ID Task Task Name Duration Start Finish Successors Predecessors Resource Cost

Mode Names Sep '23 Oct '23 Nov '23 Dec '23 Jan '24 Feb '24 Mar '24
11 18 25 2 9 16 23 30 6 13 20 27 4 11 18 25 1 8 15 22 29 5 12 19 26 4 11 18
1 Construction of G+1 84 days 9/25/2023 2/15/2024 PM ₹258,882.00
Building
2 surve & Lineout 1 day 9/25/2023 9/26/2023 4 Labours,Site engg₹2,100.00 Labours,Site engg
3 Sub Structure 22 days 9/26/2023 11/2/2023 ₹50,040.00
4 Excavation 5 days 9/26/2023 10/4/2023 5 2 JCB[1],Labours ₹10,000.00 JCB[1],Labours
5 Earth Shoring 2 days 10/5/2023 10/9/2023 6 4 Formwork[1],Labours
₹3,750.00 Formwork[1],Labours
6 PCC of foundation 1 day 10/9/2023 10/10/2023 7 5 Cement[1],Sand [1]
₹1,690.00 Cement[1],Sand [1]
7 RCC for Foundation 3 days 10/11/2023 10/14/2023 8 6 Labours,M 25 [1],Site engg,Steel [1],Vibrator[1] Labours,M 25 [1],Site engg,Steel [1],Vibrator[1]
₹11,800.00
8 Shuttering 2 days 10/16/2023 10/18/2023 9 7 Formwork[1] ₹150.00 Formwork[1]
9 Pouring concrete CF 1 day 10/18/2023 10/19/2023 10 8 Labours,Vibrator[1],Site
₹2,800.00 Labours,Vibrator[1],Site engg
engg
10 Removal of 2 days 10/20/2023 10/24/2023 11 9 Labours ₹3,600.00 Labours
shuttering
11 Column upto plinh 1 day 10/24/2023 10/25/2023 12 10 Formwork[1],Labours,Site
₹2,250.00
engg Formwork[1],Labours,Site engg
12 plinth beam 2 days 10/26/2023 10/28/2023 13 11 Formwork[1],Labours,Site
₹4,350.00 Formwork[1],Labours,Site engg
Shuttering engg
13 PB reinforcement 2 days 10/28/2023 11/1/2023 14 12 Labours,Steel [1] ₹7,600.00 Labours,Steel [1]
14 PB concreting 1 day 11/1/2023 11/2/2023 15 13 CA[1],Formwork[1],M
₹2,050.00
25 [1],Site engg CA[1],Formwork[1],M 25 [1],Site engg
15 Complection of Sub 0 days 11/2/2023 11/2/2023 17 14 ₹0.00 11/2
structure
16 Super structure 39 days 11/2/2023 1/9/2024 ₹85,496.00
17 Column Extension 2 days 11/2/2023 11/7/2023 18 15 Steel [1] ₹4,000.00 Steel [1]
18 Column reinf 2 days 11/7/2023 11/9/2023 19 17 Labours,Site engg,Steel
₹8,200.00
[1] Labours,Site engg,Steel [1]
19 Shuttering 2 days 11/10/2023 11/13/2023 20 18 Formwork[1],Labours,Site
₹4,350.00engg Formwork[1],Labours,Site engg
20 concreting 1 day 11/13/2023 11/14/2023 21 19 M 25 [1],Site engg₹1,100.00 M 25 [1],Site engg
21 Beam & Slab 5 days 11/15/2023 11/23/2023 22 20 Formwork[1],Labours
₹9,150.00 Formwork[1],Labours
shuttering
22 Bar Bending 3 days 11/23/2023 11/28/2023 23 21 Labours,Site engg,Steel
₹10,300.00
[1] Labours,Site engg,Steel [1]
23 Placing of Reinf 3 days 11/28/2023 12/4/2023 24 22 Labours ₹5,400.00 Labours
24 Checking 1 day 12/4/2023 12/5/2023 25 23 PM,Site engg ₹800.00 PM,Site engg
25 Casting 1 day 12/6/2023 12/7/2023 26,31 24 M 25 [1],Site engg₹1,100.00 M 25 [1],Site engg
26 Brick masonr 10 days 12/7/2023 12/23/2023 27 25 bricks[1],Labours,Site
₹21,006.00
engg bricks[1],Labours,Site engg
27 electrical Pipings 2 days 12/23/2023 12/28/2023 28 26 Labours,Site engg₹4,200.00 Labours,Site engg
28 Plastering 5 days 12/28/2023 1/4/2024 29 27 Cement[1],Labours,Sand
₹10,690.00[1] Cement[1],Labours,Sand [1]
29 Fixing Doors & 2 days 1/5/2024 1/9/2024 28 Labours,PM,Site ₹5,200.00 Labours,PM,Site engg
Windows engg
30 First Floor 41 days 12/7/2023 2/15/2024 ₹79,246.00
31 Column Extension 2 days 12/7/2023 12/9/2023 32 25 Formwork[1],Labours,Steel
₹7,750.00[1] Formwork[1],Labours,Steel [1]
32 Column Reinf 2 days 12/11/2023 12/13/2023 33 31 Site engg ₹600.00 Site engg
33 Column shuttering 3 days 12/13/2023 12/19/2023 34 32 Formwork[1],Steel₹4,150.00
[1] Formwork[1],Steel [1]
34 Concrete placing 1 day 12/19/2023 12/20/2023 35 33 M 25 [1] ₹800.00 M 25 [1]

