Professional Documents
Culture Documents
SACIC-S-4098 Rev - Fit Layer Laminate of RTRGRE, GRV, and GRP Piping
SACIC-S-4098 Rev - Fit Layer Laminate of RTRGRE, GRV, and GRP Piping
EQUIPMENT ID NUMBER(S) EQUIPMENT DESCRIPTION EQPT CODE SYSTEM ID. PLANT NO.
LAYOUT DRAWING NUMBER REV. NO. PURCHASE ORDER NUMBER EC / PMCC / MCC NO.
SCHEDULED INSPECTION DATE & TIME ACTUAL INSPECTION DATE & TIME QUANTITY INSP. MH's SPENT TRAVEL TIME
SAUDI ARAMCO USE ONLY
SAC TIP NUMBER SAC ACTIVITY NUMBER WORK PERMIT REQUIRED?
SACTIP-S-070-03 2/Jan/00
SAUDI ARAMCO INSPECTION LEVEL CONTRACTOR INSPECTION LEVEL
W H
ITEM
ACCEPTANCE CRITERIA REFERENCE PASS FAIL N/A RE-INSP DATE
No.
Check whether the sections to be joined together are dry, clean and at the Manufacturer
A1
right temperature. recommendation
Fill any existing gap between two pipe segments using putty, made of resin Manufacturer
A2
and CAB-O-SIL mixture. recommendation
Once the putty is cured, grind it and laminate the required number of
Manufacturer
A3 continuous fit layers around the joint as per recipe given by the pipe
recommendation
manufacturer.
Start the lamination of the fitted sections within two hours after sanding or
Manufacturer
A5 grinding; re-sanding of lamination area shall be required
recommendation
if the waiting period exceeds two hours.
Manufacturer
A7 The maximum fit length (LF) shall not exceed the laminate length (LV).
recommendation
Close the ends of the pipe during curing to avoid cooling by airflow through Manufacturer
A8
the pipe. recommendation
After gelling, the fit laminate is cured at a curing temperature of 125°C for
45 minutes (30minutes heating up and 15 minutes curing) Heating up to the Manufacturer
A10
curing temperature shall proceed gradually. The fit laminate shall be cured recommendation
in a controlled way with the aid of heating blankets.
EQUIPMENT ID NUMBER(S) EQUIPMENT DESCRIPTION EQPT CODE SYSTEM ID. PLANT NO.
LAYOUT DRAWING NUMBER REV. NO. PURCHASE ORDER NUMBER EC / PMCC / MCC NO.
SCHEDULED INSPECTION DATE & TIME ACTUAL INSPECTION DATE & TIME QUANTITY INSP. MH's SPENT TRAVEL TIME
SAUDI ARAMCO USE ONLY
SAC TIP NUMBER SAC ACTIVITY NUMBER WORK PERMIT REQUIRED?
ITEM
ACCEPTANCE CRITERIA REFERENCE PASS FAIL N/A RE-INSP DATE
No.
During the gelling and curing, the pipe parts shall not be moved and/or
dislocated until the fit laminate has cured sufficiently. Use stable Manufacturer
A12
supporting! After curing and cooling the adjusted pipe part may eventually recommendation
be moved carefully.
REMARKS:
REFERENCE DOCUMENTS:
1-SAES-S-070 -- Installation of Utility Piping Systems, 1 March 2017
2-SAES-L-610 -- Nonmetallic Piping -- 22 July, 2014
3- 01-SAMSS-029 -- RTR Sewer Pipes & Fittings for Gravity Flow -- 4 July 2014
4- 01-SAMSS-034 -- RTR Pressure Pipes & Fittings -- 19 March 2013
5-RTR Pipe Manufacturer recommendation