Fom and Sons Limited submitted a construction program for the contract to construct a staff house, install rainwater harvesting tanks, and solar lighting at Yoyo Health Centre III. The 6-month program allocates 1 month for preliminary works and mobilization. Months 2-3 focus on site preparation, excavation, and building foundations. Wall construction, mechanical works, and roofing will occur during months 3-4. General finishes, electrical, fittings, and painting will take place in months 4-5. The project will be commissioned and handed over in month 6, with a 6-month defect liability period to follow.
Fom and Sons Limited submitted a construction program for the contract to construct a staff house, install rainwater harvesting tanks, and solar lighting at Yoyo Health Centre III. The 6-month program allocates 1 month for preliminary works and mobilization. Months 2-3 focus on site preparation, excavation, and building foundations. Wall construction, mechanical works, and roofing will occur during months 3-4. General finishes, electrical, fittings, and painting will take place in months 4-5. The project will be commissioned and handed over in month 6, with a 6-month defect liability period to follow.
Fom and Sons Limited submitted a construction program for the contract to construct a staff house, install rainwater harvesting tanks, and solar lighting at Yoyo Health Centre III. The 6-month program allocates 1 month for preliminary works and mobilization. Months 2-3 focus on site preparation, excavation, and building foundations. Wall construction, mechanical works, and roofing will occur during months 3-4. General finishes, electrical, fittings, and painting will take place in months 4-5. The project will be commissioned and handed over in month 6, with a 6-month defect liability period to follow.
Plot: 1 Olwol Road Opposite Tipo Paco Lira City Email: fomandsonslimited@gmail.com Tel: 0772440375 TIN: 1012884715
Submission Date: 11th May, 2022
ATTENTION: CONSTRUCTION OF 1 SEMIDETACHED STAFF HOUSE, SUPPLY AND
INSTALLATION OF TWO 5,000 LTR CAPACITY STAINLESS STEEL RAIN WATER HARVESTING TANKS, LIGHTENING PROTECTION AND SOLAR LIGHTINGS AT YOYO HEALTH CENTRE III SUB PROJECT PROCUREMENT REFERENCE: Yumbe DRDIP/WRKS/21-22/0015 Dear Sir, SUBJECT: CONTRACTORS WORK SCHEDULE / CONSTRUCTION PROGRAMME. PROGRAMMES Duration in Months Activity 1 2 3 4 5 6
Preliminary & general
Items, Block making, Mobilisation of personnels & Equipments
Site preparatory Works, Moulding Building Units & Site Clearance Setting out, excavation & substructure work Walling, Mechanical works & Roofing
General Finishes, Electrical
Works, Fittings, Water Harvesting, Furniture, Fixings & Painting
Commissioning & hand over
DEFECT LIABILITY PERIOD IS SIX (06) MONTH AFTER COMMISSIONING
Note: The shaded area shows the activities to be carried out Sign……………. Name: Owidi Felix In the Capacity of Managing Director Duly authorized to sign on behalf of Fom and Sons Limited Dated this 30th Day of April, 2021