Professional Documents
Culture Documents
A Case Study On Behaviors of Composite Soil Nailed Wall With Bored Piles in A Deep Excavation
A Case Study On Behaviors of Composite Soil Nailed Wall With Bored Piles in A Deep Excavation
A Case Study On Behaviors of Composite Soil Nailed Wall With Bored Piles in A Deep Excavation
Abstract: A complete case of a deep excavation was explored. According to the practical working conditions, a 3D non-linear finite
element procedure is used to simulate a deep excavation supported by the composite soil nailed wall with bored piles in soft soil. The
modified cam clay model is employed as the constitutive relationship of the soil in the numerical simulation. Results from the
numerical analysis are fitted well with the field data, which indicate that the research approach used is reliable. Based on the field
data and numerical results of the deep excavation supported by four different patterns of the composite soil nailed wall, the
significant corner effect is founded in the 3D deep excavation. If bored piles or soil anchors are considered in the composite soil
nailed wall, they are beneficial to decreasing deformations and internal forces of bored piles, cement mixing piles, soil anchors, soil
nailings and soil around the deep excavation. Besides, the effects due to bored piles are more significant than those deduced from soil
anchors. All mentioned above prove that the composite soil nailed wall with bored piles is feasible in the deep excavation.
Key words: deep excavation; 3D non-linear finite element; bored pile; composite soil nailed wall; corner effect; deformation;
internal force
Fig. 1 Layout of composite soil nailed wall with bored piles (Unit: mm): (a) Graphic design; (b) Elevation design
Foundation item: Project(2009-K3-2) supported by the Ministry of Housing and Urban-Rural Development of China
Received date: 2012−09−10; Accepted date: 2013−04−10
Corresponding author: ZHU Feng-bin, PhD Candidate; E-mail: zfb_njfu@hotmail.com
2018 J. Cent. South Univ. (2013) 20: 2017−2024
practical deep excavation, and the stability of the deep depicted in Fig. 1. The triaxial cement mixing pile whose
excavation was also analyzed [1−2]. diameter, overlap distance and length are 650 mm,
2) Laboratory model tests were utilized to simulate 150 mm and 19 m, respectively, is used as the waterproof
the actual working conditions in a deep excavation and curtain in the deep excavation. The length of nine layers
research the mechanism of the composite soil nailed wall of the soil nailing which are made from a 22 mm
[3]. Besides, a number of laboratory pull-out tests were diameter steel bar differs from 11 m to 17 m. The upper
conducted by different researchers to investigate factors soil anchor made from a 36 mm diameter steel bar has a
that influence the nail/soil interface shear resistance length of 28 m, while the lower soil anchor made from
[4−6]. two 32 mm diameter steel bars has a length of 30 m.
3) The numerical method was employed to simulate Besides, two bored piles whose length and spacing are
the composite soil nailed wall and the excavation process 23 m and 2 m, respectively, are disposed in front of the
according to some actual cases. 3D FEM was taken to cement mixing pile in the calculation unit. The thickness
investigate soil displacements and internal forces of of the shotcrete surface layer is 100 mm.
components in the soil nailed wall [7−10]. Finite
difference method was performed to promote the design 3 Numerical model
and construction of the soil nailed wall in practice
[11−12]. Moreover, the plane finite element method was 3.1 Model size and boundary condition
also employed to investigate the behaviors of composite Due to the symmetry of the deep excavation, the
soil nailed wall [13−14]. numerical model only takes the quarter size in northwest
In summary, the finite element method mentioned into account, and the excavation depth here is 11.65 m.
above can not only consider soil heterogeneity and The practical length of the calculation unit of the
anisotropy, and interaction between components in the composite soil nailed wall with bored piles is about
composite soil nailed wall and surrounding soil, but also 8.6 m, so the excavation length and width are considered
simulate actual working conditions in deep excavation. as five (43 m) and ten (86 m) units, respectively, in the
The 3D FEM is used here to simulate a deep excavation numerical model. In order to eliminate the boundary
supported by the composite soil nailed wall with bored effect in the numerical analysis, the soil extends 6, 4, and
piles based on actual working conditions. Internal forces 2 times of the excavation depth out of the deep
and deformations of different components in the excavation in X, Y and Z directions, respectively. So, the
retaining structure calculated from the FEM are length, width and depth of the model presented in Fig. 2
compared with the field data to calibrate the method are 160 m, 90 m and 35 m, respectively.
employed in this work. Then, behaviors and differences
between the composite soil nailed wall with bored piles
and the composite soil nailed without bored piles or soil
anchors are compared so as to investigate the mechanism
of the composite soil nailed wall with bored piles.
Fig. 7 Horizontal displacements of soil behind cement mixing pile lied in X direction ((1) First pattern of composite soil nailed wall;
(2) Second pattern of composite soil nailed wall; (3) Third pattern of composite soil nailed wall; (4) Fourth pattern of composite soil
nailed wall): (a) 5.3 m from symmetry plane B; (b) 39.7 m from symmetry plane B
J. Cent. South Univ. (2013) 20: 2017−2024 2023
Fig. 8 Ground surface settlement and excavation bottom heave distance from symmetry plane B ((1) First pattern of composite soil
nailed wall; (2) Second pattern of composite soil nailed wall; (3) Third pattern of composite soil nailed wall; (4) Fourth pattern of
composite soil nailed wall): (a) Settlement; (b) Heave
Fig. 9 Stress contour of soil anchors and soil nailings: (a) Soil anchors; (b) Soil nailings
Whether soil anchors and bored piles are added in lack of soil anchors or bored piles, and the increasing
the composite soil nailed wall or not, the influence on range due to the lack of bored piles is larger.
axial forces of the soil anchor and soil nailing both Compared with axial forces of the soil nailing in the
disposed at the excavation corner is not significant, but first pattern of the composite soil nailed wall with bored
axial forces of the soil nailing located near the piles, axial forces of the soil nailing in the third pattern
excavation mid-span increase obviously because of the of the composite soil nailed wall located near the
excavation mid-span in X and Y directions increase by
Table 6 Axial force of soil anchors (kN) 14.78% and 16.04%, respectively. However, axial forces
Pattern of Distance from symmetry Distance from of the soil nailing in the second pattern of the composite
composite plane B/m symmetry plane A/m soil nailed wall without bored piles located near the
soil nailed excavation mid-span in X and Y directions increase by
6.05 36.95 6.05 79.95
wall 9.38% and 9.73%, respectively, compared with axial
First pattern 40.27 18.47 41.26 18.72 forces deduced from the first pattern.
