4 Job Description of Mud Engineers (valid signed copy) Li Ling Ready Send to Mr. Ali shah for review,
ready
PTIS contact and confirm. Update our calibration Received Quotations from PTIS,
13 Record of third-party inspection certificates (covering lab apparatus and appliances) Ateeq & Li Ling Ready Will assign the job to PTIS after
record,before expiry date. Eid.
Provide CCDC own lab certificate and Check Petorpak PTIS response received, own
14 Valid Calibration certificates of lab apparatus from ISO/IEC 17025-2017 certified company. Ateeq & Li Ling Ready
ISO Certificate record completed.
15 First Aid Box availability in Mud Lab Ateeq, Yard & HSE Department Purchase 4 Aid Boxes, Yard Make the Material Schedule Ongoing Procurement is purchasing this
16 Fire Extinguisher availability in Mud Lab Ateeq, Yard & HSE Department Apply it from Yard and HSE Department Ready material.Will receive today
17 SOP for Chemical Loading / Off-loading, handling and storage Ateeq, Yard & HSE Department work together with HSE Ready
Environmental Aspect & Impact Assessment (EAIA) of Mud Chemicals testing, treatment and
18 Ateeq, Yard & HSE Department work together with HSE Ready
storage
19 Risk Assessment of Mud Chemical loading / off-loading and mixing job Ateeq, Yard & HSE Department work together with HSE Ready
20 Mitigation Plan for Chemical Spillage Ateeq, Yard & HSE Department work together with HSE Ready
21 Chemical Spill Kit availability, manual and training Ateeq, Yard & HSE Department Purchase 4 Kit, Yard Make the Material Schedule Ongoing Procurement is purchasing this
material. Will receive today
22 SOP of Mud sample Testing & Analysis Li Ling Template Already Ready
23 Housekeeping of chemical storage area Ateeq, Yard & HSE Department work together with HSE Ready