Method Of Procedure

MoP - Restart Access Point

Site name : All Regional Batch 1

Prepared By :

Desember 2023
Publication Detail
Secrecy
Material contained in this document is information representing products, services,
and methods of PT. Sigma Cipta Caraka (TELKOMSIGMA). The document, includes
information in it, should not be disseminated outside of PT Telekomunikasi Seluler
Tbk (TELKOMSEL). This document may not be duplicated, used or disseminated for
purposes other than for evaluation and use in its methode of procedure purposes.

DocumentStatus
This document is the procedure for Restart access point

DocumentControl
Document File Name: MoP – Restart ClearPass nacp-dev-01 (Standby Publisher).docx
Ver. Date Author Reviewer Approval Note

1.0 05 Desember 2023 Ridwan Firdaus Nandi Pura Prasetya Nugraha Document Initial
Nugraha

Author Reviewer Approval

(Ridwan Firdaus) (Nandi Pura Nugraha) (Prasetya Nugraha)

ii
Confidential
TABLE OF CONTENTS

Publication Detail ii

TABLE OF CONTENTS iii

1. Background 4

2. Topology & IP 4

3. Detail Procedure 6
3.1. Procedure Pre Activity 6
3.2. Procedure Activity 6
3.2.1. Backup Configuration

3.3. Procedure Post Activity 7

4. Procedure Condition 7

iii
Confidential
1. Background

This document has been prepared as guidance to This document has been prepared as
guidance restart access point .

2. Topology

The details for Network topology is as follow :

Figure 1. Topology

4
Confidential
The details of network for ClearPass Policy Manager connectivity is as follow.

WLC Ip Address Server Role


Wlc.ofc.ro-renon.01.01 10.98.5.209 Server Publisher

Table 1. WLC Manager Connectivity

5
Confidential
3. Detail Procedure
3.1. Procedure Activity

Planned Planned Duration Actual Actual Duration


Activity CI (Hostname/IP) Command/Syntax Status PIC (Name & Phone) Service Capture Evidence
Start End (Min) Start End (Min)
Impact

Checkpoint Go/No Go Before Not


Activity #1 started

Pre Requisites before D-Day

Knowledge Management has been Not


updated started

Ack Business User

Pre Requisites on D-Day just before Activity Starts

Login to WLC
1.Go To Configuration
Before Configuration 2. Diagnostic > Technical Support > Backup Flash
10.98.5.209
3. Copy Backup

Checkpoint Go/No Go Preparation Not


#2 started

Deployment

Login to WLC 22.00 00.00 Not


Detail Deployment Step 1. show ap database 120 Ridwan Firdaus (+62 822-6086-8005) Impact
10.98.5.209 WIB WIB started
2. Apboot all local

Not
started
Post Deployment
Sanity Test (Login, Browse, Login to WLC 1. show ap database (makesure AP in Status UP) 00.00 00:30 Not
30 Ridwan Firdaus (+62 822-6086-8005) No Impact
Purchase Package) is pass 100% 10.98.5.209 2. Capture Status Access Point at Dashboard WIB WIB started

Not
started

Monitoring Service
Success Criteria : Not
1. SR verify status > 99% started
2. Response Time <5 s

Not
Checkpoint Go/No Go Decision #4
started

Not
Monitoring Period Full Day
started
Rollback Activity (If apply)
Not
Roll back activity
Started

6
Confidential
3.2. Change back Steps

Planne Planne Duration Actual Actual Duration


Activity CI (Hostname/IP) Command/Syntax Status PIC (Name & Phone) Service Capture
d Start d End (Min) Start End (Min)
Impact Evidence

Not
Checkpoint Go/No Go Decision #4
started

Rollback

1.Go To Configuration
2. Diagnostic > Technical Support > Restore
Login to WLC 3. Restore Backup 23.25 00:25 Not No
Restore Configuration 60 Ridwan Firdaus (+62 822-6086-8005)
10.98.5.209 WIB WIB started Impact

Capture for status access Login to WLC 1. show ap database (makesure AP in Status UP) 00.25 00.40 Not No
15 Ridwan Firdaus (+62 822-6086-8005)
point 10.98.5.209 2. Capture Status Access Point at Dashboard WIB WIB started Impact
Monitoring Service
Success Criteria : Not
1. SR verify status > 99% started
2. Response Time <5 s

4. Procedure Condition

This work procedure will be done by PT. Sigma Cipta Caraka (TELKOMSIGMA) Team and has to be supervised by authorized PT.
Telekomunikasi Seluler Team, and the schedule shall be proposed in advance to PT. Telekomunikasi Seluler.

Upon the completion of the works, PT. Sigma Cipta Caraka (TELKOMSIGMA) team shall inform to PT. Telekomunikasi Seluler that the work
has been completed

7
Confidential