Professional Documents
Culture Documents
Metal Oxide Surge Arrestor Energy Graph
Metal Oxide Surge Arrestor Energy Graph
Umer Amir Khan, Jong-Geon Lee, Sung-Woo Lim, Young-Geun Kim, JungWook Sim
Bang-Wook Lee Power Equipment R&D Center
Department of Electronic System Engineering, LSIS Co., Ltd.
HVDC EPL Lab, Hanyang University, Cheongju, Korea
Ansan, South Korea. youngk@lsis.biz
bangwook@hanyang.ac.kr
Abstract— Super grids are considered to be the technology of power from remote renewable resources to the power hungry
the future that will allow transmission and trade of huge volumes load centers and it will also enable the trade of bulk electric
of electricity over long distances. HVDC is the preferred choice power [1]-[3]. Unfortunately, the development of MTDC is
for developing super grids as HVAC transmission of bulk power delayed up till now due to absence of HVDC circuit breaker
over long distances is less efficient. However, the key obstacle in (DCCB) technology. With the latest developments in high
developing HVDC super grids is the absence of HVDC circuit power and high voltage IGBT valves, hybrid DCCBs having
breakers (DCCB) which can quickly detect and isolate the fault. IGBT valves and mechanical parts have been developed and
The huge electrical and thermal stresses subjected to DCCB lab tested [4]. However, implementation of the hybrid DCCB
during DC current interruption are one of the primary
in real HVDC network has still not been reported. This is
challenges in developing DCCB. Especially, IGBT valves in
mainly due to the cost of IGBT valves which are subjected to
hybrid DCCB are the most expensive and sensitive part and their
cost drastically increase with their maximum rating. This
huge stresses in HVDC systems during fault interruption.
research paper presents a comparative study on the electrical In MTDC, the DC fault current rises rapidly and its
and thermal stress distribution across IGBT valves of magnitude is very large compared to AC network. Breaking
conventional hybrid DCCB (CDCCB) and Superconducting this huge DC fault current results in huge electrical and thermal
hybrid DCCB (SDCCB) during fault conditions. Realistic stresses subjected to DCCB and these stresses are one of the
CDCCB and SDCCB models were developed by considering the primary challenges in developing DCCB [5]-[6]. IGBT valves
characteristic values of commercially available IGBT module. To
in hybrid DCCB are the most expensive and sensitive part and
create the electrical and thermal stress profiles, CDCCB and
SDCCB were placed in HVDC test bed model and transient
their cost drastically increase with the increase in their
simulations were performed. The voltage distribution, current maximum rating. In our previous research works [7]-[8], we
distribution and energy dissipation profiles across IGBT valves have proposed a superconducting hybrid DCCB (SDCCB)
were developed for CDCCB and SDCCB. Comparative analysis which limits the rising DC fault current and significantly
of the profiles showed that the SDCCB components were reduces the stress on SDCCB components.
subjected to relatively lower electrical and thermal stresses. In this research paper we have modelled the conventional
hybrid DCCB (CDCCB) and SDCCB models and performed a
Keywords—HVDC Circuit Breaker (DCCB), Hybrid DCCB,
Superconducting DCCB, Superconducting Fault Current Limiter,
comparative study on the electrical and thermal stresses
IGBT Valves. subjected to their IGBT valves. CDCCB and SDCCB were
placed in HVDC test bed model and transient simulations were
performed. The voltage distribution, current distribution and
I. INTRODUCTION energy dissipation profiles across IGBT valves for CDCCB and
The annual increase of electric power demand all over the SDCCB were developed. Comparative analyses of these
globe has caused an increase in High Voltage Direct Current profiles showed that the SDCCB components were subjected to
(HVDC) projects and new HVDC projects are being relatively lower electrical and thermal stresses.
commissioned every year. Although most of the HVDC
projects are point to point transmission systems, the integration II. FAULT CURRENTS IN HVDC SYSTEMS
of these point to point HVDC systems into Multi-terminal
HVDC grid configuration (MTDC) will lead to numerous A. DC Fault Current Interruption Methods
advantages. MTDC, also referred to as super grid, is the
AC circuit breakers interrupt AC fault current at its natural
technology of the future that will allow transmission of electric
zero crossing, but there is no zero point in DC fault current as
This work was supported by the Human Resources Program in Energy
Technology of the Korea Institute of Energy Technology Evaluation and
Planning (KETEP), granted financial resource from the Ministry of Trade,
Industry & Energy, Republic of Korea. (20154030200730).