Third
46.69 19.19 48.28 19.34
pattern 6 Conclusions
Table 7 Axial force of soil nails (kN) 1) The numerical and measured results both indicate
Pattern of Distance from Distance from that the corner effect which has an obvious restriction to
composite soil Symmetry plane B/m symmetry plane A/m the deformation and internal force of the bored pile,
nailed wall 4.8 38.2 4.8 81.2 cement mixing pile, soil anchor, soil nailing and soil
First pattern 24.83 9.81 24.56 9.73 located near the excavation corner appears in the three
Second pattern 27.16 10.41 26.95 10.34 dimensional deep excavation supported by the composite
soil nailed wall with bored piles.
Third pattern 28.50 10.19 28.50 10.05
2) Due to the deep excavation, the maximum axial
Fourth pattern 31.43 10.88 31.52 10.74
force and shear of the bored pile locate near the
2024 J. Cent. South Univ. (2013) 20: 2017−2024
excavation depth. So, the foundation slab should be Mechanics and Engineering, 2004, 23(15): 2585−2592. (in Chinese)
constructed after the completion of the deep excavation. [4] PRADHAN B, YUE Z Q, THAM L G, LEE C F. Laboratory study
of soil nail pullout strength in loosely compacted silty and gravelly
3) The maximum horizontal displacement of the
sand fills [C]// 12th Panamerican Conf on Soil Mechanics and
cement mixing pile and soil inside the area reinforced by Geotechnical Engineering, 39th US Rock Mechanics Symp.
soil nailings and soil anchors and the maximum axial Germany: Verlag Gluckauf Essen, 2003: 2139−2146.
force of the soil anchor and soil nailing all locate at the [5] YIN J H, SU L J. An innovative laboratory box for testing nail
upper part of the deep excavation, while the maximum pull-out resistance in soil [J]. ASTM Geotech Test J, 2006, 29(6):
1−11.
horizontal displacement outside the reinforced area
[6] SU L J, TERENCE C, CHAN F, YIN J H, SHIU Y K, CHIU S L.
locates at the ground surface and its distribution is of a Influence of overburden pressure on soil–nail pullout resistance in a
cantilever type. compacted fill [J]. ASCE J Geotech Geoenviron Eng, 2008, 134(9):
4) Soil anchors and bored piles added in the 1339−47.
composite soil nailed wall can both reduce internal [7] SIMTH I M. Three-dimensional analysis of reinforced and nailed soil
forces of the bored pile, horizontal displacements of the [C]// Proceedings of the International Symposium on Numerical
Models in Geomechancis. Rotterdam: Balkema, 1992: 829−838.
cement mixing pile and soil behind the cement mixing
[8] SMITH I M, SU N. Three-dimensional FE analysis of a nailed soil
pile, settlements of the soil surrounding the deep wall curved in plan [J]. International Journal for Numerical and
excavation and axial forces of the soil anchor and soil Analytical methods in Geomechanics, 1997, 21: 583−597.
nailing, while their effects on the bottom heave are not [9] HU M Y, PENG K S, PAN X D. Study on numerical simulation of
significant. Moreover, the effect of bored piles added in composite soil nailed wall [J]. Rock and Soil Mechanics, 2008, 29(8):
2131−2136. (in Chinese)
the composite soil nailed wall is greater than that in soil
[10] FAN C C, LUO J H. Numerical study on the optimum layout of soil
anchors. These all indicate that the composite soil nailed nailed slopes [J]. Comput Geotech, 2008, 35(4): 585−599.
wall with bored piles used as the retaining structure in [11] SIVAKUMAR BABU G L, MURTHY B R S, SRINIVAS A.
the deep excavation is reasonable and effective. Analysis of construction factors influencing the behavior of soil
nailed earth retaining walls [J]. Ground Improv, 2002, 6(3):
137−143.
References
[12] LIU J G, ZENG Y W. Application of FLAC3D to simulation of
foundation excavation and support [J]. Rock and Soil Mechanics,
[1] YANG Z Y, CAI Q L. Study on composite soil nailing mode and 2006, 27(3): 505−508. (in Chinese)
monitoring test of soil-nail stress [J]. Building Construction, 2001, [13] SONG E X, QIU Y. Finite element analysis of composite soil nailing
23(6): 427−430. (in Chinese) for excavation support [J]. Rock and Soil Mechanics, 2001, 22(3):
[2] WU Z C, TANG L S, LIU X G. Study on large-scale in-situ test on 241−244. (in Chinese)
compound soil nailing wall and deformation property analysis [J]. [14] SIVAKUMAR BABU G L. 2D Numerical simulations of soil nail
Chinese Journal of Rock Mechanics and Engineering, 2007, 26(S1): walls [J]. Geotech Geol Eng, 2010, 28: 299−309.
2974−2980. (in Chinese)
(Edited by YANG Bing)
[3] SUN T C, ZHANG M J, YANG Q. Modeling study on composite
soil nailing for deep excavation [J]. Chinese Journal of Rock