Task Project Summary Manual Task Start-only Deadline

Project: EXAM G+1 Split Inactive Task Duration-only Finish-only Progress


Date: 9/29/2023 Milestone Inactive Milestone Manual Summary Rollup External Tasks Manual Progress

Summary Inactive Summary Manual Summary External Milestone

Page 1
ID Task Task Name Duration Start Finish Successors Predecessors Resource Cost
Mode Names Sep '23 Oct '23 Nov '23 Dec '23 Jan '24 Feb '24 Mar '24
11 18 25 2 9 16 23 30 6 13 20 27 4 11 18 25 1 8 15 22 29 5 12 19 26 4 11 18
35 Beam & Slab 5 days 12/21/2023 12/29/2023 36 34 Formwork[1],Labours
₹9,150.00 Formwork[1],Labours
shuttering
36 Bar Bending 3 days 12/29/2023 1/3/2024 37 35 Labours,Steel [1] ₹9,400.00 Labours,Steel [1]
37 placing of Reinforcment
2 days 1/3/2024 1/8/2024 38 36 Labours ₹3,600.00 Labours
38 checking 1 day 1/8/2024 1/9/2024 39 37 PM,Site engg ₹800.00 PM,Site engg
39 Casting 1 day 1/9/2024 1/10/2024 40 38 Labours,M 25 [1] ₹2,600.00 Labours,M 25 [1]
40 brick masonr 10 days 1/11/2024 1/29/2024 41 39 bricks[1],Labours₹18,006.00 bricks[1],Labours
41 Electrical Pipings 3 days 1/29/2024 2/2/2024 42 40 Labours,Site engg₹6,300.00 Labours,Site engg
42 plastering 5 days 2/2/2024 2/10/2024 43 41 Cement[1],Labours,Sand
₹10,690.00
[1] Cement[1],Labours,Sand [1]
43 Fixing Doors & 3 days 2/12/2024 2/15/2024 42 Labours ₹5,400.00 Labours
Windows

Task Project Summary Manual Task Start-only Deadline

Project: EXAM G+1 Split Inactive Task Duration-only Finish-only Progress


Date: 9/29/2023 Milestone Inactive Milestone Manual Summary Rollup External Tasks Manual Progress

Summary Inactive Summary Manual Summary External Milestone

Page 2
Apr '24 May '24 Jun '24 Jul '24 Aug '24 Sep '24 Oct '24 Nov '24 Dec '24 Jan '25 Feb '25 Mar '25 Apr '25 May '25 Jun '25
18 25 1 8 15 22 29 6 13 20 27 3 10 17 24 1 8 15 22 29 5 12 19 26 2 9 16 23 30 7 14 21 28 4 11 18 25 2 9 16 23 30 6 13 20 27 3 10 17 24 3 10 17 24 31 7 14 21 28 5 12 19 26

Task Project Summary Manual Task Start-only Deadline

Project: EXAM G+1 Split Inactive Task Duration-only Finish-only Progress


Date: 9/29/2023 Milestone Inactive Milestone Manual Summary Rollup External Tasks Manual Progress

Summary Inactive Summary Manual Summary External Milestone

Page 3
Apr '24 May '24 Jun '24 Jul '24 Aug '24 Sep '24 Oct '24 Nov '24 Dec '24 Jan '25 Feb '25 Mar '25 Apr '25 May '25 Jun '25
18 25 1 8 15 22 29 6 13 20 27 3 10 17 24 1 8 15 22 29 5 12 19 26 2 9 16 23 30 7 14 21 28 4 11 18 25 2 9 16 23 30 6 13 20 27 3 10 17 24 3 10 17 24 31 7 14 21 28 5 12 19 26

1],Labours,Sand [1]

Task Project Summary Manual Task Start-only Deadline

Project: EXAM G+1 Split Inactive Task Duration-only Finish-only Progress


Date: 9/29/2023 Milestone Inactive Milestone Manual Summary Rollup External Tasks Manual Progress

Summary Inactive Summary Manual Summary External Milestone