HABITAT FOR HUMANITY ETHIOPIA

BoQ and Specification for the Construction of the 200 Meteres Masonary Retaining Wall Ditch
Location: Addis Ababa Gulele W-01
Price includes supply of materials, transport, labour, water & equipment
Price Quotation Date______________________________

UNIT TOTAL PRICE


R.# DESCRIPTION UNIT QTY PRICE (Birr)
(Birr)
1 1.Excavation & earth work
Site clearing, the clearing and grubbing work shall consist of
scraping soft soil up to 200m depth, clearing, grubbing,
1.1 removing and disposal of all vegetation including trees and
debris, which are within the site.
m2 375.00 74.02 27,757.69
Trench excavation of ordinary soil to an average depth of
130cm and width of 120cm. Price shall include removing
1.2 the existing stone masonary open ditch with 50cm width
and 40cm depth.
m3 340.00 743.77 252,883.30
Trench excavation of soft rock to an average depth of 130cm
1.3 and width of 120cm.
m3 476.00 4,120.23 1,961,228.05
Back fill granular material derived from site around the
1.4 masonary wall compacted in layer properly not exceding
20cm.
m3 136.00 894.69 121,677.23
Back fill granular selected material derived from quarry site
1.5 on top of the ditch and compacted in layer properly not
exceeding 20cm.
m3 27.00 2,371.25 64,023.70
Cart away of any excavated materials from site clearing ,
1.6 demolishing and trench to a dumping site on average 2km
away in the wereda territory. m3 728.00 220.28 160,363.48
Sub-total 2,587,933.44
2 Installation of class ''c'' full concrete pipe
Supply and lay standard full concrete pipe ditch 100cm laid
2.1 on 10cm red ash base the pipe joint shall be sealed in 1:4
cement and sand mortar
ml 60.00 16,956.15 1,017,369.26
Sub-total 1,017,369.26
3 MASONARY WORK
3.1 Supply and build hard trachytic or equivalent stone open
masonary with internal clear width of 100cm and depth of
120cm. The masonary wall shall be constructed on both
right and left side. Both walls shall have 50cm width at the
top and 70cm width at the bottom. The masonary wall bed
shall be constructed with 50cm thick trachytic stone. The
internal wall and bed of the masonary shall be properly m3 344.00
plastered and screed with 1:4 ratio cement mortar.

7,483.49 2,574,321.52
50cm thick Hard tryptic or equivalent dressed masonary
stone manhole (150cm *120cm width internally) bedding in
cement mortar (1:4). Internal wall top & bottom faces
3.2 cleanly finished with cement plastering. Including 200mm NO 3.00
thick mass concrete base.
1,160.26 3,480.78
Sub-total 2,577,802.30
4 CONCRETE WORK
15cm thick reinforced concrete manhole cover C-25 with
minimum cement content of 360kg/m3 cast in-situ into
braced timber formwork and vibrated around rod
reinforcement bars and cover the manhole with 1:4 ratio
4.1 mortar. (price shall include supply, cut and fix timber NO 3.00
formwork)

3,645.00 10,935.00

boq,spec price
HABITAT FOR HUMANITY ETHIOPIA
BoQ and Specification for the Construction of the 200 Meteres Masonary Retaining Wall Ditch
Location: Addis Ababa Gulele W-01
Price includes supply of materials, transport, labour, water & equipment
Price Quotation Date______________________________

UNIT TOTAL PRICE


R.# DESCRIPTION UNIT QTY PRICE (Birr)
(Birr)
Supply and lay 200mm thick reinforced concrete pavement
on top of concrete pipe with mix ratio of 1:2:3 cement sand
4.2 and gravel price shall include surface preparation and
compaction before applying concrete.
m2 100.00 3,375.00 337,500.00
Reinforcement steel bars according to the drawing price
4.3 includes cutting, bending, placing in position and tying with
black wire.

Dia 14mm deformed bar for concrete pavement mesh on


a tope of concrete pipe
kg 337.31 175.50 59,197.91
Dia 12mm deformed bar for 15cm thick reinforced concrete
b manhole cover
kg 56.74 175.50 9,957.87
Sub-total 417,590.78

boq,spec price
HABITAT FOR HUMANITY ETHIOPIA
Summary for 200 meters masonary retaining wall ditch
Location: Gulelw W-01
R.# Descriptions Total Amount (Birr)
1 Excavation and Earth Work
2 Installation of Class ''C'' Full Concrete Ditch
3 Masonary Work
4 Concrete Work
Sub Total
15% VAT
Total Amount Including 15% VAT
HABITAT FOR HUMANITY ETHIOPIA
BoQ and Specification for the Construction of the 700 Meteres Concrete Pipe Ditch
Location: Addis Ababa Akaki W-03
Price includes supply of materials, transport, labour, water & equipment
Price Quotation Date______________________________

