Jawab

Soal 1

Menghitung momen retak

- Hitung luas tulangan


252
𝐴𝑠1 = 𝐴𝑠5 = 3 × 𝜋 × = 1472,62 𝑚𝑚2
4
252
𝐴𝑠2 = 𝐴𝑠3 = 𝐴𝑠4 = 2 × 𝜋 × = 981,74 𝑚𝑚2
4
- Hitung nilai rasio modular (n)
𝐸𝑠 200000
𝑛= = = 7,77
𝐸𝑐 4700√30
- Menghitung nilai luas transformasi
(𝑛 − 1)𝐴𝑠1 = (𝑛 − 1)𝐴𝑠5 = 9969,63𝑚𝑚2
(𝑛 − 1)𝐴𝑠2 = (𝑛 − 1)𝐴𝑠3 = (𝑛 − 1)𝐴𝑠4 = 6646,43
- Menghitung nilai I gross
1
𝐼𝑔 𝑏𝑒𝑡𝑜𝑛 = × 300 × 7003 + (300 × 700)(0) = 85,75 × 108
12
𝐼𝑔 𝐴𝑠1 = 9969.63 × (350 − 50)2 = 8.97 × 108
𝐼𝑔 𝐴𝑠2 = 6646,43 × (350 − 200)2 = 1.49 × 108
𝐼𝑔 𝐴𝑠4 = 6646,43 × 1502 = 1.49 × 108
𝐼𝑔 𝐴𝑠5 = 9969.63 × (300)2 = 8.97 × 108

𝐼𝑔 = 𝐼𝑔 𝑏𝑒𝑡𝑜𝑛 + 𝐼𝑔 𝐴𝑠1 + 𝐼𝑔 𝐴𝑠2 + 𝐼𝑔 𝐴𝑠4 + 𝐼𝑔 𝐴𝑠5 = 106.67 × 108 Nmm3

- Menghitung I crack
Asumsi crack berada diantara As 2

(𝑛 − 1)𝐴𝑠1 = 9969.63 𝑚𝑚2


(𝑛 − 1)𝐴𝑠2 = 6646,43 𝑚𝑚2
𝑛𝐴𝑠3 = 7628.2 𝑚𝑚2
𝑛𝐴𝑠4 = 7628.2 𝑚𝑚2
𝑛𝐴𝑠5 = 11442.26 𝑚𝑚2
1
(300𝑐) × 𝑐 + 9969.63 (𝑐 − 50) + 6646.45(𝑐 − 200)
2
= 7628.2(350 − 𝑐) + 7628.2(500 − 𝑐) + 11442.26
𝑐 = 210.35 𝑚𝑚 (𝑎𝑠𝑢𝑚𝑠𝑖 𝑏𝑒𝑛𝑎𝑟)

1
𝐼𝑏 = × 300 × 210.353 + (210.35 × 300)(0.5 × 210.35)2 = 9.3 × 108
12
𝐼𝑔 𝐴𝑠1 = 9969.63 × (210.35 − 50)2 = 2.56 × 108
𝐼𝑔 𝐴𝑠2 = 6646,43 × (210.35 − 200)2 = 0.00711 × 108
𝐼𝑔 𝐴𝑠3 = 7628.2(350 − 210.35)2 = 1.48 × 108
𝐼𝑔 𝐴𝑠4 = 7628.2 × (500 − 210.35)2 = 6.4 × 108
𝐼𝑔 𝐴𝑠5 = 11442.26 × (650 − 210.35)2 = 22.11 × 108
𝐼𝑐𝑟 = 41.9 × 108 𝑁𝑚𝑚3
- Menghitung nilai fcr

𝑓𝑐𝑟 = 0.62√30
- Menghitung momen crack
𝐼𝑔𝑐
𝑀𝑐𝑟 = 𝑓𝑐𝑟 ×
𝐶𝑔
106.67 × 108
𝑀𝑐𝑟 = 0.62√30 × = 103.5 × 106 𝑁𝑚𝑚
350
Soal 3

Menghitung besar beban hidup

𝑀𝑎𝐷𝐿+𝐿𝐿 = 3.5 𝑀𝑐𝑟 = 362.25 × 106 𝑁𝑚𝑚


1
𝑀𝑎𝐷𝐿+𝐿𝐿 = 𝑞𝐷𝐿+𝐿𝐿 𝑙 2
2
𝑙 = 5500 𝑚𝑚
𝑞𝐷𝐿+𝐿𝐿 = 23.95 𝑁/𝑚𝑚
𝑞𝐷𝐿 = 𝑞𝐵𝑆 = (0.3 × 0.7)24 = 5.04 𝐾𝑁/𝑚
𝑞𝐷𝐿+𝐿𝐿 = 𝑞𝐷𝐿 + 𝑞𝐿𝐿
𝑞𝐿𝐿 = 23.95 − 5.04 = 18.91 𝐾𝑛/𝑚

Soal 2

Menghitung momen akibat beban hidup

𝑞𝐷𝐿+𝐿𝐿 = 𝑞𝐷𝐿 + 𝑞𝐿𝐿


𝑞𝐿𝐿 = 23.95 − 5.04 = 18.91 𝐾𝑛/𝑚
1 1
𝑀𝐿𝐿 = 𝑞𝐿𝐿 𝑙 2 = × 18.91 × 5.52 = 286.01 × 106 𝑁𝑚𝑚
2 2
Soal 4
Check apakah lendutan maksimum diujung bentang dengan memperhitungkan
rangkak dan susut maksimum, memenuhi syarat seviciability untuk lendutan beban
total danlendutan beban hidup saja. 𝛿 ijin LL= L/360 dan 𝛿 ijin total=L/240

