Drilling Costs
Mahmoud Radwan is a Subsurface & Integrity Op. Lead with more than 15
years of experience in oil & gas industry. Mahmoud worked in Well
Engineering, Intervention, Integrity & Work-over at several companies,
Short including AMAL Petroleum Co. (AMAPETCO), KDT Global Solutions, CUDD Well
Control, Badr El-Din Pet. Co. (BAPETCO), Qarun Pet. Co. (QPC) and Wadi El-
Biography Sahel Petroleum Co. (WASPETCO).
Also, a freelance instructor at upstream Oil & Gas in Egypt & GCC since 2008.
Mahmoud received a BSc degree in Petroleum Engineering from Al-Azhar
University in 2007.
o Evaluating Sustainable Annulus Pressure (SAP) in Sour Wells and the Possible
Causes to Avoid Recurrence to the Well Integrity Annual Middle East
Conference in Abu Dhabi; UAE in Apr 2015
o Implementing NDT methods for maintenance and inspection to the Asset
Integrity Management North Africa Conference in Cairo; Egypt in Nov 2015
o Feasibility Evaluation of Using Downhole Gas-water Separation Technology in
gas Reservoirs with Bottom Water; paper number: SPE-183739-MS to the 20th
Middle East Oil & Gas Show and Conference in Mar 2017
Publications http://dx.doi.org/10.2118/183739-MS
o Managing the Operational Challenges in Corroded Wells through Well Integrity
Management System to the Improving Brownfield Performance Technical
Convention, in Cairo; Egypt in Dec 2019
o Safe and Economic Attractive Rigless Operations Using a Digital Slickline in
Unmanned Platform with Low Structure Loads and Spacing; paper number:
SPE-202857-MS to the Abu Dhabi International Petroleum Exhibition &
Conference (ADIPEC) in Nov 2020 https://doi.org/10.2118/202857-MS
WELL COSTS
Well costs are expensive in today’s industry
and rise further as hole angle increases.
Risk
Rig cost
catering
£40,000
£1,000
day
day
60
60
£2,400,000
£60,000 Rig costs
Modifications £100,000 well £100,000
Conductor £200 foot 250 £50,000
13-3/8" casing £150 foot 2500 £375,000
9-5/8" casing
7" Liner
Conductor accessories
£50
£30
£2,000
foot
foot
well
8500
3500
£425,000
£105,000
£2,000
Drilling Hardware
13-3/8" casing accessories £4,000 well £4,000
9-5/8" casing accessories
7" Liner accessories
5" tubing
£4,000
£2,000
£50
well
well
foot 11500
£4,000
£2,000
£575,000
Tangible Costs
Tubing accessories £2,000 well £2,000
Downhole safety valve £50,000 well £50,000
Completion packers £30,000 well £30,000
Subsea Christmas trees
Nipples
£500,000
£10,000
well
well
£500,000
£10,000
Completion Hardware
Control line £5,000 well £5,000
Completion Crossovers etc £10,000 well £10,000
Mud Chemicals £50 foot 11500 £575,000
Cement and additives £30 foot 11500 £345,000
Electric Logging £30 foot 11500 £345,000
Perforating £100,000 well £100,000
Directional drilling and surveys £5,000 day 40 £200,000
Rock bits £80,000 well £80,000
PDC/Diamond bits £200,000 well £200,000
Drilling Consumables
Mud Engineers
Casing Crews
£1,000
£800
£2,000
day
day
day
40
60
20
£40,000
£48,000
£40,000
Intangible Costs
Cementers £800 day 60 £48,000
Mud Loggers £1,000 day 40 £40,000
MWD Engineers £5,000 day 20 £100,000
Fishing Services
Liner Hanger engineer
Filtration [completion phase]
£500
£1,000
£1,000
day
day
day
60
5
20
£30,000
£5,000
£20,000
Variable Costs; people and
Miscellaneous Drilling Rentals
Geology office services
Onshore office services
£2,000
£1,000
£5,000
day
day
day
60
60
60
£120,000
£60,000
£300,000
consumables…etc.
Drilling Supervision £1,000 day 60 £60,000
Wellhead serviceman £1,000 day 12 £12,000
Onshore materials man £300 day 60 £18,000
Cuttings ship to shore £5,000 day 60 £300,000
Packer crew personnel £1,000 day 6 £6,000
Completions Engineer £1,000 day 25 £25,000
Daily Transport Costs £5,000 day 60 £300,000
Standby Boat £3,000 day 60 £180,000
Total AFE Cost £8,306,000
Importance of Budgeting
Project Summary:
This AFE details the costs associated with planning and engineering 3 development 8 1/2" Sidetrack wells (BA-02-HST2,BA-03-HST2 and BA-04-HST2) running 4" expandable sand screens in the 6" horizontal sections. The 8 1/2" sidetrack and build to horizontaland with a 6"geosteered section, mobilizing / demobilizing the Jack-
up drilling unit and execution of the three well project.
Justification
Following the peer review held on the 8th and 9th March at Bangkok office, the decision was made to run a 4" ESS (Expandable Sand Screen) with a 230µ Screen into a 6" horizontal hole.
Budget Status
This AFE is part of the 2010 Production & Development Budget totalling USD 16,800k, which was presented at the August 2009 OCM.
The AFE for the horizontal Producer is estimated at USD 4,598k versus 5,200k estimated in the 2010 P&D budget.
The total AFE for the drilling phase 4 is estimated at USD 16,895k
TANGIBLE COSTS
INTANGIBLE COSTS
$ 4,569,527
Approvals
……………………………………. …………………………………….
Project Leader: Regional Operations Director
……………………………………. …………………………………….
Finance Manager:
……………………………………. …………………………………….
General Manager: Authorised Partner
Drilling Completion Total Days
– Examples;
• Stuck pipe
• Fishing