PRODUCTIVITY CALCULATIONS

Tower Floor Plate Area Sqm

Description of Item Unit Qty


Manual - Excavation & Getting Out upto Depth 1.5 to 3.0 Metre
Productivity Calculation Cum 10
Days 3
Per Team 1

Description of Item Unit Qty


Excavation by JCB upto 3 Metre Depth
Productivity Calculation Cum 3200
Days 13
Per JCB (30 Cum Per Hour) 1

Description of Item Unit Qty


Backfilling by Manual
Productivity Calculation Cum 60
Days 6
Per Team 1

Description of Item Unit Qty


Plain Cement Concrete (Through Hand Mix)
Productivity Calculation Cum 10
Days 1
Per Team 1

Description of Item Unit Qty


Concrete In Isolated Footing & Foundations
Productivity Calculation Cum 30
Days 1
Per Team 2

Description of Item Unit Qty


Concrete In Mass Concrete Raft Foundations
Productivity Calculation Cum 5200
Days 180
Per Team 2

Description of Item Unit Qty


Concrete In Columns / Shaer Walls / Retaining Walls
Productivity Calculation Cum 2100
Days 180
Per Team 1

Description of Item Unit Qty


Concrete In RCC Slab & Beams (Mixer Machine & Manually)
Productivity Calculation Cum 25
Days 1
Per Team 2

Description of Item Unit Qty


Concrete In RCC Slab & Beams Through Pump & Batching
Productivity Calculation Cum 160
Days 2
Per Team 2
Description of Item Unit Qty
Concrete In RCC Slab & Beams Through Pump & Batching
Productivity Calculation Cum 160
Days 3
Per Team 2

Description of Item Unit Qty


Foundation Shuttering
Productivity Calculation Sqm 150
Days 5
Per Team 2

Description of Item Unit Qty


Rectangular Column, Pedestal Shuttering
Productivity Calculation Sqm 750
Days 15
Per Team 2

Description of Item Unit Qty


Retaining / RCC Walls
Productivity Calculation Sqm 950
Days 30
Per Team 2

Description of Item Unit Qty


Beam & Slab Shuttering
Productivity Calculation Sqm 2000
Days 15
Per Team 2
Description of Item Unit Qty
Reinforcement Steel Works
Productivity Calculation MT 70
Days 26
Per Team 4

Description of Item Unit Qty


Brick Work 230mm Thick upto Plinth Level
Productivity Calculation Cum 65
Days 20
Per Team 2

Brick Work 230mm Thick Above Plinth Level


Productivity Calculation Cum 250
Days 20
Per Team 4

AAC Block 100mm Thick


Productivity Calculation Sqm 120
Days 4
Per Team 2

AAC Block 150 / 230 / 300mm Thick


Productivity Calculation Cum 130
Days 15
Per Team 2

Half Brick Work 115mm Thick upto Plinth Level


Productivity Calculation Sqm 150
Days 7
Per Team 2

Internal Wall Plaster Cement


Productivity Calculation Sqm 3500
Days 25
Per Team 2

Ceiling Plaster 6-8mm Thick


Productivity Calculation Sqm 850
Days 20
Per Team 2

Gypsum Plaster Cement


Productivity Calculation Sqm 3500
Days 20
Per Team 4

External Plaster Works in Two Coats 18-20mm Thick


Productivity Calculation Sqm 1600
Days 26
Per Team 4

Concrete Flooring Works / IPS Flooring (40-50mm Thick)


Productivity Calculation Sqm 180
Days 7
Per Team 2
Tile Flooring
Productivity Calculation Sqm 650
Days 20
Per Team 3

Tile Skirting
Productivity Calculation Rmt 270
Days 5
Per Team 1

18-20mm Thick Stone - Granite/ Kota / Indian / Italian./ Imported


Marble Flooring
Productivity Calculation Sqm 135
Days 8
Per Team 2

Description of Item Unit Qty


Polishing & Rubbing
Productivity Calculation Sqm 135
Days 8
Per Team 2

Description of Item Unit Qty


Stone Flooring in Staircase Riser & Treads - Cutting & Fixing
Productivity Calculation Sqm 28
Days 2
Per Team 1
Polishing & Rubbing
Productivity Calculation Sqm 28
Days 4
Per Team 2

