Vetting of Building Plan Submitted For Permit Dated 5TH July, 2023

You might also like

Download as pdf or txt
Download as pdf or txt
You are on page 1of 4

VETTING OF BUILDING PLAN SUBMITTED FOR

PERMIT DATED 5TH JULY, 2023

ITEM AREA OF FINDINGS REMARKS


APPLICANT COMMENT IN THE
DRAWING

Thomas Kofi Block plan : ARC-01 1. Need to have more open NB:
Annan & spaces for the following: 1. Please kindly
Victoria Darbo do the
Annan a. Parking space (at least 5- necessary
10% of the occupant should corrections
have packing space) * before
submitting
b. Sewage point (both solid & for
liquid). * consideration
for building
c. Landscaping and recreation
permit
space.

d. Fire assembling point and 2. * highlighted


evacuation movement denotes
direction. critical
comment
2. Orientation of the building which
should be re-considered; needed to be
(recommend the frontage to addressed
face any of the side roads).

3. Setbacks especially the


frontage is not enough. *
Ground floor:ARC -
02

Must also apply to the


other floors 1. Only one access entry and
exit; need to create at least 3
additional ones. *

2. Some of the rooms do not


have natural lighting and
ventilation (Rm
5,6,16,17,18,21,22,29,etc).

The option of providing


alternative source of ventilation
could help.

Need to support your energy


source with standby plant since
the above rooms will need
constant artificial
lighting/ventilation

3. Need for free flow


pedestrians movement; corridor
links to each other should
enhance with security system to
avoid restricting movement
with doors & blocks (not safe
in general outbreak or
emergency situation). *

4. Need to create intermediate


duct to avoid piping line issues.
*

5. The size of stairwell is small


(1m) – minimum of public
building should be 1.2m or
more. *
Section: ARC-08
1. Roof details not showing the
stepping of the roofing. Section
B-B may need to indicate the
section view and the elevation
view ( Grid 11-15). *

2. Kindly clarify the height of


the oversite concrete above the
ground (+600mm or +450mm).

3. Recheck your level


dimensions GFL – 600/450
FIL- 3150+(600/450) SFL-
6300+(600/450) etc.

1. Roof on Grid 5-6, 21-22


Roof Plan: ARC-14 should be detailed to show how
the pitch and support system
would work. Kindly provide
detail in section and on detail
sheet. *

Electrical E01 – E06 1. Detail of the lift system.

2. Kindly remove the gridlines


and dimensions to make the
layout clear and readable if
possible use colour coded. *

Plumbing 1. Kindly remove the gridlines


and dimensions to make the
layout clear and readable if
possible use colour coded. *
BENDING
SCHEDULE. 1. The floor slab rods
STR- 24/25 specification is inconsistent
with the one in 25, 26 etc.
Kindly specify T/R mild steel
or high tensile.

2. Roofing structure detail


sheet.

3. Roof slab details etc.

4. Need for more beam detail


sheet.

5. Need for ground beams and


details.