We will perform a Pareto analysis for the project chosen at the beginning of the semester, which involves the
construction of a production and storage facility in Resita. This project is encountering difficulties in delivering
the expected results.
Number of
No. Identified problems Percentage
complaints
1 Unexpected additional costs 4 3%
2 Poor quality of work 28 20%
3 Inadequate communication 39 27%
4 Inefficient resource management 10 7%
5 Frequent changes in construction plans 5 3%
6 Delays in delivery deadlines 48 34%
7 Poor risk management 6 4%
8 Lack of expertise 3 2%
Total 143 100%
The diagram shows that where the cumulative graph undergoes a sudden change is the 80%
threshold. According to the Pareto chart we've made, we notice that problems 2, 3, and 6 are the
primary ones. By eliminating these three problems, which account for a total of 27%, we remove 80%
of the total problems encountered.