DEPARTMENT OF ECONOMICS
Course Code and Title: ECN 421: Quantitative Methods
TUTORIALS SHEET 1
PROJECT 1
Activities A B C D E F
Preceding Activity ----- A B,D --- C E
Duration 5 5 5 15 10 5
PROJECT 2
EXERCISE 2.
The precedence relationships for the activities of a project are given below:
Activities A B C D E F G H I
Preceding -------- -------- ------- A A B,D B,D C,F E
Activity
Time 4 6 12 5 14 10 6 15 10
1. Present the network for this project showing their earliest start times and finished times
2. Identify the critical path using three different method
EXERCISE 3: The two project schedule A and B has the following characteristics
Activities 1-2 1-3 2-4 3-4 3-5 4-9 5-6 5-7 6-8 7-8 8-10 9-
10
Time (in 4 1 1 1 6 5 4 8 1 2 5 7
weeks)
Activities 0-1 1-2 1-3 2-4 2-5 3-4 3-6 4-7 5-7 6-7
Time (in 4 1 1 1 6 5 4 8 1 2
weeks)