DIVISION JAMMU
On behalf of the Presi dent of India , e-tenders in two cover system on turnkey basis are invited from
registered/reputed firms having sufficient relevant experience for the work mentioned below:
S. Description of work Project Estt AAA/ Earnest Cost of tender Time of Eligibility
No Authority TS Money document completio
Criterion of
Deposit n
Bidder
1 UPGRADATION AND Principal 14.13 ACCORDED Rs 28500.00 Rs 1000.00 in 30 OEM/Authorized
GMC & in the Shape of the shape of
RENOVATION OF Associated LACS CDR/FDR/TDR
days /Registered &
Challan through Reputed firms
valid for 12
PSYCHOLOGY HALL NO Hospital months
J&K Govt.
having sufficient
Jammu Treasury
1 OF GMCH JAMMU. pledged to the
indicating experience as per
Executive
Engineer MH Treasury Voucher Annexure “C”
Division Jammu No. & date and similar nature of
also indicating work
the name of work
duly credited to
0059-PWD
(Revenue) and
uploading a copy
of treasury
challan / receipt
on e-tendering
portal.
OR
The bidder may
deposit tender
fee in the shape
of e-Challan
through Account
no.
009701010000
2163 in the
name of
Executive
Engineer
Mechanical &
Hospital
Division Jammu
Name of Bank:
J&K Bank Town
Hall Jammu
Branch
Code:0097
IFSC code:
JAKA0TNHALL
MICR CODE:
180051025
THE NIT CONSISTING OF Qualifying INFORMATION, ELGIBILITY CRITERIA, BILL OF QUANTITIES (BOQ) SETS OF TERMS
& CONDITIONS OF CONTRACT & OTHER DETAILS CAN BE VIEWED / DOWNLOADED FROM THE WEBSITE
www.jktenders.gov.in.
Sd/-
Executive Engineer
Mechanical & Hospital Division
Jammu
1
OFFICE OF THE EXECUTIVE ENGINEER, MECHANICAL & HOSPITAL
DIVISION JAMMU
The Bids shall be deposited in electronic format on the J&K Govt. website www.jktenders.gov.in
1. The hard copies of original documents along with EMD in the shape of CDR/FDR/TDR should be submitted
only by the bidder who is declared as L1 after opening of financial bids in the office of Executive Engineer
Mechanical & Hospital Division Jammu
3. The Technical bids shall be opened online in the Office of Executive Executive Engineer Mechanical &
Hospital Division Jammu
4. In case of holidays/office happens to be closed on the date of opening of the bids, bids will be opened
on the next working day at the same time and venue.
6. Technical Bids must be accompanied with cost of Tender document in shape of challan
through J&K Govt. Treasury indicating Treasury Voucher No. & date and also indicating the
name of work duly credited to 0059-PWD (Revenue).
7. It is presumed that bidder is agreed upon all the terms and conditions of e-NIT and also
thoroughly read the scope of work / Technical Specifications and has accepted all in total
and is well versed with the state’s Laws / Rules of e-tendering.
8. The bids for the work shall remain valid for a period of 180 days from the date of opening of bids.
9. The Bid shall be cancelled:-
a) Any bidder/ tenderer withdraws his bid/ tender during the period of bid validity or makes any
Modifications in the terms and conditions of the bid.
b) In case contractor fails to execute the agreement within 05 days after fixation of contract
10. Instruction to bidders regarding e-tendering process:
a) Bidders are advised to download bid submission manual from the "Downloads" option as well as
from "Bidders Manual Kit" on website www.jktenders.gov.in to acquaint w i t h bid submission
process.
b) To participate in bidding process, bidders have to get 'Digital Signature Certificate (DSC)' as
per Information Technology Act-2000. Bidders can get digital certificate from any approved
vendors.
c) The bidders have to submit their bids online in electronic format with Digital
Signature. No Financial bid will be accepted in physical form.
d) List of documents to be scanned and uploaded within the period of bid submission i.e.:
i) Cost of Tender document in shape of challan through J&K Govt. Treasury indicating
Treasury Voucher No. & date and also indicating the name of work duly crediting to
0059-PWD (Revenue) and uploading a copy of treasury challan / receipt.
a. Earnest Money Deposit/Bid security in shape of CDR/FDR/TDR valid for 12 months or
more pledged to Executive Engineer Mechanical & Hospital Division Jammu.
ii) Other documents comprising of copies of PAN card, Latest income tax Clearance
Certificate/return, GST Registration Certificate, and Completion Certificate
iii) Technical specifications as per Annexure “A”.
