‫ صيانة لوح التوزيع الرئيسية‬MAIN DISTRIBUTION PANLE (MDP)

‫زمن العمل‬ ‫التوصيف‬


‫صيانة شهرية‬
5‫دقيقة‬ SCHEDULED PM SHEET SERVES AS PERMIT TO PERFORM THE CHECK UP. 1
5‫دقيقة‬ CLEAN THE PANEL FROM DUST USING BRUSH 2
5‫دقيقة‬ CHECK AND RECORD THE CURRENT/VOLTAGE 3
5‫دقيقة‬ CHECK ALL CONNECTION FOR LOOSENESS AND OVERHEATING. 4
5‫دقيقة‬ CHECK THE SET POINTS OF THE BREAKERS, TIMER, RELAYS. 5
5‫دقيقة‬ Inspect Lines For Physical Damage. Correct If Necessary. 6
5‫دقيقة‬ CHECK THE CONDITION OF INDICATION LAMPS, RELAYS TIMERS, FUSES, MINI BREAKERS. 7
5‫دقيقة‬ ENSUSRE THE PROTECTIVE EARTH IS CONNECTED TO THE PANEL. 8
Check That All Metering Instruments Are Functioning. Note Readings And Compare With Those
5‫دقيقة‬
Taken Previously. 9
5‫دقيقة‬ Check That Operating Tools/Handles, Keys Are Readily Available In Switchboard. 10
5‫دقيقة‬ Inspect Switchboard Or Circuit Breakers Enclosure For Undue Heating. 11
Check For Undue Noise, Overheating Or Vibration, Loose Parts, Tightness Of Screws/
5‫دقيقة‬
Bolts And Warping, And Report To The Management For Correction Or Repair. 12
‫صيانة ربع سنوية‬
Visually Check Pacb`S, Mccb`S Fuse Switches Or Isolators, For Signs Of Arcing/ Burning. -
5‫دقيقة‬ Checking Of The Pacb`S May Only Be Done If The Circuit Breaker Is Permitted To Be Opened For 1
Servicing And Only Under The Instruction Of The Engineer In Charge-

Examine Resistors And Devices Prone To Overheating, Where And When Possible, Without Shut
5‫دقيقة‬
ting Down The Essential Loads -Check With The Supervising Engineer- . 2
Inspect Earthing Connections, Power Terminations And Control Circuits Without Shutting Down
5‫دقيقة‬
The Mdb And As Per Engineer`S Instruction. 3
Remove All Dust And Debris Inside Cubicles Or Enclosures Where Possible With The Aid Of A Va
5‫دقيقة‬
cuum Cleaner. 4
5‫دقيقة‬ Check That Pacb`S Stored Energy Mechanisms Are Charged. Correct Any Defects. 5
Check Electrical And/
Or Mechanical Operation Of Withdrawable Main Pacb At A Time, In The Test Position And In Co
5‫دقيقة‬
nnected Position, Strictly In Accordance With Engineer`S Instructions, When The Mdb Is Not In 6
Use.
Check Operation Of Mccb`S, Pacb`S Using Their Integral Switching Arrangements To Ensure Me
5‫دقيقة‬
chanisms Are In Sound Good Order. 7

Check Operation Of All Fuse Switches And Isolators And Ensure Mechanisms Are In Sound Work
5‫دقيقة‬
ing Order. Correct Any Defects. Remove All Dust And Debris With The Aid Of Vacuum Cleaner. 8

Check Fuse Links, Carriers, Bridges, For Signs Of Arcing. Ensure Correct Grade Of Fuse Is Fitted.
5‫دقيقة‬
Correct Any Defects. 9
Check That All Metering Instruments Are Functioning. Note Readings And Compare With Those
5‫دقيقة‬
Taken Previously. 10
5‫دقيقة‬ Check That Operating Tools/Handles, Keys Are Readily Available In Switchboard. 11
‫صيانة نصف سنوية‬
5‫دقيقة‬ Inspect Switchboard Or Circuit Breakers Enclosure For Undue Heating. 1
Check For Undue Noise, Overheating Or Vibration, Loose Parts, Tightness Of Screws/
5‫دقيقة‬
Bolts And Warping, And Report To The Management For Correction Or Repair. 2