The research was also supported by LS Industrial Systems co., ltd.
575
Ultrafast Disconnector Line Commutation
Switch (UDS) Switch (LCS)
a SFCL b
Residual I1 IT
Current Main DC Breaker (MCB)
Breaker (RCB)
I2
B. Superconducting Hyrbid HVDC Circuit Breaker A. Design and Modeling of IGBT Valves
Fig. 4 shows the proposed SDCCB which is modified Fig. 5 shows the CDCCB and SDCCB models used for
CDCCB of Fig. 3. Modifications include: (1) SFCL is placed in simulation analysis. To calculate the energy dissipation across
series of main current path (I1); and (2) Series reactor has been the IGBT valves, it was critical to determine impedance values
removed as it is not needed anymore for current limiting. The of LCS and MCB valves. An IGBT valve is composed of a
SDCCB works as follows. After the DC fault, SFCL quenches number of series and parallel connected IGBT modules and
and limits the fault current. SDCCB do not interrupt current Fig. 6 (a) shows the simplified structure of an IGBT valve.
instantaneously and the decision to trip SDCCB depends on: IGBT valve’s basic building block is a single IGBT module
(1) the absence of false triggers; (2) identifying the faulty line; whose maximum blocking voltage (VCES) and maximum peak
or (3) crossing the thermal limit of any of the SDCCB current (Icrm) determines critical ratings for an IGBT valve.
components. Once the trip signal is given to SDCCB, the LCS
IGBT valve critical ratings are its maximum blocking
located in the main line opens and commutates the current to
voltage (VB) and maximum peak current (Iv). In an IGBT
the parallel line where DC current is forced to zero by a
valve, the number of IGBT modules connected in series (Ns) is
combination of MCB IGBTs and surge arresters. This current
determined by the VB and the number of parallel branches
interruption method is similar to that of CDCCB [15].
(NBR) is determined by the Iv. NS and NBR can be calculated by
IV. SIMULATION ANALYSIS Ns = VB / VCES (1)
The modeling and simulation analysis of the proposed
DCCB models were done in Matlab / Simulink / NBR = Iv / Icrm (2)
Simpowerystems. It was assumed that the DCCBs were
required to limit the fault current for 10 ms after the fault due Let Zm be the impedance of single IGBT module in Fig. 6
to the reasons explained in Section II. Transient simulations of (a). We can calculate the series impedance of a one branch (ZS)
one DCCB model were done at a time. The fault was generated of the IGBT valve by:
at 60 ms and after the 10 ms delay the DCCB was given the
trip signals at 70 ms. After the trip signal, DCCBs interrupted ZS = Ns × Zm (3)
the DC fault current and isolated the HVDC line.
Considering NBR, the total impedance of the valve (ZT) can
be calculated as:
576
VB
1 Icrm NS Iv
IGBT IGBT
1 V CES
(a) (b)
Fig. 7 Test bed model designed in Matlab/Simulink/Simpowersystems to
Fig. 6 (a) Simplified diagram of an IGBT valve with NBR parallel branches perform simulation analysis for SDCCB.
and NS IGBT in a single branch, (b) Characteristic graph of IGBT during
conduction state [17]. TABLE II. PARAMETERS OF HVDC TEST BED MODEL
TABLE I. IMPEDANCE CALCULATION OF DCCB IGBT VALVES Parameters Specification
Valve VB IV NS NBR ZT VSC HVDC Type Monopolar / Two Level
LCS 100 V 16 kA 1 7 1 m MTDC Grid Voltage 250 kVdc
MCB 460 kV 40 kA 103 17 25m DC Fault Current di/dt 10 kA/ms
Normal Load Current 2 kA
ZT = ZS / NBR (4) Power Consumption 500 MW
AC System Voltage 200 kVrms
During conduction, IGBT valve will dissipate energy across AC System Power Rating 2 GVA
AC System X/R 7
itself (Evalve) and we can calculate this energy by:
Evalve = Iv2 ZT dt (5) real HVDC systems, the DC fault current in the test bed is
composed of: (1) contribution from the AC network; (2) DC
where Iv is the instantaneous valve current. Integration is done link capacitor discharge current; and (3) discharging of the
from the start of the fault to the zero current formation of the transmission line [16].