Note: The above documents are to be uploaded on the website before opening of
technical bid
a. The bidders are advised to accept and sign each leaf of the tender document with stamp/seal
before uploading on the portal.
2
Note: - Scan all the documents on 100 dpi with black and white option.
11. The department will not be responsible for delay in online submission due to any reasons.
12.Bidders may contact office of the Executive Engineer Mechanical & Hospital Division Jammu for any
guidance for getting DSC or any other relevant details in respect of e- tendering process trough
email or in writing during office hrs on working days only(email for enquiry
mhchgmch@gmail.com)
13. Bidders are advised not to make any change in BOQ (Bill of Quantities) contents. In no case they
should attempt to create similar BOQ manually. The BOQ downloaded should be used for filling the
rate inclusive of all taxes and it should be saved/uploaded with the same name as it contains.
14. The rates and prices shall be quoted by the bidder entirely in Indian Rupees and the rates quoted
shall be deemed to include price escalation and all taxes upto completion of the work unless
otherwise, specified.
15. Bidders are advised to use "My Documents" area in their user on J&K Govt. E-Tendering portal
i.e. www.jktenders.gov.in to store such documents as is required.
1. Scheme of bidding process: The bid submitted by the Bidder shall be in two
separate parts.
A) PART I: This shall be named technical Bid and shall comprise of:
i) Scanned copies of all documents listed in 10 (d) of SBD (Hard copies only to
be submitted only after the bidder is declared L1)
B) PART II: It shall be named Financial Bid and shall comprise of:
i) Item rates price offer as specified in subject matter—the financial bid (i.e.
rates offered in the BOQ) shall be submitted & opened online only. (No
hard copy of Price BOQ shall be submitted
16. Terms and Conditions:
a) The detailed terms & conditions of the NIT are laid down in Annexure “B” of this tender
document.
b) The intending bidders are advised to visit the site to ascertain the exact quantum of work before
quoting their rates.
1. Submission of Bids:
i) The Department may extend the deadline for submission of bids online by issuing an
amendment, in which case all rights and obligations of the Department and the bidders
previously subject to the original deadline will then be subject to the new deadline.
I)
The bid submitted shall be liable to be rejected:-
i)
If the bidder does not upload all the documents as stipulated in the bid document.
ii)
If any discrepancy is noticed between the documents as uploaded at the time of submission
of bid and hard copies of L1 bidder (declared after technical and commercial evaluation as per
Annexure “A”) submitted physically after opening of the financial bid in the office of tender
opening authority.
2. Fundamental breach of contract will include:
i) Continuous stoppage of work for a period of 03 days without authorization of
Engineer-in-charge.
ii) Contractor is declared bankrupt.
iii) Any evidence of involvement of contractor in corrupt practices.
iv) Contractor delays the completion of work beyond stipulated time of completion.
v) Pursuant to the process of termination of defaulted contract, the Department reserves the
right to invite fresh tender for the balance work at the risk and cost of defaulter
contractor.
3. Major labour laws applicable to e stablishment engaged in building and other construction
work:
i) Compliance with Labour Regulation Laws of U.T.
ii) Specification/Quality Control: All items of works shall conform to specifications as per
latest IS specifications/ any other relevant prescribed specifications.
iii) Insurance: Insurance cover to Labour / Machinery / Work / Plant material / Equipment by
4
the contractor shall be mandatory and is sole responsibility of contractor.
iv) Laws Governing the Contract:-The contract shall be governed by Laws of the land.
v) Labour Laws applicable as enforced in the U.T of Jammu and Kashmir
Earnest Money:
i) The earnest money amount shall be in the form of CDR/FDR/TDR of a
nationalized/scheduled bank having branch in Jammu issued in favour of Executive
Engineer Mechanical & Hospital Division Jammu. The CDR/FDR shall be valid for 12 months
or more after the last date of receipt of bids or after the submission of performance security
whichever is later.
ii) The Bid not accompanied by an Earnest Money shall be out-rightly rejected.
iii) If i n case contractor failed to start /complete the work, within the stipulated time
period, his CDR/Earnest Money shall be forfeited after termination of the contract. Besides,
defaulting contractor shall be debarred from taking works in the Department at least for one
year.
iv) Earnest money deposit shall be released after successful completion of the work and
verification by the competent authority. However, the earnest money of unsuccessful
tenderers shall be released after finalization of the tender.
