002.3-Mek-Itp-Nk - PKT Quality Plan and Manual of Tripper Car and Telescopic Chute - Kk1
002.3-Mek-Itp-Nk - PKT Quality Plan and Manual of Tripper Car and Telescopic Chute - Kk1
0 IFA 29 Jul 21
DIPERIKS DISETUJU
DIBUAT DISETUJUI DISETUJUI
KETERANGA A I
REV. TANGGAL
N
ACS-ST NK PKT
1|Page
PROYEK PEMBANGUNAN GUDANG BAHAN
BAKU PROYEK BAKU 45.000 TON
PT PUPUK KALIMANTAN TIMUR
TABLE OF CONTENT
1. INTRODUCTION ................................................................................................................................................................... 3
2. GENERAL ................................................................................................................................................................................. 3
3. PROJECT ORGANIZATION CHART ................................................................................................................................ 4
4. RESPONSIBILTY AND AUTHORITY OF PROJECT TEAM ...................................................................................... 5
5. PROJECT MASTER SCHEDULE (PMS) .......................................................................................................................... 7
6. PROJECT CONTACT POINTS ............................................................................................................................................ 7
7. VENDOR DATA REQUIREMENTS .................................................................................................................................. 9
8. DOCUMENT ISSUE & APPROVAL PROCEDURE .................................................................................................... 13
9. PROJECT QA/QC PLAN ................................................................................................................................................... 15
10. ATTACHMENTS............................................................................................................................................................... 18
2|Page
PROYEK PEMBANGUNAN GUDANG BAHAN
BAKU PROYEK BAKU 45.000 TON
PT PUPUK KALIMANTAN TIMUR
1. INTRODUCTION
This project covers Design, Engineering, Manufacturing and Fabrication of Tripper Car to
supply for the following project:
Project Name : PEMBANGUNAN GUDANG BAHAN BAKU KAPASITAS 45.000 TON
Contractor : PT. NINDYA KARYA
Customer : PT. PUPUK KALIMANTAN TIMUR
Location : Bontang, Kalimantan Timur.
2. GENERAL
a. Vendor.
Vendor Name : PT. ADHI CIPTA SARANA
Address : Jl. R. H. Aria Surya Kencana Blok F4/7 – BSD City
Kel. Rawa Buntu, Kec. Serpong
Kota Tangerang Selatan 15323
Phone: +62 21 756 6182
Attention : Mr. loga EkaPrasta (Operation Director)
E-mail : loga.ekaprasta@acscorp.co.id
Scope of Work :
3|Page
PROYEK PEMBANGUNAN GUDANG BAHAN
BAKU PROYEK BAKU 45.000 TON
PT PUPUK KALIMANTAN TIMUR
4|Page
PROYEK PEMBANGUNAN GUDANG BAHAN
BAKU PROYEK BAKU 45.000 TON
PT PUPUK KALIMANTAN TIMUR
5|Page
PROYEK PEMBANGUNAN GUDANG BAHAN
BAKU PROYEK BAKU 45.000 TON
PT PUPUK KALIMANTAN TIMUR
6|Page
PROYEK PEMBANGUNAN GUDANG BAHAN
BAKU PROYEK BAKU 45.000 TON
PT PUPUK KALIMANTAN TIMUR
4.5 Delegation
Attention : Resti
Adress : PT. Nindya Karya, Jl. Letjend MT.Haryono Kav.22 Jakarta.