DC fault current. V. RESULTS AND DISCUSSION
For the DCCB models of Fig. 5, the IGBT valves
parameters were calculated by considering the specifications of Fig. 8, Fig. 9 and Fig. 10 shows the current, voltage and
the commercially available IGBT module FZ1200R45KL3_B5 energy stress subjected to CDCCB and SDCCB IGBT valves
which is developed by Infineon [17]. The single IGBT module when applied in test bed model of Fig. 7. At 60 ms, DC fault is
has: VCES = 4.5 kV and Icrm = 2.4 kA. Fig 6 (b) shows the IGBT generated and CDCCB immediately diverts the current to the
characteristic curve between the saturation voltages across parallel MCB branch and waits for 10 ms. The current limiting
IGBT module (VCE) during conduction state versus the current time is indicated as TLimit in Fig 8 and Fig. 9. At 70 ms the
flowing through it. Considering Icrm = 2.4 kA, we measured CDCCB was triggered and the current was forced to zero. On
VCE § 4.5 V. Thus we can calculate Zm by the contrary, after the DC fault, SDCCB did not immediately
Zm = VCE / Icrm (6) divert the fault current to the parallel branch and SDCCB
SFCL limited the fault current for 10 ms. At 70 ms, SDCCB
and we calculated Zm= 1.875 m. diverted the current to the MCB branch where it was
interrupted and forced to zero.
Table IV shows the expected maximum blocking voltage
and fault current subjected to IGBT valves in Fig. 5 and these A. Current Stress Subjected to IGBT Valves
values were used to calculate the impedance of IGBT valves.
Fig. 8 shows the current stress subjected to DCCBs and
Equations (1)-(5) were used to calculate the impedance values
of LCS and MCB IGBT valves and the estimated values are their IGBT valves when applied in test bed model of Fig. 7.
given in Table IV. Fig. 8 (a) shows the total current flowing through the DCCBs
during the fault. The presence of SFCL in SDCCB significantly
B. Test Bed reduced the total current flowing through the SDCCB. Fig. 8
(b) shows the current through LCS valves. CDCCB LCS
A testing setup was developed to perform transient
simulations on the CDCCB and SDCCB models as shown in conducted for a short duration but SDCCB LCS had to conduct
Fig. 7. Table II summarizes the general features of the test bed continuously during the current limiting duration. Therefore,
model. The test bed contains a two-level VSC-HVDC SDCCB LCS is subjected to larger current stress when
converter arranged in symmetrical monopole configuration compared with CDCCB LCS. Fig 8 (c) shows the current
[13]. Test bed Voltage = 250 kV, Load Current = 2 kA, Normal flowing through the MCB valve of the CDCCB and SDCCB. A
Power Flow = 500 MW, and HVDC transmission line length = large DC fault current conduction stress was subjected to
100 km as shown in Fig. 7. DC fault was generated and it CDCCB MCB during TLimit. Also, MCB had to break the huge
results in a DC fault current with di/dt = 10 kA/ms. DC fault current which is only limited by the current limiting
After the DC fault in test bed, VSC-HVDC converter reactor in CDCCB. On the contrary, SDCCB significantly
station IGBTs were turned off within microseconds. However, reduced the amplitude and the duration of DC fault current
fault current continued to flow through the IGBT antiparallel flowing through the MCB. Moreover, SDCCB MCB had to
diodes which form an uncontrolled rectifier [5]. Similar to the break a much smaller fault current which further reduces the
577
IT for CDCCB IT for SDCCB VT for CDCCB VT for SDCCB
50 500
40 400
30 300
20 200
10 100
0 0
55 60 65 70 75 80 55 60 65 70 75 80
TLimit Time (ms) TLimit Time (ms)
(a) (a)
ILCS for CDCCB ILCS for SDCCB VLCS for CDCCB VLCS for SDCCB
20 60
LCS Valve Current (kA)
10 30
20
5
10
0 0
55 60 65 70 75 80 55 60 65 70 75 80
TLimit Time (ms)
TLimit Time (ms)
(b) (b)
IMCB for CDCCB IMCB for SDCCB VMCB for CDCCB VMCB for SDCCB
50 500
MCB Valve Current (kA)
40 400
30 300
20 200
10 100
0 0
55 60 65 70 75 80 55 60 65 70 75 80
TLimit Time (ms) TLimit Time (ms)
(c) (c)
Fig. 8 Current stresses for CDCCB and SDCCB (a) Total fault current Fig. 9 Voltage stresses for CDCCB and SDCCB (a) Total voltage buildup
flowing through the two DCCBs, (b) Fault current flowing through the across DCCBs, (b) Voltage buildup across the LCS valves, (c) Voltage
LCS valves, (c) Fault current flowing through the MCB valves. buildup across the MCB valves.