Laminate Wooden Flooring (Normal)


Productivity Calculation Sqm 180
Days 7
Per Team 2

1mm Thick - Birla Putty


Productivity Calculation Sqm 2650
Days 10
Per Team 2

OBD Paint on Walls including Priming Coat


Productivity Calculation Sqm 750
Days 10
Per Team 2

Acrylic / Plastic Emulsion Interior Paint on Walls including Priming Coat


Productivity Calculation Sqm 2650
Days 15
Per Team 2

Exterior Texture / Weather Shield Paint including Priming Coats


Productivity Calculation Sqm 6500
Days 30
Per Team 3
Tapecrete / Polymer Based Water Proofing in Toilet / Kitchen & Wet Areas
Productivity Calculation Sqm 70
Days 4
Per Team 2
Mason Labour
0.96
10
3
0.00 3.00

Mason JCB
0.03
13
1
0.00 1.00

Mason Labour
0.30
18
3
3.00

Mason Labour
0.17 3.13
0 31
0 31
0.00 31.00

Mason Labour
0.08 0.73
2 22
2 22
1.00 11.00

Mason Labour
0.03 0.36
139 1885
1 10
0.00 5.00

Mason Labour
0.22 1.36
462 2848
3 16
3.00 16.00

Mason Labour
0.24 3.40
6 85
6 85
3.00 43.00

Mason Labour
0.16 1.12
25 180
13 90
6.00 45.00
Mason Labour
0.10 0.15
16 24
5 8
3.00 4.00

Carpanter Helper
0.10 0.15
15 23
3 5
2.00 2.00

Carpanter Helper
0.18 0.30
131 225
9 15
4.00 8.00

Carpanter Helper
0.22 0.38
210 361
7 12
3.00 6.00

Carpanter Helper
0.15 0.23
300 450
20 30
10.00 15.00
Binder Helper
6 8 700 500
420 560 4200 4000
16 22 67846.15 86153.846
4.00 5.00 154000

Mason Labour
0.72 1.78
47 115
2 6
1.00 3.00

0.94 3.34
235 834
12 42
3.00 10.00

0.07 0.29
9 35
2 9
1.00 4.00

0.62 1.75
81 228
5 15
3.00 8.00

0.09 0.25
14 37
2 5
1.00 3.00

0.08 0.26
263 910
11 36
5.00 18.00

0.06 0.17
47 142
2 7
1.00 4.00

0.20 0.12
700 420
35 21
9.00 5.00

0.12 0.34 Each Mason Per Day


192 546 0.0 17222.4 17.88 2152.80 82.8
7 21 Masons Labor
2.00 5.00 10% Labour for Scaffolding 8 20
59.076923 419.69231
0.09 0.25 950 600
16 45 56123.077 251815.38
2 6 307938.46
1.00 3.00
0.20 0.38
130 247
7 12
2.00 4.00

0.03 0.04
9 12
2 2
2.00 2.00

0.18 0.41
24 55
3 7
1.00 3.00

Mason Helper
0.50
68
8
0.00 4.00

Mason Helper
0.20 0.58
5 16
3 8
3.00 8.00
0.50
14
4
0.00 2.00

0.10 0.15
18 27
3 4
1.00 2.00

0.05 0.05
119 119
12 12
6.00 6.00

0.05 0.05
41 38
4 4
2.00 2.00

0.06 0.05
159 143
11 10
5.00 5.00

0.06 0.03
390 227
13 8
4.00 3.00
0.22 0.25
15 18
4 4
2.00 2.00
LABOUR PRODUCTIVITY / OUTPUT COEFFECIENTS IN CONSTRU
Mason / Carpanter /
Description of Works Unit Quantity
Fabricator / Painter

