Professional Documents
Culture Documents
HIRA - 04-Construction of Ball Handling Pit Rev-01
HIRA - 04-Construction of Ball Handling Pit Rev-01
Date: 03-Jan-2024
SEVERITY EXPLANATION: 1 - Insignificant (Potential Near Miss), 2-Minor (FAC), 3-Moderate (MTC), 4-Significant (LTI) & 5-Major (Fatal).
SR = Severity Rating 5 5 10 15 20 25
1 to 5 : 1 is lowest & 5 is highest
4 4 8 12 16 20
3 3 6 9 12 15
1 2 3 4 5
Risk Level = Severity X Probability LOW PROBABILITY HIGH
Risk Assessment
Approval Team:
Role Name Designation
Hierarchy of Control
orks - 6084 at Tokadeh, Liberia
HSE/6084/HIRA/04
Rev. 01
Fatal).
Low Risk - Some Risk
1 to 8 controls may PROBABILITY EXPLANATION
still justified
9 to Moderate impact Risk - Almost Certain - 5 (weekly)
15 Conduct formal risk
analysis; may
require risk controls Likely - 4 - (monthly)
4 Heavy Vehicle movement. Speed, Hit, slip, trip & fall. Possible Moderate 3 3
5 Removal of Soil Entanglement, & slip or trip Possible Significant 3 4
Possible Significant 3 4
Possible Significant 3 4
Possible Significant 3 4
19. Working in
Live Areas
20. Sling Broken, load drop.
21. Slip, trip & falls
22. Inclement
weather condition
23. Fire and
explosion
and tackles.
5. Overloading of crane
6. Uneven ground for crane set-
up.
7. Not using the tag lines to
control the movement of the
suspended load.
8. Not barricading the swing
radius of the crane.
9. Unstable ground -
Crane topple - property damage
10. Man-machine interface – hit
by, struck by, run over – injuries
12. Machine –Machine interface
– collision – damage
13. Unauthorized entry
– lack of awareness on hazards –
injuries
14. Standing/walking under the
suspended load.
15. Adverse weather
16. Lack of communication
17. Materials shall be tied before
transporting.
10 Rebar installation 1. Improper material handling Possible Moderate 3 3
2. Pinch points
3. Poor ergonomics
4. Fall of rebar
5. Protruding rebars
36. Use the correct and right tools/equipment for the right
job/task
37. Ensure safe transportation of equipment/materials at
the worksite.
38. Avoid throwing of materials
39. All of the materials to be secured while its
transportation on site
40. Keep access/walkways always clear from any
obstruction
41. Stop work all outdoor activity/work in case of any
extreme & worst weather conditions (Rain, storm, fog etc)
42. Restrict movement of heavy vehicles/equipment in
rain / fog
43. Lift plan & Lifting permit to be filled and signed by
Supervisor, Rigger & Crane operator before start of work.
9 1. While handling the rebar, care shall be taken. 1 3 3
2. Watch out pinch points.
3. Proper body poster shall be ensured.
4. wear all mandatory ppe's.
5. Rebars caps shall be provided.