stress for MCB. Thus, SDCCB MCB valve will have smaller and it was not directly related with the amplitude of the DC
current rating and consequently lesser number of IGBT parallel fault current. Fig. 9 (b) shows the voltage across the LCS
valve. LCS in both the DCCBs had small voltage drop which
branches in the MCB valve. This will significantly decrease the
was expected and explained in Section III.A. Fig 9 (c) shows
size and cost of the MCB valve. Table III shows the percentage the voltage across the MCB valves of the CDCCB and
change in fault current subjected to the two DCCBs and their SDCCB. The maximum inverse voltage that will ignite the
IGBT valves. The positive values of percentage change in surge arrester bank will appear across the MCBs of the
Table III indicate the increase in stress and the negative values DCCBs. Also, for the SDCCB the SDCCB SFCL voltage drop
show the decrease in the stress. appeared across the SDCCB MCB during the TLimit duration as
shown in Fig. 9 (c). However, this voltage buildup is
B. Voltage Stress Subjected to IGBT Valves unimportant as it is lower than the SDCCB MCB voltage rating
Fig. 9 shows the voltage stress subjected to DCCBs and and also results in no power loss as SDCCB MCB is not
their IGBT valves when applied in test bed model of Fig. 7. conducting. Table III shows the percentage change in the
Fig. 9 (a) shows the total voltage buildup across the DCCBs voltage drop across the DCCB IGBT valves.
during the fault current interruption. This voltage was
dependent on the activation voltage of the surge arrester bank
578
CDCCB SDCCB
20
CDCCB SDCCB were performed. The voltage distribution, current distribution
6
and energy dissipation profiles across IGBT valves were
5
developed for CDCCB and SDCCB. In SDCCB, the largest
15
4 and the most expensive IGBT valve (MCB) of hybrid DCCB
3 10 was subjected to significantly lower electrical and thermal
2
stresses. This will significantly decrease the size and cost of the
5 MCB valve. However, there is a need to analyze the stresses
1
subjected to SFCL in SDCCB and it will be presented in our
0 0 future research work.
LCS Valve MCB Valve
(a) (b)
Fig. 10 Energy stresses on IGBT valves in CDCCB and SDCCB (a) Energy
REFERENCES
dissipated across LCS valves, (b) Energy dissipated across MCB valves. [1] J. W. Feltes, B. D. Gemmell, D. Retzmann, "From smart grid to super
grid: solutions with HVDC and FACTS for grid access of renewable
TABLE III. PERCENTAGE CHANGE IN STRESSES ON IGBT VALVES energy sources," IEEE PESGM 2011, San Diego, pp. 1-6, July 2011.
DCCB CDCCB SDCCB % Change [2] Z. Xu, H. Dong, and H. Huang, "Debates on ultra-high-voltage
Voltage 42 V 54 V + 28.6 % synchronous power grid: the future super grid in China?," IET Generat.,
LCS Current 12.6 kA 16.3 kA + 24.6 % Transm. & Distrib., vol. 9, no. 8, pp. 740-747, May 2015.
Energy 0.25 KJ 5 kJ + 1900 % [3] D. Jovcic, D. V. Hertem, K. Linden, J. Taisne, and W. Grieshaber,
Voltage 460 kV 435 kV - 5.4 % “Feasibility of DC Transmission Networks,” IEEE PES ISGT Europe,
MCB Current 47.2 kA 20.2 kA - 57.2 % Manchester, pp. 1-8, Dec. 2011.
Energy 0.25 MJ 15.55 MJ - 6120 % [4] M. Callavik, A. Blomberg, J. Hafner, and B. Jacobson, “The hybrid
HVDC breaker – an innovation breakthrough enabling reliable HVDC
grids,” Technical Paper, ABB Grid Systems, Nov 2012.