General Works
Loading / Unloading of Cement Bag at Plant Bag 140

Loading / Unloading of Reinforcement Steel MT 90

Civil Works
Foundation Excavation

Excavation & Getting Out upto Depth 1.5 to 3.0 Metre Cum 1

Excavation & Getting Out upto Depth 1.5 to 3.0 Metre Cum 1

Backfilling by Manual Cum 1

Backfilling by JCB Cum 30

Foundation Excavation by JCB

Excavation & Getting Out upto Depth 1.5 to 3.0 Metre Cum 1

Excavation & Getting Out upto Depth 1.5 to 3.0 Metre Cum 20

Concreting Works

Plain Cement Concrete Cum 1 0.17

Plain Cement Concrete Cum 1 0.17

Concrete In Foundation / Raft / Footing Cum 1 0.17

Concrete In Isolated Footing & Foundations Cum 1 0.08


Concrete In Mass Concrete Raft Foundations Cum 1 0.027

Concrete In Columns / Shaer Walls / Retaining Walls Cum 1 0.22

Concrete In Columns / Shaer Walls / Retaining Walls Cum 1 0.22

Concrete In RCC Slab & Beams Cum 1 0.24

Concrete In RCC Slab & Beams Cum 1 0.16

Concrete In Staicase / Chajjas / Counter Slabs Cum 1 0.30

Concrete In Staicase / Chajjas / Counter Slabs Cum 1 0.30

Concrete Pump Capacity Per Hour Cum 25

Conventional Plywood Shuttering Works - Shuttering Making, Fabrication, Shifting & Erection & Deshutt
Foundation Shuttering Sqm 1 0.10

Rectangular Column, Pedestal Shuttering Sqm 1 0.18

Retaining / RCC Walls Sqm 1 0.22

Beam & Slab Shuttering Sqm 1 0.13

Lintal & RCC Band, Counter Shuttering Sqm 1 0.25

Reinforcement Steel Works


Reinforcement Steel Works MT 1 6.00

Masonary Works - Including, Mixing of Mortar, Shifting of Materials, Scaffolding & Curing
Brick Work 230mm Thick Walls (650 to 700 Bricks/ Per Mason) Cum 1 0.72
Brick Work 230mm Thick Walls (530 to 550 Bricks/ Per Mason) Cum 1 0.94

Half Brick Work 115mm Thick (625 to 650 Bricks / Per Mason) Sqm 1 0.09

Half Brick Work 115mm Thick (470 to 500 Bricks / Per Mason) Sqm 1 0.12

AAC Block 100mm Thick Sqm 1 0.07

AAC Block 150 / 230 / 300mm Thick Cum 1 0.62

Plastering Works - Including Scaffolding, Mixing & Curing


Internal Plaster Works 12-15mm Thick Sqm 1 0.08

Gypsum Plaster Works 12-15mm Thick Sqm 1 0.20

External Plaster Works in Two Coats 18-20mm Thick Sqm 1 0.12

External Plaster Works in Single Coats 18-20mm Thick Sqm 1 0.07

Ceiling Plaster 6-8mm Thick Sqm 1 0.06

Neat Cement Punning @ 4.4 Kg / Sqm Sqm 1 0.03

Flooring Works
Concrete Flooring Works

Concrete Flooring Works / IPS Flooring (40-50mm Thick) Sqm 0.09

Concrete Pavement in Road Work Cum 0.45

Concrete Pavement in Road Work (Through Concrete Pump) Cum 0.45

Tile Flooring Works


Tile Flooring - 15-20mm Thick Mortar Sqm 0.20

Tile Cladding with 12mm Thick Mortar Sqm 0.25

Tile Skiriting with 12mm Thick Mortar Rmt 0.033

Tile Flooring in Staircase Riser & Treads - Cutting & Fixing Sqm 0.25

Tile Flooring - 15-20mm Thick Mortar Sqm 0.30

Tile Cladding with 12mm Thick Mortar Sqm 0.35


18-20mm Thick Stone - Granite/ Kota / Indian / Italian./ Imported Marble
Flooring

Stone Flooring - Cutting & Fixing Sqm 0.12


Polishing & Rubbing Sqm

18-20mm Thick Stone - Granite/ Kota / Indian / Italian./ Imported Marble


Flooring
Stone Flooring - Cutting & Fixing Sqm 0.175

Polishing & Rubbing Sqm

Stone Flooring in Staircase Riser & Treads - Cutting & Fixing Sqm 0.195

Polishing & Rubbing Sqm

Kota Stone Flooring in Staircase Steps & Risers- Cutting & Fixing Sqm 0.30

Polishing & Rubbing Sqm


18-20mm Thick Stone - Granite/ Kota / Indian / Italian / Imported Marble
Flooring