Email : nindyakaryabontang@gmail.com
Email CC : restiastriana0197@gmail.com, fahrez.ry@gmail.com,
matheusselalu@gmail.com, nurbaqin.pktproject@gmail.com
7|Page
PROYEK PEMBANGUNAN GUDANG BAHAN
BAKU PROYEK BAKU 45.000 TON
PT PUPUK KALIMANTAN TIMUR
8|Page
PROYEK PEMBANGUNAN GUDANG BAHAN
BAKU PROYEK BAKU 45.000 TON
PT PUPUK KALIMANTAN TIMUR
9|Page
PROYEK PEMBANGUNAN GUDANG BAHAN
BAKU PROYEK BAKU 45.000 TON
PT PUPUK KALIMANTAN TIMUR
10 | P a g e
PROYEK PEMBANGUNAN GUDANG BAHAN
BAKU PROYEK BAKU 45.000 TON
PT PUPUK KALIMANTAN TIMUR
4. Submission Type
All documents generated by office software, such as MS Office & Auto Cad, etc. shall be
submitted in both original source files and converted Acrobat PDF format. All other
documents generated by hand-writing, photo and proprietary analysis software, etc. Shall
be submitted in either Acrobat PDF or TIFF white-black compressed image format with
minimum 600 DPI resolution.
Also, these documents in binder (Standard: 3 Hole binder (A4 Size) / in case of over A3
Size, fold the paper in A4 size) shall be submitted to NK OR PKT by the due date as shown
below.
All Documents and Vendor’s subcontractor list shall be approved by NK OR PKT before
Engineering stage and prior to construction. When submitting revised vendor documents
& drawings, Vendor shall clearly indicate all revised points with cloud mark and/or
revision marks. This is mandatory requirement. Vendor shall be responsible for all
possible results caused by omitting revision mark. Any document omitting the revision
marks may be returned without comment.
11 | P a g e
PROYEK PEMBANGUNAN GUDANG BAHAN
BAKU PROYEK BAKU 45.000 TON
PT PUPUK KALIMANTAN TIMUR
12 | P a g e
PROYEK PEMBANGUNAN GUDANG BAHAN
BAKU PROYEK BAKU 45.000 TON
PT PUPUK KALIMANTAN TIMUR
Revision Designation
The Revision Number for technical document is a sequential numeric code defining the
Approved Revision of that document (A,B,C, etc.)
1. Issuance
All documents issued to NK OR PKT shall be forwarded with a document transmittal (see
the format in Attachment #3), stamped or checked in the appropriate box for review,
approval, construction, record, or information. Document and Drawing shall not be mixed
in the same Transmittal.
2. Document for Approval
a. Submission
Vendor shall submit to NK OR PKT documents for approval. All the documents and
the drawings prepared by the Vendor will be clearly marked on each Document
Cover as following:
- For Approval
- For Final
- For Information
- As Built
After NK examine the documents and drawings, NK OR PKT shall give vendor
written notice by official letter or marked-up copy with document transmittal form
indicating "approved" or "approved with comment".
b. Approval Time
NK OR PKT will respond within five (5) working days. Otherwise documents in
question issued by Vendor will be deemed to have approval from NK OR PKT, if
NK OR PKT does not notify vendor of its approval period beforehand. In some
13 | P a g e
PROYEK PEMBANGUNAN GUDANG BAHAN
BAKU PROYEK BAKU 45.000 TON
PT PUPUK KALIMANTAN TIMUR
cases, this specified period could be extended under mutually agreement between
NK OR PKT and Vendor.
If an urgent review is required, the Vendor may declare in the transmittal as "it is
required an urgent review and/or approval within three (3) days".
c. Comments
If comments which are not approved are received from NK OR PKT, Vendor shall,
upon receipt of the returned documents, take the following action.
• Revise the documents to incorporate the comments,
• Send a reply letter to the comments within five (5) working days upon
receipt of comments, or In some cases, this specified period could be
extended under mutually agreement between NK OR PKT and Vendor.
• Meet with NK OR PKT and discuss the comments. The results of the meeting
will be recorded as minutes of the meeting or record of conversation.
Then the revised documents shall be issued for Final or record. If no comment is
made, the documents shall be deemed to have been approved and shall be issued
for Final or record.
