Weekly Report - Week 6

You might also like

Download as pdf or txt
Download as pdf or txt
You are on page 1of 2

T.Y.

LIN INTERNATIONAL SDN BHD Form TYL/IF10


Sheet No: 1 of 2
TO: Kiaramas Development Sdn Bhd

cc : T.Y.Lin (HQ) & Urusreka Architect

WEEKLY SITE REPORT

CONTRACT PERIOD : 36 weeks


PROJECT:
Kiaramas deDaun (P1196-P5) COMMENCEMENT DATE : 3.1.2022

CONTRACTOR: COMPLETION DATE : 10.9.2022


CONSTRUCTION WEEK NO: DATE
Pintaras
6 FROM: 7.2.2022
TO: 12.2.2022
WORK FORCE / PLANT & EQUIPMENT PLANT & MATERIALS
DAY M T W T F S S ON SITE SHORTAGES
ENGINEER
SURVEYOR
CARPENTER
STEELFIXER
CONCRETOR
LABOURER 1
OTHERS - SI WORKERS 3 3 3 3 3
PROJECT MANAGER 1 1 1 1 1 1
SUPERVISOR
CHAINMAN
SITE SAFETY SUPERVISOR 1 1 1 1 1 1

OPERATORS
CRANE 1 1 1 1 1
BACKHOE
BULLDOZER
SI MACHINE 1 1 1 1 1

WEATHER Reasons For delay


TOTAL HOURS OF RAIN
DELAY (HRS) DUE TO RAIN
DELAY (HRS) - OTHERS

STATUS ON MATERIAL TESTING

SAFETY ISSUE

Rev.: 4 Effective Date: 1 February 2009


T.Y.LIN INTERNATIONAL SDN BHD Form TYL/IF10
Sheet No: 2 of 2
REPORT ON WORK IN HAND AND PROGRESS

MONDAY: SI work for NBH-2

TUESDAY: Move SI machine to NBH-3

WEDNESDAY: SI work for NBH-3


Deliver air compressor, welding set & tsunami pump

THURSDAY: SI work for NBH-4


Concrete trial mix at strong mix concrete Sdn Bhd

FRIDAY: Complete SI work for NBH-4

SATURDAY: Cleaning Kiaramas site office

SUNDAY: Sunday

Site
Memo Description Drawing Received Source

Prepared By : Verified By :
Name : Hakiman / Lam Kok Wai Name : Ir. Lam Kok Wai
Signature : Signature :
Date : 14.2.22 Date : 14.2.22