Sd/-
(Er. Vishal Mahajan)
Executive Engineer
Mechanical & Hospital Division
Jammu
5
OFFICE OF THE EXECUTIVE ENGINEER, MECHANICAL & HOSPITAL
DIVISION JAMMU
ANNEXURE “A”
TECHNICAL SPECIFICATION/ SCOPE OF WORK
3 Digital Projecter: The Digital Projecter should have have display of Poly silicon TFT active Matrix, with 01
digital Zoom adjustment having ratio of 1:1.35 and internal sound system of 16W Monaural should be
1024 X 768 pixels and Lens focal length 3.71 mm having manual focus adjustment and digital zoom
adjustment with 02 No’s of USB port compatibility and should be wall,ceiling or front mounted.Make:
ASUS, Barco, BenQ, Canon, Christie, Dukane
4 Providing and fitting of split AC Hot & Cold of 2 TR capacity at Dissection Hall of Anatomy 08
Department of GMCH Jammu of make Voltas /Blue Star/ Diakin/ Hitachi with 01 Nos. Remote Control,
Copper condenser, having minimum 3 star rating along with 5 KVA copper wound automatic wall
mount voltage stabilizer having input voltage range of 110-240 V & output range of 200-240V. The job
includes Providing and laying of 2.5 Sq mm 20 mtr approx from inner to outer unit of AC and also
Copper pipes approx 30 feet length of size( ½,1/4 inches) along with insulation. outdoor stand 01
No, drain pipe upto the main drain, PVC clamps, PVC gutties and screws, tape rolls, Drilling holes in the
wall, window glass cutting for proper installation of AC. Complete job includes cost of material, labour,
to & fro charges and taxes etc.
NOTE: - 1.) The bidders are requested to visit the site to get acquainted with the nature and quantum of job.
Sd/-
Executive Engineer
Mechanical & Hospital Division
Jammu
6
OFFICE OF THE EXECUTIVE ENGINEER, MECHANICAL & HOSPITAL
DIVISION JAMMU
Annexure “B”
The tenderers should bear in mind and comply with the following instructions and terms & conditions
while tendering for the work/contract on turnkey basis as per scope of work and terms and
conditions of the detailed tender document:
1. The tenderer should inspect the site of the proposed work and fully acquaint himself with the
working conditions before quoting their rates as the job is of turnkey basis. It will be construed that
the tenderer has studied the site conditions completely and satisfied him with respect to the same.
2. Definitions: In constructing the terms and conditions of this tender document or of the documents
forming part thereof, unless the context otherwise requires, the following words and expressions
shall have the meanings hereinafter assigned to them.
i) “Department” shall mean Hospital Division GMCH , Jammu represented by The Executive Engineer ,
Mechanical & Hospital Division, Jammu and/or his authorized representative.
ii) “Engineer-in-charge” shall mean Executive Engineer , Mechanical & Hospital Division, Jammu and/or
his authorized representative.
iii) “Contractor” shall mean the tenderer whose tender has been accepted and who is authorized to
enter into an agreement with the Department for execution and completion of the works tendered
for by him.
iv) “Works” shall mean all works to be executed by the contractor in accordance with the specifications
and scope of work as specified in the tender document.
v) Notice in writing or written Notice shall mean a notice or a communication in writing, typed or
printed, sent either under registered post, ordinary post or electronic form to the last known private
or business address or delivered personally by hand to the contractor.
vi) Words incorporating the singular only also include the plural and vice versa.
viii) The Marginal Headings and notes shall not be deemed to be part of this contract or taken into
consideration in the interpretation or construction of this contract.
3. Rates: The rates quoted shall be FOR site, which will include the cost of transportation of materials
to the site, storage at site, all handling at site and incidental expenses, all taxes such as GST, entry
tax, toll tax at Lakhanpur and octroi etc. and the fixing in position for which the items of work is
intended to be operated.
4. Price Escalation: No cost escalation on any account shall be entertained in the quoted rates and
the rates quoted shall be firm & final and shall remain valid till the completion of the contract
5. Tender Acceptance: The acceptance / approval of the tender will rest with the Executive Engineer ,
Mechanical & Hospital Division, Jammu who does not bind himself to accept the lowest tender and
reserves to himself the authority to reject any or all of the tenders received without assigning any
reason(s). Conditional tenders shall be out rightly rejected.
