Professional Documents
Culture Documents
Design Basis Memorandum1
Design Basis Memorandum1
DESIGN BASIS
MEMORANDUM
PROJ. DOC. No.: M869-50-00-A-RP-001
SINCOR
Enhanced Oil Recovery Project
TABLE OF CONTENTS
1 SCOPE ............................................................................................................9
1.1 ABBREVIATIONS .............................................................................................................. 10
2.3 General............................................................................................................................... 16
6 MECHANICAL DESIGN................................................................................89
6.1 Equipment Design Basis (includes sparing philosophy) ............................................. 90
6.1.1 Shell and Tube Heat Exchangers................................................................................ 90
6.1.2 Air Coolers................................................................................................................... 90
6.1.3 Pressure Vessels......................................................................................................... 91
6.1.4 Storage Tanks ............................................................................................................. 91
6.1.5 Rotating Equipment ..................................................................................................... 91
6.1.6 Pumps.......................................................................................................................... 92
6.1.7 Packaged Equipment and Miscellaneous Items ......................................................... 92
6.1.8 Fire Protection ............................................................................................................. 92
6.1.9 Steam Generation ....................................................................................................... 93
6.1.10 Miscellaneous:............................................................................................................. 93
8 PIPING DESIGN..........................................................................................109
8.1 General............................................................................................................................. 109
Issue No. A1 Standard Number
P:\Z06835 Sincor Venezuela EOR Project\20-00 PROJ
MANAGMNT\20-20 DBM\Final DBM Document\Master Page: 4 of 166
DBM Rev 0 April 30.doc Issue Date 30/04/07 M869-50-00-A-RP-001
SUBJECT:
DESIGN BASIS
MEMORANDUM
PROJ. DOC. No.: M869-50-00-A-RP-001
9 CIVIL DESIGN.............................................................................................123
9.1 Civil Design Basis........................................................................................................... 123
11.18 Water Treating (Warm Lime Softener, ORF, WAC/SAC Units) ............................... 147
12 OVERALL SCHEDULE...............................................................................148
14 COMMISSIONING.......................................................................................160
Issue No. A1 Standard Number
P:\Z06835 Sincor Venezuela EOR Project\20-00 PROJ
MANAGMNT\20-20 DBM\Final DBM Document\Master Page: 7 of 166
DBM Rev 0 April 30.doc Issue Date 30/04/07 M869-50-00-A-RP-001
SUBJECT:
DESIGN BASIS
MEMORANDUM
PROJ. DOC. No.: M869-50-00-A-RP-001
1 SCOPE
1.1 ABBREVIATIONS
The current proposal is to locate the new EOR facilities within “EOR
Delineation Area” in the south-western part of SINCOR Main Station Area.
This area covers the existing cold Clusters JA, JB, JC, JD and IC. The
precise location of EOR pads and wells will be defined only after completion
of delineation activities in 2007. Also the exact number of well pair per
Cluster will be defined at the completion of delineation. In this Pre-FEED
phase the preliminary locations of the four Clusters and the number of well-
pair on each Cluster were provided by SINCOR. No alternative locations
were considered..
FC PB
OB
FB PC
FA OA OC PA
GE NC QD
GD QE
GC NB ND QC
NA QB
GA QA
GB
HD MD
MC01_st2
ME
HC MC03_st2
HC
1
MC Main Station
RC
RD
HB HC02
MC04
MC12_st2
RC02_st1
WB XA04_st1
HC03
1
HC13_st1
HC
MC05_st3 RC03
RA04 XA
RC06 RA03 WA02_st1
RC05_st1 WA01
HC04_st1
WC
YC0
WC04
RC04
MC06 XA0
RA
SE0
LE YC
IF02 IF01_st1
SE SC
IF
SE1
VD
SE05 SC01 YC10_st1
IE IB01
IF10_st1
LD0
SE1
VD04
WA09
YC04
YC11_Mai
LD
SE06
SE1 SC02_st1
VC02
IB
IF03_st1
SB
VD1 YC11_Later
VC
EOR
VD06
ID01 SB01 WA04_st1 YB06 YB02_st1
IB02 IB03
LC01 LC02_st1 SE07 LD06_st1 SB07_st1
SB0
LC
IF05 YC05_st2 YB07
VC03 VD1 YB04_st1
ID YB
ID03 LD08
IF06 SC06_st3
SB02 VC08 VD08_st1
IB05 LC03_st1
LC0 LC04 VD20_st1 YA01 YB0 YB08
VB08 VD2 YA03_st1 YB05_st2
ID04_st1 LA0 LA2 SD01 SD0
Delineation
LA0
LA2 SA0 LD09_st1 SD06 VC05
VB YA
SA01 SD02_st1 VC1 VB09
YA04_st1 VD23_st1
ID05_st2 SA07_st1
VC10
IA
IB06 LC11_st2 LA2 LD10_st1 SB03_st3 SB06_st1
SA
ID06 IA02 IA01_st1 LA1
SD0
LD04_st1 SB0
SD
VC09_st2 VB10_st1
IB07 SD03
VB02 YB10
IC01 YA1
VB0
LA
LA2
LD05_st1 YA05
Area
IC06 IA04 IA11LA0 LC12_st1
SA09
ZC
IA1 YA09
ID07 SD04
VB12_st1
LC06 SA04
LB
LB0 VB04 YB12_st2
JB05 LB01
JB01_st1 VB05
ID08_st1 IA05_st1 LA1
JB02 JB06 YA10YB13_st1
LB0 SD05 SD09 VB06
IC UC
LB07_st1 SA06_st1
ID09 ID10_st2 LA12_st1
IC03_st3 LB0
IA10
UD
JB03_st2
JB IA06_st1 LB0 LB0
TC
TB
IC05
LA0
JA09_st1
LA05_st1
KA02 KA07
KA0 LB11_st3
JB04_st1
JA02_st3 IC08_st1
KA LA04 ZB
IC1
LB05 JA UB
JA01_st2 KA08
JB07_st3
JA12
KC UE ZA
KA09_st1
JB08_st5 KA04
JA03_st3 KA1
JD01 JA11_st1 KA1
JD08
KA0 KA10
JA07
JC01_st1
JD06_st1 JD12_st1
JC04_st1
JC03_st1 JC06
The SINCOR Enhanced Oil Recovery (EOR) Project is a thermal heavy oil
production facility. It will be designed to produce extra heavy oil (EHO;
8.5°API) at a rate of 20,000 barrel per calendar day (BOPCD). The project will
consist of four well-pads and a Substation with interconnecting pipelines. All
major processing equipment components are located at the Sub Station with
some production testing and group separation facilities located at the well
pads.
Diluent will be blended with the produced fluids to allow conventional oil-water
separation techniques to be utilized. The facilities will consist of numerous
processes that will be integrated to provide a good range of operating
flexibility, efficiency, and reliability.
2.3 General
The aim of the EOR project is to prove the effectiveness of the steam
assisted hot production mechanism and to define a process scheme adapted
to treat the produced Extra Heavy Oil. The surface facilities will be designed
with enough flexibility to test the various EOR mechanisms.
The field facilities will initially be comprised of 4 Clusters which will contain
surface facilities necessary for injection of steam and recovery of EHO
production. Oil will be collected in four Clusters that will include the following
features:
Three Clusters with a total of 18 SAGD well pairs
• Steam distribution header
• Lift gas distribution header
• Production header
• Group separator
• Test separator
• Produced gas condenser and separator
• Group emulsion pumps
The EOR Sub Station will be designed to treat 20,000 BPD of EHO. The
EHO will be diluted using a naptha diluent. This diluted EHO is called DCO,
Diluted Crude Oil. The Sub Station will treat either Make-up water from the
Main Station, produced water from the production wells or a combination of
the two waters. The treated water will be used in steam generators to
produce high pressure steam for the steam injection wells.
The Substation facilities comprise of the following processes:
• Oil Treatment
• Produced Gas Treatment
• Produced Water De-oiling
• Produced Water Treatment
• Steam Generation
• Tank farm
• Utilities and support facilities
The Substation and the existing Main Station will be connected by the
following pipelines:
• Makeup water to Substation (de-oiled produced water from cold
production)
• High pressure sweet dry natural gas to Substation
• Diluent to Substation
• Diluted heavy oil product to main station
• Disposal water from Substation to injection well pipeline
Prevailing Direction SW
Maximum recorded 35 °C
Design maximum 35 °C
Average 26.7 °C
Design maximum 88 %
Maximum recorded in 1 95 mm
hour
3.8 Atmosphere
Thunderstorm N.A.
Frequency
5 PROCESS DESIGN
5.1.1 General
The design factor philosophy shown below has been defined according to the
specificity of the project and the uncertainties of the simulation results.
The design philosophies for all facilities have been defined by SINCOR and
are summarized in the following table:
Clusters Substation
Clusters Substation
Clusters Substation
Environmental Regulations
The Oil – Water Separation design shall be based on the following cases:
The base case design for the produced water treatment plant assumes that
100% of the injected steam will be recovered as produced water. However,
the mass balance study and sizing of equipment was undertaken to
accommodate the start up of the plant, which allows for a lower produced
water recovery rate.
Ample cold produced make up water is available, hence, significant losses of
hot produced water to the reservoir will not adversely impact the long term
performance of the water treatment system. If volumetric flowrates of
produced water increase dramatically, disposal may be limited by the
current/proposed capacity of the system and may need to be investigated at
the detailed design stage.
The plant design parameters for the oil and de-oiling systems are based on
an assumed SOR of 2.7. However, the oil treatment train will be designed to
accommodate higher oil production rates that would be expected if the
operating SOR reaches 2.0. Operators should reduce the steam injection
rates as the SOR drops. They should focus on keeping the total liquid
throughput (oil + water) at about 74,000 BPD.
Two treating trains will be installed to operate in parallel. Each treating train
will consist of a free water knockout drum (FWKO) followed in series by a
treater. Each train will be sized to accommodate 50% of the plant’s oil
processing capacity. Using two smaller treating trains offers the following
benefits:
• Smaller loads when shipping the vessels to site;
• Reduced disruption in the event of treater upset;
• Better turndown capacity (reducing throughput to below 40% of design
capacity can lead to fluid channelling and off-spec product);
• Allows alternative chemicals to be tested with one treatment train
without jeopardizing the performance of the other train; and
• Allows sustained production if one of the treatment trains requires
servicing (de-sanding, valve replacement, instrumentation service, grid
replacement, exchanger cleaning, etc.).
The water treatment system will be designed for the removal and control of
several key water scaling components. The removal and/or control of these
parameters are important to avoid process conditions where excessive high
temperature boiler tube scaling occurs that may result in tube failure. These
components are listed below:
• Residual Hardness
• Residual Reactive Silica
• Residual Free Oil
• Residual DOC
• OTSG Blowdown TDS
No over-design factor will be built into the boiler feed water treatment train or
steam generators. The system must be designed to produce a total of 8,507
tonnes per day of dry saturated steam at 9,900 kPag for distribution to the
Clusters (53,500 BWPD cold water equivalent).
The following assay data should be used for the simulation and for the
process design basis:
Cut Point (mass %) TBP (degC)
0 128.3
2 215.58
5 268.16
10 313.18
15 346.88
20 378.06
30 439.88
40 490.34
50 543.56
60 607.78
70 704.22
80 811.37
90 866.24
Density at Std. Cond. = 1011 kg/m3
Viscosity at 47.6 degC = 9960 cSt
Viscosity at 150 degC = 36.26 cSt
Reference density data was obtained from the LB-07 PVT Analysis Summary
in section 4.1 of the SINCOR EOR Project General Technical Description
Pre-Qualification Dossier – Annex 1.
Reference viscosity data was obtained from section 3.6 of the TOTAL Hot
Production Phase 1 (HPP1) Process Report Conceptual Study
H2S levels in the produced gas are expected to start out at about 0.01% (100
ppm), and could ramp up to 1.2% due to the aquathermolysis phenomenon.
Lift gas will significantly dilute the produced gas.
Diluent is needed to reduce the density and viscosity of the EHO. This will
allow the water to be removed from the oil using conventional gravity
separation processes.
The diluent is a naptha mix of effluent mainly from Hydro-treatment and Mild
Hydro-cracker coming from the downstream upgrader.
The diluent mixture is expected to correspond with the following average
assay data
The diluent supply for the Substation will be obtained from the Diluent Trunk
line next to derivation to Cluster IC. The operating conditions at this tie-in
point are listed below.