UNIT PRICE TOTAL PRICE


R.# DESCRIPTION UNIT QTY (Birr) (Birr)
1 1.Excavation & earth work
Site clearing, the clearing and grubbing work shall consist of
scraping soft soil up to 200m depth, clearing, grubbing,
1.1 removing and disposal of all vegetation including trees and
debris, which are within the site.
m2 720.00 74.02 53,294.76
Trench excavation of ordinary soil to an average depth of
80cm and width of 100cm. Price shall include removing the
1.2 existing stone masonary open ditch with 50cm width and
50cm depth.
m3 528.50 619.81 327,570.64
Trench excavation of soft rock to an average depth of 80cm
1.3 and width of 100cm.
m3 2.80 3,433.52 9,613.86
Back fill granular material derived from site around the
1.4 masonary wall compacted in layer properly not exceding
20cm.
m3 111.30 894.69 99,578.50
Back fill granular selected material derived from quarry site
1.5 on top of the ditch and compacted in layer properly not
exceeding 20cm.
m3 6.00 2,371.25 14,227.49
Cart away of any excavated materials from site clearing ,
1.6 demolishing and trench to a dumping site on average 2km
away in the wereda territory. m3 337.50 220.28 74,344.33
Sub-total 578,629.58
2 Installation of class ''c'' full concrete pipe
Supply and lay standard full concrete pipe ditch 60cm laid
2.1 on 10cm red ash base the pipe joint shall be sealed in 1:4
cement and sand mortar
ml 280.00 15,414.69 4,316,112.02
2.2 Ditto as item 2.1 but with dia.40cm concrete pipe ml 350.00 18,669.84 6,534,442.96
Sub-total 10,850,554.98
3 MASONARY WORK
3.1 50cm thick trachytic or equivalent dressesd masonary
stone manhole (80cm*80cm width internally)bedded in
cement mortar (1:4). Internal wall top & bottom faces
cleanly finished with cement plastering. Including 200mm
thick mass concrete base. The manhole shall be constructed NO 25.00
with in 12-meter interval alongside the ditch and at every
road junction.
6,236.24 155,906.10
50cm thick Hard tryptic or equivalent dressed masonary
stone manhole (60cm *60cm width internally) bedded in
cement mortar (1:4). Internal wall top & bottom faces
cleanly finished with cement plastering. Including 200mm
3.2 thick mass concrete base. The manhole shall be constructed NO 30.00
within 12-meter interval a longside the ditch and at every
road junction.
966.88 29,006.51
Sub-total 184,912.61
4 CONCRETE WORK
15cm thick reinforced concrete manhole cover C-25 with
minimum cement content of 360kg/m3 cast in-situ into
braced timber formwork and vibrated around rod
reinforcement bars and cover the manhole with 1:4 ratio
4.1 mortar. (price shall include supply, cut and fix timber NO 55.00
formwork)

3,645.00 200,475.00

boq,spec price
HABITAT FOR HUMANITY ETHIOPIA
BoQ and Specification for the Construction of the 700 Meteres Concrete Pipe Ditch
Location: Addis Ababa Akaki W-03
Price includes supply of materials, transport, labour, water & equipment
Price Quotation Date______________________________

UNIT PRICE TOTAL PRICE


R.# DESCRIPTION UNIT QTY (Birr) (Birr)
Supply and lay 200mm thick reinforced concrete pavement
on top of concrete pipe with mix ratio of 1:2:3 cement sand
4.2 and gravel price shall include surface preparation and
compaction before applying concrete.
m2 12.00 3,375.00 40,500.00
Reinforcement steel bars according to the drawing price
4.3 includes cutting, bending, placing in position and tying with
black wire.
- -
Dia 14mm deformed bar for concrete pavement mesh on
a tope of concrete pipe
kg 108.81 175.50 19,096.16
Dia 12mm deformed bar for 15cm thick reinforced concrete
b manhole cover
kg 488.40 175.50 85,714.20
Sub-total 345,785.36

boq,spec price
HABITAT FOR HUMANITY ETHIOPIA
Summary for 700 meters concrete pipe ditch
Location: Akaki W-03
R.# Descriptions Total Amount (Birr)
1 Excavation and Earth Work
2 Installation of Class ''C'' Full Concrete Ditch
3 Masonary Work
4 Concrete Work
Sub Total
15% VAT
Total Amount Including 15% VAT
HABITAT FOR HUMANITY ETHIOPIA
GRAND SUMMARY
Construction of 200 Meters Masonary Retaining Wall Ditch and 700 Meters Concrete Pipe Ditch
Location: Gulele W-01 & Akaki W-03
R.# Descriptions Total Amount Including 15% VAT (Bir

1 Construction of 200 Meters Masonary Retaining


Wall Ditch

2 Construction of 700 Meters Concrete Pipe Ditch

Grand Total Amount Including 15% VAT