Visually Check Pacb`S, Mccb`S Fuse Switches Or Isolators, For Signs Of Arcing/ Burning. -
5‫دقيقة‬ Checking Of The Pacb`S May Only Be Done If The Circuit Breaker Is Permitted To Be Opened For 3
Servicing And Only Under The Instruction Of The Engineer In Charge-

Examine Resistors And Devices Prone To Overheating, Where And When Possible, Without Shut
5‫دقيقة‬
ting Down The Essential Loads -Check With The Supervising Engineer- . 4
Inspect Earthing Connections, Power Terminations And Control Circuits Without Shutting Down
5‫دقيقة‬
The Mdb And As Per Engineer`S Instruction. 5
Remove All Dust And Debris Inside Cubicles Or Enclosures Where Possible With The Aid Of A Va
5‫دقيقة‬
cuum Cleaner. 6
5‫دقيقة‬ Check That Pacb`S Stored Energy Mechanisms Are Charged. Correct Any Defects. 7
Check Electrical And/
Or Mechanical Operation Of Withdrawable Main Pacb At A Time, In The Test Position And In Co
5‫دقيقة‬
nnected Position, Strictly In Accordance With Engineer`S Instructions, When The Mdb Is Not In 8
Use.
Check Operation Of Mccb`S, Pacb`S Using Their Integral Switching Arrangements To Ensure Me
5‫دقيقة‬
chanisms Are In Sound Good Order. 9

Check Operation Of All Fuse Switches And Isolators And Ensure Mechanisms Are In Sound Work
5‫دقيقة‬
ing Order. Correct Any Defects. Remove All Dust And Debris With The Aid Of Vacuum Cleaner. 10

Check Fuse Links, Carriers, Bridges, For Signs Of Arcing. Ensure Correct Grade Of Fuse Is Fitted.
5‫دقيقة‬
Correct Any Defects. 11
‫صيانة سنوية‬
5‫دقيقة‬ Substation Must Be Shut Down And Dead Before Annually Tasks Are Carried Out 1
Check That All Metering Instruments Are Functioning. Note Readings And Compare With Those
5‫دقيقة‬
Taken Previously. 2
5‫دقيقة‬ Check That Operating Tools/Handles, Keys Are Readily Available In Switchboard. 3
5‫دقيقة‬ Inspect Switchboard Or Circuit Breakers Enclosure For Undue Heating. 4
Check For Undue Noise, Overheating Or Vibration, Loose Parts, Tightness Of Screws/
5‫دقيقة‬
Bolts And Warping, And Report To The Management For Correction Or Repair. 5

Visually Check Pacb`S, Mccb`S Fuse Switches Or Isolators, For Signs Of Arcing/ Burning. -
5‫دقيقة‬ Checkinng Of The Pacb`S May Only Be Done If The Circuit Breaker Is Permitted To Be Opened F 6
or Servicing And Only Under The Innstruction Of The Engineer In Charg

Examine Resistors And Devices Prone To Overheating, Where And When Possible, Without Shut
5‫دقيقة‬
ting Down The Essential Loads -Check With The Supervising Engineer- . 7
Inspect Earthing Connections, Power Terminations And Control Circuits Without Shutting Down
5‫دقيقة‬
The Mdb And As Per Engineer`S Instruction. 8
Remove All Dust And Debris Inside Cubicles Or Enclosures Where Possible With The Aid Of A Va
5‫دقيقة‬
cuum Cleaner. 9
5‫دقيقة‬ Check That Pacb`S Stored Energy Mechanisms Are Charged. Correct Any Defects. 10
Check Electrical And/
Or Mechanical Operation Of Withdrawable Main Pacb At A Time, In The Test Position And In Co
5‫دقيقة‬
nnected Position, Strictly In Accordance With Engineer`S Instructions, When The Mdb Is Not In 11
Use.
Check Operation Of Mccb`S, Pacb`S Using Their Integral Switching Arrangements To Ensure Me
5‫دقيقة‬
chanisms Are In Sound Good Order. 12