A supply pipeline to the EOR Substation will be tied into the water re-injection
pipeline leaving the SINCOR New Water Disposal Tank (Main Station
Upgrade Project). The water is expected to be de-oiled water from cold
Issue No. A1 Standard Number
P:\Z06835 Sincor Venezuela EOR Project\20-00 PROJ
MANAGMNT\20-20 DBM\Final DBM Document\Master Page: 40 of 166
DBM Rev 0 April 30.doc Issue Date 30/04/07 M869-50-00-A-RP-001
SUBJECT:
DESIGN BASIS
MEMORANDUM
PROJ. DOC. No.: M869-50-00-A-RP-001
Component Concentration
+
Na 2,440 mg/L
+
K 79 mg/L
++
Ca 5.1 mg/L
Mg++ 9.2 mg/L
SiO2= 9 mg/L
CO3= 25 mg/L
HCO3- 2473 mg/L
SO4= 1.8 mg/L
Cl- 2,436 mg/L
Total Hardness 50.5 mg/L
pH 8.1
Salinity mg/L
Oil and Grease 40 mg/l
Total Alkalinity 2,069.6 mg/l
The anticipated operating conditions at the tie-in point are listed below.
A pipeline and disposal well system will be designed provide for the final
disposal of all wastewaters generated by the process. This water may
originate from any of the sources listed below.
Flow Stream 1:
• OTSG Blow Down Wastewater
Flow Stream 2:
• SAC regeneration waste.
• WAC regeneration waste.
• Spent WLS sludge liquids (supernatant from a settling pond or centrate
from a centrifuge).
• Excess Produced water from thermal heavy oil production.
The flow rates from each source will vary throughout any given operating day.
For the preliminary design these wastewater flows have been separated into
two streams. The first stream designated for direct deep well injection is the
OTSG blow down wastewaters. All other wastewater flows from the plant are
combined in this pond for subsequent disposal. This combined flow from the
pond represents the second stream for disposal.
The preliminary design combined these Flow Streams into a single deep well
disposal system. This design assumption was based upon the thought that
the pond settling system will provide sufficient time for Flow Stream 2 to
stabilize and reach chemical equilibrium.
However, before the final design can be confirmed, a detailed chemical
compatibility evaluation of these wastewater streams will need to be
undertaken to confirm long term performance and assess potential deep well
operational limitations associated with the potential for chemical compatibility
problems. It may be likely that two separate deep well disposal systems will
be required to ensure a high reliability of the system. Logical pre-treatment
Issue No. A1 Standard Number
P:\Z06835 Sincor Venezuela EOR Project\20-00 PROJ
MANAGMNT\20-20 DBM\Final DBM Document\Master Page: 42 of 166
DBM Rev 0 April 30.doc Issue Date 30/04/07 M869-50-00-A-RP-001
SUBJECT:
DESIGN BASIS
MEMORANDUM
PROJ. DOC. No.: M869-50-00-A-RP-001
The proposed wastewater disposal routing indicates that water from the
Substation should be routed after pre-treatment and conditioning directly into
the existing Water Disposal Tank T-3920. The existing Water Disposal Pump
P-3920 A/B will be used to re-inject the water to disposal wells. These
disposal routes will need to be further confirmed after the chemical
compatibility investigations.
Our current design philosophy is to size the deep well disposal equipment to
accommodate the flow rate that will occur when none of the produced water
was recycled into the boiler feed water system. Listed below are the main
equipment component expected for this system design.
• Disposal water tank at the Substation
• Disposal water pumps
• Disposal water filters
• Disposal water pipeline
• Produced water chemistry
Produced Water Characteristics and Observed Trends
The produced water composition from thermal production is largely
dependent upon the reservoir characteristics. It will predominantly consist of
condensed steam that has interacted with the rock formation and in-situ water
in the steam chamber. Experience from other thermal heavy oil operations
indicates that the silica level will be significantly higher than expected with
cold production and the concentrations of other background ions will be lower
due to the effects of dilution.
Total Dissolved Solids are generally found to be lower in the 1,000 to 1,500
mg/L range, consisting primarily of background sodium, potassium, chloride,
sulphate and carbonate alkalinity. Sodium is generally the most prevalent
cation with values in the range of 300 to 1,200 mg/L being observed.
Hardness components have been generally observed to be very low, typically
Issue No. A1 Standard Number
P:\Z06835 Sincor Venezuela EOR Project\20-00 PROJ
MANAGMNT\20-20 DBM\Final DBM Document\Master Page: 43 of 166
DBM Rev 0 April 30.doc Issue Date 30/04/07 M869-50-00-A-RP-001
SUBJECT:
DESIGN BASIS
MEMORANDUM
PROJ. DOC. No.: M869-50-00-A-RP-001
less than 20 mg/L as combined ion and similarly the potassium levels are also
generally observed to be low however, values as high as 50 mg/L have been
observed. However, occasionally produced water can demonstrate higher
hardness levels, particularly during the first few years after initial start-up.
Chloride is the most prevalent anion, with ranges observed from 500 up to
1,500 mg/L being observed. Another prevalent anion species is the
bicarbonate and carbonate ion which generally ranges form 250 up to 450
mg/L. Sulphate anions are typically the lowest in concentration and have
been observed as high as 160 mg/L.
Facilities in Canada typically experience Silica levels in the range of 150 to
250 mg/L of Reactive Silica with the higher reported values in the 400 mg/L
range.
Foam No foam
Stain 5.0 mg/l
Phenols 0.5 mg/l
Fluorides 5.0 mg/l
Total Phosphor 10 mg/l
Total Iron 20 mg/l
Total Manganese 2.0 mg/l
Total Mercury 0.01 mg/l
Total Nitrogen 40 mg/l
(expressed as nitrogen)
Nitrites + Nitrates 10 mg/l
(expressed as nitrogen)
Issue No. A1 Standard Number
P:\Z06835 Sincor Venezuela EOR Project\20-00 PROJ
MANAGMNT\20-20 DBM\Final DBM Document\Master Page: 46 of 166
DBM Rev 0 April 30.doc Issue Date 30/04/07 M869-50-00-A-RP-001
SUBJECT:
DESIGN BASIS
MEMORANDUM
PROJ. DOC. No.: M869-50-00-A-RP-001
pH 6-9
Total Silver 0.1 mg/l
Total Lead 0.5 mg/l
Selenium 0.05 mg/l
Floating solids No
Suspended solids 80 mg/l
Sedimentable solids 1.0 mg/l
Sulfates 1000 mg/l
Sulfites 2.0 mg/l
Sulphur 0.5 mg/l
Zinc 5.0 mg/l
BIOCIDES
Carbonates and 0.25 mg/l
phosphorous organics
Chlorides organics 0.05 mg/l
RADIOACTIVITY
α Activity Maximum 0.1 Bq/l
β Activity Maximum 1.0 Bq/l
A pipeline will be installed to carry diluted crude oil (DCO) from the Substation
to the SINCOR Main Station. The tie-in point will be in the Oil Export pipeline
leaving the Main Station (Discharge of export Pump P-3002).
The anticipated operating conditions at the tie-in point are listed below:
Temperature 89 95
84
(°C)
The diluted crude oil (DCO) leaving the EOR Substation will be metered.
Pressure, temperature, base settlement and water-cut (BS&W), density, and
viscosity will be measured on line. Sample ports will be provided to allow
verification of the data, and to check other properties such as Reid vapour
pressure. Losses of diluent in the field due to evaporation shall not exceed
2% of the imported diluent quantity
Notes
(1) The maximum water-cut of 2% (normally 1%) volume in exported diluted
crude oil shall not be exceeded.
(2) Average specific gravity of final product shall be 0.953 (17 °API).
(3) RVP (Reid vapor pressure) of the final product shall be less than 0.76
bara (11 psia) for storage in floating roof tanks at Downstream Facilities.
Component % mol
CO2 7.3900
H2O 0.0116
H2S 0.0012
N2 0.1500
C1 92.1101
C2 0.1400
C3 0.0400
i-C4 0.0300
n-C4 0.0200
i-C5 0.0200
n-C5 0.0080
C6 0.0500
C7 0.0200
C8 0.0080
C9 0.0010
C10+ 0.0001
Total 100.0000
Temperature 46
(°C)
The SINCOR EOR Project will have four Clusters each having the following
number of wells.
The piping and equipment at the Clusters must be designed to allow a good
margin of flexibility.
The piping and instrumentation tied into every well must be sized to
accommodate the peak anticipated flow rates. The test separator must also
be designed for these peak rates.
During normal operation, all of the production wells at each Cluster will flow
into a designated group separator. Not all of the wells will be expected to flow
simultaneously at their peak rates. The following items will be sized to
accommodate 50% of the wells operating at peak rates plus 50% of the wells
operating at normal rates.
• Steam injection pipeline and distribution header
• Lift gas pipeline and distribution header
• Group separator
• Group pumps
• Produced gas condenser
• PG condensate separator
• PG condensate pumps
• Produced liquids
The following conditions shall be used for the Clusters and pipelines design,
as described here below.
SAGD Clusters Test
Well Design (Tubing Sizing) Design QO SOR Qliq Qs BHT BHP BHP GOR
Inj
Cluster Spacing Aquifer Length Tick Cond. bopd v/v bpd bpd C Bars Bars Scf/bbl
SAGD1 150 Yes 500 25 Maximum 1100 3 4400 3300 45-230 40-45 45 15-30
Normal 600 3 2400 1800 45-230 40-45 45 15-30
SAGD3 150 No 1000 25 Maximum 2200 2.5 7700 5500 45-230 40-45 45 15-30
Normal 1200 2.5 4200 3000 45-230 40-45 45 15-30
SAGD4 150 Yes 500 25 Maximum 1100 3 5133 3667 45-230 40-45 45 15-30
Normal 800 2.5 2800 2000 45-230 40-45 45 15-30
Well Design (Tubing Sizing) Design QO SOR Water Qliq Qsteam GOR
Balance
Mech Spacing Aquifer Length Tick Conditions bopd v/v bpd bpd Scf/bbl
HASD2 Peak 1833 3 100% 7333 5500 200-400
ALT. HASD 150 No 1000 10
WELL Normal 875 4.2 100% 4375 3500 200-400
Cluster # 1 2 3 4
Number of well pairs 5 8 5
Number of wells 10 7 16 10
Qoil Design (bopd) 4250 5417 13600 5667
Qliq design (bpd) 17000 18916 47600 19833
Qsteam design (bpd) 12750 13500 34000 14167
Cluster # 1 2 3 4 TOTAL
Number of well pairs 5 8 5 18
Number of wells 10 7 16 10 43
Qoil Design (bopd) 3000 3500 9600 4000 20100
Qliq design (bpd) 12000 14000 33600 14000 73600
Qsteam design (bpd) 9000 10500 24000 10000 53500
Water is expected in the steam pipeline to the Clusters during start-up. The
steam line will be provided with drains at low points that could drains into
holding tanks.
The piping will be designed so that the wellhead wing valves are the low
points so as to ensure that liquids will drain to the well from the module and
reduce the chance of slugging and water hammer.
The piping will be designed with swivel connectors to allow for 600 mm of
well-head growth without exceeding allowable stress limits.
5.1.3.5 Production
The piping will be designed so that the wing valves are the low-points so that
liquids will drain back to the wellhead from the well-pair module.
The piping will be designed with swivel connectors to allow for 600 mm of
well-head growth without exceeding allowable stress limits.
The piping will be designed to withstand possible steam communication from
the injector well to the producer well.
Break flanges will be provided 3 metres from the production wellhead to
permit removal of the production piping spools for service rig access. These
spools shall have calcium silicate insulation instead of mineral wool for better
durability. They will also have lifting lugs protruding from the insulation for
crane hook attachment.
Steam flow to each injector shall be measured using flow nozzles. Steam
flow to each injector shall be controlled using a steam flow control valve.
Produced emulsion flow from each producer well shall be measured using the
test module. An automated choke valve shall control the pressure.
Fuel gas flow to each well head shall be measured. An automated flow
control valve shall control the flow.
Downhole measurements provided by SINCOR are as follow:
Injector Wells
• Temperature measurement – fiber optic, sensor every 2 (two) meters,
which will give some 250 measurement points (for each 500 long
meter well) and some 500 measurement points (for each 1000 meter
long wells).