Executive Engineer , Mechanical & Hospital Division, Jammu also reserves the right of accepting the
whole or any part of the tenders received and the tenderers shall be bound to perform the same at
the quoted rates.
6. GST: GST as applicable under law.
7. Commencement of work: The contractor shall commence work on site within 03 days from
the date of issue of work order/letter of intent
8. Site Supervision: The work shall be carried out under the direction and supervision of the
Engineer- in-charge or his representative at site. The contractor shall intimate the name of their
accredited representative who would be supervising the installation and would be responsible for
taking instructions for carrying out the work on day to day basis.
9. Quality: The decision of the Engineer-in-charge with regard to the quality of the material and
workmanship will be final and binding and the material/equipment rejected by the Department shall
be immediately removed by the contractor from the site.
10. Time of completion: (30) Thirty days from the date of issue of work order/letter of intent
7
11. Extension in time: If the contractor shall desire an extension in time for completion of the works
on the grounds of his having been un-avoidably hindered in its execution or on any reasonable
ground certified as such by the Engineer-in-charge, he shall apply to the Executive Engineer ,
Mechanical & Hospital Division, Jammu within 02 days of the date of such event. The Executive
Engineer Mechanical & Hospital Division, Jammu, Government Medical College & Hospital, Jammu
may on reasonable grounds therefore authorize such extension as in his opinion is necessary for
completion of the works in its entirety.
12. Penalty: In the event of contractors failure, neglecting declining or delaying the supplies /
installation or in the event of any damage occurring or being caused or in the event of any default or
failure in complying with any of the terms and conditions of the contract, the govt. shall with or
without prejudice any other remedy available to it under any law for the time being in force in the
state:
a. Terminate the contract after 30 days notice.
b. Recover the amount of loss caused by damage failure or default including the consequential
damage as may be determined by the department and /or
c. Recover the extra cost, if any, involved in allotting the contract to other party and/or.
d. Impose a penalty in form of liquidated damages on accounts of delay beyond the scheduled
delivery period subject to 0.1% value of the contract per day and not exceeding 10%
value of the contract and /or.
e. Forfeiture of earnest money/security deposit.
.
13. Defects Liability Period: The firm shall be bound for a period of 12 months from the date of
commissioning of job for satisfactory operation of the same and shall furnish a guarantee to this
effect to the department/ Government. Any defects found in equipment or any part thereof, which
may be caused by bad workmanship, use of inferior material or otherwise, or if in the opinion of the
department, any repairs / replacement are required to be made to the equipment the firm shall be
liable to remove the defect/ or conduct repairs at his own cost and expenses within a period of 03
days of the receipt of the notice from the department. In the event of failure on the part of the firm
to remove these defects or make repairs within the stipulated period, the department may get the
defects removed or repairs made by any other agency and the cost thereof shall be recovered from
the firm.
14. Addition/Alteration in work contract: No addition/alteration in the work shall be allowed without
prior approval from the competent authority i.e Executive Engineer , Mechanical & Hospital Division,
Jammu. However, any addition/ alteration exceeding 2% of the value of contract value that
improves the overall performance of the system shall be allowed at L.M.R. subject to approval from
Chief Engineer.
15. Contract Signing: After acceptance of the contract the tenderer shall sign the necessary contract
papers/agreement within 05 days of the intimation. Expenses for the agreement including
cost of stamp papers etc. shall be borne by the contractor. The delay or failure to execute the
agreement shall in no way affect the time of completion of work which will be reckoned from the
date of placement of supply order/ work order/ letter of intent.
16. Employee State Insurance: ESI charges, if applicable on the workforce employed, shall be borne
by the contractor.
17. Terms of Payment:
All payments will be made in Indian Currency and will be subject to deduction of Income tax, and
J&K Service Tax at source, on the rates as are in vogue at the time of release of payment.
a) 70% of against safe delivery of material/equipment in full at site and Rest of payment shall be
released after installation, testing & successful commissioning of the all the equipment at site.
However, 10 % payment shall be kept as deposit & shall be released after successful completion
of the warranty period or against bank guarantee of equivalent amount i.e. 10 % of the contract
value from nationalized/reputed bank
8
iii) If i n case contractor failed to start /complete the work, within the stipulated time
period, his CDR/Earnest Money shall be forfeited after termination of the contract. Besides,
defaulting contractor shall be debarred from taking works in the Department at least for one
year.
iv) Earnest money deposit shall be released after successful completion of the work
and verification by the Concerned AEE. However, the earnest money of unsuccessful
tenderers shall be released after finalization of the tender..
