Professional Documents
Culture Documents
3-3-3. MOS Fire Alarm Equipment Installation
3-3-3. MOS Fire Alarm Equipment Installation
: ALF-M-MS-003
METHOD STATEMENT FOR Installation of Rev.: 01
Fire Alarm & Detection System Date: 10.03.2020
3. References
4. Responsibility
6. Procedure
7. Attachment
Page 1 of 4
CLASSIFICATION: INTERNAL
Quality Management System Ref No.: ALF-M-MS-003
METHOD STATEMENT FOR Installation of Rev.: 01
Fire Alarm & Detection System Date: 10.03.2020
3. Reference:
• NFPA 70 ( National Electrical Code )
• NFPA 72 ( National Fire Alarm Code )
• NFPA 75 ( Protection of Electronic Computer / Data Processing Equipment )
• NFPA 101 ( Life Safety Code )
• NFPA 251 ( Fire Endurance of Building Construction and Materials )
• NFPA 255 ( Surface Burning Characteristics of Building Materials )
4. Responsibilities:
Project Manager
• The Project Manager will be responsible for the implementation of Method of
Statement (MOS)
Site Manager
• The Site Manager will be responsible for the over-all supervision, monitoring,
coordination, and control of all the construction activities related to Fire Alarm
Equipment Installation.
Page 2 of 4
CLASSIFICATION: INTERNAL
Quality Management System Ref No.: ALF-M-MS-003
METHOD STATEMENT FOR Installation of Rev.: 01
Fire Alarm & Detection System Date: 10.03.2020
6. Procedure:
• Prior to commencement of installation of equipment’s and associated devices, the support
location(s) requirements shall be checked as per IFC drawing.
• If the fire alarm support location does not support the IFC drawing then the supports
need to be modified as per the existing facilities and site conditions keeping in view that
1.- The supports shall not interface with operator and maintenance access area .
2.- The supports shall not under drain point and above the vent point of process lines.
• The support for panel frame and post stands / brackets shall be verified according to
updated/ latest IFC Drawing
• Lay-out arrangements / orientation of support shall be according to respective location
of control panel, detectors (smoke and heat), manual call point, horn/siren/ and other
associated devices.
• Ensure that cable sleeves, duct / stub up conduits and trays are in correct line, location.
• All the assembly shall be primed and painted where is applicable and all the rough sharp
edge on support frames shall be removed.
• The installed support assembly shall be rigid and leveled in vertical direction/position.
• The precast cover foundation / support shall be tight and secure.
• In case the supports are to be welded to steel structure, the welding activities shall be
carried out as per PTS and the applicable touch may be applied after welding.
Page 3 of 4
CLASSIFICATION: INTERNAL
Quality Management System Ref No.: ALF-M-MS-003
METHOD STATEMENT FOR Installation of Rev.: 01
Fire Alarm & Detection System Date: 10.03.2020
• Ensure that the complete assembly are vertical aligned and leveled after tighten the bolts..
• Ensure that the Panels / cabinets are properly grounded / bonded.
• All foreign debris / materials shall be removed
6.2 Pre-Commissioning
• All the cable / wiring shall be terminated with proper tagging as per updated IFC drawing
• Ensure that all cable / wiring are tested and the inspection installations are properly
recorded and documented.
• Ensure all the required sealing has provided for spare /open cable/duct entry& exist area.
7.0 Attachment:
Page 4 of 4
CLASSIFICATION: INTERNAL