
t.
AKAUNMUKTAMAD
ON Irl{JN
DESCRIPTION UNIT BQ ACTUAL AMOUNI
QTY. QTY.
A Mobilisetioo and dcrnobilisation of piling
cquipmeog plant ctc.
LS 23,000.00 23,O00.00
TOTtrL
,ADDTfiON 102,470.00 108,66920
6,199.20
Ruj.Kami: ( 6 )dlm.JKR.KPKk020.050/03 KlL4
Tarikh: 20 September20O0
Tr.wr,
3.0 Memandangkan kos bagi memperbaiki kecacatan.bol€h dituntut daripada bon pelaksanaan,
Peralamn Muktamad bolehdikelua*an tanpatnenunggusehinggaTempoh Tanggwrgan Kecacatan tamal
Oleh iar keputusan telah dibuar stpaya Perataun Mulrarnad hendaklah dikeluarkan dalam tempoh enam
(Q bulan selepas Perakuan Siap Kuja dikeluarkan
4.0 Adalah diingatkan bahawa analan mendapaflcan tandatangan Kontraktor sebelum Perakuan
Muktamad dan Arahan Perubahan Kerja / Pelarasan Harga Kontrak berkenaan diluluskan bukanlah
merupakail satu syarat yarg ditempkan di bawah Kontak B4gi mengelak kelewatan yang mungfiin timbul
daripada amalan ini, tempoh'masa unhrk Kontaktor mengembalikan Peralatan bedeitan hendaklah
dihadkan kepadaempatbelas(ialharibqgi.ArahanPenrbahan.Kedal'Pelarasan,Harga,Kontrakdantiga
puluh (30) had bagi Perakuan Muktamad Sekiranya Kontraktor gagal berbuat demikian, tindakan t
Sekian
NO. KONTRAK:
HARGA ASAL KONTRAK : Ril
JUM LATI BERSIH TATBAHAI{TPiOTOIIGATII.: Rm
Tarlkh : ..-.-.---
( PegnH nengesprl
B. Saya dengan lnl metrytatrkt Dayail rnlltama.l {il ffii lnl Derfunsah F[ngglt Malaysla
( .. .--l mcnur$ukt batl multamd C ffir Xontat #dt patut dan kena dl
bayar oleh lteralaan scpetd berlhrt:
1 Kontrakbr utama
(l) Nllal kerla dan arnann aanrn triln il
(ll) Pelepasan DqdtlarEg Jar*ran Folef,saan t ffi
2^ K_epadq SubkontrattorlPenerlma EqTaran seped dl l-AtrPlRAN .A' R!,l
3. Krcdlt Hasll b{l Gantrugl T€rEntl tbt l}ltfapftrt
e Ril ......-. selama -.---- Harl RT]l
Akuan Statutorl atau Peraluan y3g CUargfld oleh &r bagl plhak Ketra Pengarah Buruh
yang dlkehendakl dibatdl FGd 4t (d! ffi-syard kqrtat U* dltemulrakan olefr kontrktor.
Tarlkh:
(Pegtral Penguasa)
*Tambahan / Pdongan yarag t&r df**rstfli swt Panyata Pelarasan Harya Kontrak
Mukasuratl/4
C. PEIIGAKUAN PEreETI'JUAll KOIITRAKTOR TE ATAS PERAKUAII AI(AUN DAN BAYARAN
HUKTAIAD
No. K.P:
Alamat. Alamag
t
Tarlkh: Terltt:
Mukasurat2/4
Lamplran'A'
PERAKUAN AKAI,'N DAiI BAVARAiI f,t'KTAUAD
Jumlah
Ruj. Penerima Bayaran Jenis Kerja atau Jumlah Bayaran Amaun yang
Bulan l-.larga Terdahulu Diperakukan
(1) et (3) (4) (5) (6)
A. Su bkonbaktor Dinamakan
i)
Juml*r lccik
B. Pembekal Efnamatah
)
i)
ii)
iii)
Jumldr kecil:
c. Penerima Hak
JunHr lccit
D. Peoawai Penvelia
Juml*r keciE
P;g;;a];;sesy;i
Nota:
(2) lsikan nama subkontakbrfueneriola @pran yang ber*enat.
(3) Nyatakan j.eltg.kega st6konffiorda, bdcdan *ar hrkr ya,g berkenaan bagi kategori pegawai
penyelia. Tidak berkeraan bqi penerina H.
(4) lsikan.jumlah harga sl6kont#tr rirll*r yang dserd*r*- Tinat bertermr untuk kategori peganai
penyelia.
llukaeur*3/4
PENYATA PET.ARASAN HARGA KONTRAK
TA'UK
KERJA:
NO. KONTRAK:
KONTRAKTOR:
HARGA ASAL KONTRAK:
{'-'t
(/
JUHLAH
JUTI,AH AERSIH
Tarikh:
Pegawai Penguasa
PROJECT
EMPLOYER
MAIN CONTRACTOR
VARIATION ON CONTRACT
1) Additions from Summary of Variations RM
2) Omissions from Summary of Variations RM
NETT ADDITION/OMISSION RM RM
FINAL CONTRACT SUM RM
lArVe the undersigned hereby acknowledge receipt of the above Statement of Final Account and agree to the Final
Contract Sum as shown and declare that we have no further claim under this contract.
CONTRACTOR WITNESS
Name: Name:
Date Date:
Fr
z.xE'
ob Y
&
g
E$ u,
&
4
TL
z
o
F
o
o
F
l-
ul
,.\z
z
o
6
q)
'=
o
L;
z
o
E
o
o
o
z
IF
d.
II
o
t
E
3
= a
z
o o
;.
q
xO
q)
tt,
cl
o
z
j
uj
io o
F z
() +
d
tuJ l-
zo
#
UJ o
) o oo
o o- z iz
xo- a
ul
FINAL CERTIFICATE
PROJECT:
MAlttl CONTRACTOR
): _;issions
as per V.O. No. RM
Nett Additions/Omissions RM
DEDUCTIONS
{) RM
2) RM
3) RM RM
Ringgit Malaysia :
:IPARED BY:
(QUANTTTY SURVEYOR)
CERTIFIED BY:
Date
(SUPERINTEND|NG OFFTCER)
APPROVED BY:
Date
(EMPLOYER)