• Pressure – 2 sensors, at heel and toe.
Production wells
• Pressure – 2 sensors, at heel and toe.
Use maximum normal flows for calculations. For viscous liquids, the velocity
criteria could lead to excessive pressure drops: in those cases, the pressure
drop criteria rules.
HC Vapour Lines
In the case of vapours, two approaches may be followed, depending on the
magnitude of the compressibility effect. For vapours with low pressure drop
or low velocity (pressure drop equal to or less than 10% of the upstream
pressure, or the velocity equal to or less than 60 m/sec) the following ranges
for velocity and pressure drops can be used for vapour line sizing. Should
pressure drop be exceeded by 10% of the upstream initial absolute pressure,
the calculation should be split into a number of segments with corresponding
physical properties.
Recommended Maximum Allowable Pressure Drop
Allowable Velocities
Maximum for gas = 122/SQRT(Dg), m/sec,
where Dg is the gas density in kg/m3.
Compressor Suctions
Operating Range
Maximum Limit 7% sonic
Screw type
Rated Flowrate
15% of the variable system drop
(excluding the control valve) or
70 kPa whichever is greater.
Pumps
Charge, product transfer services 1.1
Critical services 1.2
Compressors 1.2
For pumps specified for bubble point fluids show “B.P.” on the pump
specification sheet rather than the actual vapour pressure. Note that this also
applies to fluids containing dissolved/entrained gas. Fluid shall be considered
as bubble fluids (boiling liquids) if the operating pressure is less than 110% of
the liquid vapour pressure at the operating temperatures.
The followings are equipment sizing criteria used for the Pre-FEED:
Cluster #1
Cluster #2
A-1021 Produced Gas Base Case, Low SOR + 10% of heat duty
Condenser 1X100% air cooler
K-1021 Produced Gas Base Case, Low SOR + 20% of flow-rate (SINCOR
Compressor design criteria)
A - 1022 Produced Gas Base Case, Low SOR + 10% of heat duty
Cooler
Water De-oiling
D-6001 IGF Vessel Design Basis – PW Base Case + Make-up Water from
Base Case + 10% of PW Base Case (WSR=1.1)
1 x 100%
Supplied by IGF Package Vendor
P-6001 IGF Eductor PW Base Case + Make-up Water from Base Case +
A/B/C Pumps 10% of PW Base Case (WSR=1.1) + 10% of total flow
3 x 50% Centrifugal Pumps
Supplied by IGF Package Vendor
P-6002 IGF Design Basis – Make-up Water from Base Case + 10%
A/B/C Discharge of PW Base Case (WSR=1.1) + 10% of total flow
Pumps 3 x 50% Centrifugal Pumps
P-6003 IGF Froth Design Basis – 10% of IGF total inflow + 10% of flow
A/B/C Pumps 3 x 50% Progressive Cavity type
U-6002 ORF Package Design Basis – PW Base Case + Make-up Water from
Base Case + 10% of PW Base Case (WSR=1.1)
D-6002 A/B ORF Vessels Design Basis – PW Base Case + Make-up Water from
Base Case + 10% of PW Base Case (WSR=1.1)
2 x 100%
Design Performance: 20 ppm (inlet) and 2 ppm oil out
(outlet)
Issue No. A1 Standard Number
P:\Z06835 Sincor Venezuela EOR Project\20-00 PROJ
MANAGMNT\20-20 DBM\Final DBM Document\Master Page: 63 of 166
DBM Rev 0 April 30.doc Issue Date 30/04/07 M869-50-00-A-RP-001
SUBJECT:
DESIGN BASIS
MEMORANDUM
PROJ. DOC. No.: M869-50-00-A-RP-001
Water Treating
D-6502 A/B/C Primary SAC Design Basis – PW Base Case + Make-up Water from
Base Case
3x50%
D-6503 A/B Polishing Design Basis – PW Base Case + Make-up Water
WAC Design Flowrate
2x50%
P – 6504 A/B Brine Pumps Design Basis – Brine flow-rate based on PW Base
Case + Make-up Water from Base Case + 10% of
flowrate
2x100%
T – 6504 Brine Tank Design Basis – Brine flow-rate based on PW Base
Case + Make-up Water from Base Case
1x100%
T-6005 Skimmed Oil Design Basis – 10% of (PW Base Case + Make-up
Tank Water from Base Case)
1 x 100%
Sizing basis: 4 hours working volume
P-6005 A/B Skimmed Oil Design Basis – Skimmed Oil Tank inflow + 10% of
Pumps flow
2 x 100% Progressive Cavity Type
T-6004 Slop Oil Tank Design Basis – Slop Rate estimated from Rag Layer
evacuation from HO treating area.
1 x 100%
Sizing basis: 160 m3 (1000 bbl) capacity.
P-6004 A/B Slop Oil Design Basis – Slop Rate +10% Slop Rate (SINCOR
Pumps design criteria)
2 x 100% Progressive Cavity Type
T-6006 ORF Design Basis – Water flow-rate during backwash
Backwash based on one 10 minutes backwash per 12 hours
Tank using full filter inlet water stream.
1 x 100%
Sizing basis: working capacity 6 hours from HLL to
LLL
P-6006 A/B Backwash Design Basis – Water flow-rate during backwash
Recycle Pump based on one 10 minutes backwash per 12 hours
using full filter inlet water stream +10% of flow-rate
(SINCOR design criteria).
Tank Farm
P-5502 A/B/C Sales DHO Design Basis – Substation Sales DHO design
Booster Pumps production + 10% of rate (SINCOR design criteria) +
design margin (SINCOR tank empting option)
3 x 50% API type centrifugal pumps. (Consider
ANSI type)
Fuel Gas
D-8102 VRU Suction Design Basis – Base Case see VRU package.
Scrubber 1 x 100%
A-8101 VRU Seal Design Basis – Base Case +10% of duty (SINCOR
Water Cooler design criteria)
1 x 100% air cooler
2 x 100%
Centrifugal pumps
D – 7501 Produced Gas Design Basis – Base Case, Low SOR
Slug Catcher 1 x 100% Two Phase Horizontal Vessel
D - 8401 HP FKOD Design Basis –
1 x100%
All Units to run on both mixed fuel gas and pure fuel.
Burners shall be Low NOx Burners.
E-7001 A/B BFW/BD Design Basis – Base Case
Exchanger 1 x 100% S&T Exchanger
D – 7001 A/B HP Steam Design Basis – Base Case
Separator 2 x 100% (1 vessel for 2 generators)
5.2.1.1 General
Emulsion and Wet Produced Gas are sent separately from the Clusters to the
Emulsion Treating and the Produced Gas System.
The Cluster effluent, oil and water plus the remaining gas is routed to a free
water knock out drum to remove the free water and the remaining gas. It is
then pumped to the dehydrator where the BSW specification is achieved.
The produced water is used for the steam generation. To reach the
specification requested by the steam generator, the water is processed in a
de-oiling unit (Skimmer tank and Induced gas flotation unit) and then it is
treated in a boiler feed water treatment. Finally, the treated water is routed to
the steam generator.
The produced gas is routed to a Fuel Gas skid and then routed to the boiler
as Fuel Gas
In the following sections a detailed description is included.
The emulsion from each Cluster merges into a Substation feed header. The
emulsion is cooled by cross exchanging with boiler feed water (BFW) in the
Emulsion/BFW exchanger E-5501/E-5511. The BFW is throttled to control
the operating temperature in the treating trains at 140°C.
Diluent from Diluent Pumps P-8001 A/B/C is blended with the emulsion
entering each FWKO drum D-5501/D-5511. The diluent injection rate is
controlled to keep the operating oil phase density at about 17°API through the
treatment train (952.9 kg/m3 at standard conditions). The diluent injection
rate is expected to be about 0.544 Sm3 of diluent per Sm3 of dry EHO
(producing about 35.2% blend before shrinkage effects).
The FWKO drum provides settling time for free water droplets to separate
from the oil phase. The emulsified oil phase leaving the FWKO drum is
expected to contain about 10% residual water.
Issue No. A1 Standard Number
P:\Z06835 Sincor Venezuela EOR Project\20-00 PROJ
MANAGMNT\20-20 DBM\Final DBM Document\Master Page: 73 of 166
DBM Rev 0 April 30.doc Issue Date 30/04/07 M869-50-00-A-RP-001
SUBJECT:
DESIGN BASIS
MEMORANDUM
PROJ. DOC. No.: M869-50-00-A-RP-001
The emulsion leaving the FWKO is fed into the Treater D-5502/D-5512 for
additional coalescence and settling time. The maximum allowable water-cut
in the oil product leaving the treaters is 2%. The normal operating water-cut
is expected to be about 1%.
The oil product leaving each treater is cooled by cross-exchanging with boiler
feed water in the Sales DCO/BFW exchanger D-5505/D-5515.
An Aerial Trim Cooler A-5502/A-5512 will be used:
• To further cool the oil product. This will help reduce flashing as the oil
is fed into the DCO product tank. The oil is then pumped to the main
station by above ground pipeline.
• To allow the oil treating train to remain in operation when the supply of
BFW is disrupted. When the steam generators are turned down, the
flow of boiler feed water will drop, and the process streams that need
the water flow for cooling will have to disperse their heat through the
aerial cooler.
The produced gas from the Clusters is combined with vapours from the
FWKO vessels and treaters. The mixture is sent to the Slug Catcher D-7501.
The vapour from the slug catcher will normally flow to the mixed fuel gas
system which feeds the main burners of the steam generators. Nozzles and
valves will be provided to allow the produced gas to be routed through a
future sulphur removal unit upstream of the mixed fuel gas system if required.
Normally, the steam generators will consume more gas than can be obtained
from the production wells. If the steam generators are turned down while the
production wells continue to flow, then the produced gas rate (including lift
gas returns) may exceed the steam generator fuel consumption rate. This is
not expected to be a normal occurrence. However, during rapid operational
transitions it may be necessary to divert some of the produced gas from the
slug catcher to the flare system.
H2S levels in the produced gas are expected to start out at about 0.01% (100
ppm), and could ramp up to 1.2% due to the aquathermolysis phenomenon.
This concentration is based on the liberated solution gas coming from the
reservoir.
Issue No. A1 Standard Number
P:\Z06835 Sincor Venezuela EOR Project\20-00 PROJ
MANAGMNT\20-20 DBM\Final DBM Document\Master Page: 74 of 166
DBM Rev 0 April 30.doc Issue Date 30/04/07 M869-50-00-A-RP-001
SUBJECT:
DESIGN BASIS
MEMORANDUM
PROJ. DOC. No.: M869-50-00-A-RP-001
The produced gas from the reservoir will be thoroughly diluted by lift gas. This
dilution should be sufficient to allow the produced gas + lift gas + makeup gas
mixture to be burned in the steam generators without installing an SRU.
hardness, while the WAC units remove any residual calcium and magnesium
ions that escape from the SAC units.
The soft produced water leaving the polisher WAC unit is routed to the BFW
tank T-7001.
Makeup water from cold production activities in other parts of the oilfield is
obtained from the produced water pipeline leaving the Main Station. The
makeup water fed to the Substation is expected to contain small amounts of
residual oil. It will be fed into the Make Up Water Skim Tank T-6007 to float
out any oil droplets or slugs that may have coalesced anywhere in the
makeup water supply line.
The cold water will be pumped by the Makeup Water Pumps P-6007 A/B/C
from the Makeup Water Skim Tank to the. It also improves the reliability of
the boiler feed water supply. Make up rate will automatically drop if there is
an abundance of produced water. Conversely, the make up rate will
automatically increase if the flow of produced water is disrupted for any
reason.
The soft produced water is pumped by the LP BFW Pumps P-7001 A/B/C
from the BFW Tank T-7001 and is preheated in the following exchangers:
• DCO / BFW Exchanger E-5505
• PW / BFW Exchanger E-5503/E-5513
• Emulsion / BFW Exchanger E-5501/E-5511
It is then passed through the high-pressure BFW pump P-7002 A/B/C and
heated further by cross-exchanging with boiler blow-down in the BFW / Blow
Down Exchanger E-7001 A/B. The hot boiler feed water is then fed into the
once-through steam generators (OTSGs) H-7001 A/B/C/D.