14 | P a g e
PROYEK PEMBANGUNAN GUDANG BAHAN
BAKU PROYEK BAKU 45.000 TON
PT PUPUK KALIMANTAN TIMUR
15 | P a g e
PROYEK PEMBANGUNAN GUDANG BAHAN
BAKU PROYEK BAKU 45.000 TON
PT PUPUK KALIMANTAN TIMUR
16 | P a g e
PROYEK PEMBANGUNAN GUDANG BAHAN
BAKU PROYEK BAKU 45.000 TON
PT PUPUK KALIMANTAN TIMUR
17 | P a g e
PROYEK PEMBANGUNAN GUDANG BAHAN
BAKU PROYEK BAKU 45.000 TON
PT PUPUK KALIMANTAN TIMUR
10. ATTACHMENT
18 | P a g e
PROJECT ORGANIZATION CHART
PROYEK PEMBANGUNAN GUDANG BAHAN BAKU KCL 45000 TON
(phone : 081348457630)
PROJECT MANAGER
================== (email : loga.ekaprasta@acscorp.co.id )
Loga Ekaprasta
(phone : 081394940188)
PROJECT CONTROL (email : ahmad.fauji@acscorp.co.id )
==================
Ahmad Fauji
PROCUREMENT FINANCE
==============
PRODUCTION Irsal A.M =========
Lia Yulianti ENGINEERING
MECHANICAL MECHANICAL
(phone : 081228867154) ------------------------- ------------------------- (phone : 081348457630)
(email : arpik@sikotechno.co.id ) Arfik Sumarga Loga Ekaprasta (email : loga.ekaprasta@acscorp.co.id )
DURASI
NO ITEM PEKERJAAN START FINISH JUNI 2021 JULI 2021 AGUSTUS 2021 SEPTEMBER 2021 OKTOBER 2021 NOVEMBER 2021 DESEMBER 2021
(Hari)
M-1 M-2 M-3 M-4 M-1 M-2 M-3 M-4 M-1 M-2 M-3 M-4 M-1 M-2 M-3 M-4 M-1 M-2 M-3 M-4 M-1 M-2 M-3 M-4 M-1 M-2 M-3 M-4
A PENGADAAN TRIPPER & TELESCOPIC CHUTE
1 Engineering & Konsinyering 01/06/2021 22/06/2021 21
2 Pabrikasi 23/06/2021 06/09/2021 75
3 Purchase Parts & Accs 23/06/2021 06/09/2021 75
4 Assembly Test 23/08/2021 06/09/2021 14
5 Pengiriman Structure 07/09/2021 28/09/2021 21
6 Pengiriman Part & Accs 07/09/2021 25/10/2021 48
7 Assembly Test 26/10/2021 09/11/2021 14
DOCUMENT TRANSMITTAL
(DISTRIBUSI DOKUMEN)
Submitted to
(Diserahkan kepada) : Ibu Resti
Name / Company
(Nama / Perusahaan) : PT. Nindya Karya
Division / Attn
(Divisi / Attn) : Document Control
Received by Submitted by
(Diterima Oleh) : (Diserahkan oleh):
A. Fauji
Date Date
(Tanggal) : (Tanggal) : 29 Jun 21
*) sheet/bundle/exemplar/disc
(lembar/bundle/exemplar/disket) **) (Coret yang tidak diperlukan)
PROYEK PEMBANGUNAN GUDANG BAHAN
BAKU PROYEK BAKU 45.000 TON
PT PUPUK KALIMANTAN TIMUR
DOCUMENT TITLE
DOKUMEN NO. : -
DOCUMENT TITLE
REVISION SHEET
2
PROYEK PEMBANGUNAN GUDANG BAHAN
BAKU PROYEK BAKU 45.000 TON
PT PUPUK KALIMANTAN TIMUR
DOCUMENT TITLE
TABLE OF CONTENT
COVER … ......................................................................................................................................................................................... 1
REVISION SHEET............................................................................................................................................................................. 2
TABLE CONTENT ............................................................................................................................................................................ 3
DETAIL ENGINEERING DRAWING
CLIENT
CONTRACTOR
VENDOR
VENDOR :
DATE
NAME
SIGN
SUB VENDOR :
DATE
NAME
SIGN
PROJECT :
PROYEK PEMBANGUNAN
GUDANG BAHAN BAKU KCL 45.000 TON
TITLE :
CLIENT DWG. NO :