19. Watch and ward of equipment/material: The contractor shall be responsible for the watch and
ward of his equipment / materials at site till the completion of work/handing over to the department
In case of any loss or damage to the said equipment / material etc. on any account, the contractor
shall make good the loss or replace the deteriorated material at his cost and expenses and the
Department shall in no case be liable to pay any compensation
20. Currency of bid and payment: The rates and prices shall be quoted by the bidders entirely in
Indian Rupees. Accordingly, all payments shall be made in Indian Rupees.
21. Indemnity:
The contractor shall make the Department harmless and shall settle all compensation claims arising
as a result of accidents etc. aforesaid during the execution of the works at his own cost.
22. Damage to works during or after execution: If the contractor or his workers break, deface,
injure or destroy any part of the structure or other property in the vicinity of the works belonging to
any person in or on which they may be working, such structure, road kerbs, embankments, fence
enclosure, water pipes, cables, drains, electrical or telephone posts, or wares, trees, grass or
grassland or cultivated ground contiguous to the premises on which the work or any part of it is
being executed shall make the same good at his own cost and in default, the Engineer-in-charge
shall cause the same to be made good and deduct the cost thereof from any sums that may due to
the contractor under this contract or from his security deposit for other works under the
Department.
23. Materials, Plants & appliances: The contractor shall arrange at his cost all materials, plants,
tools, appliances and temporary works required for the execution of the works.
24. Force Majeure: Any failure or omission to carry out the provisions of the contract shall not give rise
to any claim by the department or the approved supplier/contractor one against the other if such
failure or omission arises from an “Act of God” which shall include all natural calamities such as fires,
earthquakes, floods, hurricanes, strikes, riots, embargoes or from any political or other reasons
beyond the control of parties including war, whether declared or not, civil war or a state of
insurrection.
25. Decision of the Executive Engineer to be final: Except where otherwise specified in the contract,
the decision of the Executive Engineer , Mechanical & Hospital Division, Jammu, shall be final,
conclusive and binding upon the contractor on all questions relating to the meaning specifications,
design, drawings, the instructions mentioned and the quality of workmanship or
materials/equipment used for the works.
26. Subletting: The contractor shall not assign or sublet the works in whole or part without the written
permission from the competent authority & incase the contractor assign or sublet the contract or
attempt to do so. The contract will be terminated and actions as deemed fit shall be taken by the
department.
27. Warranty Period: The overall job shall be guaranteed for a period of 12 months.
28. Jurisdiction of Court: For any dispute arising out of this contract the Hon’ble High Court of Jammu
&d Kashmir at Jammu only shall have jurisdiction.
29. All other terms and conditions shall be governed by PWD Form No. 25 of J&K Government.
30. All other terms and conditions as reflected in NIT shall also be applicable.
31. ARBITRATION CLAUSE: If any question, dispute or difference whatsoever, arises between the
firm & the Department/Government in relation to or in connection with this contract either of the
parties may give notice in writing of such questions, dispute or difference and the same be referred
to the arbitration of a person to be mutually agreed upon or failing such agreement within thirty
days of receipt of such notice of person appointed by the Jammu & Kashmir government. This
submission shall be deemed to be a submission to arbitration within the meaning of the Jammu &
Kashmir Arbitration Act. In witness thereof the parties hereto have signed this agreement on the
dates respectively mentioned against their signatures. The provision of J&K Arbitration Act Samvat
2002 and of the rules there under and statutory modification thereof shall be deemed to apply to the
arbitration disputes if any regarding reference to courts shall be subject to jurisdiction of J&K courts
only.
32. The hard copies of original documents along with EMD in the shape of CDR/FDR/TDR should be
submitted only by the bidder who is declared as L1 after opening of financial bids in the office of XEN ,
9
Mechanical & Hospital Division, Jammu, Jammu within seven (07) days, failing which bid liable to
be rejected
34. If any item is not mentioned / incorporated in scope of work of NIT, but necessary for successful
commissioning of the job, it shall be deemed to have been incorporated for which no extra cost shall
be paid by the Department.
35. The bidders are requested to visit the site to get acquainted with the nature and quantum
of job.