- Menghitung Δ𝑡𝑜𝑡𝑎𝑙
𝐿 5500
∆𝑙𝑜𝑛𝑔 𝑡𝑒𝑟𝑚 ≤ ∆𝑡𝑜𝑡𝑎𝑙 = = = 22.91 𝑚𝑚
240 240
- Menghitung nilai Δ𝐿𝐿
𝐿 5500
∆𝐿𝐿 = = = 15.28 𝑚𝑚
360 360
- Menghitung nilai ∆𝐷𝐿+𝐿𝐿 𝐼𝑛𝑠𝑡𝑎𝑛𝑡
𝑞𝐷𝐿+𝐿𝐿 × 𝑙 4
∆𝐷𝐿+𝐿𝐿 𝐼𝑛𝑠𝑡𝑎𝑛𝑡 =
8𝐸𝐼𝑒𝑓𝑓
3
𝑀𝑐𝑟 𝑀𝑐𝑟 3
𝐼𝑒𝑓𝑓 =( ) × 𝐼𝑔 + (1 − ( ) ) × 𝐼𝑐𝑟
𝑀𝑎 𝑀𝑎
𝐼𝑔 = 106.67 × 108 𝑁𝑚𝑚3
𝑀𝑐𝑟 = 103.5 × 106 𝑁𝑚𝑚
𝑀𝑎 = 362.25 × 106 𝑁𝑚𝑚
𝐼𝑐𝑟 = 41.9 × 108 𝑁𝑚𝑚3
𝐼𝑒𝑓𝑓 = 204.12 × 108 𝑁𝑚𝑚3

23.95 × 5500
∆𝐷𝐿+𝐿𝐿 𝐼𝑛𝑠𝑡𝑎𝑛𝑡 = = 24.5 𝑚𝑚
8 × 4700√30(204.12 × 108 )
- Menghitung nilai ∆𝐿𝐿 𝐼𝑛𝑠𝑡𝑎𝑛𝑡

∆𝐿𝐿 𝐼𝑛𝑠𝑡𝑎𝑛𝑡 = ∆𝐷𝐿+𝐿𝐿 𝐼𝑛𝑠𝑡𝑎𝑛 − ∆𝐷𝐿 𝐼𝑛𝑠𝑡𝑎𝑛𝑡


𝑞𝐷𝐿 × 𝑙 4 5.04 × 55004
∆𝐷𝐿 𝐼𝑛𝑠𝑡𝑎𝑛𝑡 = = = 2.09 𝑚𝑚
8𝐸𝐼𝑒𝑓𝑓 8 × 4700√3(106.67 × 108 )
- Menghitung nilai ∆𝑙𝑜𝑛𝑔 𝑡𝑒𝑟𝑚

∆𝐿𝐿 𝐼𝑛𝑠𝑡𝑎𝑛𝑡 = 24.5 − 2.09 = 22.43 𝑚𝑚 > 15.28 𝑚𝑚


Tidak memenuhi
∆𝑙𝑜𝑛𝑔 𝑡𝑒𝑟𝑚 = ∆𝐷𝐿+𝐿𝐿 + 𝜆∆𝐷𝐿
∆𝑙𝑜𝑛𝑔 𝑡𝑒𝑟𝑚 = 22.43 + 2 × 2.09 = 28.68 > 22.91 𝑚𝑚
Tidak memenuhi

Soal 5

Check apakah tegangan beton maksimum, baja tekan, dan semua baja Tarik
memenuhi syarat serviceability

Untuk beton, tegangan harus lebih kecil dari 0.45(f’c)


𝑀𝑎− 𝑐 (362.25 × 106 )(210.35)
𝑓𝑐− = = = 18.18 𝑀𝑃𝑎
𝐼𝑐𝑟 41.9 × 108

Tidak Memenuhi

Untuk tegangan baja harus lebih kecil dari 200 MPa

Untuk As1

𝑀𝑎− (𝑐 − 50) (362.25 × 106 )(210.35 − 50)


𝑓𝑐−
= (𝑛 − 1) = 6.77 = 93.9 𝑀𝑃𝑎
𝐼𝑐𝑟 41.9 × 108
Memenuhi
Untuk As2

𝑀𝑎− (𝑐 − 200) (362.25 × 106 )(210.35 − 200)


𝑓𝑐− = (𝑛 − 1) = 6.77 = 6.06 𝑀𝑃𝑎
𝐼𝑐𝑟 41.9 × 108
Memenuhi
Untuk As3

𝑀𝑎− (𝑐 − 350) (362.25 × 106 )(210.35 − 350)


𝑓𝑐− = 𝑛 = 7.77 = 93.8 𝑀𝑃𝑎
𝐼𝑐𝑟 41.9 × 108
Memenuhi

Untuk As4

𝑀𝑎− (𝑐 − 500) (362.25 × 106 )(210.35 − 500)


𝑓𝑐−
=𝑛 = 7.77 = 195 𝑀𝑃𝑎
𝐼𝑐𝑟 41.9 × 108
Memenuhi
Untuk As5

𝑀𝑎− (𝑐 − 650) (362.25 × 106 )(210.35 − 650)


𝑓𝑐− = 𝑛 = 7.77 = 295 𝑀𝑃𝑎
𝐼𝑐𝑟 41.9 × 108
Tidak Memenuhi