During normal operation, the OTSGs will convert 77% of the boiler feed water
to steam. The remaining 23% remains in the liquid phase to help flush
dissolved minerals out of the boiler tubes. Attempting to operate the OTSGs
at higher steam quality will increase the risk of fouling the tubes and
damaging the steam generators. The liquid phase (boiler blow down) is
separated from the steam using a high-pressure cyclonic separator D-7001
A/B.
The steam from the top of the separator is sent to the Clusters for injection
into the reservoir. The hot blow down is sent to the BFW / Blow Down
Exchanger E-7001 A/B to recover some of the heat back into the boiler feed
water. The partially cooled blow-down is then flashed in the LP Steam
Separator D-7002 to generate utility steam.
The blow-down water leaving the utility steam flash drum will contain a high
concentration of dissolved solids. It will be trim-cooled in the LP Blowdown
Cooler E-7003 and sent to the Waste Water Disposal Tank T-6512.
5.2.1.2.5 Utilities
Utility Steam
Refer to Process Flow Diagrams in Appendix A
M869-50-50-B-PF-003 EOR Substation - Steam Generation - BD
M869-50-50-B-PF-001 EOR Substation - Steam Generation – BFW
Steam generator blow down water will typically leave the BFW/BD Exchanger
E-7001A/B at a temperature of about 153°C. As the hot water passes
through the control valve, some of it will flash to steam in the LP Steam
Separator D-7002.
This steam will be used for utility heating purposes and equipment cleaning.
Low-pressure steam will be distributed to hose connections at utility stations
throughout the plant.
An auxiliary air-cooled condenser A-7004 will be used to accommodate the
surplus utility steam. The condensed utility steam will be sent to the Distilled
Water Tank D-7002.
Condensed utility steam is relatively clean TDS-free water. This water will be
distributed to several utility stations located throughout the plant. Each utility
station will be fitted with hose connections to facilitate equipment cleaning.
The remainder of the condensed utility steam will be sent to the BFW Tank.
Fuel Gas System
Refer to Process Flow Diagrams in Appendix A
M869-50-50-B-PF-003 EOR Substation - Steam Generation - BD
M869-50-25-B-PF-001 - Utility and Fire Water System
High-pressure natural gas is obtained from a distribution pipeline leaving the
main station. A branch to the Substation will be installed as part of the
SINCOR EOR Project.
High-pressure natural gas is metered as it arrives at the Substation. The flow
is then distributed to the following users:
• Substation critical gas service (flare system purge; flare pilot)
• Substation fuel gas system (makeup fuel gas, utility gas, vessel
blanketing, tank blanketing)
The Lift Gas Compressor K-8102 A/B boosts the pressure of the gas and the
flow is distributed to the well pads.
Each well-pad is equipped with an emergency shutdown valve (ESD valve).
Likewise, the branch that feeds the Substation fuel gas system is also
equipped with an ESD valve. These ESD valves are needed to disrupt the
fuel flow in the event of a fire or rupture in the facility.
The branch that feeds the Substation critical gas service will not be equipped
with an automated ESD valve. The flare system must remain operable and
reliable during any possible emergency situation. It is important that the flare
purge gas and pilot flames remain active during a plant shutdown. If the flare
system is damaged, the critical fuel gas supply can be turned off using a
manual block valve at the Substation perimeter.
The Substation fuel gas system will consist of the following main components:
• Lift Gas System (operating at about 7,600 kPag)
• Substation inlet header (operating at about 6,000 kPag).
• Critical fuel gas system (operating at 1,000 kPag; not affected by
ESD).
• Fuel gas heater (using utility steam to heat the fuel gas to about 50°C).
• Medium pressure fuel gas header (operating at 1,200 kPag; pressure
vessel blanket gas; makeup gas to the mixed fuel gas system).
• Low-pressure fuel gas system (operating at 350 kPag; tank blanketing,
slop tank heaters, steam generator pilot flames).
• Odorized gas system (operating at 34 kPag; fuel for gas appliances in
occupied buildings).
• Mixed fuel gas system (operating at 300 kPag; mixture of produced
gas, lift gas returns, and makeup gas to feed main burners in the
steam generators).
A raw water system shall be provided for the supply of potable water, utility
water and fire water at the Substation.
Water to be used in the fire and utility services shall be stored appropriately in
a 7,800 m3 capacity Utility and Firewater Tank, from where it can be
distributed.
Biocide injection is provided for potable water use. Potable water is filtered at
upstream and downstream of the potable water storage tank. The potable
water units shall be designed as a typical package system. Provision is made
for a fresh and potable water storage tank with a 48 hours supply capacity.
Pressure is boosted before entering the downstream fine filter so that, it will
be available to users at an adequate pressure.
Firewater System
The Substation shall be equipped with a dedicated fire station. The fire
station shall be supplied by a firewater tank, which will provide more than 6
hours full flow requirement.
Three firewater diesel engine driven pumps with nominal capacity of 400
m3/h each (3 x 50%) to cover the firewater requirement of EOR Substation
are provided. Two Jockey pumps have been provided with nominal capacity
of 15 m3/h each.
The prime movers for the firewater pumps shall be able to operate for a
minimum of 12 hours. Each will have a dedicated fuel tank of 12 hours
capacity with top up facilities from the fuel storage tank.
Foam concentrate package shall be provided to supply foam concentrate for
maximum duration of 65 minutes to a single fire zone at a time. Two foam
concentrate pumps, one electric driven and other diesel driven will be
supplied. Additionally, a jockey foam pump will maintain the foam ring header
pressure between 5 - 10 barg.
Refer to Appendix A
Refer to Appendix A
Normal
Utility Unit Consumption
HP Steam
Export to Clusters Kg/h 354 440
HP Steam Separator Kg/h (354 440)
LP Steam
LP Steam Separator Kg/h (5 610)
LP Steam Condenser Kg/h 5 610
BFW
LP Steam Condenser (5 610)
OTSG Kg/h 460 311
BFW from Water Treatment Kg/h (454 701)
Fuel gas
Refer to Appendix A
Refer to Appendix A
SAGD wells
5.34 sm3 gas /
Sm3 of EHO
HASD wells
53.4 sm3 gas / sm3
of EHO
destination of all recovered heat. The heat recovered to the boiler feed water
will help reduce fuel consumption and/or will increase the steam production
capacity of the OTSGs. The boiler feed water should be routed to the
recoverable heat sources in the following order: Produced Water – DCO,
Produced Emulsion and Boiler Blow Down.
The option to recover heat from produced vapours coming from the group
separators at the well-pads was examined. The study revealed that no
substantial improvement in heat recovery is achievable compared to the Base
Case. The main drawbacks of this option are the need to convey this heat to
the Substation to reach the preferred heat consumer (boiler feed water) and
several significant cost and operability implications on the heat integration of
Boiler Feed Water/DCO - Produced Water.
Several options were considered for the water treatment. The following
conclusions have been drawn from this study:
• The risk of not having a WLS to guarantee oil removal to below 1 ppm,
is too great, hence WLS will be part of the Base Case. The WLS can
treat the water in the three scenarios considered for design basis.
• The most important factors for the WLS to operate properly are the
temperature and the rate of change in temperature or water chemistry.
Operations must have complete control of these two variables to make
the WLS work.
• The Make-up Water will be heated to ~85oC using heat from the
disposal water stream, the OTSG blowdown water stream and the LP
steam (during initial start-up, plan will have to be put into place to deal
with the lack of heat). This heat integration arrangement does not rely
on production volume. Hence, temperature control will be more
effective and constant going into the WLS. All produced water will
initially be sent to disposal, until the chemistry of the produced water is
known and stabilized. Once the produced water chemistry has
stabilized, the operator then can select to blending in the produced
water. Each change in water chemistry will cause a short upset to the
WLS, but it can be controlled if the event is planned.
• No IGF is required for the Make-up water, since the Make-up water
has gone through an IGF at the Main Station. The Make-up Water
Tank is required to provide flexibility to operations. A skimming system
could be added to this MUW Tank to remove oil build up over time.
6 MECHANICAL DESIGN
These criteria outline the basis of design for all mechanical equipment in this
EOR Project.
The latest editions of the SINCOR specifications were reviewed and gap
analyses were performed to compare the difference between the existing
SINCOR specifications and industry standards for SAGD projects. Where
there is no specification for required equipment, new specifications were
written. The list of applicable specifications is can be found in Appendix B.
Deviations and clarifications to the Project specifications will be done through
Technical Deviation Notices (TDN) which will be submitted to SINCOR for
approval.
Other applicable industry standards required for this project include the
following:
• American Society of Mechanical Engineers (ASME)
• Instrument Society of America (ISA)
• American Petroleum Institute (API)
• ASME piping codes
• ANSI Standards
• American Standard Testing Society (ASTM)
• National Fire Protection Association (NFPA)
• National Electrical Manufacturer’s Association (NEMA)
o Factory Mutual Engineering Corporation (FM)
o Underwriters Laboratories Inc (UL)
The same remarks as for shell and tube exchangers apply regarding thermal
ratings for air coolers.
Mechanical design and fabrication shall be according to the relevant
Standards and SINCOR specifications.
All air-coolers shall be designed based on maximum ambient inlet air
temperature of 35oC.
50% of manually adjustable pitch fans and 50% of auto variable pitch fans will
be used for flow control.
Manual louvers will be used at the air inlet. Automatic louvers with a
mechanical link to the side louvers will be used at the top and for re-
circulation.
For fan speed reduction, chains and pulleys will be used. Removable bug
screens will be used.
Vendor sizing and calculations for heat exchangers shall be checked by EPC
Contractor using HTRI or similar software.
6.1.6 Pumps
All process pumps will have Mechanical Seals. For specific ignitable or
hazardous fluids, Tandem, Double, or Inside Wet and Outside Dry running
seals will be used, after consultation with SINCOR.
If reciprocating pumps are used, then they will be horizontal for accessibility
and to control packing leaks.
The Fire Protection system shall include fireproofing, foam system, fire water
system with storage and pumps, automatic water spray system, and hydrants.
6.1.10 Miscellaneous:
Construction material will be as shown on the equipment data sheets and the
Materials Selection Diagram in Appendix B.
Material selection for the equipment (vessel, tanks, pumps, exchangers,
valves, compressors, coolers, equipment packages, steam generators,
treatment units) should be based on the life service.
All selected materials should be identifiable and conform to the ASTM
standard specifications.
Upset conditions, shutdowns, start-ups, environmental conditions,
contaminant levels, stream analysis, should be evaluated when selecting
materials.
• Cathodic Protection
The specification JOB SPEC 4478-70A13A Rev 1 will be followed for
corrosion control of metal in contact with soil, buried concrete, water,
and hydrocarbons.
• Inhibition Program
Inhibitor Injection packages will be identified in the P&ID, and is listed
in the equipment list, for corrosion protection.
• Scheduled Maintenance
It is recommendable to be proactive and initiate monitoring before
problems occur. Monitoring allows the establishment of a corrosion
rate baseline upon which future operations can be compared and aids
in system life span forecasting. It will assist in pointing out problem
areas or trends before a failure occurs, and also proves due diligence
in protecting assets, safety and the environment.
• Steam Generators;
• Tanks;
• Vessels;
• Air Coolers Heat Exchangers,
• Shell and Tube Heat Exchangers;
• Compressors;
• Pumps;
• Filters, Stacks, and Miscellaneous;
• Packaged Equipment;
• Motors; and
• Miscellaneous.
Also included is a summary list which is linked to the individual equipment list
with the key process conditions for quick reference. The equipment list can
be sorted by services, tag number or by name. Each equipment will have
process conditions both design and operation. The mechanical list will
include materials, insulation and vendor information, as appropriate.
For the packaged equipment, a number of individual components such as
vessels, pumps, tanks, coolers, exchangers are included within the
appropriate package identified by tag numbers.
All equipments will be ordered using an approved SINCOR vendor list.
Spare parts philosophy will depend on the type of equipment and also as per
input from the owner, SINCOR. Overall practice is to have installed standby
pumps.
Usually equipments requiring the supplier’s site presence during pre-
commissioning and commissioning will require spare parts.
A spare parts template sheet will be issued with the quotation as an option
and this will be evaluated and decided during the purchasing stage.
The manufacturer shall recommend all spare parts for start-up and
subsequent operation for one year.
For commissioning spares and for special maintenance handling tools,
include wearing parts, which need replacement after start-up, test and
shutdown prior to production start.
The following information is required on all spare parts lists:
• Part description and number (sufficient detail to order size, material,
etc.);
• Unit cost each part (identify unit-sets, pairs, etc.);
• Total quantity of items;
• All Owner purchase order number applicable;
• Supplier’s identification (shop order number, etc.) if applicable;
• Date of price quotation; and
Equipment with a long delivery time has been identified and included in the
document called Long Lead Items bidder list, which is included in Appendix B.
Long lead items apply to both individual and skidded equipment which have
to be identified and ordered so they will meet the project schedule. These
equipment lists along with engineering work packages will be issued during
the FEED stage together with approximate delivery time.
A long lead item is an equipment which has more than six month delivery or
an equipment required early in the project.
Steam Generator’s preliminary inquiry indicated an estimate possible delivery
time of 2 years, after the Purchase Order release.
The Long Lead Item has been sorted by category and includes the potential
bidders from international vendors as well as Venezuelan vendors.
The SINCOR field production area presents high susceptibility to soil erosion
and sediment process. This is caused by the soil characteristic, the climatic
conditions, the predominant geoform type and the protection exerted by the
vegetation coverage.
The hilly landscapes and plateaus which have different evolution stadiums,
are characterized by a strong morphogenetic activity in natural conditions,
which are increased by interventions, such as sheep herding and earth works.
In general, the superficial material is very friable with exceptions where the
ferrous cuirass is surfacing or where soil is partially protected by a stony
pavement, originated by cuirass meteorization.
The scarce vegetation coverage, which dominates the highest areas, is
represented by gramineaes growing in Clusters. This may expose soil areas
and trees or isolated bush presence. Vegetation covering is only found in the
valley depths where wide gallery forests are developed, associated with
morichales (swamp palm).
Rain intensity is significant which causes loose soil. Another element to be
considered is the terrain slope. Terrains with slopes within 4-5% may cause
the acceleration of the erosion process.
On the other hand, the area presents a high density of water streams, with a
great quantity of headwaters, which confluence in bigger streams, are
colonized by morichales and forest galleries. The area is also characterized
by a high biodiversity making contrast with the nearby plains. However, these
ecosystems are largely affected by fires and by presence of agricultural
activities.
The SINCOR area is one with a high environmental sensitivity. This increase
high erosion and sediments potential, conjugated with the highly diverse and
complex presence of morichales. Therefore, the following environmental
elements shall be considered during the development of the new facilities.
Based on the Forestal Law of Soils and Waters, the following areas shall be
protected:
• 25 m from each side of intermittent water streams.
• 50 m from each side of continuous water streams.
• 300 m from each side of the navigable rivers
• 50 m around lakes and lagoons
Issue No. A1 Standard Number
P:\Z06835 Sincor Venezuela EOR Project\20-00 PROJ
MANAGMNT\20-20 DBM\Final DBM Document\Master Page: 99 of 166
DBM Rev 0 April 30.doc Issue Date 30/04/07 M869-50-00-A-RP-001
SUBJECT:
DESIGN BASIS
MEMORANDUM
PROJ. DOC. No.: M869-50-00-A-RP-001
Gaseous Effluents
Gaseous emissions control must comply with the following principles:
• Reducing greenhouse gas emissions (GHG);
• Reducing the emission of any gaseous or solid compounds affecting
air quality (H2S, SO2, NOx, nmVOC, CO, Particulates, etc.);
• Monitoring the flow and characteristics of significant emissions before
release to the atmosphere.
The following basic principles shall be applied:
• No continuous flaring of associated gas during normal operation,
unless there is no feasible alternative;
• No continuous venting of associated gas, unless there is no feasible
alternative.
These principles do not apply to emergency, safety, temporary operational
upsets and start-up periods. In addition, the following emission reduction
measures are included in the design:
• Selection of the most energy efficient equipment;
• Use of Vapour Recovery Unit versus venting;
• Process optimization to minimize flaring caused by process upsets.
Emission sources shall be designed so that ground level concentrations meet
ambient air quality standards. Dispersion studies should be undertaken on a
case-by-case basis in order to assess the potential impact on air quality.
Diluent losses from tank vents can be significant. Normal temperature and
pressure transitions can light ends to flash off. Fluctuating tank levels can
also result in out-breathing of diluent vapours. This can lead to odour
problems and loss of valuable product. In extreme cases, explosive vapour
clouds could develop within the plant site. A vapour recovery unit (VRU) will
be installed to recover the diluent vapours and to prevent emissions of
flammable and noxious compounds.
The aquathermolysis phenomenon is expected to create H2S in the reservoir.
The H2S will be produced with the reservoir gas and carried through the
produced gas train. If the production wells are switched from lift gas to down-
hole pumps, then it may be practical to recover the H2S from the gas using a
sulphur removal unit (SRU). Produced gas, lift gas returns, and additional
makeup gas is fed to the mixed fuel gas system. All of this mixture is burned
by the steam generators. The firebox of the steam generators operates at
very high temperatures with adequate residence time to completely destroy
Issue No. A1 Standard Number
P:\Z06835 Sincor Venezuela EOR Project\20-00 PROJ
MANAGMNT\20-20 DBM\Final DBM Document\Master Page: 101 of 166
DBM Rev 0 April 30.doc Issue Date 30/04/07 M869-50-00-A-RP-001
SUBJECT:
DESIGN BASIS
MEMORANDUM
PROJ. DOC. No.: M869-50-00-A-RP-001
and fitted with a labelling correctly marked on the packaging. MSDS shall
include eco toxicological data.
Handling procedures shall be set up, Operators handling the chemicals shall
be trained, and Personal Protective Equipment (PPE) shall be available on
work site. Bulk supply of chemicals via tote tanks or dedicated containers
shall be considered to minimize transfer operations and avoid packaging
waste. Chemical stock shall be properly managed to ensure that any over
capacity and leftover chemicals is avoided. Chemicals / materials supply
contracts should consider the possibility of returning the unused products to
the suppliers.
Chemical storage shall include secondary containment, either a double walled
container or a skid base plate or a bonded area and adequate ventilation.
The storage should be protected from rainfalls and direct sun radiation. On
logistic bases, large storage areas shall be fitted with an impervious slab
(concrete or other) with a slope towards a gutter and a relevant drainage
system. The storage design shall take into account chemicals compatibility.
The storage of laboratory chemicals is subject to specific regulations.
Open drain and closed drain are provided for the proper collection, treatment
and disposal of oily and non-oily drain residues. Collection and treatment are
selected according to the water and oil content so as to optimize investment
and processing effort in dealing with the corresponding streams.
Non-oily rain water, not requiring treatment, is collected in one runoff pond.
The overflow system in the runoff pond will be arranged to pass the water to
the runoff pond sump from there it will be tested and transferred to the Waste
Water Disposal Tank or to ditches and final disposition.
Oily water goes to an API separator where most of the oil is taken out to be
reprocessed after proper intermediate storage. Water is treated in the API
Separator to get a maximum of 20 ppm oil in water. After passing to the
runoff pond sump the treated water is tested and discharged to ditches and
final disposition. Skimmed oil will be sent to the oil sump and pumped to the
slop oil tank.
The Closed Drain System collects liquid hydrocarbons drained from
equipment and storage tanks, thus recovering valuable product and avoiding
environmental pollution. The Closed Drain Drum is designed to handle one
third of the normal liquid volume of the largest separator drum. Emptying time
is two hours. Collected material is recovered and sent to the slop oil tank.
The clarified supernatant from the Sludge Pond has been identified as having
a potential disposal problem. It will likely be oxygen-saturated and could
contain traces of oil released from the sludge. The oxygen content poses
corrosion problems if the water is pumped back into the process. The
contaminants in the supernatant preclude the option of discharging the pond
contents into the environment. Sending the supernatant to disposal could
create corrosion problems in the disposal pipeline and injection wells if not
treated. High rainfall rates in the region and low evaporation rates would
require a roof be installed over the settling pond. (Optional – A centrifuge
should be considered for dewatering the sludge; sending the centrate to the
disposal water pipeline and the solids to a landfill).
The flare systems must be designed and operated in accordance with all
applicable engineering and safety standards. These include (but are not
limited to):
• American Petroleum Institute (API) Recommended Practice 521:
Guide for Pressure-Relieving and Depressuring Systems.
• API Recommended Practice 520: Sizing, Selection, and Installation of
Pressure-Relieving Devices in Refineries.
• API Recommended Practice 537: Flare Details for General Refinery
and Petrochemical Service.
• ASME Boiler and Pressure Vessel Codes
The flare relieves shall be evaluated for all contingencies which may result in
equipment overpressure including external fire, utility failure, equipment
failure and malfunction, abnormal processing conditions, thermal expansion,
equipment trips and operator errors.
All pressure vessels must be protected by pressure relieving devices to
prevent the pressure from rising above the design pressure according to the
following table
Maximum Allowable
Overpressure (% AWP)
Fire Contingency 21
The area classification for the EOR plant is shown on the drawing No. M869-
50-41-A-SK-001 “EOR – Area Classification Drawing for Substation” in
Appendix D.
The area classification is based on the equipment distribution according to the
EOR – Substation Plot Plan. The methods used to prepare the area
classification are outlined in SINCOR document No. CA04-04-33-P-DC-101
“Electrical System Design Criteria”. Hazardous Area Classifications for the
Clusters will follow the same procedure and will be produced in the FEED
stage of this project.
At the Substation two separate flare headers are included in the design. A
high-pressure (HP) flare header will be installed for emergency
depressurization valves and PSV relief. A low-pressure (LP) flare header is
needed to accommodate discharges from devices that cannot withstand high
backpressure. Normally there will be no flow to either flare header.
Both headers will have continuous purge to prevent oxygen ingress. Purge-
reduction devices must be installed to allow lower purge rates (below 0.05
ft/s). This will minimize purge gas consumption and normal operating
emissions.
The HP flare header will consist of an aboveground flare knockout drum, flare
knockout pumps, and a flare stack with a continuous re-ignition device. Some
of the emergency relief scenarios could send non-combustible vapours to the
flare stack (i.e. high steam content may prevent the vapours from burning). In
this case, the flare stack will act as an emergency vent stack. The flare stack
will automatically reignite and return to normal readiness as soon as the flow
of non-combustible vapours subsides.
The LP flare header will be used to collect the tank vents in the event of VRU
upset, shutdown, or overload. The LP flare header and the stack will be sized
to minimize backpressure when tank vents are diverted to flare.
At each Cluster, a vent stack instead of a flare will be used based on the
following considerations:
• Design basis uses lift gas;
• Gas phase diluted 75% by steam and gas;
• Normally no vent at ground level;
• H2S from vent gas not to go beyond 1 PPM at ground level. There will
be smell of H2S but should be no danger;
• There are no local regulatory constraints against such vent stacks.
The facilities shall meet high standards where Health and Safety are
concerned.
Safety shall be everybody’s concern. It shall not be limited to gas releases
and fire, but shall involve other specialists and in particular process and
instrumentation and shall require a multidisciplinary approach.
Regulation monitoring shall be based on the appliance of international Codes
and Standards.
The SINCOR General Specifications shall be applicable. The order of
prevalence of the different applicable Safety document shall be:
• Venezuelan Laws and Regulations;
• Safety Concept to be developed for the Project;
• Project particular specifications;
• SINCOR General Specifications;
• Other Codes, Standards and Norms and in particular API and NFPA.
The Safety Concept developed for the EOR Project is based on Un-Manned
Clusters and Permanently Manned Substation.
The following basic principles shall be applied:
• Primary and secondary escapes routes shall be provided to facilitate
personnel evacuation in critical situations.
• Chemical and Hazardous Substances are anticipated to be handled at
the Substation so safety showers/eye wash shall be installed close to
chemical injection packages to allow easy and quick access in the
event of exposure to harmful chemical.
• The four new Clusters will have fire and fixed H2S detection. No fixed
firewater system is required on the Clusters but mobile/portable
equipment are to be permanently provided. Stand-alone safety
showers and eye washer shall be installed close to the chemical skids.
• Fixed Fire Water and provision for monitors and hydrants are required
at the Substation.
Issue No. A1 Standard Number
P:\Z06835 Sincor Venezuela EOR Project\20-00 PROJ
MANAGMNT\20-20 DBM\Final DBM Document\Master Page: 107 of 166
DBM Rev 0 April 30.doc Issue Date 30/04/07 M869-50-00-A-RP-001
SUBJECT:
DESIGN BASIS
MEMORANDUM
PROJ. DOC. No.: M869-50-00-A-RP-001
Hazard Identification (HAZID) Study has been carried out during PRE-FEED
to asses the impact of the facilities on their surroundings, the impact of the
surroundings on the facilities, the interferences between main items and the
general hazards. In Appendix F, the effect or possible consequences and
the possible causes of the main events evaluated by the HAZID Team are
presented.
HAZID shall be reviewed at each major modification during the project
development.
8 PIPING DESIGN
8.1 General
SINCOR advised the project of four possible locations for the Sub Station
site. All sites are large enough and suitable to accommodate the EOR Sub
Station. A separate evaluation compared the options and recommended
Option #3 as the preferred location for the Pre-FEED.
Locations for the Clusters were given by SINCOR.
Layout of the Sub Station and the Clusters were done with the following
criteria:
• The prevailing wind direction
• The natural topography of the site location: drainage to creeks and
rivers
• The existing infrastructure: roads, pipeline right of ways and power
• The constructability of the plant
• The operation of equipment
• The maintenance of equipment
• The safety of equipment
Issue No. A1 Standard Number
P:\Z06835 Sincor Venezuela EOR Project\20-00 PROJ
MANAGMNT\20-20 DBM\Final DBM Document\Master Page: 109 of 166
DBM Rev 0 April 30.doc Issue Date 30/04/07 M869-50-00-A-RP-001
SUBJECT:
DESIGN BASIS
MEMORANDUM
PROJ. DOC. No.: M869-50-00-A-RP-001
• The Sub Station is divided into process areas. For example, Water
Treating, De-oiling, Steam Generation, etc.
• Placing heavy equipment on undisturbed soil (not compacted fill)
• Placing drainage ponds to take advantage of natural topography
• Locating odour causing process to take advantage of prevailing winds
• Locating equipment that have high noise levels away from office
facilities
• Providing adequate space around equipment for constructability,
operation and maintenance
The plot plan was then reviewed with SINCOR representatives and
comments were noted. The drawing was issued Rev. C, to reflect the
comments from the client review then re-issued, for the DBM. Essentially, the
plot plan is frozen at Rev. C. The Project will continue to make refinements to
the plot plan, but will not be re-issued during Pre-FEED unless there are
changes that may significantly affect the cost estimate.
be provided with a pipe stack ending at least 3 meters above any platform
within a 8 meter radius. A NPS ¼” threaded weep hole shall be provided at
the bottom of the stack to prevent liquid accumulation. If the weep hole would
discharge to a platform, a NPS ½” sockolet and a ½” line shall be provided to
a safe location.
Exchanger piping shall not be run over channel or shell cover areas, or in the
way of built-in or mobile handling facilities except removable local
interconnections. Wrench clearance shall be provided at the exchanger
flanges. Spool pieces shall be provided beyond the channel nozzles to permit
the removal of the exchanger channel head and tube bundle. Cooling supply
and return lines shall be routed to minimize bypass lengths.
Pump suction piping shall be arranged with particular care to avoid
unnecessary pressure drop and vapour pockets. Concentric reducers are
preferred where size changes are necessary, except in horizontal suction
lines at pumps with end or side suction. In these locations, irrespective of
suction piping being routed from above or below the pump, eccentric top flat
reducers shall be used.
Piping at pumps and turbines shall be arranged to avoid interference with
operation or maintenance access. Removable spool piece shall be provided
as appropriate, such as at suction end pump inlets, to permit maintenance
without major piping disassembly.
Conical type temporary strainers shall be provided at all pump suctions and
turbine inlets unless permanent strainers are specified.
Pipe supports shall normally be designed to transmit all piping loads directly
to foundations. Loadings to be considered in design calculations include:
• Weight of pipe and insulation;
• Weight of the line contents based on water, or process fluid, whichever
is greater;
• Wind loading;
• Lateral loading due to movement of lines on supports;
• Vibrations due to pulsations from reciprocating pumps and
compressors and possible line surges.
Supports shall be located so that the force transmitted to connections on
equipment such as pumps, compressors, etc. does not exceed that allowed
by the manufacturer. The design of such supports shall be detailed and not
left for field improvisation.
In general, the new pipe-ways run beside to existing pipelines. The limit of
clearing is determined by existing Right-of-Way boundary. The new pipeline
shall be installed 7 m (as a minimum) from the outer pipeline on the existing
pipe-way.
Main Station to EOR Substation:
The pipelines from Main Station (Gas Supplied, Water Make-Up, Diluent,
Diluted Crude Oil and Water Disposal) shall be tied ins at Main Station.
Those pipelines route runs to the Substation by new pipe-way to be installed
beside the existing pipe-way.
It is expected to install approximately 16,000 m of each of the above pipelines
between the Main Station and EOR Substation.
The new pipelines shall follow the existing topographic conditions and similar
routing alignment of the existing pipelines. For supporting the new pipelines,
piping supports shall be installed according to the pipe standard spans.
Stress loops shall be installed along the pipe-ways with loop projections
toward opposite side of the existing pipe-way. The preliminary design
contemplates loops each 260 m. Loop typical arrangement is shown in
drawing M869-50-16-0-SK-001, in Appendix C.
For maintenance purposes, valves and flanged connections shall be installed
at both pipelines ends (Main Station battery limit and EOR Substation pigging
area) to allow installing traps.
Routing preliminary details are shown in drawing M869-07-10-N-DR-001-
Pipelines Export/ Import - Main Station to/from EOR Sub Station –
Conceptual Route. Details related to piping supports in drawing M869-07-10-
N-DR-001.
EOR Substation to Clusters:
The pipelines from EOR Substation (Gas Lift, Steam, Produced Emulsion,
Produced Gas and Diluent) begin or finish at Pigging area. Those pipelines
to or from clusters 1, 2, 3 and 4 shall be installed on new pipe-way beside to
the existing pipe-way.
It is expected to install approximately 57,000 m (total) of the above pipelines
between the Clusters 1, 2, 3 and 4 and EOR Substation.
The new pipelines shall follow the existing topographic conditions. For
supporting the new pipelines, piping supports shall be installed according to
the pipe standard spans.
Stress loops shall be installed along the pipe-ways with loop projections
toward opposite side of the existing pipe-way. The preliminary design
contemplates loops each 260 m. Loop typical arrangement is shown in
drawing M869-50-16-0-SK-001, in Appendix C.
For maintenance purposes, pig traps (launcher and receivers) shall be
installed only for Produced Emulsion and Produced Gas pipelines. For the
rest of pipelines (trunk lines), valves and flanges connections shall be
installed to allow for traps connections. Traps and valves shall be installed at
Pigging Areas (EOR Substation, Main Station battery limit and Clusters).
Routing preliminary details are shown in drawing M869-08-10-N-DR-001-
Pipelines Export/ Import – Clusters to/from EOR Sub Station – Conceptual
Route. Details related to piping supports in drawings M869-07-10-N-DR-001
and M869-08-10-N-DR-006.
The new pipelines shall be bended to adapt the pipelines to the expected
topographic conditions.
For adjust the pipelines to the existing topography, fittings (elbows) can be
used along the pipeline, but the minimum required pigging radius has to be
considered.
For supporting the new pipelines, piping supports shall be installed according
to the pipe standard spans. As well as, settlements that may induce
additional loading on the pipeline must be minimized.
Routing profile details are shown in drawings:
• M869-07-10-N-DR-002 Pipeline Export/ Import – Main Station
to/from EOR Substation – Longitudinal Profile
• M869-08-10-N-DR-002 Pipeline Export/ Import – Cluster 1 to/from
EOR - Longitudinal Profile
• M869-08-10-N-DR-003 Pipeline Export/ Import – Cluster 2
to/from EOR - Longitudinal Profile
• M869-08-10-N-DR-004 Pipeline Export/ Import – Cluster 3
to/from EOR - Longitudinal Profile
8.4.1.2 Crossings
It is anticipated that the pipelines will be above ground, with minor exceptions
(line-crossing).
Pipeline river crossings shall be aboveground through designed pipe-way
bridges. Pipe-way bridge as per preliminary design shown in drawing M869-
08-10-N-DR-006.
Pipelines roads crossing shall be through culverts. The culverts shall be built
so that the Pipelines routing remains without level changes for avoiding
unnecessary pockets to Steam pipeline. Culverts’ preliminary design is as
per detail in drawing M869-08-10-N-DR-006.
Pipelines electrical line crossing shall be buried. It is considered that pipes
shall be installed inside casings covered with borrowed material.
In general, the detailed design of crossings shall preserve pipeline integrity
particularly through minimization of accumulation of water around the
pipeline; avoid interference with adjacent pipelines; allow convenient and
inexpensive routine inspection of road and line crossings; avoid pocketing of
water externally in the road casing and minimize external and internal
corrosion.
The exact location of the Substation will have to be defined during the
engineering phase taking into account the following “notional” pad locations:
Pad 1
Pad 2
Pad 3
Pad 4
Remark :D1-D2 sand map plotted Remark :A2 sand map plotted
Notes:
1. The detailed positioning of the pads and SAGD and HASD wells will be
finalized only after the delineation campaign which will be carried in 2
phases. The first phase will consist of 30 wells to narrow down the
thermal development area and a second campaign (~25 wells) to
precisely locate the wells
2. However, the location of the Substation will be fixed prior to the
completion of the delineation campaign based on “notional” pad location
as shown above.
Clusters Locations:
• Original pads locations given by SINCOR Geosciences are interfering
with existing facilities. The given coordinates were:
SINCOR advised the Project of the desired approximate location of four sites
suitable to accommodate SAGD well Clusters for sites numbered 1, 3, 4 and
HASD well Clusters for site number 2.
Plot plan studies were developed using PFD’s and the Equipment List for all
four Clusters with the following criteria:
• The prevailing wind direction;
• The natural topography of the sites;
• The existing infrastructure: roads, pipeline right of ways and power
supply;
Steam piping shall be designed for complete condensate removal. The vent
stack is to be located a minimum distance of 25 meters away from production
wells or process equipment. Flexible ball joints with removable spools are
required to accommodate wellhead expansion and service rig deployment. A
6 meter access road leading to a 25 meter clear area perpendicular to wells is
required for service and drilling rigs. With process equipment and pipe racks
running between production/injection wells, it will reduce any conflict with
future expansion. A berm and containment ditch to circuit the plot plan
Cluster sites is required for runoff or spills.
With respect to pipe flexibility, stresses due to thermal expansion or
contraction shall be analyzed by the methods in ASME B31.3 or ASME B31.1
as applicable. Where the layout does not provide sufficient flexibility, the
following may be used, in order of preference:
A detailed stress analysis will be performed for all piping and pipelines
according to the relevant Standards and SINCOR specifications CA04-00-00-
L-SP-011-X1. This study will ensure piping stress levels and thermal growth
are within acceptable limits and to code requirements.
Modeling will evaluate the piping system under weight, hydro-test loads, and
pressure and temperature differentials (installed and operating cases). The
modeling will be conducted using Caesar latest Edition stress analysis
software or equivalent and ASME B31.1 / B31.3 / B31.4/ B3.1.8.
The following piping systems shall be considered for formal stress review:
• Entire Steam piping system for the steam generation, distribution, and
injection, including boiler feed water, and blowdown;
• Piping going to or from sensitive equipment as centrifugal pumps,
reciprocating or centrifugal compressors, air-cooled exchangers, heat
exchangers, rotating or sensitive equipment with limited piping loads;
• Piping with flexible components (hoses, expansion joints, swivel joints,
etc.);
• Piping to tanks subjected to settlement;
• Piping to wellheads (Clusters) subjected to thermal growth;
• Piping subject to vibration;
• Piping subject to seismic loads;
• Piping subject to severe cyclic service;
9 CIVIL DESIGN
The civil design basis covers all preliminary design for development of all civil
facilities for the following areas:
• EOR Substation
• Clusters
• Pipeline from/to Main Station to/from EOR Substation
• Gathering lines from/to Clusters to/from EOR Substation
9.3.1 Foundations
In general, all the sites will be levelled and graded. At the Sub Station, the
storm runoff water shall be collected through open concrete channels and
routed to the Runoff Pond. At the Clusters runoff will be drained to perimeter
concrete channels and route to runoff pond located at each Cluster.
The interconnection of drainages channels, under internal road or process
areas will be provided by carbon steel pipes API 5l Grade B.
9.3.4 Underground
9.3.5 Buildings
a conference room, a lunch room and restrooms. The lunch room will
be not have a kitchen because the meal will be sent from Main
Station’s kitchen.
This warehouse building will dedicate some area to storage of most
common spare parts related to EOR Substation equipments.
• Control Room Building:
This building will have facilities to allow control room for operation
personnel in the operation plant. In addition, these facilities comprise
offices, conference room and restrooms.
• Changing Room
This building contains restrooms, showers and a locker area allowing
personnel to change their coveralls prior to returning home.
• Fire Station & First AID Building.
This building contains the fire station offices, the first aid station for all
operation personnel as well as lockers and restrooms.
• Gates Security Offices Buildings.
This building contains all the facilities which control access to the plant of
operational personnel as well as guests.
The new pipelines to install from Main Station to the EOR Substation and
between Clusters to the EOR shall be aboveground, supported on piles and
structural steel.
The material for piles will be structural steel grade pipe, carbon steel ASTM
A53.
Pipelines from Main Station to EOR Substation:
The pipelines between the Main Station and the Sub Station will cross
existing roads, rivers and creeks as shown in the typical detail Drawing No.
M869-07-10-N-DR-003.
9.4.1 Foundations
In general, the site will be graded and levelled using native soil or fill material
from borrow pits. The storm water on each Cluster will be captured through
open concrete ditches at the perimeter and collected in a runoff pond.
9.4.4 Undergrounds
10 ELECTRICAL DESIGN
As stated in section 10.1, the power for Sub Station will be supplied from the
Main Station’s generator room through a 34.5kV power line. In the new
MVSG-3 (by others) there shall be provisions for one power circuit breaker for
this 34.5kV power line. This power circuit breaker, with its cell, will be the
battery limit for this project.
The outgoing 34.5kV power cables will run underground up to a new cable
tray designed specifically for this Project. These power cables will cross the
whole process area along the existing pipe rack, and again will run
underground in order to reach the new dead end gantry. The new overhead
powerline will start from this dead end gantry and will run along side the
existing powerline (line Circuit #2), with the new circuit maintaining a
minimum clearance distance of 9m between lines. The new powerline will be
integrated on existing SINCOR standard 12 sided poles with an average span
of 100m. The estimated size of the conductors for this line will be 465.9kCM.
Reference to this document can be made in Appendix “D”, specification
CAD04-04-33-P-SP-023.
At the end of the powerline, reaching the EOR Substation, there will be a 12
sided pole dead end gantry similar to the ones provided for existing Clusters.
From the Sub Station there shall be an outgoing powerline with a conductor
size of 246.9kCM to feed the four Clusters. All deviation branches to the
Clusters will be made through disconnect switches in the poles. Each Cluster
will have its own respective dead end gantry made with the 12 sided poles as
the ones mentioned above.
In order to take advantage of the proximity of existing Cluster IC, there will be
a backup 34.5kV line from this Cluster. This back up powerline will be for
essential loads only since it will not have enough capacity to feed the whole
Sub Station. The powerline route from the Main Station to the EOR is shown
on Drawing No. M869-07-10-N-DR-001. The powerline route from the EOR
to the Clusters is shown on Drawing No. M869-08-10-N-DR-001
This 34.5kV switchgear will feed the 34.5/6.9kV power transformers feeding
the 6.9kV MV switchgear which will provide the power for the MV MCC, the
power transformers for the LV MCC and the power transformers for general
lighting.
All of the 34.5kV Switchgear, MV MCC, LV MCC and applicable related
equipment will be located in a Prefabricated Electrical Cabinet (PEC) within
the boundaries of the plant. This will be in accordance to SINCOR
specifications, codes and standards. Reference may be made to documents
listed in Appendix “D”.
The distribution system, from the secondary side of the transformer, shall
follow the standards and criteria shown on the latest revision of SINCOR´s
specification CA04-04-33-P-DC-101 and supplemented by the applicable
single line drawing.
The internal electric distribution may be referenced to the “EOR - General
Preliminary Single Line Diagram” drawing No M869-00-33-P-SK-001 and
various equipment locations. For this reason, the power cables from the PEC
will run above ground over the cable trays along the pipe rack to reach the
critical motor driven equipment. For the other buildings (office buildings, fire
buildings, control room, etc.), the power distribution will be made through local
panel boards for lighting and necessary power outlets.
The single line diagram No. M869-01-33-P-SK-009 “EOR Pads Single Line
Diagram” shows a brief schematic distribution to provide the power from the
incoming 34.5kV line to each electric motor driven load associated within
each Cluster.
Standby power equipment will take over essential electrical service during a
normal power outage. There shall be standby power equipment for control
system requirements, feeders, panels, and branch circuits. All wiring shall
conform to the provisions of the NEC, SINCOR specifications, and all other
regulations covering this type of installation.
The emergency back up power equipment will consist of:
• A 1 MW (estimated) diesel driven Emergency Generator which will
connect to the 460V bus; this will be determined in the FEED stage of
the project.
• A 34.5kV overhead back-up line from Cluster IC that will be connected
to the 34.5kV switchgear bus bars.
The electric loads are preliminary and are listed on document No. M869-50-
33-P-SK-001. The preliminary and estimated load for the EOR is 10.5 MW.
For each of the Clusters, with exception of Cluster 2, the driven load is
estimated to be 0.5 MW. The load lists for the Clusters may be found in
documents No. M869-01-33-P-SK-001, No. M869-01-33-P-SK-002, No.
M869-01-33-P-SK-003, and No. M869-01-33-P-SK-004
The following is a list of long lead electrical items and potential suppliers:
• Power Transformers - ABB, Federal, Marcus, Pioneer
• Low and Medium Voltage Motors - ABB, WEG, Westinghouse/Teco,
Toshiba, Siemens, Hyundai
• Power Dist Cables – CABEL, OKONITE, ICONEL, ALCAVE
• Power Poles - P & M per SINCOR standards
• Power Breakers - ABB, Toshiba, Schneider, Sace, Controlled Power,
GE
• Emergency Generators - Finning, Caterpillar, Mitsubishi, Detroit Diesel,
Volvo Penta
• Medium Voltage VFDs – ABB, Toshiba, Rockwell, Siemens, Robicon
Indoor and outdoor lighting for building and parking areas shall be made
according to SINCOR recommendations. Reference shall be made to
Document No. CA04-04-33-P-DC-101, “Electrical System Design Criteria”,
and any other applicable standards such as COVENIN, API, NEC, and IEC.
Lux levels and work plane details are listed in this document.
For larger areas, 3 HPS floodlight poles will be used; roadways two light poles
will be used for street and roads. For the working areas around the process
equipment the appropriate hazard lighting fixture will be used.
Issue No. A1 Standard Number
P:\Z06835 Sincor Venezuela EOR Project\20-00 PROJ
MANAGMNT\20-20 DBM\Final DBM Document\Master Page: 134 of 166
DBM Rev 0 April 30.doc Issue Date 30/04/07 M869-50-00-A-RP-001
SUBJECT:
DESIGN BASIS
MEMORANDUM
PROJ. DOC. No.: M869-50-00-A-RP-001
11.1.1 Manufacturers
Instrument air shall be the main motive force used for all actuated control and
ESD valves. Minimum supplied instrument air pressure shall be 550 kPag
(80psig) and the shutdown pressure will be 415 kPag (60psig). All
instruments shall be sized for a maximum supplied air pressure of 830 kPag
The instrument index shall be generated during the FEED stage base on
P&ID. This index shall be a single point data entry for all information on
instrumentation and controls. The information contained within the instrument
index will be complete and approved by SINCOR.
Standard projects instrument data sheets shall be completed for all major
instrumentation. All suppliers shall complete the data sheets supplied. All
control valves, pressure safety valves and flow measurement devices shall be
supplied with calculation data sheets.
Two wire, 24 VDC loop powered, 4-20mA signals shall be specified for all
analog instruments. All analog instrumentation shall be provided as “smart”,
with HART protocol communications for ease of calibration and maintenance.
This basis shall also enable the implementation of an Asset Management
System. See section 11.9 of this document for a concise definition of an AMS
type system.
Redundant analog instrumentation shall be utilized where control and
shutdown functions are required. Each function (control and shutdown) shall
be handled separately, refer to 11.6 of this document. Discrete instruments
shall only be used for trip initiators if an analog device is not applicable.
All process trip initiators shall have “soft bypass” switches provided from the
BPCS operator interfaces to facilitate the on-line testing of all field devices.
Flow measurement shall be temperature & pressure compensated (as
required) and displayed in standard units. All flow compensation, totalizing,
etc., with the exception of custody transfer applications, shall be done in the
BPCS. Custody transfer application being any of higher accuracy used for
final transfer of product to other companies or facilities.
24VDC shall be utilized for field mounted discrete devices, solenoids, etc.
Any motor control or MCC devices that require 120VAC control circuit shall be
provided with such an interface within the control system.
All control valves and actuators shall be sized to ensure the appropriate level
of shutoff and performance of the specific service.
All valves shall be supplied with smart positioners with HART communication.
The use of high diagnostic type positioners shall be evaluated on selected
(i.e. severe service) valves, but shall not be supplied on all valves.
Appropriate testing procedures shall be submitted to SINCOR by all
contractors or vendors for approval.
All control valves shall be sized for noise level no higher than 85dBA.
Secondary noise abatement shall be used only if valve cannot be sized
accordingly.
Single Port globe bodies with top guide or cage shall be the preferred type of
control valve. Rotary design where larger size economics apply, or where
required by service (i.e. heavy oil, solids, etc.)
Severe Service shall include high noise, high D/P, cavitations, high
temperature or sour service.
All pressure safety valves shall be sized selected and installed according to
the latest edition of API 520 and must meet ASME Section I or VIII
requirements or ASME Section IV for Boiler applications.
11.1.13 Metering
All metering shall comply with the classification laid out in SINCOR
specification “Flow Instruments” CA04-00-35-J-SP-025 X1.
This diagram describes the relationship between the different systems such
as the BPCS, SIS, Fire and Gas, ESD system, and downhole monitoring, as
well as the communication methods between these systems and
components.
Please refer to the Project Drawing M869-50-35-J-SK-001 Rev A.
The initial Sub Station shall be designed as a stand-alone facility, with limited
expansion capabilities (25%). The BPCS shall provide all basic control
functions and equipment operation, as well as main HMI capabilities. As well
the BPCS shall include:
• Alarm management;
• Seamless interface with packaged equipment;
• Seamless interface with SIS system, and AMS;
• Historical event and analog value trending;
• Supply of data to the business LAN;
• Full online configuration change capability;
• Maintenance functions and system diagnostics.
Maintenance functions shall include the ability to stroke all shutoff (ESD,
BDV) manually from the operator interface.
Alarm Management shall consist of strategies to eliminate “alarm flooding” on
critical equipment or process failure.
Operations interface shall be via a central control room, as well as in the
underground MCC building. All Areas of the facility shall be accessible from
any of the system interfaces. Packaged equipment shall have stand-alone
operator interface local to the equipment which shall have complete control
and monitoring capabilities.
Issue No. A1 Standard Number
P:\Z06835 Sincor Venezuela EOR Project\20-00 PROJ
MANAGMNT\20-20 DBM\Final DBM Document\Master Page: 140 of 166
DBM Rev 0 April 30.doc Issue Date 30/04/07 M869-50-00-A-RP-001
SUBJECT:
DESIGN BASIS
MEMORANDUM
PROJ. DOC. No.: M869-50-00-A-RP-001
All controlled systems shall be designed with a minimum 25% free cabinet
space and 15% wired spares within the system. The CPU (Processor)
loading and memory usage shall not exceed 65%.
Selection of the control system will be performed during the FEED stage. A
study evaluating different control systems has been completed as part of the
Pre-FEED result. Please refer to Document No. M869-50-00-J-RP-001 Rev
B PLC/SCADA and DCS Study in Appendix E.
The ESD system shall be part of the Safety system. All pushbuttons and final
elements (solenoids, MCC’s) shall be connected to the SIS. This system
shall be designed to give Safe and reliable operation and ensure the safety of
the personnel equipment and the environment.
The Safety System shall be designed to the requirements of the facility. This
system shall be designed in accordance with ANSI/ISA-84.00.01-2004. As a
minimum, the ESD and USD functions, Fire and Gas detection shall be
connected through this system. All emergency beacons, horns and
indications shall be driven from this system. All inputs to this system shall be
displayed on the same interfaces as the operating information. Indications
separate from the BPCS shall signal any alarm condition to the operations
group. This system shall be separate from the BPCS, but may be the same
hardware type as the BPCS if the equipment selected is capable and certified
for handling the SIF’s identified during HAZOP, and/or SIL review.
