Professional Documents
Culture Documents
Disputes On Construction Contracts Powerpoint
Disputes On Construction Contracts Powerpoint
CONTRACT
CYPRUS DISPUTE RESOLUTION FORUM – 11 JUNE 2010
Rowan Planterose
Dispute Resolution Procedure under Clause 20
DAB provides its decision within 84 days DAB fails to do so within 84 days
under Sub-Clause 20.4 or under Sub-Clause 20.4
Yes
No
Is either
Party dissatisfied
with the decision?
Is the dispute
settled amicably Yes
Yes Dispute is settled
No
The Parties have 56 days to
resolve the Dispute
amicably. Sub-Clause 20.5
Dispute shall be finally
settled by International Arbitration,
Sub-Clause 20.6
Compliance with the Decision of the DAB
DAB provides its decision
within 84 days under
Sub-Clause 20.4
No Is either Yes
Party dissatisfied?
Non-compliant Party
Proceed to Sub-Clause is in breach of contract
Dispute will be settled
20.7 & refer the failure End Lacuna in 1999 Books
through arbitration
itself to arbitration Refer to Arbitration in Gold Book
FIDIC Contracts
Red Book - Conditions of Contract for Construction for Building
and Engineering works designed by Employer
Yellow Book - Conditions of Contract for Plant and Design Build for E&M Plant
Plant and for Building and Engineering Works designed
by Contractor
– Full supporting particulars of the basis of the claim, of extension of time and
additional payment claimed
– Sanction: “If the Contractor fails to comply with this or another Sub-Clause
in relation to any claim, any extension of time and/or additional payment
shall take account of the extent (if any) to which the failure has prevented or
prejudiced proper investigation of the claim.”
– (Gold Book) If the Contractor fails to provide the contractual or other basis
of claim within 42 days, the Notice lapses, subject to DAB permitting late
submission. (This is additional sanction).
Ongoing Claims
– Fully detailed claim considered as interim
– May approve
– Under the Red and Gold Books the DAB will already exist. Must be
appointed by date stated in Appendix to Tender or Contract Data.
Default is 28 days after Commencement Date (i.e. commencement
of execution of the works)
– Either Party fails to nominate a member (for approval by the other Party)
within time period
– Personal appointment
– Confidentiality obligation
General Conditions of Dispute
Adjudication Agreement(2)
• DAB shall
(a) act fairly and impartially as between the Employer and the Contractor, giving
each of them a reasonable opportunity of putting his case and responding to the
other’s case, and
• Within 28 days of receiving decision, Party gives notice to other Party of its
dissatisfaction. Gold Book requires copy to Chairman of DAB
• Notices of dissatisfaction must set out matter in dispute and reason for
dissatisfaction (but not binding in arbitration)
• Gold Book only: if decision of DAB requires a payment, DAB may require payee
to provide an appropriate security.
• Where a DAB decision has become final and binding and a Party fails
to comply with the decision, then the other Party may refer the failure
itself to arbitration. (No attempt at amicable settlement is necessary)
• Specifically dealt with in Gold Book. “In the event that a party fails to
comply with any decision of the DAB, whether binding or final and
binding, then the other party may… refer the failure itself to arbitration…
for summary or other expedited relief…”
Direct referral to Arbitration
If a dispute arises between the Parties in connection with, or arising out of,
the Contract or the execution of the Works and there is no DAB in place,
whether by reason of the expiry of the DAB’s appointment or otherwise:
• This was a contractual right; even though the decision might later be
reversed.