C. Energy Stress Subjected to IGBT Valves [5] J. Rafferty, L. Xu, and D. J. Morrow, “DC Fault Analysis of VSC based
Fig. 10 shows the energy dissipated by the CDCCB and Multi-Terminal HVDC Systems,” ACDC 2012, Birmingham, pp. 1-6,
Dec. 2012.
SDCB IGBT valves when applied in test bed model of Fig. 7.
[6] M. Hadjikypris and V. Terzija, "Transient fault studies in a multi-
Fig. 10 (a) shows the energy dissipated by the LCS valves. terminal VSC-HVDC grid utilizing protection means through DC circuit
SDCCB LCS had to conduct during the complete current breakers," IEEE POWERTECH 2013, Grenoble, pp.1-6, June 2013.
limiting duration and the energy dissipated across SDCCB LCS [7] U. A. Khan, J. Lee, I. Seo, F. Amir, and B. Lee, “Feasibility analysis of
was much greater than CDCCB LCS. This will require better a novel hybrid-type superconducting circuit breaker in multi-terminal
cooling system for the SDCCB LCS. The most significant HVDC networks,” Physica C: Superconductivity and its Applications, in
energy difference was between CDCCB and SDCCB MCB press, available online since 4 April 2015,
http://dx.doi.org/10.1016/j.physc.2015.03.015.
valves as shown in Fig 10 (b). MCB valve is the most
[8] U. A. Khan, J. Lee, I. Seo, F. Amir, and B. Lee, “A novel model of
expensive and complex component of hybrid DCCB. SFCL in HVDC hybrid-type superconducting circuit breaker and its performance
SDCCB had significantly decreased the energy dissipated analysis for limiting and breaking DC fault currents,” in IEEE Trans.
across the MCB. This will considerably increase the efficiency Appl. Supercond., unpublished.
and life of the SDCCB MCB. Table III shows the percentage [9] C. M. Franck, “HVDC circuit breakers: a review identifying future
change in the energy dissipated across IGBT valves of DCCBs. research needs,” IEEE Trans. Power Del., vol. 26, No. 2, April 2011.
[10] C. Meyer, M. Kowal, and R. W. De Doncker, "Circuit breaker concepts
From the results we could infer that the SDCCB had for future high-power DC-applications," 40th IEEE IAS Annu. Meeting
decreased the stress levels for the costly and critical MCB Conf., vol. 2, pp. 860-866, Oct. 2005.
valve during the DC fault current conduction interruption [11] K. Nakanishi, Switching Phenomena in High-Voltage Circuit Breakers,
stages. There was a significant decrease in the energy Marcel Dekker Inc., New York, 1991, pp. 163-168.
dissipation across the SDCCB MCB and also a considerable [12] K. R. Padiyar, HVDC Power Transmission Systems, 2nd ed., New
decrease in the peak DC fault current that MCB had to Academic Science Ltd, Kent, UK, 2011, pp.337–355.
interrupt. [13] G. Asplund et al, “HVDC Grid Feasibility Study Working Group B4-
52,” CIGRE, April 2013.
[14] A. Dennis et al (2013 Sept.), “DC Grids: motivation, feasibility and
VI. CONCLUSION outstanding issues”, TWENTIES Project Report D5.4 [Online],
This research paper presents a comparative study on the Available: http://www.twenties-project.eu, pp. 29-40, Sept. 2013.
electrical and thermal stress distribution across IGBT valves of [15] J. Hafner, and B. Jacobson, “Proactive hybrid HVDC breakers – a key
innovation for reliable HVDC grids,” CIGRE International Symposium -
the conventional hybrid DCCB (CDCCB) and superconducting The Electric Power Syst. of Future, Bologna Italy, 2011.
hybrid DCCB (SDCCB) during fault conditions. Realistic
[16] M. K. Bucher and C. M. Franck, "Contribution of Fault Current Sources
CDCCB and SDCCB models were developed by selecting the in Multiterminal HVDC Cable Networks," IEEE Trans. Power Del., vol.
impedance values of commercially available IGBTs. To create 28, pp. 1796-1803, July 2013.
the electrical and thermal stress profiles, CDCCB and SDCCB [17] Technical Information FZ1200R45KL3_B5 IGBT module, Infineon,
were placed in HVDC test bed model and transient simulations revision 3.0, date of publication 2013-11-08.
579