Check Operation Of All Fuse Switches And Isolators And Ensure Mechanisms Are In Sound Work
5‫دقيقة‬
ing Order. Correct Any Defects. Remove All Dust And Debris With The Aid Of Vacuum Cleaner. 13

Check Fuse Links, Carriers, Bridges, For Signs Of Arcing. Ensure Correct Grade Of Fuse Is Fitted.
5‫دقيقة‬
Correct Any Defects. 14

Inspect Electrical Primary And Secondary Connections, Cables And Supports, Insulation For Disc
5‫دقيقة‬ oloration, Excessive Corrosion, Secure Connections, Clean Contacts, Insulation Chafing And Em 15
broiled And Discoloured Cable Or Insulator. Correct Any Defects

Clean The Stationary Part Of The Switchgear With A Clean Cloth, Use Compressed Dry Air For In
5‫دقيقة‬
accessible Areas. Clean Out Debris Or Dust With The Aid Of A Vacuum Cleaner. 16

Examine All Air Filters For Dust Content, Flush With Water & Recoat With Super Coat Adhesive
5‫دقيقة‬
As Recommended By Manufacturer. 17
Check That All Conduit And Cable Gland Terminations Associated With The Switchboard Are Se
5‫دقيقة‬
cure. ********Withdrawable Lv Switchgear******** 18
5‫دقيقة‬ Manually Discharge -For Safety- And Draw Out The Circuit Breakers. 19
5‫دقيقة‬ Check, Clean And Lubricate The Carriages. 20
5‫دقيقة‬ Check All Stationary Primary Disconnects For Evidence Of Overheating 21
5‫دقيقة‬ Arcing Or Corrosion. Clean Or Replace And Apply Protective Coating As 22
5‫دقيقة‬ Recommended. Check Secondary Disconnects And Clean/Adjust As Necessary. 23
5‫دقيقة‬ Inspect All Circuit Breaker`S Drawout Captive Positions, Interlocks And 24
5‫دقيقة‬ Shutter Mechanism Operation. ********All Circuit Breakers******** 25
5‫دقيقة‬ Check Anti Pump Relay Operation. 26
5‫دقيقة‬ Check And Clean Insulated Parts Using A Mild Detergent, A 27
5‫دقيقة‬ Lint-Free-Cloth, Rinsing With Clear Water And Dry. 28
5‫دقيقة‬ Inspect Arc Chutes And Contacts Of Circuit Breakers, Fuse-Switches, 29
5‫دقيقة‬ Isolators, And Repair Or Replace As Per Manufacturer`S Procedures. 30
5‫دقيقة‬ Check Security Of All Electrical Terminations And Connections And Tighten A Necessary. 31
5‫دقيقة‬ Check That All Barriers And Guards Are In Place And Secure. 32
5‫دقيقة‬ Check That Phase Discs And Labels Giving Circuit References Are Securely 33
5‫دقيقة‬ Fixed. Replace Any Missing Items And Update Information As Necessary. 34
5‫دقيقة‬ Ensure That 380 Volt And Other Warning Labels Are Position Where Applicable. 35
5‫دقيقة‬ Check Door Interlocks And That Doors Can Be Securely Closed. 36
5‫دقيقة‬ If A Lock Is Provided, Check That It Functions Correctly. 37
5‫دقيقة‬ Check Enclosure For Paint Work Condition And Signs Of Corrosion. 38
5‫دقيقة‬ Correct Any Defects. 39
5‫دقيقة‬ Visually Inspect Under Voltage Relay, Clean And Carry Out Simulation 40
5‫دقيقة‬ Visually Inspect, Clean And Simulate Test Of Auto-Throw-Over-System-Where Applicable. 41
After Energizing The Substation, Check The Loading Of All Outgoing Circuits On The Lv Circuit Br
5‫دقيقة‬
eakers And Record Readings. 42

Check That The Rating Of The Circuit Breakers And Setting Of The Micro-Processor -
5‫دقيقة‬ Mps- Overcurrent And Ground Fault Relay Are Correct With Regard To Loading, Cabling, Type 43
Of Load, Etc.

Check Relys, Fuses And Other Control Elements For Their Proper Functioning And Signs For Any
5‫دقيقة‬
Abnormalities Like Over-Heating/Arcing Etc. 44