Stone Flooring - Cutting & Fixing Sqm 0.12

Polishing & Rubbing Sqm

Laminate Wooden Flooring (Normal) Sqm 0.10


Laminate Wooden Flooring (Harringbone Pattern) Sqm 0.30

Painting & Finishing Works - Including Surface Prepration & Scaffolding (Note for Old Surfaces Painting
1mm Thick - Birla Putty Sqm 0.045

Internal Finishings
White Wash / Colour Washing Works - Two Coats Sqm 0.030

Distempering on Walls including Priming Coat Sqm 0.080

OBD Paint on Walls including Priming Coat Sqm 0.054


Acrylic / Plastic Emulsion Interior Paint on Walls including Priming Coat Sqm 0.060

External Finishings
Exterior Texture / Weather Shield Paint including Priming Coats Sqm 0.060

Painting on Wood & MS Steel Sufaces


Painting of Wood Surfaces with Primer Sqm 0.085

Synthetic Enamel Paint of MS Plain Surfaces with Primer Sqm 0.066

Polishing on Wood Sufaces


French Spirit Polish Sqm 0.350

Melamine Polish Sqm 0.035

Wax Polish Sqm 0.080

Water Proofing Treatments Works


Tapecrete / Polymer Based Water Proofing in Toilet / Kitchen & Wet Areas Sqm 0.220
Water Proofing Treatment Over Roof Sqm 0.300
CIENTS IN CONSTRUCTION WORKS
Beldar / Mazdoor /
Remarks
Helper / Bhisti

1 Loading & Unloading Both Sides

2 2 Hydra Full Day

0.96 Foundation

0.63 Trench

0.30 Upto 50 Meter Lead / Normal Filling

1.00 Trench & Foundation Works

0.03 Foundation / Hour

1.00 Trench / Hour

3.13 By Hand Mix

2.54 By Plant / Mixer Machine

2.90 By Mixer Machine & Manually Placing

0.73 By Batching Plant Through Pump


0.36 By Batching Plant Through Pump

4.11 By Mixer Machine & Manually

1.36 By Plant / Mixer Machine by Tower Crane

3.40 By Mixer Machine & Manually Placing

1.12 By Batching Plant Through Pump

5.41 By Mixer Machine

3.03 By Batching Plant Through Pump

1 Concrete Pump with 2 Transit Mixer

ng & Erection & Deshuttering


0.15

0.30

0.38 Slab Height upto 3600mm

0.23

2.25

8.00

& Curing
1.78 Upto Plinth Level
3.34 Super Structure Works Above Plinth Level

0.25 Upto Plinth Level

0.42 Super Structure Works Above Plinth Level

0.29 Super Structure Works Above Plinth Level

1.75 Super Structure Works Above Plinth Level

0.26 Internal Walls upto 3600mm Height

0.12 Internal Walls upto 3600mm Height

10% Labour for additional floors for Scaffolding


0.34

10% Labour for additional floors for Scaffolding


0.18

0.17 Ceiling Height upto 3600mm Lvl.

0.03 In Drains & Wall Dados

0.25

2.56 (Mixing with Mixer & Placed Manually)

1.28 (Mixing with Plant & Placed with Concrete Pump)


0.38

0.43
Without Grouting (Joint to Joint Finish)
0.04

0.43

0.48
With 3mm Spacer with Epoxy Grout in Groove Filling
0.53

Normal Plain Flooring


0.38
0.50

0.41 Pattern Flooring

0.50

0.40

0.70

0.58

0.70

0.38

0.50

0.15 Shifting, Cutting & Installation


0.15 Shifting, Cutting & Installation

53.82 53.82
or Old Surfaces Painting Factors are 50% Applicable) 550 350

0.045 Min. Two Coats 0.097855 0.153771

0.010 Min. Two Coats

0.040 Min. Two Coats

0.050 Min. Two Coats


0.054 Min. Two Coats

0.035 Min. Two Coats

0.060 Min. Two Coats

0.066 Min. Two Coats

0.100 Single Coat

0.035 Single Coat

0.080 Min. Two Coats

0.250 With Two Layer Coating with Mortar Protection


0.150 With Two Layer Coating with Concrete Protection