All fire and gas detection equipment, as stated above, will be connected to
the safety system. As a minimum, this equipment will be connected to a
physically separate hardware than any other safety functions.
All MCC installed control panels shall be of top entry design with top hat. All
panels will be designed for a minimum 25% free space for expansions. All
panels shall be FAT tested in the supplier’s facility by an EPC representative.
Issue No. A1 Standard Number
P:\Z06835 Sincor Venezuela EOR Project\20-00 PROJ
MANAGMNT\20-20 DBM\Final DBM Document\Master Page: 141 of 166
DBM Rev 0 April 30.doc Issue Date 30/04/07 M869-50-00-A-RP-001
SUBJECT:
DESIGN BASIS
MEMORANDUM
PROJ. DOC. No.: M869-50-00-A-RP-001
The BPCS and safety systems shall be designed with an interface to an AMS
type. The AMS system will monitor all equipment tied to the systems, and aid
operations and maintenance in troubleshooting problems, failures and rectify.
This system shall give predictive diagnostics for any instrument connected to
the BPCS,or SIS that has the capability. This system shall track any failure
and provide aid in identifying the type of problem, and the possible solutions
that the diagnostics identify. This system shall be capable of communicating
with the BPCS, and giving this information to the operations group. This
system will also be capable of communicating with higher level corporate type
asset management systems in order to facilitate capital and costing control,
as well as manpower planning, and other maintenance and operational
management activities.
The control and safety systems in the Substation’s MCCs and Field Clusters
shall be connected together in one network using fibre optic media. The
communications to the Main Station and existing facilities shall also be
connected using fibre optic media.
~22Km
1-2 Km
4-6 Km
4-6 Km
As shown in the above illustration, the tie-in for the fibre optical
communications to the Main Station shall be done in the existing fibre optic
junction box. This box is located 1 to 2 km away from the EOR Sub Station at
an existing Cluster. All telecoms and communication to the Main Station shall
be routed through this connection.
The facility will be connected (as shown in the above diagram) with SINCOR’s
existing Main Station.
A LAN communications infrastructure will be provided that will span the field,
plant, offices and the control buildings, as well as interconnecting the
Substation to the Main Station.
• The “site” LAN system, consisting of personal computer workstations
(for e-mail and Microsoft Office Suite software), server(s), and printer
will be capable of connection to the Control Network/Administrative
LAN and the Main Station SINCOR´s offices;
• Firewalls will be installed for security isolation between the “site” LAN
and the outside world;
• The LAN servers, router and PC’s will require network support and
user administration.
11.13.3 Telephone
11.13.4 Radio
All metering shall be done within the BPCS. Any Custody Transfer shall be
done with external equipment and then communicated with the BPCS.
Special attention will be given to the injection and production wellhead
metering. This will be necessary to track the behaviour of these ‘pilot’ well
facilities. Refer to SINCOR Project Drawing M869-50-35-J-SK-002 REV A.
The OTSG packages shall be supplied with their own separate Burner
Management Systems (BMS). These systems will monitor flame status and
start-up to ensure safe operation of the burner. All fuel rate and multiple fuel
sources will be controlled by a system supplied by the vendor but of the same
equipment as the selected BPCS. The BMS’s shall interface seamlessly with
the control system (BPCS) and the Safety System (SIS).
The Lease Automatic Custody Transfer skid shall be supplied with its own
flow computer to give custody transfer quality flow metering. This system
shall fully integrate with the facility BPCS to give seamless control, and
information transfer.
The VRU package(s) shall be controlled and monitored by the BPCS and all
shutdowns will be performed by the Safety system (SIS). There shall be local
indication with full access to controls for unit start-up and operation.
The water treatment area shall be controlled and monitored by the BPCS and
all shutdowns will be performed by the Safety system (SIS). There shall be
local indication and access to controls for unit mode changes and operation.
12 OVERALL SCHEDULE
The overall project schedule for FEED, Detail Engineering, Procurement and
Construction for the EOR project is shown in Appendix G. The assumption is
that Detail Engineering will start approximately six months after the
completion of FEED, due to the EPC contract selection process.
Some of the highlights of the schedule are:
• It typically takes 6 months after start of Detail Engineering to get the
piping model to 60% complete. At this point the rack pipings are define
and spooling or modules may proceed. The remaining piping layout
has to wait for vendor information.
• The critical path for detail engineering is always procurement of
equipment. Procurement has to complete early to provide vendor data
to designer.
• If procurement is on time, the model can reach 90% complete within 9
months of Detail Engineering start. At this point, on-site mechanical
work can begin.
• Civil will start working on an overall site plan early, but the details of
the plan site usually do not start until the model is 60% complete. For
this reason, civil works usually start about 9 months after Detail
Engineering start.
• With the start of Detail Engineering in mid year, the earth work will be
starting in spring. This is the start of the wet season, hence, higher
risks of weather delays and cost overruns for earth work activities.
• Delivery of the OTSG is the most critical long lead items. This
schedule assumes 60 weeks delivery for the OTSGs. Typically
construction requires 9 months after setting of the OTSG to complete
mechanical construction. If the OTSG delivery time is longer, it could
delay the start-up.
• The construction of these facilities will most likely be “stick built”, that
is, piping and equipment are installed at site. When all the
construction man-hours are spent on-site, the risks for delays are
higher than when the works are distributed to various sub-contractors’
facilities. The current schedule does not have much float for
construction duration.
• Overall the duration between Detail Engineering start and Steam-in is
slightly more than two and a half years. This is reasonable for a
project of this size, with careful planning, well defined WBS, availability
of skilled resources, good Subcontractors, and well staffed
Construction Management Team.
13 CONSTRUCTION PHILOSOPHY
13.1 Scope
Labour Register:
Contractor maintains a Labour Register, based on recent experience in
the industry projects for the Strategic Alliances, and especially for the
EOR Project. Extensive use of this register and the recent updates shall
be made in order to determine the labour availability at various stages of
the construction phase. The construction subcontractors will maintain
their own register of labour and shall use it to complement and update the
Owner’s register.
13.3.1 Procurement
13.3.2 Construction
Equipment Installation
Testing
HVAC Installation
Others
Demobilization/Dismantling Temporary facilities
• Heavy Lifting
Heavy Equipment Transportation
Heavy Equipment Installation
• Mechanical Works
Mobilization and Temporary Facilities Construction
Static Equipment/Vessels/Towers Installation
♦ Internal Assembly
♦ Cleaning/Closing
Prefabrication of Small Bore Piping <= 2, 5 inches
Prefabrication of Large Bore Piping > 2, 5 inches
Underground Piping Installation
Aboveground Piping
Steam Tracing
Painting
Equipment Insulation
Piping Insulation
Pipe Hydro test, Flushing and Reinstatement.
Other
Demobilization/Dismantling Temporary Facilities
• Electrical Work
Mobilization and Temporary Facilities Construction
Trenches
Conduits/Trays installation
Cabling
Lighting System
Small Transformers Installation
Panels Installation
Connection
Testing
Cathodic Protection Installation/Testing and Start-up
Other (Electrical Equipment & Telecommunications
Included)
Demobilization/Dismantling Temporary Facilities
• Instrumentation Work
Mobilization and Temporary Facilities Construction
Trenches
Conduit & Trays
Cabling & Connection
Loop Tests
Other (Instruments & Instrument Equipment Included)
Automatization/Software Installation
• Demobilization/Dismantling EPC Temporary Facilities
• Demobilization/Dismantling PMC Temporary Facilities
13.5 Contracting
The EPC Contract shall be Lump Sum Basis/Unit Price referential. The EPC
contractor shall be aware of site conditions and an EPC contractor with
experience in the area is recommended. The EPC prime contractor can be a
joint venture between local EPC contractors of Venezuela or just one with
solid financial capabilities. Subcontractors are defined according the Work
Break Down Structure.
• SINCOR
• Project Management Service (PMC)
• EPC Contractor
14 COMMISSIONING
14.1 Definitions
Mechanical Completion/Check-Out
All of the mechanical, instrumentation, electrical and control features
necessary for safe operation of the facility modifications are in place and
no type “A” deficiencies exist. Wiring continuity checks, panel
terminations, end device installations, end device calibrations,
adjustments and primary settings, etc. are completed and checked-off as
meeting the design requirements and specifications.
Deficiency List
Is a list of deficiencies which are categorized and numbered with an
action, schedule & responsible designate to get the work done.
Deficiencies are categorized A or B:
A = Completion required to operate (includes safety and
environmental issues).
B = Completion not required to operate (touch-ups, etc.).
Turnover
Completion of the ‘Transfer to Operations Form’ transfers care, custody
and control of the mechanically complete new control systems and
equipment to Operations.
Pre-Commissioning
Pre-Commissioning is the period when conformity, non-operating checks
and verifications that the installation conforms to plans, specifications and
drawings are carried out. The new control system wiring, hardware,
software and communications are also checked. Pre-commissioning
includes the calibration of instruments, cold-alignment checks, testing of
safety devices, loop checks. The loop check includes checking from the
end device through the DCS I/O, DCS logic and HMI.
Commissioning
Start-Up
Start-up is the initial running of equipment and facilities with process fluids.
Operations
SINCOR operating personnel.
Contractors
EPC - EPC Contractor
Sub – Subcontractors
14.2 Activities
PRIMARY SUPPORTING
ITEM
RESPONSIBILITY ROLE
Mechanical Completion
Checkout for Mechanical Completion Construction Manager Contractors
Energize electrical & DCS equipment Operations Contractors
Energize End-Devices & Loops Operations Contractors
Instrument Calibrations Construction Manager Electrical
Subcontractor
Control System Communications EPC Contractor Electrical
Checkout Subcontractor
Pre-Start-Up Safety Review Operations Contractors
List Mechanical Deficiencies “A” + “B” Construction Manager Contractors
with completion dates
Check-off sheets with deficiency lists to Construction Manager Contractors
Operations for sign-off.
Pre-Commissioning
DCS and HMI communications Operations & EPC Electrical
Contractor
Loop checks Operations & EPC Electrical
Contractor
Control Function checks Operations & EPC Electrical
Contractor
Cause & Effect Key – Function Checks Operations & EPC Electrical
Contractor
Site Acceptance Testing Operations EPC
Commissioning
Electrical Motors & Pumps Operations Contractors
Instrumentation Operations Contractors
Process Fluid Introduction Operations Contractors
Purge and Leak Tests Operations Contractors
Process System Test-runs Operations Contractors
Turn-over
Transfer of Operations Construction Manager All
Start-Up Operations
Start-up Operations All
Control System Training EPC
As part of the Quality Assurance plan for the project, EPC, SINCOR and the
Subcontractors will carry out a detailed check of the completed facility against
the latest approved edition of the “Issued For Construction” drawings and the
“Construction Completion Checklists” listed below.
These marked-up drawings provide the final data for any “as-built” drawings
and identify any deviations from the design. They also form the basis of the
Transfer to Operation’s documentation. The standard for this drawing mark-
up is:
• Each line, item and note on the drawing shall be highlighted in
YELLOW as being correctly installed,
• Deviations will be marked off in RED and itemized by a number. A
comment bearing the same number will be listed on the back of the
drawing with a dated reference to the follow-up,
• Upon satisfactory resolution to technical queries, the RED highlight will
be highlighted in YELLOW.
Deficiency lists used in the final completion stages to track and prioritize any
outstanding items will be generated for each of the mechanical, electrical,
instrumentation and controls disciplines.
Checklists
• Mechanical Completion Checklists (by the Construction Manger);
• Electrical Completion Checklists (by the Electrical Subcontractor);
• Instrument Completion Checklists (by the Electrical Subcontractor);
• Instrument Calibration Forms (by the Electrical Subcontractor);
• DCS I/O Drawings and Loop Diagram Check-offs (by EPC &
Operations);
• HMI Check-offs (by EPC & Operations); and
• Pre-Start-Up Safety Review (by Operations).
14.6 Commissioning
14.8 Start-Up
Start-up is complete when the new equipment and control systems are
operating & transferring information to/from the HMI. Operations are
responsible for the safe start-up and operation of the new and existing
systems.