OHSE MANAGEMENT SYSTEM PROCESSES Doc. No.

AFC/1706/HSE/15
(ISO 45001: 2018 & ISO 14001: 2015) Job code-1706
CONSTRUCTION OF MUMBAI – AHMEDABAD HIGH SPEED Rev. No:00
RAIL Package No: MAHSR – C 2
Date: 26.05.2023
Page:

Permit-to-work -Working on Pressurised Lines & Contaminated Areas

No. Item Addressed Compliant Comment


Y N N/A s
1 Level of Contaminated Gas checked initially & noted.
(Continue recording frequently & note)

2 BA Set available?

3 Open Cable/ Joints de-energised?

4 Escape Route provided?

5 Keep running Fire Water Hose & portable Fire Extinguishers


ready?

Assessment Completed By : Responsibility Accepted By

Date/Time: Permit reference No: