GHANA ECONOMIC TRANSFORMATION (GET) PROJECT Classic Schedule Layout 11-May-23 10:02

Activity ID Activity Name Original Start Finish Predecessors Total Float Q Q Q Q Q Q Q Q


Duration
J J A S O ND J F M A M J J A S ON D J F M A M J
GET-1 GHANA ECONOMIC
ECO TRANSFORMATION (GET) PROJEC 453 03-Jul-23 30-Sep-24 600 30-Sep-24, GET-1 GH

GET-1.1 Phase1 453 03-Jul-23 30-Sep-24 600 30-Sep-24, GET-1.1 P

GET-1.1.1 Site Mobili


Mobilization & Organazation 26 03-Jul-23 28-Jul-23 248 28-Jul-23, GET-1.1.1 Site Mobilization & Organazation
GET1090 ContractorsTemporary Camp establishment 20 03-Jul-23 22-Jul-23 248 ContractorsTemporary Camp establishment
GET1095 Machinery, and Personnel on site 5 24-Jul-23 28-Jul-23 GET1090, GET 248 Machinery, and Personnel on site
GET-1.1.2 Land Clear
Clearing & Preparation 67 24-Jul-23 28-Sep-23 183 28-Sep-23, GET-1.1.2 Land Clearing & Preparation
GET1080 Setting out 5 24-Jul-23 28-Jul-23 208 Setting out
GET1085 Land Clearing 60 31-Jul-23* 28-Sep-23 GET1080, GET 183 Land Clearing
GET-1.1.3 Surveys & Design works 88 02-Oct-23 31-Dec-23 160 31-Dec-23, GET-1.1.3 Surveys & Design wor
GET1100 Surveys 30 02-Oct-23 31-Oct-23 114 Surveys
GET1105 Preliminary Design 14 01-Nov-23 14-Nov-23 GET1100 114 Preliminary Design
GET1110 Design Review 14 15-Nov-23 28-Nov-23 GET1105 114 Design Review
GET1115 Modification of Design and Approval 30 29-Nov-23 31-Dec-23 GET1110 114 Modification of Design and Approval
GET-1.1.4 Temporary Office 102 02-Jan-24 12-Apr-24 141 12-Apr-24, GET-1.1.4 Temporary Of
GET1020 Setting out and Excavation works 7 02-Jan-24* 08-Jan-24 141 Setting out and Excavation works
GET1025 Foundation 15 09-Jan-24* 23-Jan-24 GET1020, GET 141 Foundation
GET1030 Structure Works 30 24-Jan-24* 22-Feb-24 GET1025, GET 141 Structure Works
GET1060 Finishing Works 30 23-Feb-24* 23-Mar-24 GET1030 141 Finishing Works
GET1065 MEP Works 20 24-Mar-24* 12-Apr-24 GET1060 141 MEP Works
GET-1.1.5 Water Supply
Sup & Waste management Works 135 15-Apr-24 27-Aug-24 27 27-Aug-24, GET-1.1.5 W
GET1045 Well drilling 30 15-Apr-24* 14-May-24 27 Well drilling
GET1050 Water Supply pipe 40 15-May-24* 23-Jun-24 GET1045 27 Water Supply pipe
GET1070 Effluent Treatment Plant works 30 15-May-24 13-Jun-24 GET1045 69 Effluent Treatment Plant works
GET1075 Solid waste management station 35 24-Jul-24 27-Aug-24 19 Solid waste managemen
GET-5-03 Equipment Installation and Testing 30 24-Jun-24* 23-Jul-24 Equipment Installation and
GET-1.1.6 Power supply
sup Works 68 03-May-24 09-Jul-24 600 09-Jul-24, GET-1.1.6 Power
GET1000 Overhead lines 40 03-May-24* 11-Jun-24 83 Overhead lines
GET1005 Transformers Installation 14 12-Jun-24* 25-Jun-24 GET1000 83 Transformers Installation
GET-6-03 Power Supply Testing 14 26-Jun-24* 09-Jul-24 435 Power Supply Testing
GET-1.1.7 Road Works
Work 71 02-Jul-24 10-Sep-24 0 10-Sep-24, GET-1.1.7
GET1015 Road Base 60 02-Jul-24* 30-Aug-24 1 Road Base
GET1040 Asphalt surface treatment 10 01-Sep-24* 10-Sep-24 GET1015 0 Asphalt surface treatme
GET-1.1.8 Completion
Completio Handover 20 11-Sep-24 30-Sep-24 0 30-Sep-24, GET-1.1.8
GET1035 HANDOVER 20 11-Sep-24* 30-Sep-24 GET1040, GET 0 HANDOVER

Actual Level of Effort Remaining Work Page 1 of 1 TASK filter: All Activities
Actual Work Critical Remainin... © Oracle Corporation