January-2024

MONTHLY REVIEW SHEET


Payment
Sr. Length of Physical Project cost of EPC Till date payment Total nos. of Nos. of closed
Project Name Coordinator Sub - Coordinator recommend till date Consultancy Fees Status of EOT (if any) Critical pending Issues
No. Project (km) Progress (%) Contractor (In Cr.) received of AE NCR NCR
of EPC Contractor

1 Rampachodavaram- Koyyuru Viki Patel Hinal Patel 70.12 50.68% 304.60 1497427771.00 48232718 13385153

2 Madanapalle Ashish Phanse Hemal Prajapati 40.460 4.53% 332.11 1,66,65,79,919.00 5,16,57,502.00 1,47,57,977.30 1 1 - -

3 Tadipatri Viki Patel Krupali Rathod 51.119 36.68% 4,24,99,00,000.00 1,34,98,80,395.00 5,61,29,734.00 79,12,041.00 11 1 _

4 Mudigubba Ashish Phanse Hemal Prajapati 33.00 7.05% 270.00 1,40,95,39,724.00 4,87,07,600.00 1,30,59,271.00 Nill Nill - -

5 Papgini Viki Patel Hani Patel 1.81 65.93% 54.51 333804628.67 1,22,30,360 9065465.58 1 0 - -

6 Raychoti Viki Patel Hinal Patel 53.59 24.01% 241.68 2416899240.00 49263100 18536389 6 4

7 Madhugiri Viki Patel Hani Patel 51.5 22.25% 235.00 417489225.51 6,87,69,180 0 2 0 - -

8 Kadiri bypass Ashish Phanse Bindiya Jagtap 1,40,07,182.00 _ _ Pending (EPC Contractor)

9 Andhra Pradesh ROB (LC - 119) Viki Patel Hinal Patel 1.2 Yet not started - - 99,34,000 - - - - -

10 Arunachal pradesh Viki Patel Hani Patel 35.26 40.55% 297.00 1096740500.16 7,32,39,520 3,50,69,676.35 2 0 EoT up to 04.02.2024 -

11 Assam Sunetra dutta Jeel Soni 30 Completed. 192.31 21505200 + (EOT) 2,39,68,205.00 - - - -

12 Purnia (Bihar) Sunetra dutta Jeel Soni 49 89.98% 1905.00 5,46,16,750.00 1,95,26,060.00 - - - -

13 Mindhola River Bridge Vijayant singh Darshna Gosai 0.74 0% 197.88 (Bridge) 0.00 5,13,58,896.00 0 Nill Nill -

14 NHAI Surat (Abhava-Khajod) Vijayant singh Darshna Gosai 3.4 10.51% 42.67 4,08,76,228.00 91,77,043 (without Nill Nill Pending (EPC Contractor) Pending utility shifting work
1,02,81,343 (with EOT)
15 NHAI Surat (Budhiya-Gabheni) Vijayant singh Darshna Gosai 3.18 21.84% 39.07 8,01,03,745.00 EOT) 2 2 Pending (EPC Contractor)

16 Una-kodinar - Package -4 Aliakbar Lokhandwala Rutvi Vora 40.98 95.82% 555.00 0 0

17 Una-kodinar - Package -5 Aliakbar Lokhandwala Rutvi Vora 40.95 86.44% 623.00 32 15


6,63,22,728.00 1,99,79,217.00
18 Una-kodinar - Package -6A Aliakbar Lokhandwala Rutvi Vora 7.6 76.86% 158.20

19 Una-kodinar - Package -6B Aliakbar Lokhandwala Rutvi Vora 33.18 74.22% 670.00

20 Aslali Aditya Pancholi Hani Patel 5.5 0.00% 41.46 0.00 75,05,036 36,31,281 - - approval pending -
(i)Issues with irrigation
21 Gadu porbandar Aditya Pancholi Bindiya Jagtap 1,50,94,877 1 1 Approved
division for approval of design
22 Pathankot Vijayant singh Mansi Shah 16.275 Yet not started - - 6,96,28,850.00 44,86,506.00 - - -

23 Dholera Krunal Patel Dhruv Patel 37.959 55.21% 942.67 Cr. 0.52 7,75,11,802.00 34 34 EOT Approved

24 Rajouri (J &K) Vijayant singh Mansi Shah 55.52 48.04 284.21 1302986338.00 7,71,01,840.00 4,29,89,149.00 4 4 -

25 Vijayapura - Sankeshwar Sunetra dutta Jeel Soni 79.77 50.03% 504.00 1066060528.00 3,91,35,850.00 1,43,99,084.00 29 21 - -
Approval of EOT-IV
26 Manipur-1A Krunal Patel Krupali Rathod 22.34 39.01% 1,51,14,70,000.00 529652113.70 3 3
pending from Authority
10,79,97,974.86
Approval of EOT-III
27 Manipur-1B Krunal Patel Krupali Rathod 17.66 73.34% 1,28,54,55,000.00 90,54,11,661.65 7,87,46,474.11 5 4
pending from Authority
Approval of EOT-III
29 Manipur-2B Krunal Patel Krupali Rathod 18.16 97.02% 1,45,86,85,000.00 1388313186.19 0 0
pending from Authority
Approval of EOT-IV
30 Nagaland -PKG-1 Krunal Patel Ashutosh Tripathi 21.72 94.95% 193.79 1,82,21,16,689.10 18 18 Tests on Completion (Sch-K)
awaited from Authority
31 Nagaland -PKG-2 Krunal Patel Ashutosh Tripathi 21.90 Terminated 202.00 75,17,96,490.95 10,77,46,208.00 10,45,31,755.00 - - N.A
A.E Extension of Time approval
Contractor submission due from authority
32 Nagaland -PKG-3 Krunal Patel Ashutosh Tripathi 22.70 73.27% 206.26 1,44,97,75,107.00 12 6
pending
33 Jalore - Rajasthan Vijayant singh Mansi Shah 41.115 31.20% 277.48 846261382.00 6,66,53,082.34 1,90,36,621.00 24 5

34 Barmer- Rajasthan ( Road ) Vijayant singh Mansi Shah 68.938 78.71% 173.05 1362523715.00 4 -

35 Barmer- Rajasthan ( ROB -LC-328-Barmer) Vijayant singh Mansi Shah 1.86 78.71% 39.91 284707410.00 7,17,07,941.00 1,34,11,318.00 1 -

36 Barmer- Rajasthan ( ROB -Jalore ) Vijayant singh Mansi Shah 2.044 76.03% 55.11 413001185.00 - -

37 Nathdhwara Dhaval Mistry Hemal Prajapati 88.8 0.39 411.04 Nill 6,97,62,205.00 Nill Nill Nill Nill