Professional Documents
Culture Documents
Project Management and Systems Engineeri
Project Management and Systems Engineeri
First the article addresses the commonalities and the sources of unproductive tensions between
project management and systems engineering, and the professionals performing them. Later,
it describes how the two disciplines are critical for the Work Breakdown Structure (WBS)
delivery.
The above PMI project definition is clear considering that a project is not only oriented
to a product development but a service or a result as well. Here, due to its intersection with
systems engineering, the article addresses product oriented projects.
The managing of product oriented project is a topic considered by both disciplines systems
engineering and project management. Both disciplines have commonalities in the product
or system development management. These commonalities are positive when the processes
Academia Letters, July 2021 ©2021 by the author — Open Access — Distributed under CC BY 4.0
1
supported by both disciplines are integrated and the common responsibilities are shared by
the systems engineer and the project management.
To identify the commonalities of both disciplines systems engineering and project man-
agement two sources are used here, one is NASA System Engineering Handbook [2] and the
other is INCOSE SE Handbook [3]. The commonalities identified are stakeholder manage-
ment, requirements management, scope management, risk management and change manage-
ment.
The project manager is responsible for project outcomes as well as the time, cost and
resources required for the project. The systems engineer manages the technical baseline of
the product under development.
Stakeholder management, scope management and particularly requirements management
are shared by both disciplines. Systems engineers are critical for complex product oriented
projects since engineering better requirements reduce scope creep and unwanted surprises.
Risk management is shared, but project manager is the primary owner of the risk man-
agement process but the systems engineer provides significant inputs to all aspects of risk
management.
Change management is shared. Change management is part of configuration management.
But a seamless integration of systems engineering and project management is not always
the commonplace. As pointed out by Boswell [4], unproductive tensions between project
management and systems engineering are due to:
• Unclear definition of roles and authority when the roles of systems engineer and project
manager are performed by different persons, as it is the case in large projects.
Academia Letters, July 2021 ©2021 by the author — Open Access — Distributed under CC BY 4.0
2
• Better a project manager with experience as systems engineer
• Assign the roles of project manager and systems engineer to the right people
• Be aware of the importance of decisions and their impact on either the system or project
Academia Letters, July 2021 ©2021 by the author — Open Access — Distributed under CC BY 4.0
3
of process oriented WBS can be found in the PMI Guide for WBS [8] and the US Department
of Energy [9].
The WBS for a very large and complex program or project is a hierarchy of multiple levels.
Kezner [10] recommends a six levels hierarchy for a large program where the hierarchy levels
represent: Total program, project, task, subtask, work package and level of effort activity.
For product oriented projects with systems engineering tasks, the intentionally incomplete
WBS presented in Figure 1 below is proposed here. The product breakdown, where subsys-
tems A and B, and still incomplete, is based on the decomposition of the physical architecture
of the product being developed, nowadays modeled by systems engineers using Model-Based
Systems Engineering approaches [11].
Academia Letters, July 2021 ©2021 by the author — Open Access — Distributed under CC BY 4.0
4
Figure 1 is illustrative of the diverse tasks identified in the WBS: project management
tasks, such as 1.1.1, 1.1.2, 1.1.3 and 1.1.4, crosscutting tasks, such as 1.2.1 and 1.2.2, and
product tasks such as 1.4.1 and 1.4.2.
The more difficult to identify are the so called crosscutting elements that transect the peer
WBS elements at each level. Haugan [12], identifies four types of crosscutting tasks:
• Integrative: work element that integrates two or more peer WBS elements.
• Analytical: work element that spans the work elements of a common parent.
• Project management: These work elements have common characteristics with the above
work elements of the classification.
• The level 2 elements in a product oriented project include the product, any other major
deliverables and major crosscutting work elements necessary to support the product
work
• The level 3 work elements of the product reflect its physical hierarchy. So the contri-
bution of engineers and particularly systems engineers is very important.
• Cross cutting work elements of type integrative, analytical or process may appear at
diverse levels as needed
• Work in each work element is equivalent to the sum of the work in subordinate work
elements
• The lowest level is the level above the project activities and it is called work package
Figure 1 is complemented with the WBS dictionary where the work in each WBS element
is described in detail. Table 1 is a template for describing each work element in the WBS
dictionary.
Academia Letters, July 2021 ©2021 by the author — Open Access — Distributed under CC BY 4.0
5
Table 1. WBS Dictionary
Academia Letters, July 2021 ©2021 by the author — Open Access — Distributed under CC BY 4.0
6
3. To conclude
Project management and systems engineering commonalities and intersections can result in
unproductive tensions that should be mitigated by collaboration and the integration of efforts.
The definition of the project scope using the WBS is an important contributors of a seamless
integration of systems engineering, project management and specialties engineering although
the human factor is still a main issue.
References
[1] PMI. A Guide to the Project Management Body of Knowledge, 6th Edition. Newtown
Square, PA: Project Management Institute, 2017.
[2] NASA. Systems Engineering Handbook. NASA SP-2016-6105 Rev2. Washington, DC:
NASA, 2016.
[3] Walden D.D., et al. Systems Engineering Handbook – A guide for system life cycle pro-
cesses and activities, INCOSE-TP-2003-02-04. Hoboken, NJ: John Wiley&Sons, 2015.
[4] Boswell J.W. Anbari, F.T. and Via J.W. “Systems Engineering and Project Management:
Points of Intersection, Overlaps and Tensions,” 2017 Proceedings of PICMET ́17: Tech-
nology Management for Interconnected World, 2017.
[5] Van Gemert, D. “Systems engineering the project.” Paper presented at PMI® Global
Congress 2013—North America, New Orleans, LA. Newtown Square, PA: Project Man-
agement Institute, 2013.
[6] Martinez Leon, C., Fernandez J.L. and Cross, J.A.” Taxonomy on Product Dependencies
for Project Planning.” Proceedings of the 2018 IISE Annual Conference. K. Barker, D.
Berry, C. Rainwater, Eds., 2018.
[7] Kordova, S., Katz, E., Frank, M. “Managing development projects-The partnership be-
tween project managers and systems engineers.” Systems Engineering. Vol 22, Is 3, pp
227-242, doi:10.1002/sys.21474, 2019.
[8] PMI. Practice Standard for Work Breakdown Structures. Second Edition. Newton Square,
PA: Project Management Institute, 2006.
Academia Letters, July 2021 ©2021 by the author — Open Access — Distributed under CC BY 4.0
7
[9] US DoE. Work Breakdown Structure Handbook., Washington, DC: Department of Energy,
August 16, 2012
[10] Kezner, H. Project Management a Systems Approach to Planning, Scheduling, and Con-
trolling. Hoboken, New Jersey: John Wiley & Sons, Inc., 2009.
[11] Fernandez J.L. and Hernandez, C. Practical Model-based Systems Engineering, Nor-
wood, MA: Artech House, 2019.
[12] Hagan, G. Effective Work Breakdown Structures. Vienna, VA: Management Concepts,
2002.
Academia Letters, July 2021 ©2021 by the author — Open Access — Distributed under CC BY 4.0