Introduction
Manager Networks is an organisation that provides networking events for business people across Australia. The
project is to organise a formal conference on cutting edge leader topics which focus on leadership skills,
knowledge and trends. The outcome of the project is to promote Management Networks and provide
professional development for members. The purpose of this document is to determine the resource requirements
used to develop a preliminary cost estimate. Furthermore, based on the estimated cost, the project budget and
registration fees will be proposed to cover the costs of the project and bring a 50% profit to the organisation.
Resource requirements
To successfully estimate the project costs, the major resources requirements need to be identified. Firstly, the
selection criteria for the venue are required. The venue needs to be located in the centre of Brisbane, which has a
conference room that can accommodate up to 150 people. Furthermore, the venue must be able to provide
required conference equipment, including audio-visual equipment, lecterns and an electronic whiteboard.
Additionally, conference catering should be on-site and include a high-quality morning tea, lunch and afternoon
tea. Finally, accommodation needs to be booked for speakers who do not locate at Brisbane and staff of
Manager Networks, which is approximately 20 people.
The second resource requirement is speakers. Five speakers will speak at the conference, and
they should be well-known across industries and knowledge about leadership. It is expected to have four
Australian speakers and one international speaker at the conference. $2,000 fee will be paid for each speaker,
which includes travel costs depending on their location.
The marketing costs should also be included in this document. The marketing team identified
six different marketing methods to promote this conference. The first one is digital marketing
communication using social media channels combining with search engine advertising and organisation-
sponsored websites, the cost of a digital marketing package will be listed in the
project costs. Additionally, direct marketing using several types of media will be utilised. The
marketing team has suggested collaborating with Leader Community News Magazine which is a famous
magazine in leadership in Australia to promote the conference both online and offline.
Furthermore, the organisation already has a database of potential participants who came to previous
conferences, so the team will directly email and mail them invitations of this
conference. Finally, sponsorship marketing through associating with other organisations will be used. This
marketing approach will help to reduce the costs of the project as it will bring
incomes to the project. The team is now working with potential sponsors and will provide the list as a separate
document. Finally, sales promotion will be applied to participants who register early.
Finally, the costs for event staff and other facilities will be covered. For example, the conference may require a
photographer to take photos and film the conference for future promotions.
1
Accommodation for 20 staff and 5 speakers. $2,604
Publicity $15,000
Courier for mailing invitations $1,595
Printing 500 invitations (including delivery fees) $292.04
Facility (including visual and audio equipment) Included in the Venue fee as a
package
Digital campaign package (including social media advertising and $6,000
Google Ads)
Total $53,295.04
If the CV is a negative value, it means that the project is over budget. However, if the CV is a positive value,
then the project is under budget.
Budget variances of up to 5% can be accommodated but must be reported. The below table
indicates the approval hierarchy that the project manager needs to follow to obtain the
approval.
2
Dear team,
I have made our project cost management plan for the annual conference needs. The plan required is still a draft
and I need your input of it. Please be kind to review the draft project cost management plan which is attached.
Thank you.
Best regards.
Manager Networks
Project Cost Management Plan
Introduction
Manager Networks is an organisation that provides networking events for business people across Australia. The
project is to organise a formal conference on cutting edge leader topics which focus on leadership skills,
knowledge and trends. The outcome of the project is to promote Management Networks and provide
professional development for members. The purpose of this document is to determine the resource requirements
used to develop a preliminary cost estimate. Furthermore, based on the estimated cost, the project budget and
registration fees will be proposed to cover the costs of the project and bring a 50% profit to the organisation.
Resource requirements
To successfully estimate the project costs, the major resources requirements need to be identified. Firstly, the
selection criteria for the venue are required. The venue needs to be located in the centre of Brisbane, which has a
conference room that can accommodate up to 150 people. Furthermore, the venue must be able to provide
required conference equipment, including audio-visual equipment, lecterns and an electronic whiteboard.
Additionally, conference catering should be on-site and include a high-quality morning tea, lunch and afternoon
tea. Finally, accommodation needs to be booked for speakers who do not locate at Brisbane and staff of
Manager Networks, which is approximately 20 people.
The second resource requirement is speakers. Five speakers will speak at the conference, and
they should be well-known across industries and knowledge about leadership. It is expected to have four
Australian speakers and one international speaker at the conference. $2,000 fee will be paid for each speaker,
which includes travel costs depending on their location.
The marketing costs should also be included in this document. The marketing team identified
six different marketing methods to promote this conference. The first one is digital marketing
communication using social media channels combining with search engine advertising and organisation-
sponsored websites, the cost of a digital marketing package will be listed in the
project costs. Additionally, direct marketing using several types of media will be utilised. The
marketing team has suggested collaborating with Leader Community News Magazine which is a famous
magazine in leadership in Australia to promote the conference both online and offline.
Furthermore, the organisation already has a database of potential participants who came to previous
conferences, so the team will directly email and mail them invitations of this
conference. Finally, sponsorship marketing through associating with other organisations will be used. This
marketing approach will help to reduce the costs of the project as it will bring
incomes to the project. The team is now working with potential sponsors and will provide the list as a separate
document. Finally, sales promotion will be applied to participants who register early.
Finally, the costs for event staff and other facilities will be covered. For example, the conference may require a
photographer to take photos and film the conference for future promotions.
3
Projected costs
Venue for the conference $10,030
Catering for the conference (including morning tea, tea break, lunch Included in the Venue fee as a
and dinner) package
Speaker fees (including travel fee) $10,000
Airfare for speakers who do not locate in $2,774
Brisbane / Australia
Airfare for staff ($250 x 20) $5,000
Accommodation for 20 staff and 5 speakers. $2,604
Publicity $15,000
Courier for mailing invitations $1,595
Printing 500 invitations (including delivery fees) $292.04
Facility (including visual and audio equipment) Included in the Venue fee as a
package
Digital campaign package (including social media advertising and $6,000
Google Ads)
Total $53,295.04
If the CV is a negative value, it means that the project is over budget. However, if the CV is a positive value,
then the project is under budget.
Budget variances of up to 5% can be accommodated but must be reported. The below table
indicates the approval hierarchy that the project manager needs to follow to obtain the
approval.
4
1% - 5% Approved Project Manager and Chief of Finance
5.1% - 6% Approved by Project Sponsor
6.1% - 7% Approved by Management Board
More than 7% Cancel the project
Dear Sir,
I have made our project cost management plan for the annual conference needs. The plan required your
evaluation to completely done. Please be kind to review the final project cost management plan which is
attached. Thank you.
Best regards.