36. Cancellation: The Department reserves the right to cancel the order in case of fault on the part of
the contracting agency and also prior to the receipt of the intimation regarding taking in hand
execution of work against the order. No, claim whatsoever, shall be tenable against the department
on this account.
Sd/-
Executive Engineer
Mechanical & Hospital Division
Jammu
10
ANNEXURE “C”
LIST OF DOCUMENTS TO BE SCANNED AND UPLOADED WITHIN THE PERIOD OF BID SUBMISSION
1) Cost of Tender document in shape of challan through J&K Govt. Treasury indicating Treasury Voucher No. &
date and also indicating the name of work duly crediting to 0059-PWD (Revenue) and uploading a copy of
treasury challan / / receipt on e-tendering portal. OR The bidder may deposit tender fee in the shape of e-
Challan through Account no. 0097010100002163 in the name of Executive Engineer , Mechanical &
Hospital Division, Jammu
2) Name of Bank : J&K Bank, Town Hall, Jammu.
Branch code : 0097,
IFSC code : JAKA0TNHALL,
MICR CODE : 180051025
3) Earnest Money Deposit in shape of CDR/FDR/TDR valid for 12 months or more pledged Executive
Engineer , Mechanical & Hospital Division, Jammu
4) Copy of PAN card
5) Latest Income Tax Clearance Certificate/return (ITR) (Assessment year 2023-24)
6) Copy of GST Registration Certificate.
7) The firm should be registered on JKPWDOMS
8) Similar Nature Works Completed Certificate along with work order/allotment order copies from
Govt./Semi Govt. During Last 07 Years Ending 30.11.2023 As Mention Below :-
03 Similar Nature Completed Works Costing Not Less Than The Amount Equal To 40% each Of The
Estimated Cost.
Or
02 Similar Nature Completed Works Costing Not Less Than The Amount Equal To 50% each Of The
Estimated Cost.
Or
01 Similar Nature Completed Works Costing Not Less Than The Amount Equal To 80% each Of The
Estimated Cost
9) Intending bidders have to sign & stamp bid acceptance form i.e, Annexure “E” with confirmation of Yes or
No for item no. 1 to 05 in respect of terms and conditions of e-Nit, failing which bid is liable to be rejected.
10) The Bidder should give an undertaking in shape of Affidavit (Notary Attested) for Rs 100/- of currency of
tender dates on non Judicial stamp paper as per Format Enclosed at Annexure “D”. The Stamp paper
should also have clearly mentioned the 1st party name as contractor/ Firm name and 2nd party name as
Executive Engineer , Mechanical & Hospital Division, Jammu along with reference of e-Nit
no.
11) Tender document (SBD) duly signed & stamped on each leaf should also be uploaded.
12) The firms shall have mandatory local services setup i.e within Jammu so as provide the
prompt services to avoid inconvenience to the patient care.
S.NO Percentage of unbalanced bid viz -a- viz Adv.cost on account of Additional performance security
low rate
1 Upto and including 15% below Nil
2 >15% upto and including 20% below 5% of the Advertised cost
3 >20% upto and including 25% below 10% of the Advertised cost
4 >25% upto and including 30% below 15% of the Advertised cost
5 >30% below 20% of the Advertised cost
The condition with regard to APS in case of Abnormally low bids (ALB’s) shall remain as per the prevision of JKPWD manual 2020
1. If the successful bidder L1 fails to submit the APS (additional performance security) failing which the tender will be
cancelled and his bid will not be considered for the same work in case of fresh tender.
2. The additional performance security shall be released only after successful completion of work.
Sd/-
Executive Engineer
Mechanical & Hospital Division
Jammu
11
ANNEXURE “D” On Rs 100/- Stamp paper
(Notary Attested)
FORMAT FOR AFFIDAVIT
2. The undersigned also hereby certifies that neither our firm M/S__________ have abandoned any
work in erstwhile Mechanical Engineering Department Jammu or any other department nor any
contract awarded to us for such work have been rescinded during the last five years period prior to
the date of this bid.
Signature:-
Name:-
Designation:-
Name:-
Address:-
Date:-
Place:-
12
OFFICE OF THE EXECUTIVE ENGINEER, MECHANICAL & HOSPITAL
DIVISION JAMMU
ANNEXURE “E”
1. Payment clause
Terms of payment:-
3. Warranty Clause
12 months (Yes/No)……..
13