Shield Project Summary Phased Budget
Shield Project Summary Phased Budget
Phased budget*
ACCCOUNT TOTAL BUDGET Total
CODE COSTS GROUP BUDGET DESCRIPTION USD MTH 1 MTH 2 MTH 3 MTH 4 MTH 5 MTH 6 USD
3010 Project salaries & benefits 23,400 3,900 3,900 3,900 3,900 3,900 3,900 23,400
3020 Consultants fees 29,000 11,000 7,000 0 5,500 5,500 0 29,000
3040 Recruitment 640 0 640 0 0 0 0 640
Staffing
3050 costs Staff training 0 0 0 0 0 0 0 0
3060 Per-diems & meal allowances 480 0 0 480 0 0 0 480
3070 Volunteers expenses 2,400 0 0 2,400 0 0 0 2,400
3090 Other staff costs 0 0 0 0 0 0 0 0
3110 Vehicle running 1,660 65 50 845 325 325 50 1,660
3120 Public transport 1,060 300 0 600 80 80 0 1,060
Travel
3130 costs Air travel 0 0 0 0 0 0 0 0
3140 Distribution costs 1,053 0 0 0 0 403 650 1,053
3190 Other travel costs 0 0 0 0 0 0 0 0
3210 Venues & accommodation 3,293 400 0 2,893 0 0 0 3,293
3220 Publicity & Public Relations 1,000 600 0 0 0 0 400 1,000
3230 Communications 600 100 100 100 100 100 100 600
3240 Project Printed materials 100 50 0 0 50 0 0 100
3245 activity Workshop consumables 1,460 0 200 1,200 60 0 0 1,460
costs
3250 Medical supplies 13,120 0 0 0 0 6,120 7,000 13,120
3270 Storage costs 330 0 0 0 165 165 0 330
3290 Other project activity costs 0 0 0 0 0 0 0 0
DIRECT PROJECT COSTS: SUB TOTAL 79,596 16,415 11,890 12,418 10,180 16,593 12,100 79,596
Indirect
9000 Project contribution ( +12%) 9,552 1,970 1,427 1,490 1,222 1,991 1,452 9,552
costs
TOTAL PROJECT COSTS 89,148 18,385 13,317 13,908 11,402 18,584 13,552 89,148
*NOTE: The Phased Budget shows a breakdown of the Summary Budget by month, based on the project
activity plan. The phased budget is used in project budget monitoring reports to compare planned
expenditure with actual expenditure.